page 1 of 1 Detailed Estimate
DETAILED ESTIMATE
Pre-Construction Works, Plumbing Works, Electrical Works, and Architectural Works
PROPOSED INTERIOR RENOVATION OF TOILET & BATH No. 2 AND RE-PIPING PORTION OF EXTERIOR WATERLINE
Burgos, Pilar, Bataan
Project Name and Location
LABOR / DIRECT ESTIMATED
Item DESCRIPTION QTY UNIT MATL. EQPT. UNIT DIRECT TOTAL COST UNIT
No. COST COST COST COST COST
(1) (2) (3) (4) (5a) (5b) (5c) (6) (14) (15)
(6)+(13) (14)/(3)
I. PRE-CONSTRUCTION WORKS
I-A Dismantling ( 3.00) cu.m. ( 230.60) ( 10.00) ( 240.60) ( 721.80) ( 721.80) ( 240.60)
I-B Backfill ( 2.00) cu.m. ( 15.00) ( 15.00) ( 30.00) ( 30.00) ( 15.00)
I-D Hauling and Disposal of Debris ( 1.00) lot ( 6,000.00) ( 6,000.00) ( 6,000.00) ( 6,000.00) ( 6,000.00)
I-E Daily Clean-up ( 7.00) days ( 150.00) ( 150.00) ( 1,050.00) ( 1,050.00) ( 150.00)
I-F Mobilization/Demobilization ( 1.00) lot ( 3,000.00) ( 900.00) ( 3,900.00) ( 3,900.00) ( 3,900.00) ( 3,900.00)
Sub-Total ( 7,075.00) ( 10,305.60) ( 11,701.80) ( 11,701.80)
II. ARCHITECTURAL WORK
II-A Tiling Works
1 Floor: 200x600mm Ceramic Floor Tiles and Accent Wall (Lav and WC Area) - Light Wood design ( 30.00) pc ( 100.00) ( 30.00) ( 130.00) ( 3,900.00) ( 3,900.00) ( 130.00)
2 Floor: 300x600mm Ceramic Floor Tiles (Shower Area) - Sugar Finished Tiles ( 10.00) pc ( 205.00) ( 61.50) ( 266.50) ( 2,665.00) ( 2,665.00) ( 266.50)
3 Wall: 600x600mm Ceramic Wall Tiles (Shower Area) - Marble white & gray ( 20.00) pc ( 390.00) ( 117.00) ( 507.00) ( 10,140.00) ( 10,140.00) ( 507.00)
4 Wall: 600x600mm Ceramic Wall Tiles (Lav and WC Area) - Plain white ( 15.00) pc ( 370.00) ( 111.00) ( 481.00) ( 7,215.00) ( 7,215.00) ( 481.00)
5 Tile Adhesive ( 5.00) bag ( 370.00) ( 111.00) ( 481.00) ( 2,405.00) ( 2,405.00) ( 481.00)
6 Tile Grout ( 5.00) bag ( 90.00) ( 27.00) ( 117.00) ( 585.00) ( 585.00) ( 117.00)
7 Cement and Sand ( 3.00) bag ( 370.00) ( 111.00) ( 481.00) ( 1,443.00) ( 1,443.00) ( 481.00)
II-B Doors
1 D-01 Toilet Aluminum Panel Door 0.70m x 2.10m ( 2.00) pc 4,500.00 ( 1,350.00) ( 5,850.00) ( 11,700.00) ( 11,700.00) ( 5,850.00)
2 T&B Door Tubular Lever Type Lockset ( 2.00) pc 800.00 ( 240.00) ( 1,040.00) ( 2,080.00) ( 2,080.00) ( 1,040.00)
3 4"x3"x30 Hinges ( 6.00) pcs 520.00 ( 156.00) ( 676.00) ( 4,056.00) ( 4,056.00) ( 676.00)
4 Concrete Door Jamb 0.70 x 2.10m ( 2.00) set 3,000.00 ( 900.00) ( 3,900.00) ( 7,800.00) ( 7,800.00) ( 3,900.00)
II-C Carpentry / Cabinetry
1 Hanging Cabinets/Shelves including accessories & hardware ( 1.00) set 5,000.00 ( 1,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00)
2 Lavatory Under Counter Cabinets including accessories & hardware ( 1.00) set 5,000.00 ( 1,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00)
III-D Ceiling Works and Painting
1 Ficem Board Ceiling Finish including furrings, etc ( 1.00) pcs ( 1,750.00) ( 525.00) ( 2,275.00) ( 2,275.00) ( 2,275.00) ( 2,275.00)
2 Paint and Accessories, etc ( 1.00) set 3,000.00 ( 900.00) ( 3,900.00) ( 3,900.00) ( 3,900.00) ( 3,900.00)
Sub-Total ( 7,639.50) ( 33,104.50) ( 73,164.00) ( 73,164.00)
III. PLUMBING WORK
III-A Fixtures and Accessories
1 Japanese Type Water Closet inc fittings & accessories ( 1.00) pc ( 12,320.00) ( 3,696.00) ( 16,016.00) ( 16,016.00) ( 16,016.00) ( 16,016.00)
2 Lavatory Sink ( 1.00) pc ( 3,160.00) ( 948.00) ( 4,108.00) ( 4,108.00) ( 4,108.00) ( 4,108.00)
3 Stainless Floor Drain ( 2.00) pc ( 850.00) ( 255.00) ( 1,105.00) ( 2,210.00) ( 2,210.00) ( 1,105.00)
4 Stainless Faucet ( 1.00) pc ( 3,300.00) ( 990.00) ( 4,290.00) ( 4,290.00) ( 4,290.00) ( 4,290.00)
5 Shower (Rain Type) ( 1.00) pc ( 8,200.00) ( 2,460.00) ( 10,660.00) ( 10,660.00) ( 10,660.00) ( 10,660.00)
6 Stainless Grab bar - WC ( 1.00) pc ( 3,960.00) ( 1,188.00) ( 5,148.00) ( 5,148.00) ( 5,148.00) ( 5,148.00)
7 Stainless Grab bar- Shower Area ( 2.00) pc ( 1,200.00) ( 360.00) ( 1,560.00) ( 3,120.00) ( 3,120.00) ( 1,560.00)
8 Bathroom Mirror (ordinary 1,800) with LED Lights ( 1.00) pc ( 4,000.00) ( 1,200.00) ( 5,200.00) ( 5,200.00) ( 5,200.00) ( 5,200.00)
9 Bathroom Accessories (Towel holder, Tissue Holder etc.) ( 1.00) pc ( 5,000.00) ( 1,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00)
III-B Water Line
1 PPR Pipe 3/4"Ø, ½"Ø, Gate valve, G valve Fittings, Teplon , etc ( 1.00) set ( 10,000.00) ( 3,000.00) ( 13,000.00) ( 13,000.00) ( 13,000.00) ( 13,000.00)
2 Sediment Water Filter ( 1.00) pc ( 1,750.00) ( 525.00) ( 2,275.00) ( 2,275.00) ( 2,275.00) ( 2,275.00)
Sub-Total ( 16,122.00) ( 69,862.00) ( 72,527.00) ( 72,527.00)
III. ELECTRICAL WORK
III-A Fixtures, Wiring and Accessories
1 Multi-point Water Heater ( 1.00) pc ( 8,200.00) ( 2,460.00) ( 10,660.00) ( 10,660.00) ( 10,660.00) ( 10,660.00)
2 Ceiling Exhaust Fan ( 1.00) pc ( 1,500.00) ( 450.00) ( 1,950.00) ( 1,950.00) ( 1,950.00) ( 1,950.00)
3 Two way switch (2-gang w/ LED) ( 2.00) pc ( 170.00) ( 51.00) ( 221.00) ( 442.00) ( 442.00) ( 221.00)
4 Convenience Outlet (Duplex Universal) ( 1.00) pc ( 180.00) ( 54.00) ( 234.00) ( 234.00) ( 234.00) ( 234.00)
5 Pinlight with Bulb ( 1.00) pc ( 500.00) ( 150.00) ( 650.00) ( 650.00) ( 650.00) ( 650.00)
6 Wire, Accessories and Other Misc. ( 1.00) set 5,000.00 ( 1,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00) ( 6,500.00)
Sub-Total ( 4,665.00) ( 20,215.00) ( 20,436.00) ( 20,436.00)
Total Direct Cost (Materials, Labor and Equipment) ( 177,828.80)
Labor and Equipment ( 35,501.50)
Materials Cost ( 142,327.30)
Contractor's Profit 8,891.44
Total Project Cost ( 186,720.24)