Pile Test Evaluation Report
Pile Test Evaluation Report
ON
PILE LOAD TESTS
May, 2007
CONSULTANT:
PROJECT MANAGER:
3 LOADING MECHANISM 12
7 RECOMMENDATIONS 67
APPENDICES
Cast-in-situ RCC Piles are being considered as a foundation system for various
structures of the Zayed Center, Lahore, Pakistan. Theoretical design of the piles
was evolved on the basis of geotechnical investigations carried out at the project
site. On the basis of theoretical pile design, the Project Designers i.e. M/s LERA
International selected two types of piles for full scale load testing.
Detailed specifications and tender documents for the pile load testing program
were developed in accordance with the general requirements of the Project
Designers. The specifications included construction method, instrumentation of
piles, and load testing. The testing program comprised load testing of six piles.
The piles with two different diameters; 1200 mm and 1500 mm having lengths 18
m and 23 m respectively were selected for the load testing program as required by
the Project Designers.
The contract for the pile load testing program was awarded to M/s IVCC of
Lahore.
A total of six (06) piles were tested during the testing program as detailed below;
Sr. # Test Pile Test Pile Test Pile Type of Test Design Test Grouted
No Designation Diameter Length Load Load or Un-
(mm) (m) (ton) (ton) grouted
1 P1 1500 23 Compression 800 2400 Un-
grouted
Boreholes for all the test piles were drilled using a bucket type auger. In order to
stabilize the boreholes Bentonite mud was used during the drilling. Piles P1& P3
(1500 mm diameter) were drilled down from El. (–) 18 m while other piles
P2,P4,P5 & P6 (1200 mm diameter) were drilled down from the proposed
basement floor level of El. (–) 16.5 m.
Very extensive instrumentation was used for these tests to obtain detailed
information regarding behavior of the test piles during the load testing.
The pile load testing program was executed during the period from 24th January,
2007 to 8th April, 2007. This report provides details of construction of test piles, its
instrumentation, load testing data, and interpretation of the load test data.
Recommendations regarding safe load carrying capacities of both types of piles are
also provided in this report.
2.1 General
The piles were drilled utilizing crane mounted pile diggers. Suitable service
cranes were deployed to handle the tremmie concreting and the cage
lowering operations. The pile centre was established from baselines /
benchmarks. Reference pins were placed at 90° to offset the position of the
pile centre. These reference pins were then used to periodically reconfirm
the centre of the pile during the construction operations.
The rig was set up over the pile centre pin and the verticality of the Kelly
bar was checked with a spirit level to ensure verticality of the borehole. The
drilling unit bored a pilot hole approximately 20 mm larger in diameter than
the diameter of the pile being installed. A temporary casing approximately
2-3 meters long, which was kept true to the centre of the pile by checking
from the reference pins, was installed in this pilot hole. Bentonite was then
poured into the pilot hole (where required), for the stability of the borehole,
and the drilling of the bore was continued with appropriate digging tools
down to the proposed tip level of the test pile. After this operation the
bottom of the bore was cleaned out using a purpose made cleaning bucket
Prior to the cage lowering and concreting operations the bentonite sand
content in the borehole was checked. Depending on the sand contamination
the bentonite was recycled. This recycling operation continued until the
sand content in the bentonite was within required limits.
Cement, sand and coarse aggregate in the concrete mix were used as per
approved mix design. The Concrete Batching Plant had already been
installed and calibrated and concrete was produced under the Engineer’s
supervision. Cylinders of concrete were cast to check the 7 days and 28
days compressive strengths.
1. Before the concrete was placed in the pile, the grout tubes were
filled with water and were plugged at the top.
3. At least 4 days after the pile had been concreted the base grouting
was carried out in accordance with the following procedure:-
a. The plugs were removed from the top of all U-tubes, and a
grouting banjo fitted to one leg of each U-tube, and a plug to
the other.
4. The level of the top of the pile was observed throughout the
grouting operation by means of a precise level.
5. The grout was a neat cement grout with a water cement ratio 0.5.
The test piles were provided with extensive instrumentation for monitoring the
behavior of the piles during load testing. The details of various instruments used
during the testing program are provided in the following sections.
Four vibrating type strain gages were installed with the cage at each 3 m interval
for test Piles P1, P2 and P6 to record deformation of pile at the respective
section of pile. A view of the strain gages is shown in Photograph 2-1. The
average of four gages for each interval was taken to compute skin friction in each
pile section.
ii Extensometers
Extensometer
iv Dial Gages
For piles P1, P2 & P6, two dial gages were also set at the head of the pile to
record total settlement of the pile manually. Such precautionary measure
was taken to avoid any possible accidental error in measurements recorded
by LVDT’s.
Dial gage
LVDT
During load testing of piles P1, P2, P3, P4 & P6, to monitor the total
deformation of pile head in two dimensions (2D), image analysis system
was introduced. In this method, high resolution digital camera was fixed at
a suitable distance from the pile to capture photos of the imprinted grid on
the pile during loading. Camera was attached to a laptop computer through
cables and control was automatically made using the keyboard.
In order to capture images with the maximum possible details, camera was
adjusted for its zoom settings. Moreover the tripod used for mounting the
camera was adjusted for its tilt and pan so that perfect alignment with the
grid was ensured prior to capture.
The time setting was then synchronized with the other instrumentation on
the site (extensometers, LVDT and their data logging arrangement).
Four types of loading mechanisms were employed to conduct pile load tests.
Detailed description is given below.
A data-logging unit monitored all parameters in real time and recorded data
automatically. The unit also maintained applied loads within close
tolerances through the hydraulic loading system.
The nominal test duration was dictated by the loading schedule as per
ASTM D1143 and each test was carried out as a continuous process
according to the loading schedule. All the devices employed for load
testing including load cells, LVDTs, dial gages, strain gages, pressure
gages, image analysis system etc. were calibrated before starting the load
tests. During loading, the movements of reference beam were also
monitored by precise leveling at regular intervals.
• Reading from an optical level to check datum beam fixings, fixed bench
marks and kentledge extremities.
The purpose of the including PDA testing in this test program was to
calibrate this method of testing with actual load tests, so that working piles
would be tested with this quick method.
Four pairs of transducers were attached to the pile head during the test.
These transducers were equally spaced along the pile circumference.
This test was carried out using the equipment manufactured by Pile
Dynamics Inc. USA. Information on pile identity, length and diameter,
construction type, installation and strata details were collected prior to the
test.
The identified pile for test was first checked to ensure that the pile head
was clean, of sound concrete and free from standing water, loose concrete,
laitance and blinding concrete. The sonic echo integrity test was carried out
by tapping the pile head with a light plastic headed hammer to generate a
downwards traveling acoustic wave. The wave was reflected by any
Zayed Center, Lahore
Test Piles & Load Test Report 13
changes in the pile shaft impedance (normally corresponding to changes in
pile shaft cross-sectional area) and detected at the pile head by a transducer
held firmly to the pile head.
Each pile was tapped a number of times around the pile head and 3 similar
traces were displayed and stored digitally within the data collection unit.
Pile load tests were conducted on six piles designated as P1, P2, P3, P4, P5 and P6.
The information regarding the test piles and type of tests is summarized in Table
4.1.
Design Planned
Item Pile Type of
Description Verification Load Test Load
No Designation Load Test
(DVL) in (Tons) (Tons)
Bored Cast in Place
Concrete Pile with Diameter Axial
1 P1 800 2400
= 1500 mm and Length = 23 compression
m.
Bored Cast in Place
Concrete Pile with Diameter Axial
2 P2 500 1500
= 1200 mm and Length = 18 compression
m.
Bored Cast in Place
Concrete Pile with Diameter Lateral load
3 P3 80 240
= 1500 mm and Length = 23 test
m.
Bored Cast in Place
Concrete Pile with Diameter Lateral load
4 P4 50 150
= 1200 mm and Length = 18 test
m.
Bored Cast in Place Pile
Concrete Pile with Diameter Dynamic
5 P5 500 1000
= 1200 mm and Length = 18 Analysis.
m. (PDA)
Bored Cast in Place
Concrete Pile with Diameter
Axial
6 P6 = 1200 mm and Length = 18 500 1500
compression
m. The pile was also base
grouted.
Various stages of pile load testing and instrumentation are shown on photographs
including in Appendix-1. The construction details of different test piles are
provided on construction drawings in Appendix-2.
A test load of 3 times the anticipated Safe Working Load (SWL) was to be
applied on this pile. The load was planned to be applied in 3 cycles, the first
cycle was planned up to 1 x SWL; the second cycle to 2 x SWL and the last
cycle to the final test load. Between the cycles the load was reduced to zero
and held for a minimum period of 1 hour to allow the measurement of net
settlement. Following criteria were applied prior to continuing the load
increments;
Prior to increasing the load after any holding period a minimum rate of
settlement was observed, up to the maximum hold period specified.
-20
-40
-60
Plastic strain
-80
(mm)
-100
-120
-140
-160
Elastic strain
-180
-200 0 200 400 600 800 1000 1200 1400 1600 1800 2000
20
Axial displacement by image analysis
Pile-P1
0
-20
-40
-60
-80
(mm)
-100
-120
-140
-160
-180
-200 0 200 400 600 800 1000 1200 1400 1600 1800 2000
1.5
1.0
Point of max. curvature
0.5
0.0
-0.5
-1.0
-1.5
-2.0
Pile dia = 1500 mm
-2.5 Pile length = 23 m
-3.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0
5
Lateral displacement by image analysis
Pile-P1
4
1
(mm)
-1
-2
-3
-4
-5
-200 0 200 400 600 800 1000 1200 1400 1600 1800
3000
2500
Load (Kips)
2000
1500
1000
-500
0 1 2 3 4 5 6 7
Displacement (Inches)
Fig. 5.1.5: Computing ultimate capacity by Tangent method
4000
Pile-P1 Limit Value (Davisson 1972)
3500
3000
2500
Load (Kips)
2000
1500
-500
0 1 2 3 4 5 6 7
Displacement (Inches)
0.0006
0.0005
1/2
Y =3.51E-4 + 3.12E-4 X
Displacement
0.0004
0.0003
0.0001
4000
Pile-P1 90 Percent (Hansen 1963)
3500
3000
2500
Axial load (Kips)
2000
1500
1000
Displacement = 0.4 in
500 Load = 1226 kips
-500
0 1 2 3 4 5 6 7
Axial displacement (Inches)
The loading sequence and procedure was similar to that employed in test
pile P1. The only differences were as follows:
-80
(mm)
-100
-120
-140
-160
-180
-100 0 100 200 300 400 500 600 700 800 900 1000
20
Axial displacement by image analysis
0
Pile-P2
-20
-40
-60
(mm)
-80
-100
-120
-140
-160
-180
-100 0 100 200 300 400 500 600 700 800 900 1000
3.0 Pile-P2
2.0
1.5
1.0
0.5
0.0
-0.5
-1.0
-1.5
-2.0
-2.5
-1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5
8
Lateral displacement by image analysis
7 Pile-P2
3
(mm)
-1
-2
-3
-100 0 100 200 300 400 500 600 700 800 900
1750
1500
1250
Load (kips)
1000
750
500
Displacement = 0.0597 in
250 Load = 390.1 kips
0
-250
-1 0 1 2 3 4 5 6 7
Displacement (Inches)
Fig. 5.2.5: Computing capacity of pile by Tangent method
2250
Pile-P2 Limit Value (Davisson 1972)
2000
1750
1500
1250
Load (kips)
1000
750
500
-250
-1 0 1 2 3 4 5 6 7
Displacement (Inches)
0.0010
Displacement
Displacement = 1.8 in
0.0005 Load capacity = 645 kips
-0.4 -0.2 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4
Displacement (Inches)
2250
Pile-P2 90 Percent (Hansen 1963)
2000
1750
1500
Axial load (kips)
1250
1000
750
-250
-1 0 1 2 3 4 5 6 7
The loading sequence and procedure was similar to that employed in test
pile P1. The only differences were as follows:
Pile was base grouted as per method statement described in article 2.3.
Minimum Holding
Load (% of SWL) Load (kN) Remarks
Duration (min.)
0 0
25 1250 60 Max 2 hours
50 2500 60 Max 2 hours
75 3750 60 Max 2 hours
100 5000 360 Max 12 hours
75 3750 10
50 2500 10
25 1250 10
0 0 60 Minimum Hold
50 2500 10
100 5000 10
125 6250 60 Max 2 hours
150 7500 60 Max 2 hours
175 8750 60 Max 2 hours
200 10000 360 Max 12 hours
175 8750 10
150 7500 10
125 6250 10
100 5000 10
50 2500 10
0 0 60 Minimum Hold
50 2500 10
100 5000 10
150 7500 10
200 10000 10
225 11250 60 Max 2 hours
250 12500 60 Max 2 hours
275 13750 60 Max 2 hours
300 15000 720 Max 24 hours
250 12500 10
200 10000 10
150 7500 10
100 5000 10
50 2500 10
0 0 60
-40
-60
Compression Pile Load Test
-80 Pile dia = 1200 mm
(mm)
Pile length = 18 m
-100
-120
-140
-160
-180
20
Axial displacement by image analysis
Pile-P6
0
(with base grouting)
-20
-40
-60
(mm)
-80
-100
-120
-140
-160
-180
0
-1
-2
-3
-4
-5
-6
-7
-8
-100 0 100 200 300 400 500 600 700 800 900 1000 1100
4
Pile-P6
3 (with base grouting)
Log (displacement in mm)
-1
-2
-3
-1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5
1000
500
Displacement = 0.08 in
Load = 728 kips
0
-1 0 1 2 3 4 5 6 7
2500
Pile-P6 Limit Value method (Davisson 1972)
(with base grouting)
2000
Axial load (kips)
1500
1000
Displacement = 0.67 in
Load = 1226 kips
500
-1 0 1 2 3 4 5 6 7
1/2
0.0008
0.0007
0.0006
1/2
0.0005
Y =4.1E-4 + 4.2E-4 X
Axial displacement
0.0004
Displacement = 0.976 in
Load = 1205 kips
0.0003
0.0002
0.0 0.1 0.2 0.3 0.4 0.5
2500
Pile-P6
(with base grouting)
2000
Axial load (kips)
1500
1000
-1 0 1 2 3 4 5 6 7
The test load of 2400 kN i.e. 3 times the SWL was applied to this test pile.
The load was applied following ASTM D3966-90.
The load deformation relationship is shown in Figures 5.4.1, 5.4.2 & 5.4.3.
90 Pile-P3
Lateral Pile Load Test
80 Pile dia = 1500 mm
Horizontal displacement by
Pile length =23 m
70
LVDTs(mm) 60
50
40
30
20
10
-10
-20
-20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
100
90 Pile-P3
80
Horizontal displacement by
70
image analysis(mm)
60
50
40
30
20
10
-10
-20
-20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
90 Pile-P3
Lateral Pile Load Test
80 Pile dia = 1500 mm
Horizontal displacement (mm) Pile length =23 m
70
60
50
40
30
20
10
-10
-20
-20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
The test load of 1500 kN i.e. 3 times the SWL was applied to this test pile.
The load was applied following ASTM D3966-90.
The load deformation relationship is shown in Figures 5.5.1, 5.5.2 & 5.5.3.
Horizontal displacement 60
by LVDTs (mm) 50
40
30
20
10
-10
-60 -40 -20 0 20 40 60 80 100 120 140 160 180 200
90
Pile-P4
80
70
Horizontal displacement
by image analysis (mm)
60
50
40
30
20
10
-10
-60 -40 -20 0 20 40 60 80 100 120 140 160 180 200
60
50
40
30
20
10
-10
-60 -40 -20 0 20 40 60 80 100 120 140 160 180 200
For the data processing, two types of analyses were performed. The
analyses performed on site were limited to a preliminary assessment of soil
resistance by the CASE method, using a conservative assessment of the
local soils damping properties.
The measured force time and velocity time data digitally stored in the Pile
Driving Analyser is applied to a Smith type wave equation pile driving
program. After imputing the raw data, the CAPWAP program produces a
unique soil model by matching the measured force time and velocity time
data with computed signals. By changing six variables in the program,
namely, static resistance during driving, soil damping and soil elasticity
(quack), both on the shaft and toe of the pile a computed force time and
velocity time history can be obtained to realistically match the measured
stress wave.
In this test on P5, both types of analysis were performed. The summaries of
both field and CAPWAP analysis results are as follows.
Zayed Center, Lahore
Test Piles & Load Test Report 43
Summary of PDA Field Results
LE LP DROP RMX FMX CSX TSX EMX SET PILE
(m) (m) (m) (tonne) (tonne) (MPa) (MPa) (tonne-m) (mm) INTEGRIT
Y
P5 110 100 - -
The pile was tested with 3 hammer impact blows. The first blow indicated that the pile
settled about 18 mm with a hammer stroke of 500 mm. A subsequent blow with a stroke of
300 mm indicated that the pile had settled 16 mm and a final blow of 500 mm was used
with the pile settling 30 mm.
Conclusions:
The results obtained from the sonic echo integrity testing were considered
satisfactory and did not indicate any significant anomalies to be present
within the pile shaft. Any minor changes in pile impedance were most
likely due to the type of pile construction and changes in soil conditions at
the time of testing.
Load test results obtained for the load testing program provide load settlement
behavior of single piles. However, for working piles, the behavior of the particular
pile group is to be considered. From the prescribed settlement of pile group it is
possible to predict the expected settlement of a single pile using correlations
suggested by various researchers. One such correlation is proposed by Tomlinson,
M.J. (1977); which has been used here to determine permissible settlement of a
single pile. Because no permissible settlement of the pile group has been
prescribed by the Project Designers, the permissible settlement of single piles has
been evaluated for a range of permissible settlement of pile groups. From the
evaluated permissible settlement of single piles, the pile load test results have been
utilized to determine the allowable pile capacity for three different types of piles.
Table 6.1 and Fig. 6.1 present the proposed allowable load carrying capacities of a
1500 mm diameter and 23 m long pile for a range of permissible settlement of pile
group pile group width.
Tables 6.2 and Fig. 6.2 provided proposed allowable pile capacities for 1200 mm
diameter 18 m long ungrouted pile.
Similarly Tables 6.3 and Fig. 6.3 provided proposed allowable pile capacities for
1200 mm diameter 18 m long grouted piles respectively.
Moreover, Table 6.4 and Fig.6.4 provides individual pile capacities against given
permissible settlements of P1, P2 and P6.
22 12 50 4.2 478
75 6.3 505
100 8.3 524
125 10.4 532
150 12.5 571
22 12 50 4.2 201
75 6.3 215
100 8.3 229
125 10.4 245
150 12.5 250
280
260
240
220
200
22 12 50 4.2 375
75 6.3 437
100 8.3 466
125 10.4 491
150 12.5 500
Test pile P2
1000
Test pile P6
900
800
700
600
500
400
300
200
0 10 20 30 40 50 60
Permissible settlement of single pile (mm)
Fig. 6.4: Allowable load in compression for single piles P1, P2 and P6
against given permissible settlements.
The allowable settlement for an individual pile is 10 mm. Therefore, the individual pile
capacities are as follows;
The average shaft friction obtained from vibrating type strain gages attached with the cage
is as follows;
The average shaft friction per unit length for pile P1 = 270 kN/m.
The average shaft friction per unit length for pile P2 = 247 kN/m.
The average shaft friction per unit length for pile P6 = 233 kN/m.
As if the length of test piles P1, P2 and P6 is larger than 10 times the pile diameter
therefore it is expected that tip resistance will remain constant beyond this length. The
only change in ultimate capacity of individual pile can be linked with the change in length.
It is possible to get larger pile capacity with the increase in length of individual pile. The
capacity of each pile P1, P2 and P6 with the change in length is given in Table 6.5 and is
shown in Fig. 6.5.
Capacity
Length (Tons)
Pile Description
(m) Tip Skin
Total
resistance friction
23 147 400 547
25 147 454 601
27 147 508 655
29 147 562 709
31 147 616 763
P1
33 147 670 817
(1500 mm diameter)
35 147 724 871
37 147 778 925
39 147 832 979
41 147 886 1033
43 147 940 1087
18 72 175 247
20 72 224.4 296.4
22 72 273.8 345.8
24 72 323.2 395.2
26 72 372.6 444.6
P2
28 72 422 494
(1200 mm diameter,
without base grout) 30 72 471.4 543.4
32 72 520.8 592.8
34 72 570.2 642.2
36 72 619.6 691.6
38 72 669 741
40 72 718.4 790.4
18 155 340 495
20 155 386.6 541.6
22 155 433.2 588.2
24 155 479.8 634.8
26 155 526.4 681.4
P6
28 155 573 728
(1200 mm diameter,
with base grout) 30 155 619.6 774.6
32 155 666.2 821.2
34 155 712.8 867.8
36 155 759.4 914.4
38 155 806 961
40 155 852.6 1007.6
900
Pile P1
Pile capacity (tons)
800
700
Pile P6
600
500
Pile P2
400
300
200
10 15 20 25 30 35 40 45 50
Length of individual pile (m)
Allowable
Allowable settlement
Width of R = (settlement of pile settlement of
of individual pile
pile group group)/(settlement of single pile group given by
under same working
(m) under same working load) LERA
load (mm)
(mm)
6.2 7.8 20 2.56
8.5 9.0 20 2.22
17 11.5 20 1.74
22 12.0 20 1.67
The average shaft friction obtained from vibrating type strain gages attached with the cage
is as follows;
The average shaft friction per unit length for pile P1 = 270 kN/m.
The average shaft friction per unit length for pile P2 = 247 kN/m.
The average shaft friction per unit length for pile P6 = 233 kN/m.
It is possible to get larger pile capacity with the increase in length of individual pile.
The capacity of pile P1, P2 and P6 for the width of mat foundation of 6.2 m is given in
Table 6.7 and is shown in Fig. 6.6.
The capacity of pile P1, P2 and P6 for the width of mat foundation of 8.5 m is given in
Table 6.8 and is shown in Fig. 6.7.
The capacity of pile P1, P2 and P6 for the width of mat foundation of 17 m is given in
Table 6.9 and is shown in Fig. 6.8.
Similarly, the capacity of pile P1, P2 and P6 for the width of mat foundation of 22 m is
given in Table 6.10 and is shown in Fig. 6.9.
Pile P1
Pile capacity (tons)
750
Pile P6
500
Pile P2
250
0
15 20 25 30 35 40 45
Length of individual pile (m)
Pile P1
Pile capacity (tons)
750
Pile P6
500
Pile P2
250
0
15 20 25 30 35 40 45
Length of individual pile (m)
Pile P1
Pile capacity (tons)
750
Pile P6
500
Pile P2
250
0
15 20 25 30 35 40 45
Length of individual pile (m)
Pile P1
Pile capacity (tons)
750
500
Pile P6 Pile P2
250
0
15 20 25 30 35 40 45
Length of individual pile (m)
3. Allowable pile capacity curves have been prepared for a range of pile group
settlement and pile group widths. These curves (Fig. 6.1, 6.2 and 6.3) may
be used to determine pile capacity of selected pile type which is relevant to
the project structures. Additionally, capacity of individual piles against
settlement has been also provided in Fig.6.4.
5. Selection of a particular type of pile out of the tested types (i.e. 1500mm
diameter, 1200mm diameter without base grouting and 1200 mm diameter
with base grouting) should be based on the relative economy of
construction.
6. For the given range of pile settlements, it is ascertained that most of the
load in compression is taken by the skin friction. Therefore length of the
adopted working piles may be increased to get larger pile capacity if so
desired by the Project Designers.
2- Tomlinson, M.J. (1977), Pile Design and Construction Practice, The Grand City Press
Limited Letchworth, Hertfordshire SG6 1JS.
/ " $
Positioning of LVDTs
A1
NOTES:
A1
NOTES:
A1
NOTES:
A1
NOTES:
A3
"/ 0 '
Pile Cut-Off
In order to determine the pile cut-off (the top of the
pile), it is necessary to establish a series of variables:
a. the elevations of the top of the finished basement
floor;
b. the finishes or screeds, if any, by location;
c. the required allowances for the distribution of
building services, if any, located below the basement
floor slab;
d. the location and depth of below-slab tunnels, if any;
e. the location and depth of lift pits and the like;
f. the thickness of the floor slab;
g. the location of the top of the pile caps and their
depths; and
h. the location of the top of the concrete mats, and their
depths.
Items f., g., and h. are determined from the information
included in items a. through e., which information is beyond
our control. It is our intent, then, to tabulate pile cut-
offs at a conservatively high level. Should Turner wish us
to proceed in some other fashion, we are in need of its
input.
FINIS
"/ 0 *