S No.
Activity Manpower / day Machinary Remark
Mason -4 , Plate Compactor- 1,
labour-4, JCB Backhoe -0.3
1 Interlock 50m2 Charge Hand -0.3 ,
Operator -0.3
Labour -3, Excavator -1 ,
Flagman - 3, Tipper Truck -2
2 Excavation 160m3 Depth <2m Chargehand -1,
Operator -3
Labour -3, Excavator -1 ,
Flagman - 3, Tipper Truck -2
3 Excavation 120m Depth >2m
3
Chargehand -1,
Operator -3
Helper -2 , Wheel loader -1 ,
4 Disposal 800m3 Flagman-2 , Tipper Truck -1
Operator -2
Helper -4 , Plate Compactor-1
Pipe bedding Material Compaction 100m3 Flagman-1 , Jcb/Boom Loader -0.3
5 Operator -0.3x2, Tipper Truck -0.2
depth <2m 53m3 and >2m 46m3
Chargehand -0.5
labour -3 , Hand Roller Compactor -1,
Flagman-1 , plate Roller Compactor -1,
Operator -0.3x2, Water Tanker -0.4,
6 Backfilling 100m3 Depth <2m lab technician -0.5 Tipper Truck -0.2 ,
Bobcat-1
labour -3 , Hand Roller Compactor -1,
Flagman-1 , plate Roller Compactor -1,
Operator -0.3x2, Water Tanker -0.4,
7 Backfilling 100m3 Depth >2m lab technician -0.5 Tipper Truck -0.2 ,
JCB -1.
Helper -6 , Crane -1,
Flagman-1 , Vibratory Hammer -1,
Crane Operator -1, Excavator -1,
8 Shoring 14 m Formen -1, Tipper Truck -2,
Welder & Cutter -2
Helper -6 , Crane -1,
Flagman-1 , Vibratory Hammer -1,
Crane Operator -1, Excavator -1,
9 Removal of Shoring 2 0m Formen -1, Tipper Truck -2,
Welder & Cutter -2
10 Site Clearance 3000m3 Based on Site Condition