Value Addition Through Engineering Expertise
By: Shailesh Mirkar
MIVAN SHUTTERING
Definition of formwork
 It is the total system of support for freshly placed concrete
 including the mould or sheathing which contacts the
 concrete as well as all supporting members, hardware and
 bracings.
  Sometimes also called as falsework or shuttering.
Types of formwork
 Type of material used
 By the concrete element supported
 Construction Technique
 Removable or permanent
Types of formwork (Materials)
        Steel              Aluminum             Timber
                 Fabric               Plastic
Types of formwork(Member)
     Foundation             Column          Beam
                  Slab               Wall
Types of formwork(Construction Technique)
       Precast              Tunnel           Table
                 Slipform
                            Jumpform        Metal Deck
Types of formwork(Permanent or Removeable)
       Permanent Insulated              Pile liner
Concept of formwork
The pressure exerted by the concrete on the facing material.
Spacing of studs will depend on strength of facing material.
Studs will span between walings.
Studs must be designed for the loads imposed on them by the
facing material.
Spacing of walings should be chosen to suit studs of a convenient
size.
Walings will span between ties which go through to the opposite
face.
Walings must be designed for the loads imposed on them by the
studs.
Spacing of the ties should be chosen to enable walings of a
convenient size to be used.
Load in the ties is determined from this.
Economy in Formwork
 Economical design will result when spacing between
 studs, wales and ties increase progressively.
 The plan of the building should imply a minimum number
 of variations in the size of rooms, floor area, etc. to permit
 reuse of the formwork repeatedly.
 Design should be perfect to use slender sections only in
 the most economical way.
 Minimum changes to be made to enable reuse of the
 material many times. The quantity of surface finish
 depends on the quality of the formwork.
Formwork requirements
 To obtain required size, shape, finish, position and
 alignment of concrete members.
 Enough load carrying/transferring capacity to take
 pressure or weight of fresh concrete at any other loads,
 without distortion, deflection, leakage, failure or danger to
 workmen.
 Design for quick erection and removal.
 Should be Tight & rigid to prevent loss of mortar.
 Should be appropriate to method of placing/compacting.
Formwork requirements
 Should be made of made of suitable material to suit
 thermal requirements.
 Should provide concrete of the correct shape and surface
 finish.
  Should withstand without excessive deflection, worst
 combination of self weight, rebar & concrete weight
 besides all loads.
 Should be capable of easily striking without damaging
 concrete.
Formwork requirements
 Construction of formwork should permit removal of
 various parts in desired sequences without damage to the
 concrete.
 The material of the formwork should be cheap, readily
 available, and should be suitable for reuse
 Capable of being cleaned or coated if necessary,
 immediately prior to casting.
 Able to provide temporary openings where required.
 It should be as light as possible
Importance of Formwork
 Design Team                    To ensure final form as per design intent
 Planning team                  To plan timelines as per type of formwork
 QS & Budgeting team            To estimate precise quantity and cost
 Contracts & procurement team   To procure optimum sets of formwork
 Quality control team           To achieve desired quality
 Execution team                 To achieve minimum slab cycle
 Safety team                    To implement safety measures
 Bill certification team        To measure actual progress
History & development of Aluminum Formwork
 W.J. Malone developed aluminum formwork system in 1970
 for developing countries
 Used gulf countries like Iraq & Iran
 Later in 1990, the Mivan Company Ltd, a Malaysian firm
 started manufacturing these formworks, hence giving the
 name 'Mivan Technology’.
 Mivan technology got introduced in India in 2001-02
 L&T was the first company to use it in 2003
History & development of Aluminum Formwork
   MIVAN
   KUMKANG
   S FORM
   DURAND
   KNEST
   MFE
‘What’ & ‘Why’ of Aluform or Mivan Formwork
 Cost effective cast in situ or cast in place construction
 Casting the whole slab, beam, wall, column at one go
 Easily withstand high pressure from freshly poured concrete.
 Load carrying capacity – 7-8 Tonnes/Sqm(60KN/Sqm-safe
 working load)
 Highly suitable for load bearing wall construction
 Fulfills increased demands of rapid urbanization
 Controls speed and quality of construction
‘What’ & ‘Why’ of Aluform or Mivan Formwork
 Increases usable floor space(Carpet area)
 Eliminates need for external and internal plaster
 Flexible, lightweight and easy to install.
 Easy to assemble, safety in built system
 A semi-skilled labour force is adequate
 Less joints so less leakage
Comparison of Aluminum Formwork vs Conventional Formwork
Sl.                                    Aluminum
          Characteristics                                     Conventional Formwork
No.                                 Formwork(Mivan)
1      Speed of construction        4-6 days cycle time       Min. 21 days cycle time
                                  Excellent. Plastering not
2     Quality of surface finish                               Ok. Plastering required
                                         Required
          Pre-planning of
3                                        Required                  Not required
             formwork
4      Type of construction         Cast in situ cellular        Simple RCC frame
5      Wastage of formwork               Very less                Relatively more
6            Accuracy                 More accurate           Relatively less accurate
      Coordination with other
7                                        Essential            Not necessarily required
             agencies
Comparison of Aluminum Formwork vs Conventional Formwork
Sl.                                 Aluminum
          Characteristics                              Conventional Formwork
No.                              Formwork(Mivan)
           Resistance to
8                                      Good                 Relatively less
            earthquake
      Removing of slab forms
9                                     Possible               Not possible
      without removing props
10         Re-use value            250-300 times           Max 50-60 times
       Sustainability for high
11                                    Suitable               Not suitable
               rise
12       Initial Investment             High                     Less
                                 Economical for mass
13           Economy                                   Economical on small scale
                                      housing
‘Physical properties of Mivan Formwork
 Basic element is the panel
 Extruded Aluminum rail section, welded to Aluminum
 sheet confirming to IS 733 - 1983
 6061(T6) - heat-treated aluminum alloy that has good
 strength and corrosion resistance
 Thickness – 4mm thk.
 Weight – 18-20 Kg per Sqm.
 Colour – Silver white
‘Components of Mivan Formwork
 Wall Components
 Beam Components
 Slab Components
‘Wall Components
                                                 Rocker                     Wall tie
   Wall panel
It forms the face of                           It is a supporting         It connects
      the wall.           External Corner        component of            internal and
      20 -25 Kg                                wall. It is L-shaped   external wall panel
                       It forms the external      panel having          and maintains
                            corner of the       allotment holes        width in between
                         formwork system.          for stub pin.
 ‘Wall Components
                                                                              Wedge & Pins, Long pin
     Internal Corner
                                          Kicker Bolt                       It helps in joining two wall
  It connects two pieces of
vertical formwork pieces at     It forms the wall face at the top of the   panels. It helps in joining two
their exterior intersections.   panels and acts as a ledge to support.                 joints.
‘Beam Components
    Beam panel               Beam prop head        Beam soffit Panel          Beam soffit Bulkhead
   It forms the side of
                            It forms the soffit
    the beams. It is a                               It supports the soffit    It is the bulkhead
                          beam. It is a V-shaped
        rectangular                                    beam. It is a plain     for beam. It carries
                               head for easy
   structure and is cut                            rectangular structure of    most of the bulk
                             dislodging of the
  according to the size                                   aluminum.            load.
                                 formwork.
       of the beam.
‘Slab/deck Components
    Slab panel                  Slab prop            Prop Length               Middle Beam
       It forms the                                It is the length of the   It supports the
  horizontal surface       It forms a V-shaped
                          prop head. It supports     prop. length of the     middle portion
 for casting of slabs.                                       slab.           of the beam. It
 It is built for proper    the deck and bears
                           the load coming on                                   holds the
  safety of workers.                                                          concrete 9 kg
            13Kg           the deck panel. 2kg
 ‘Slab/deck Components
     Soffit Length               Slab Beam Bar               External Soffit Corner         Internal Soffit Corner
                                                                                                It forms the vertical
 It provides support to the                                                                  internal corner between
                              It is the deck for the beam.   It forms the external corner
 edge of the deck panels at                                                                 the walls and the beams,
                               This component supports        between the components
their perimeter of the room                                                                  slabs, and the horizontal
                              the deck and beam. 0.8 Kg
           15 Kg.                                                                           internal cornice between
                                                                                              the walls and the beam
                                                                                                slabs and the beam
                                                                                                       soffit.
‘Staircase Components
      Special      Step Panel                    Step Angle Panel
                                Step Cap Panel
  staircase step
       panel
‘Tools and accessories
      Working Bench
      Panel puller
      Claw Hammer
      Tie rod
      Hole bar
      Tie puller, Tie ejector,Tie
      Breaker
      Measuring tape
‘Tools and accessories
      Al-New clamp
      Bracing
      Adjustable Bracket
      Water barrier
‘Construction using MIVAN
   Design & Manufacturing
   Factory Inspection
   Dispatch & receipt
   Drawing reading and installation of Dry Mock up
   Concreting
   De-shuttering and shifting
‘Design of MIVAN shuttering
   Design based on - IS 14687 -1999 – Clause 5.2
   IS 800-2007 & IS 2075- 1964
   IS 456
‘Design of MIVAN shuttering
Annex B of IS 14687 - 1999 mentions about information to be
supplied by manufacturer of proprietary formwork systems.
   Identification, description and intended use of components
   Drawings of major components giving dimensions, weight, locating
   & fixing arrangements
   Details of material used
   Modifications for extended or additional uses and limitations for
   every use
‘Design of MIVAN shuttering
 Strength details of components and assemblies as given below:
    Characteristic failure load
    Maximum working load for different conditions
    Deflections and camber at maximum working load
    Conditions of limiting deflection
    Assumed working stresses and material properties
    Section properties
    Design of bracing against lateral load
 Maximum allowable wear and tear and defects due to long usage
 and life
‘Design of MIVAN shuttering
   Erection method, erection stages, erection tools, precautions and
   test on complete structure
   Method of stripping and releasing system
   Suggested method of stacking and maintenance of system
‘Manufacturing of MIVAN
     Melting
     Billets
     Billets Cutting
     Moulding
     Extruding
     Cutting
     Punching
     Auto welding
     Coating
‘Manufacturing of MIVAN
‘Factory Inspection of MIVAN
     Pre-dispatch activity
        Straightness
        Sizes
        Joints and welding of panels
        Joinery slots (side faces and wedge slots)
        Right angles of fixing edges
        Surface uniformity
        Coding as per design
        Wall tie slots locations and sizes
        Fixing rigidity
        Uniformity of installed panels
‘Receipt of MIVAN
Demarcation of Stock Yard and set up for the unloading of the formwork material
and accessories
This Stock Yard location close proximity or within the compound of the project
work site, properly fenced up and secured.
Upon arrival of formwork panels at Project Site, Site personnel shall ensure that
the panels are stacked and stored according to sizes and marking using proper
separator such as pallets for easy identification and allocation for subsequent
distribution.
Dry Mockup should be assembled as per schemes at factory; this will eliminate
the usual problematic discrepancies of odd size panels which need to be
fabricated at project site
‘Dispatch and receipt of MIVAN
‘Dispatch and receipt of MIVAN
‘Drawings of MIVAN & Assembly
 Wall panel Layout,
 Slab Panel Layout,
 Starter Block Layout,
 Corner Layouts,
 Beam Panel Layout,
 Soffit Layout,
 Staircase Layout,
 Bracket and Soldier layout,
 Miscellaneous Layout which includes sunken portion, upstand portion etc,
 Elevations and sections drawings indicating the location of formwork panels and
 component, Typical Fixing Detail drawings, Location of Box outs and Transfer Box out
 drawings for transfer of Formwork, etc.
‘MIVAN Drawings
                  Mivan Unit Layout
MIVAN Drawings
                 Mivan Sub-unit Layout
MIVAN Drawings
                 Deck Layout
‘MIVAN Drawings
                  Prop Layout
‘MIVAN Drawings
Mivan drawings
                      Wall Layout
        Beam Layout
Mivan drawings
                             Beam Soffit Layout
          Beam side Layout
Mivan drawings
                         Kicker Layout
         Corner Layout
Mivan drawings
                                Wall elevation Layout
         Miscellaneous Layout
Mivan drawings
      Wall elevation Layout
‘Assembly of MIVAN
 Setting Up Level & Marking of Position
 Checking on form panels( Cleaning of form)
 Applying form release agent. For best results
    Uniform application
    Immediately after stripping
    Prevent contact with rebar
 Installing rebar and MEP fixtures( not necessary for dry
 mock up)
 Fixing cover blocks
 Positioning of outlets for electrical switch boxes
‘Assembly of MIVAN
Install external corner
Install external wall panels as per sequence
Install internal corner
Install internal wall panels as per sequence
Install wall tie with sleeve and PVC cover
Install slab corner
Connect prop length and prop head together for
beam and slab support.(Beam splice bar)
Install beam side panel
Commence to assemble the slab panels
Install beam bottoms panel
Follow sequence of pins installation
‘Assembly of MIVAN
   Install kicker
   Install drop frame, transfer box
   Assemble external working bracket
   Number all panels as per sequence
   Check verticality
‘Assembly of MIVAN
‘Assembly of MIVAN
‘Assembly of MIVAN
         Slab corner
        Internal
‘Typical MIVAN Assembly
‘Typical MIVAN Assembly
‘Assembly of Staircase
              Installation of kicker     Installation of soffit length
      Installation of Step Panel & SSP   Installation of step angles
‘Typical MIVAN Assembly
‘Concreting
Pre-pour check
    Ensure that the position of the walls and column formwork are in accordance
    with the set up marking.
    Check to ensure correct spacing of props for slab formwork.
    Check the verticality and horizontality level of the wall and slab panels
    respectively.
    Ensure that all pins, wedges and ties are properly secured and tightened.
    Re-check the opening such as door and window panels are correct.
    Re-check all propping stands to ensure its height are in accordance to
    drawings.
    Adequate bracing (if necessary) to ensure stability. Ensure cover blocks are
    placed correctly.
    Check for room dimensions.
‘Concreting
During pour check
   Ensure site coordinators are available and on stand-by
   during the concreting process
   Ensure that concrete pouring is distributed evenly
   throughout the wall sections before commencing to
   cast the slab level areas.
   Recheck the areas whenever cement slurry leakage is
   noted to determine the cause of it. Remedy work
   should be done immediately to ensure the concreting
   process is not affected.
   During concreting, always ensure that immediate step is
   taken to remove / clean all the excess concrete that is
   stuck on the back of the formwork panels.
Deshuttering and shifting
After 12 hours, remove the Internal Wall panels by
knocking out the wedges and pins.
After removing the External Wall Forms (kicker should       Starter
remain undisturbed), the dismantled wall forms are
                                                            Block
moved to upper floor.
After removing the Wall Panels, proceed to the Slab       Super
Panels after 36 hours by removing the long pins and
                                                          plate
wedges on the joint bars the end and middle beam
section.
Upon removing the Aluspans Mid Beams and Alu span
cantilevers End Beams, the prop shall remain
undisturbed during this process to support the concrete
slab.
Deshuttering and shifting
 Proceed to strip the Slab Panels and transfer to the next
 level according to the designated area and installation
 sequence.
 Strip the Slab Corner.
 Pull out Wall flat Tie using Wall Tie puller and remove
 the Wall tie sleeve using Nose player.
 When the cube tests show that the slab concrete is
 sufficiently strong, the prop together with the prophets
 are removed and transferred to the next level.
Safety Measures
The external working brackets/platforms or scaffoldings
should not be used to stack materials or equipment.
Minimize the working heights for persons performing the
assembly and dismantling formwork.
Mixing of formwork components should be avoided to
prevent unsafe installation such as mixing pins and braces
which may lead to collapse of the formwork.
Do not allow drop stripping of formwork as it is an unsafe
practice.
Safety Measures
Partially assembled or dismantled formwork should be
secured during break time to prevent against overturning or
collapsing due to strong wind or accidentally /
unintentionally knock over by workers.
Protruding flat ties or projecting nails should be removed
immediately with appropriate tools at dismantling stage.
Use of personal protective equipment by all persons working
at work areas (such as safety hardness, safety helmets, eye
protection etc) should be strictly implemented.
‘Team structure
      Engineering team
      Formwork & material shifting team
      Surveyor
      Foreman and formwork team
      Rebar & MEP team
      Concreting
      Quality & safety team as per requirement
Daywise activities
      Day 1      Grid Line marking, Thesi work, rebar of
                 column & walls
      Day 2      MEP fixures installation, Column & Wall
                 panel erection
      Day 3
                 Column & Wall panel erection, deck slab
      Day 4      installation
                 Rebar of beam and slab,
      Day 5
                 Leveling work Electrical conduting work,
      Day 6
                 Grid line checking, verticality check,
      Day 7      Quality check, Concreting work
Typical Slab cycle
                                        TIME >>> DAYS                                    0        1             2             3             4              5               6               7
                                       TIME >>> HOURS                                    0   12       24   36       48   60       72   84       96   108       120   132       144   156       168
1                                 Concrete of previous pour
2                         Dismantling of brackets from below slab
3            De shuttering of recently casted slab's beam sides for bracket fixing
4                             Bracket fixing start on casted slab
5                        Grid line marking on recently casted slab
6                       Scaffold erection for column erection start
     Platform fixing on bracket & simultaneously start the vertical scaffold extension
7
                                      for net fixing
8                         Deshuttering & shifting of wall panels
9             Erection of vertical scaffold extension & net fixing complete.
10                         Reinforcement of all vertical element
11                               Form work fixing for walls
12                          Form work fixing for decking of slab
13                               Beam reinforcement work
14                                 Levelling work of slab
15                                Slab reinforcement work
16                     Beam out side shuttering + supporting kicker
17                                      Pour concrete
Measures to improve cycle time
 Use of welded wire mesh
 Early removal of props          using
 concrete maturity method.
 Prefabricated frame for plumbing
 lines
Common defects in Mivan
 Cracks due to shrinkage of concrete are likely to appear.
    Loss of capillary water
 honey-combing is commonly seen problem.
    Due to less thickness of wall
    Leakage of grout
    Due to complexity and high density of reinforcement at corners
    segregation occurs.
 Bulging
    Inadequate support
    Use of old form
‘Disadvantages / Limitations of Mivan Formwork
 Aluminum Formwork have high-cost value, so its one-time
 investment is quite difficult.
 It rental cost is also higher. Unsuitable for small work
 Its repair is impossible after the deformation.
 Its initial setup takes more time compared to steel formwork.
 Modifications/alterations are not possible.
 Segregation and stocking require more space
 Very less or in fact, no scope for future modifications and
 alterations.
‘Disadvantages / Limitations of Mivan Formwork
 The shear walls may cause higher generation of heat of
 hydration.
 Contraction cracks are major problem for mivan formwork.
 Even though it provides a smoother finish, the lines will
 often be visible because of the minuscule components used
 in construction.
                        GEM Values
         CUSTOMER FOCUS                    INTEGRITY
                              OWNERSHIP
       VALUE CREATION
       THROUGH                             RESPECT FOR INDIVIDUAL
       COMPETENCE
                                                                  For Enquiry:     www.gemengserv.com
REGISTERED OFFICE:
                                                                             Shailesh Mirkar – VP Operations
   GEM Engserv, A-210, The Great Eastern Chambers, Plot No. 28,
   Sector 11, CBD Belapur, Navi Mumbai 400614                             +91 99300 03510
   NCR Regional Office coming up soon                                     Shailesh.mirkar@gemengserv.com