Contents
PAGE                                                      PAGE
         Articles of Agreement                        5    5.5     Nominated Supply Contract
                                                                   documents
         Attestation                                  8    5.6    Further drawings , details ,
                                                                  descriptive schedules and similar
         The General Conditions                                   documents
                                                           5.7    Documents to be provided to
 1       Interpretation and definitions               9           Contractor on time
                                                           5.8    Electronic copies of drawings
 1 .1   Governing law                                      5.9    Documents on Site
 1.2    Singular , plur剖, masculine and                    5.10   Return of drawings
       feminine                                            5.11   Submission of manuals and
 1.3   Method of reference to clauses and                         assignment of warranties
       Articles                                           5.12    Submission of as built drawings
                                                                                     >
 1.4   Articles of Agreement , Conditions                 5.13    Li mits to use of documents
       and Appendix to be read as a whole                 5.14    Issue of Architect's certificates
 1.5   Clauses divided into sub-clauses to                5.15    Copy of notice to be given
       be read as a whole                                         to Employer
 1.6   Definitions
 1.7 The role of the Engineer                             6       Statutory obligations                     24
 1.8   Sectional completion of the Works
 1.9   Communications                                     6.1     Statutory Requirements
 1.10 Notices of default or determination                 6.2     Compliance with the Statutory
       to be sent by special delivery                             Requirements
 1 .11 Parties to act reasonably and                      6.3     Fees or charges
       expeditiously                                      6 .4    Statutory undertakers and utility
                                                                  companles
2       Contractor's obligations                     16
                                                          7       Setting out the Works                     25
2.1     Contractor's obligations
2.2     Contractor's responsibility                               Setting out and levels
2.3     Contractor's skill and care
2.4     Contractor to inform Architect if                 8       Materials , goods , workmanship
        he finds ambiguities in documents                         and work                                  25
3       Master programme                             17   8.1     Types , standards and quality
                                                          8.2     Inspection and tests
3.1     Master programme to be submitted                  8.3     Materials , goods , workmanship
3.2     Programmes to be updated                                  or work not in accordance with
3.3     Programme and other documents                             Contract
        not to be documents forming                       8 .4    Rectifying defects
        the Contract                                      8.5     Dismissal from the Works
4       Architect's instructions                     19   9       Intellectual   prope付y   rights           27
4.1     Architect may issue instructions up to            9.1     Intellectual prope付y in design of the
        the issue of the Final Certificate                        Works
4 .2    Architect to issue instructions in writing        9.2     Intellectual property in materials and
4.3     Compliance with Architect's                               goods
        instructions                                      9.3     Intellectual property i 們 plant and
4 .4    Contractor to carry out preventative                      equipment
        work                                              9 .4    Payment of royalties included in
                                                                  Valuation
5       Documents forming the Contract
        and other documents                          20   10      Contractor's site management team         27
5.1     The documents forming the Contract                10.1    Contractor's site management team
5.2     Architect and Quantity Surveyor to                10.2    Construction manager
        keep documents available
5.3     Copies of documents for                           11      Access for the Architect to the
        Contractor                                                Works                                     28
5 .4    Nominated Sub-Contract
        documents                                                 Contractor to give access
                                                  PAGE                                                          PAGE
12     Architect's representative                       28   18.4 Li quidated and ascertained damages
                                                             18.5 Damage by a Special Peril
12.1 Architect's representative
12.2 Delegation of duties and powers                         19      Assignment and sub-Ietting                       37
12.3 Instruction to bind parties
                                                             19.1 Assignment
13     Variations , Provisional Quantities ,                 19.2 Sub-Ietting
       Provisional Items and Provisional
       Sums                                             29   20      Injury to persons and property and
                                                                     indemnity to Employer              38
131Archltect's
     instructionsauthouPrirriotiny
                   requiring     vgitsoa
                                       aioiVsnsaaurl
                                                   ie
                                            Variation                Contractor to indemnify Employer
13.2 Instructions for Provisional Quantities ,
     Provisional Items and Provisional                       21      Insurance against      inju 吋 to   persons
     Sums                                                            or property                                      39
13.3 Valuation of Contractor's work
13.4 Valuation rules                                         21.1    Employees' Compensation Insurance
13.5 Adjustment of Contract Sum                              21.2    Third party liability insurance
13.6 Contractor's right to be present during                 21.3    Insurers and terms to be approved
     measurement on Site                                     21 .4   Policies to be produced
13.7 Variation necessitated by fault of                      21.5    Event of failure to insure
     Contractor                                              21.6    No prejudice to Contractor's indemnity
13.8 Valuation of Nominated Sub-
     Contractor's work or Nominated                          22      Insurance of the Works                           40
     Supplier's materials and goods
                                                             22.1    Alternative ciauses for Contractors'
14     Contract B iII s                                 33           AII Risks Insurance of the Works
                                                             222BAaHsRicisrkesq|unisreumraennctes for Contractors ,
14.1 Quality and quantity of work inciuded                                                        of the Works
     in Contract Sum                                         22.3 Specific requirements for Contractors'
14.2 Standard Method of Measurement of                             AII Risks Insurance of the Works
     Building Works                                          22 .4 Insurance of the Works to be in joint
14.3 Errors in Contract Bills                                      names and period of insurances
                                                             22.5 Parties' obligations if loss or damage
15     Contract Sum                                     34         occurs
                                                             22.6 Contractor's payment not more than
       Adjustment of Contract Sum                                  insurance proceeds
                                                             22.7 Insurance without prejudice to
16     Materials and goods on or off-site               34         Contractor's obligations
       Property in materials and goods                       22A     Insurance of the Works by the
                                                                     Contractor                                       43
17     Substantial Completion and
       defects liability                                34   22 A. 1 Contractor to effect Contractors' AII
                                                                     Risks Insurance of the Works
17.1   Substantial Completion Certificate                    22 A. 2 Insurer to be approved and remedy
       for the Works                                                 if Contractor fails to insure
17.2   Separate Defects Li ability Period for                22 A. 3 Use of annual policy maintained by
       each Section and Relevant Part                                Contractor
17.3   Rectifying defects
17.4   Defects Rectification Certificate for                 22B     Insurance of the Works by the
       the Works                                                     Employer                                         44
17.5   Separate certificate for each Section
       or Relevant Part                                      22B.1 Employer to effect Contractors'
17.6   Damage by a Specified Peril                                 AII Risks Insurance of the Works
17.7   Other rights and remedies                             228.2 Remedy if Employer fails to insure
18     Partial possession by Employer                   36   22C     Insurance of existing building and
                                                                     insurance of the Works by the
18.1 Partial possession                                              Employer                                         44
18.2 Substantial Completion
18.3 Completion of rectifying defects                        22C.1 Employer to effect insurance against
                                                                   Specified Perils to the existing building
2
                                                  PAGE                                                       PAGE
      22C.2 Employer to effect Contractors'                 29      Nominated Sub-Contractors and
            All Risks Insurance of the Works                        Nominated Suppliers                       57
      22C.3 Remedy if Employer fails to insure
                                                            29.1    Nomination of a sub-contractor or a
      23     Possession, commencement and                           supplier
             completion                                45   29.2    Contractor's right of reasonable
                                                                    objection
      23.1 Possession of Site                               29.3    Sub-contractor and supplier warranty
      23.2 Commencement and completion                              to Employer
      23.3 Postponement or suspension                       29.4    Contractor's tender for work provided
                                                                    for by a Prime Cost Sum
      24     Damages for non-completion                45   29.5    Nomination using the standard
                                                                    conditions
      24.1 Architect to certify Contractor's failure        29.6    Contractor's responsibility for
           to complete on time                                      Nominated Sub-Contractors and
      24.2 Liquidated and ascertained damages                       Nominated Suppliers
      24.3 Refund if Completion Date revised                29.7    Quantity Surveyor's notification of
                                                                    interim payments
      25     Extension of time                         46   29.8    Direct payment of Nominated Sub-
                                                                    Contractors and Nominated Suppliers
      25.1 Contractor's first notice of delay               29.9    Extension of time for completion
      25.2 Contractor's second notice '                             of Nominated SUb-Contract works or
      25.3 Fixing new Completion Date                               delivery of Nominated Supply
      25.4 Contractor's default involved in the                     Contract goods
           delay                                            29.10   Substantial completion of Nominated
      25.5 Rate of progress                                         Sub-Contract works
      25.6 Nominated Sub-Contractors and                    29.11   Architect to certify Nominated Sub-
           Suppliers to be kept informed                            Contractor's failure to complete on
                                                                    time
      26     Delay recovery measures                   51   29.12   Early final payment to Nominated
                                                                    Sub-Contractor or Nominated
      26.1 Delay recovery measures                                  Supplier
      26.2 Delay recovery proposals                         29.13   Re-nomination
      26.3 Contractor to carry out delay recovery           29.14   Architect's consent
           measures                                         29.15   Employer not liable to a Nominated
      26.4 Extension of time to cover shortfall in                  Sub-Contractor or Nominated
           recovering delay                                         Supplier
      26.5 Contractor to be reimbursed for the
           cost of preparing the proposal if delay          30      Persons engaged by Employer               63
           recovery not instructed
                                                            30.1 Persons for whom the Employer is
      27     Direct loss and/or expense                53        responsible
                                                            30.2 Access to Site and permission to
      27.1 Contractor's notice of claim for                      carry out work
!          additional payment                               30.3 Contractor to fulfil his obligations to
1
      27.2 Quantity Surveyor's ascertainment of                  persons engaged by the Employer
I          Contractor's claim
i     27.3 Contractor's default involved in the             31      Facilities for statutory undertakers
I          delay or disruption
      27.4 Nominated Sub-Contractor's claim
                                                                    and utility companies                64
I•    28
           for additional payment
             Notice of claims for additional
                                                                    Access to Site and facilities to carry
                                                                    out work
I
J
i
             payment
      28.1 Contractor to give notice of claim
      28.2 Contractor to submit particulars
                                                       55   32
                                                            32.1
                                                                    Certificates and payments
                                                                 Interim Certificates and interim
                                                                 valuations
                                                                                                               64
!     28.3 Condition precedent to Contractor's              32.2 Estimate of amount due in Interim
1          entitlement to additional payment                     Certificate
I
i                                                           32.3 Off-site materials or goods
I
 I,
,I                                                                                                              3
J
                                                                                                                                   卡 iEjj!ji--lj
                                                     PAGE                                                                   PAGE
32 .4 Calculation of Retention                               37 .4 Quantity Surveyor to prepare finai
32.5 Retention Rules                                               account
                                                              ,7 The final settlement
                                                                  RU 門
                                                             qunJ
32.6 Quantity Surveyor to prepare final                        7t
                                                                     b
      account                                                      Architect to notify sub-contractors
32.7 Adjustment of the Contract Sum                                and suppliers
32.8 Issue of Final Certificate
32.9 Effect of Final Certificate                             38          Fluctuations                                         84
32.10 Proceedings commenced before
      Final Certificate                                      38.1 Fluctuation provisions only applicable
32.11 Proceedings commenced after Final                           if expressly stated to be
      Certificate                                            38.2 Adjustment for fluctuations occurring
32.12 Effect of Architect's certificates                          after the Completion Date
32.13 Late payment
                                                             39          Notices. certificates and other
33              Sure句 Bond                              73               communications                                       85
33.1            Contractor to obtain guarantee from                      Submission of notices , certificates and
                insurance company or bank                                other communications
33.2            Release of insurance company or
                bank                                         40          Recovery of money due to the
33.3            Employer's remedy if Contractor fails                    Employer                                             85
                to deliver bond
                                                                                                          o ecov e      a mages
                                                                         仁」 e
                                                                                m比
                                                                                     nv ovyera-S nvo we
                                                                                                      VFB
                                                                                                          +L   rl   rt Hu
34              Antiquities                             73
34.1            Effect of finding antiquities                41          Settlement of disputes                               85
34.2            Architect's instructions concerning a
                fossil , antiquity or object                 41.1        Procedures and Designated
                                                                         Representatives
35              Determination by Employer               74   41.2        Reference to Designated
                                                                         Representatives
35.1            Default by Contractor                        41.3        Reference to mediation
35.2            Insolvency of Contractor                     41 .4       Reference to arbitration
35.3            Employer's rights upon notice of             41.5        Timing of arbitration
                default or determination                     41.6        Arbitrator's powers
35 .4           Consequences of determination                41.7        The place of arbitration
35.5            Quantity Surveyor to prepare final           41.8        Contractor to continue to proceed
                account                                                  diligently
35.6            The final settlement
35.7            Delayed commencement of                                  Appendix                                             89
                completion works                                         Schedule 1                                           90
35.8            Other rights and remedies                                Form of Surety Bond to be given by
                                                                         the Contractor to the Employer
36              Determination by Contractor             78
                                                                         Schedule 2                                           94
36.1 Default by Employer                                                 Form of Warranty to be given by the
36.2 Insolvency of Employer                                              Nominated Sub-Contractor to the
36.3 Consequences of determination                                       Employer in consideration of
36.4 Contractor to submit final account                                  Nomination
36.5 Quantity Surveyor to check final
     account                                                             Schedule 3                                           97
36.6 The final settlement                                                Form of Warranty to be given by the
36.7 Architect to notify sub-contractors                                 Nominated Supplier to the Employer
     and suppliers                                                       in consideration of Nomination
36.8 Other rights and remedies
                                                                         Index to The General Conditions
37              Determination by Employer or
                Contractor                              82
   123
    7 , 7 ,『/
quququ
                Grounds for determination
                Site security
                Consequences of determination