ULTICON BUILDERS, INC.
UBI Compound, Don Julian Rodriguez Ave., Maa, Davao City
Tel. (082) 282-0280 / Fax No. (082) 282-0631
September 26, 2022
Engr. Rey Peter B. Gille, D.M
Regional Director, DPWH Regional Office XI
Davao City
Thru : Engr. Aurora M. Lacasandile
Chief – Construction Division
Attention : Engr. Victor O. Bentinganan
Project Engineer III
Subject : Results for High Strain Dynamic test (P.D.A) and Crosshole – Sonic
Logging Test (CSL) – Pier 6
Contract ID: 22LO-0004 – Construction of Concrete Bridge – Davao City
Coastal Bypass Road (Bago Aplaya – Times Beach – Roxas Avenue – Sta.
Ana Wharf – R. Castillo), Package 1, Davao City
Sir:
In connection to the above-mentioned subject, in compliance to your request to submit
results for Pile Dynamic Test (PDA) for two (2) locations at Pier 6 (P6-C1 and P6-D3) and
Crosshole-Sonic Logging Test (CSL) for eight (8) locations at Pier 6 (P6-A1, P6-A2, P6-A3,
P6-B1, P6-B3, P6-C2, P6-D1, and P6-D2) tested last September 13, 2022.
Please see attached summary report for further details on the results of the conducted Pile
Dynamic Test (PDA) and Crosshole-Sonic Logging Test (CSL).
Thank you very much.
Very truly yours,
Danifel Jess D. Quiboquibo
Project Engineer
Noted:
Marionito S. Dela Cruz
Project Manager
ULTICON BUILDERS, INC.
UBI Compound, Don Julian Rodriguez Ave., Maa, Davao City
Tel. (082) 282-0280 / Fax No. (082) 282-0631
January 6, 2020
Engr. Allan S. Borromeo, CESO IV
Regional Director, DPWH Regional Office XI
Davao City
Thru : Engr. Teofila U. Tan
Chief – Planning and Design Division
Attention : Engr. Algin A. Gingatan
Engineer III, Bridge Section Chief
Subject : Request for Planning Representative
Contract ID: 18LO-0108 - Davao City Coastal Road at Jct. Davao - Cotabato
Road - Bago Aplaya – Talomo - Matina Aplaya - Roxas Avenue - Sta. Ana
Wharf - R.Castillo (Bago-Aplaya - Times Beach), Package 5, Incl. Bridge,
Davao City
Sir:
This is to inform you that we already completed bored piling works at Pier 10. As part of your
requirement, to ensure the structural integrity, soundness and resistance of drilled shafts,
Cross Hole Sonic Logging Test and High Strain Dynamic Test (PDA) must be conducted.
Thus, we will schedule the testing tomorrow, January 7 and 8, 2020.
In lieu with this, we humbly ask you to send any planning representative to witness the said
testing.
Thank you very much.
Very truly yours,
Danifel Jess D. Quiboquibo
Project Engineer
Noted:
Marionito S. Dela Cruz
Project Manager
ULTICON BUILDERS, INC.
TALOMO-MATINA BRIDGE
UBI Compound, San Nicolas Village. Matina Aplaya, Davao City
November 13, 2023
MANUEL S. GONZALEZ
EVP-CEO
Ulticon Builders, Inc.
Thru : Engr. Ruben M. Garcia
Vice President for Operations
Subject : Request for Consideration
Talomo-Matina Bridge and Sta. Ana Bidge Yard
Sir:
Good day. We have requested materials for Guardhouse on Talomo Yard as a replacement
for the old and already damaged Guardhouse which was built last 2018. The roof were only
Nipa Hut, which stands 5 years already and needed to be replaced with GI Sheets.
We requested 10 sheets of GI Sheets Corrugated Gauge 26 and 1 sheet of Plain GI
Sheet Gauge 26 under MRF No. 27680.
It was relayed to us by the Office of the Vice President for Operations that all requested
materials under Admin Cost must be budgeted in detailed. We humbly ask for your
consideration to our request.
Thank you very much.
Very truly yours,
Marionito S. Dela Cruz
Project Manager
PERSAN CONSTRUCTION INC. /ULTICON BUILDERS, INC.
(JOINT VENTURE)
UBI Compound, Don Julian Rodriguez Ave., Maa, Davao City
Tel. (082) 282-0280 / Fax No. (082) 282-0631
November 30, 2023
Engr. Juby B. Cordon
Regional Director, DPWH Regional Office XI
Davao City
Thru : Engr. Aurora M. Lacasandile
Chief – Construction Division
Attention : Engr. Victor O. Bentinganan
Project Engineer III
Subject : Rectification of Punchlist
Contract ID: 22LO-0004 – Construction of Concrete Bridge – Davao
City Coastal Bypass Road (Bago Aplaya – Times Beach – Roxas
Avenue – Sta. Ana Wharf – R. Castillo), Package 1, Davao City
Sir:
In connection to the above-mentioned project, we would like to submit herein
attached pictures of the punch list which was rectified.
For your perusal. Thank you very much.
Very truly yours,
Carlos Miguel L. Gonzalez
Authorized Managing Officer