January 2019
                                                              i
                                      Disclaimer
This report is based on the data provided by the relevant representative of the concerned
departments. DG M&E disclaims, expressed or implied, as to the accuracy or completeness
of any information reported herein, disclaims and makes no pledge that the information in
this document will fulfil any of your particular purposes or needs. DG M&E does not
undertake to assure the performance of any individual project or services by virtue of this
report.
In dissemination and making this document available, DG M&E is not undertaking to render
professional or other services for or on behalf of any person or entity, nor is DG M&E
undertaking to perform any duty owed by any person or entity to someone else. Anyone
using this document should rely on his or her own independent judgment or as appropriate,
seek the advice of a competent professional in determining the exercise of reasonable care
in any given circumstances.
DG M&E does not undertake police or enforce compliance with the contents of this
document. DG M&E does not certify, test, or inspect products, designs, or installations for
safety or health purposes. Any other statement of compliance with any health or safety-
related information in this document shall not be attributable to DG M&E and is solely the
responsibility of the relevant stakeholders.
                               PROJECT MONITORING REPORT
                                                                                     ADP
   1. Project    Remodeling of Existing Bio-Medical Workshops at
                                                                                   2017-18
      Title:     Lahore
                                                                                   GS# 1891
   2. Sector:                         Health
                                                                                                 1
15. Project Objectives:
                                             Fully Achieved (100%), Substantially Achieved
                                                 (<100%) Partially Achieved (50%), Not
     Overall Project Objectives
                                                           Achieved (< 50%)
                                             Results       Justification
1. To accommodate the increasing             Partially     The Biomedical Equipment
   workload                                  Achieved      Resource System of BERC is
                                                           providing repair & maintenance
                                                           services for the biomedical
                                                           equipment in DHQs and THQs of
                                                           Punjab since November 2017.
                                                           During the last 11 months 4147
                                                           complains were registered at
                                                           Centralized Complaint management
                                                           center of BERC.
2. To speed up the process of                Partially     − All complaints have been logged on
   maintenance for biomedical                Achieved        centralized complaint management
   equipment.                                                center of BERC.
                                                           − Work Orders have been assigned
                                                             on same day.
                                                           − Engineers visit the health facility
                                                             on next day to resolve the issues at
                                                             site.
3. To include new, precise and efficient     Substantially Mandatory test Equipment (49 out
   equipment having new analytical           Achieved      of 57) was procured.
   techniques                                                (Complete list is attached in Annexure: B)
4. Up-Gradation & Re-Strengthening of        Substantially BERC has procured most of
   existing biomedical equipment             Achieved      dedicated tools for repair &
   repair facilities and the calibration &                 maintenance of the bio-Medical
   testing system through addition of                      Equipment (49 out of total 57).
   high tech. & sophisticated equipment                      (Complete list attached as Annexure: B)
   along with provisions of quality tools
   and reference standards.
5. To enhance the strength and               Partially       A well-designed and equipped In-
   technical skill of the staff through      Achieved        house training center has been
   ongoing orientation and training                          established at BERC. This center has
   programs in the country and abroad.                       initiated training sessions for in
                                                             house technical staff on repair &
                                                             maintenance techniques of bio-
                                                             medical equipment.
6. To customize the working of               Partially       Computerized Maintenance
   biomedical test equipment                 Achieved        Management System (CMMS) was
   Laboratory through biomedical                             procured from another PC-I*.
   equipment inventory management                             − Equipment inventory was
   software and local area networking                             updated on the web-based
   (LAN).                                                         software. Quick Response (QR)
                                                                  Tagging placed on equipment
                                                                  and android application was
                                                                  developed for scanning of QR
                                                                                                          2
                                                                     Code and complaint registration
                                                                   − Complaints were also logged
                                                                     through android based
                                                                     application.
                                                               *(Biomedical Equipment Resource Center
                                                                for P&SHC Department.
7. To perform the PPM (Periodic & Partially                     The process of hiring of technical
   Preventive Maintenance), CM          Achieved                manpower and procurement of
   (Corrective Maintenance),                                    mobile workshops was partially
   Inspections, Sport Procurements,
                                                                completed.
   Standardization of biomedical
   equipment specification, Contract                            BERC team was regularly
   Management of whole biomedical                               performing these tasks i.e. PPM, CM,
   equipment in Punjab, Validation /                            Calibration and Training for the
   accreditations of Biomedical                                 operations & maintenance of
   Equipment through Calibration,                               biomedical equipment in DHQs and
   Certification & training of                                  THQs of Punjab
                                                                (List of HR is attached in Annexure: F)
   Operational & Maintenance human
   resource in public sector hospitals.
                                                                                                          3
18. Physical Targets and Performance (Civil Work):
                                 Fully Completed (100%), Substantially Completed
 Physical Targets &                                   (<100%)
                         Unit
   Achievements                 Partially Completed (50%), Not Completed (< 50%)
                                  Results                     Remarks:
                                            Physical Progress: 85%
Replacement of                 Partially
                       01 Job               Electrical wiring replaced however main
electric wiring                Completed
                                            power cable & DBs were pending
Shifting of WAPDA                           Physical Progress: 0%
meter                          Not
                       01 Job               Request submitted to LESCO for shifting
                               Completed
                                            /installation of Meters
Rebuilding of
                               Partially    Physical Progress: 50%
Windows, Doors          01Job
                               Completed Work was under progress
and main Gates
Sewerage Disposal              Partially    Physical Progress: 80%
System & Supply        01 Job Completed Civil work of Disposal tank completed but
line Built                                  motor was not installed
Water Storage Tank             Partially    Physical Progress: 80%
& piping               01 Job Completed OHR Constructed the installation of motor
                                            was remaining.
Flooring of            01 Job Partially
                                            Physical Progress: 70%
Workshop                       Completed
Roof Treatment         01 Job Partially     Physical Progress: 70%
                               Completed
Construction of                Partially
                                            Physical Progress: 76%
boundary wall 9’’              Completed
                       640 Rft              Height of boundary wall was found 6 ft
thick and 8ft Height
                                            height also fencing work was not started.
with fencing
Construction of                Not          Physical Progress: 00%
Parking shed           01 Job
                               Completed Work not started yet
Road Carpeting
                               Not          Physical Progress: 00%
from main gate to     01 Job
                               Completed    Work not started yet
workshop
Carpeting of roads             Not          Physical Progress: 00%
inside workshop       01 job
                               Completed    Work not started yet
Construction of                Not          Physical Progress: 00%
Generator room        01 Job
                               Completed    Work not started yet
Renovation of Wash             Partially    Physical Progress: 33%
                      03 Nos
room                           Completed    One was renovated rest two were pending
False ceiling of               Partially    Physical Progress: 10%
workshop              01 Job
                               Completed    Work in progress
                                                                                      4
19. Quality of the Project Activities:
Quality of Procurement (if any)
Poor:                 Average: √               Good:                 Excellent:
Quality of Civil Work (if any)
Poor:              Average:    √       Good:                        Excellent:
Quality of operation and project implementation
Poor:            Average:           Good: √            Very Good:           Excellent:
23. Observations:
DGM&E team has conducted monitoring of the project considering all factors that affect
project design, execution, implementation and operations. During the monitoring, project
purpose & design, strategic planning & project results were analyzed and accordingly the
monitoring report was prepared. Some specific observations are mentioned below.
   1. The Biomedical Equipment Resource System of BERC has been providing repair &
      maintenance services for the medical equipment in DHQs and THQs of Punjab since
      November 2017. A networked Computerized Maintenance Management System
      (CMMS) and Customer Centre were used to manage the system and to ensure uptime
      of 95% of all medical equipment in DHQs and THQs.
                                                                                          5
2. According to revised PC-I, the fund release (23%) and expenditure (18%) were quite
   low against the total cost of the project. However, in terms of project activities, the
   project output or progress was about 60%-70%. To address this issue, interview was
   conducted with Provincial Coordinator of BERC. It transpired that a separate PC-I
   ‘Biomedical Equipment Resource Center for Primary & Secondary Healthcare
   Department’ with the Project cost of 56.9 million was submitted and approved in
   2015-2016. Therefore, available funds were used for various project activities from
   both projects/PC-Is. To determine the scope of both projects/PC-Is, DGM&E team
   made a comparative review of both PC-I and found number of repetitions under
   various heads including human resource, procurement of software, lab, IT and office
   equipment.
10 19 26 16 13 15 16 11 14 15
272 483 672 416 327 395 404 287 359 402
          Nov-17 Dec-17 Jan-18       Feb-18 Mar-18 Apr-18        May-18    Jun-18     Jul-18   Aug-18
         Number of Calls per Month   Number of Calls per day *   *Calculated as 26 working days in month
•   The BERC office was located at a rented place in Lahore, where an expensive office
    interior designing, furnishing and furniture was placed/in-use (see pictures at
    Annex-A). Given the rented temporary place, this appeared to be an exaggerated use
    of project funds.
                                                                                                           6
Civil Work
   1.       The physical progress of the civil work of the project was about 55%, however
            financial progress was 53%. The project is behind the planned schedule/planned
            due to shortage of funds.
   2.       The project was over budget as revised project cost (Rs. 10 Million) was greater
            than the original approved project cost (Rs. 27.186 Million). The project was
            revised due to additional scope.
   3.       OHR was constructed at site but the foundation of the steel stair of OHR was not
            constructed as shown in Figure No. 11
4. The skirting at some sections was not fixed properly as shown in figure No 12.
   5.       It was planned to construct 640 Rft boundary wall, however 490 Rft boundary
            wall was constructed till the time of visit. Moreover, the height of boundary wall
            was found 6ft at site but originally it was planned to construct 8ft height
            Boundary wall as shown in figure No 14 &15.
18. Suggestions/Recommendations:
On the basis of assessment of DGM&E Team, some recommendations are outlined below;
   •     Objective monitoring and evaluation process requires that specific objectives of any
        project are linked exclusively to activities of the said project. In view of the fact that
        there were two PC-Is and there were substantial redundancies between them, it was
        important to monitor and evaluate these documents concurrently. It is suggested that
        future cases of such nature may be handled accordingly.
   •    Regarding low call volume/work load, compared to number of people working at the
        BERC Call Centre. It is important to critically appraise such proposals in future which
        may sound intuitive in present-day context, but are less efficient and strip the
        exchequer of scarce resources. Similarly, investment in office interior designing and
        furnishing vs. project activities also needs to be rationalized and prioritized.
Civil Work
   •    Reference to the observation No 1, Requisite funds for completion of the project may
        be provided for timely completion of the project.
                                                                                          7
•   Reference to the Observation No. 2, the project should be well planned & the major
    activities should be performed as per schedule to avoid any alteration in the project
    cost.
• Reference to the observation no 5, the executing agency must clarify in this mater
                                                                                         8
ANNEXURE A: PICTORAL REFRENCE
                                                     9
Figure 2 : Meeting of DGM&E team with Provincial Coordinator of BERC in his office
                                                                                     10
Figure 4 : Call Center in BERC
                                 11
Civil Work
                                                               12
Fig 11: Step of OHR                           Fig 12: Improper Filling of Skirting
Fig 13: View Electrical panel need to shift Fig 14: Remaining portion of boundary wall
outside the room
                                                                                         13
ANNEXURE B: Biomedical Lab Tools Testing Repairing and Calibration Equipment
                                       Quantity   Total
                                                          Quantity Functional
   Sr.#         Name of Item           planned Quantity                                  Remarks
                                                          Verified   Status
                                        in PC-I purchased
          Toolkit for
   1                                     27         20       20    Functional
          Engineers/Technicians
   2      Laptop for technical Staff     28         28       28    Functional
                                       Quantity   Total
               Name of General                            Quantity Functional
   Sr.#                                planned Quantity                                  Remarks
                 Equipment                                Verified   Status
                                        in PC-I purchased
   1      Generator 100KVA                1         1         1     Installed                 -
   2      Photocopier                     1         1         1    Functional                 -
                                                                                Due to non-availability of the
   3      Vacuum cleaner                  1         0         0       N/A
                                                                                           funds.
   4      Servo control stabilizer 5      2         0         0       N/A                  ---do---
          KVA
          Servo control Stabilizer
   5                                      4         0         0       N/A                 ---do---
          2KVA
          UPS 10KVA with
   6                                      1         0         0       N/A                 ---do---
          maintenance free batteries
   7      Fax machine plane paper         1         0         0       N/A                 ---do---
          Bio Metric Attendee
   8      system with software            1         0         0       N/A                 ---do---
          printer from PITB
          Telephone Exchange 10
   9                                      1         0         0       N/A                 ---do---
          lines Ext
   10     CCTV System complete          1 set       0         0       N/A                 ---do---
   11     Security Scanner              1 set       0         0       N/A                 ---do---
          Air conditions Split
   12                                     5         0         0       N/A                 ---do---
          inverter type Hot & Cool
Total 57 28 28
                                                                                                  14
ANNEXURE D: MAINTENANCE MANAGEMENT SOFTWARE, HARDWARE, COMPUTERS & ETC
                               Quantity   Total
                                                  Quantity Functional
  Sr.# Name of Equipment/Items planned Quantity                                         Remarks
                                                  Verified   Status
                                in PC-I purchased
          Laptop Computers with                                                 Funds
  1                                        7     0
          Window Branded
          Desk top Computers with                                               -
  2                                        4     4
          windows Branded
          Multimedia For Training                                               Funds
  3                                        1     0
          & Conferences
  4       Printers                         2     2                              -
  5       Scanners                         2     2                              -
          UPS 1KVA with                                                         Funds
  6       maintenance free                 3     0
          batteries
          Networking Hardware            01                                     Funds
  7                                            0
          with software                Package
          Inventory control,                                                    Funds
          Human resource &               01
  8       Financial management                 0
                                       Package
          Software with
          hardware server
          Audio system for                                                      Funds
  9                                       01     0
          conference & Class room
          Video Link System for                                                 Funds
  10      workshops, training             01     0
          ETC
          Maintenance Management                                                Funds
  11      Call Center and tracking        01     0
          System Software &
          Hardware
          International software for                                            Funds
          Biomedical Equipment
  12      Maintenance Management          01     0
          System (WHO
          recommended)
Total 27 8
                                       Quantity   Total
                                                          Quantity Functional
  Sr. #          FURNITURE             planned Quantity                                 Remarks
                                                          Verified   Status
                                        in PC-I purchased
   4.    Divisional Engineers                 03           03           -
         District / Clinical
   5.                                         09           05          04
         Engineers
         Associate Engineers /
   6.                                         09           05          04
         Technicians
   7.    Network Administrator                01           01           -
   8.    Data Analyst                         02            -          02
9. Drivers 5 - 5
Total 32 15 17
                                                                                         16
ANNEXURE G: Training and R & D
    Sr.                                                                    Current
              Description/Details of Proposed Trainings
     #                                                                     Progress
   1.     Operational trainings for engineers and operational
                                                                 Training Conducted
          staff of various equipment being used in hospitals
   2.     Preventive and periodic maintenance training (PPM)     Training Conducted
   3.     Corrective and downtime equipment maintenance          Training Conducted
   4.     DDO training for relevant officers of BERC.            Training Pending
   5.     PPRA Procurement, standardization and inspections
                                                                 Training pending
          training
   6.     To develop manual for above trainings                  In process
   7.     Specialized Advance training of Biomedical Equipment
                                                                 Training Conducted
          and WHO recommended software
   8.     To develop a complete protocol for repair &            SOP’s are under development
          maintenance of bio medical                             progress.
                                                                                    17
© Directorate General of Monitoring and Evaluation, Planning and Development Department, Govt. of the Punjab
(January, 2019)