Part 1 - General: SECTION 16232 Diesel Engine Generator
Part 1 - General: SECTION 16232 Diesel Engine Generator
SECTION 16232
DIESEL ENGINE GENERATOR
PART 1 - GENERAL
1.1 SUMMARY
A.Section Includes:
Performance.
Engine.
Generator.
Fuel system.
1.2 SYSTEM DESCRIPTION
A complete functioning system with six (6) x 2600 KVA, Water Cooled (HEX) (Continuous duty), 0 %
tolerance, 50 Hz, 1450 RPM, 3,300 Volt generator, and three (3) x 2000 KVA, Radiator Cooled
(Continuous duty), 0 % tolerance, 50 Hz, 1450 RPM, 415 Volt generator, auxiliary controls and starting
equipment, capable of starting and delivering power to connected loads within 10 seconds from instant of
start command or power failure. There will be six (6) 3,300 Volt diesel generators running in parallel.
Synchronization control panels consisting of all required components for synchronization and load sharing
and load shedding shall be provided, installed and commissioned. The remaining three (3) 415 Volt
Generators shall each include a MCCB & Trip unit mounted on the generator for isolation and shall be
connected directly to the basement MCC’s via mechanical/electrical interlocks. Generators shall run on a
designed power factor of 0.94.
REFERENCES
Prime Movers
ISO 3046 (BS 5514) – Specification for reciprocating internal combustion engines, parts 1 to 6.
ISO 8528 – Reciprocating internal combustion engine driven alternating current generating sets, parts
1 to 10.
The engine and its auxiliaries shall be manufactured and/or controlled under a registered quality
control system approved to ISO 9001.
Generators.
IEC 34-1 – Rotating electrical machines.
BS2615 – The Electrical Performance of Rotating Electrical Machinery.
BS 4999 (IEC 341) – General requirements for rotating electrical machines.
BS 5000 (IEC 341) – Rotating electrical machines of particular types or for particular applications.
NEMA MG1: Motors and Generators.
EN 50081 (BS EN 500812) – Electromagnetic compatibility. Generic immunity standard.
EN 50082 (BS EN 500822) – Electromagnetic compatibility. Generic immunity standard.
The generator and its control system shall be manufactured under a registered quality control system
approved to ISO 9001.
1.3 SUBMITTALS
A. Comply with the Tender Invitation for Submittal Procedures.
B. Product Data:
1. Manufacturer's standard catalog sheets for engine generator set with complete listing of accessories
including the following.
a. Dimensioned outline drawings of complete engine generator sets locating connections and
indicating weights.
b. Engine specifications with complete listing of accessories.
c. Certified horsepower, fuel rate, and altitude derating curves at specified continuous rating.
d. Complete description of vibration damping mounts.
e. Alternator (generator) specifications including voltage regulator and exciter specifications.
f. Detailed drawing of oversized radiator.
g. Data to be submitted detailing pressure drop values.
D.A factory authorized Maintenance Agency shall specifically warranty maintenance of the system, as
described under SPECIAL WARRANTIES.
E.A factory authorized Maintenance Agency shall regularly stock replacement parts for this system over
the life expectancy of the equipment.
F.A factory authorized Maintenance Agency shall be located within 320km of the site and shall, during the
warranty period, start non-scheduled maintenance services by no later than noon of the day following a
request for such services.
1.6 WARRANTY
A.Special Warranty
B.Provide warranty service for work specified in the Tender Invitation. The warranty period shall be 24
months from the date of commissioning and acceptance by the Owner, following installation completion
and a successful demonstration of the system performance to the Owner. Warranty service shall include
all material, labor, travel and living expenses for the replacement of parts found defective due to defective
material or workmanship and the correction of developing defects due to faulty design or installation.
C.Provide emergency services as often as needed on a 24 hour basis including weekends and legal
holidays. Such service shall respond to an emergency situation within four hours of notification. Provide a
24 hour telephone number including weekends and legal holidays. Calls shall be handled immediately by
personnel who are full time employees of the service company.
D.Problems encountered and solutions applied shall be documented and turned over to the Owner within
30 days of each service call.
E.Provide certification from engine generator system manufacturer that the final installation is proper and
in no way voids equipment warranty.
F.The Extended Service Warranty, as referred to in the unit prices, shall provide full coverage for major
repairs/replacement of unit, provided the manufacturers required maintenance has been performed as
recommended.
1.7 MAINTENANCE
A.Maintenance Service
1. Provide maintenance service for work specified in this Section for one year beginning on the day
mutually agreed to by the Owner and the contractor following completion of a successful
demonstration and acceptance of the system to the Owner.
2. Perform on-site maintenance when necessary and requested by the Owner, including not less than
two (2) scheduled service calls at approximate six (6) month intervals, without additional cost to the
Owner. Service calls shall include system inspections and testing with written reports to the Owner.
3. Maintenance tests performed, and routine maintenance accomplished shall be documented and
turned over to the Owner within thirty (30) calendar days of each service call.
4. Provide sixteen (16) spare oil filters, two spare air filters and sixteen (16) spare fuel filters of each
size.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A.Acceptable Manufacturers: Caterpillar; Cummins, MTU (Germany).
B.Certain products may be identified by manufacturer and/or model, in the following paragraphs.
C.Supplying distributor must have permanent stock and parts facility within 160 km of the site.
2.2 ENGINE GENERATOR - PERFORMANCE
A.The unit is to be continuous rated at 3-phase, 3-wire, 50Hz, for operation at not less than 0.94 power
factor. The capacity of the unit shall be sufficient to provide the minimum performance values described
below. Submit factory calculations supporting the selected unit rating.
1. Unit performance values shall be met with the inclusion of specified or required unit modifications, at
project altitude and at 50 degrees C radiator inlet and combustion air temperature.
2. The unit is to support process loading requirements as per loading steps.
B.Under steady state conditions, output frequency shall be maintained within plus or minus 0.5 percent
(1.0 percent total) of nominal between no load and full specified load (droop) and within plus or minus 0.25
percent (0.5 percent total) of nominal at any given load (drift).
C.Under steady state conditions, output voltage shall be maintained within plus or minus 1.0 percent (2.0
percent total) of nominal between no load and full specified load (droop) and within plus or minus .5
percent (1.0 percent total) of nominal at any given load (drift).
D.Upon the single step assumption or volt drop of either the chiller load or any other process loading step,
the unit shall limit the instantaneous voltage drop to a maximum of 15 percent of nominal and shall
recover its specified droop within 24 cycles (0.4 seconds).
E.The permanent magnet excitation system shall derive excitation current from a pilot exciter mounted on
the rotor shaft. It shall enable the generator to sustain 300 percent of rated current for ten seconds during
a fault condition.
F.Construction and performance of engine generator set to comply with requirements of NFPA 110.
2.3 ENGINE
A.Engine: Water cooled for the 3.3 KV and radiator cooled for 0.415 KV engine, 1500 RPM, four cycle
diesel (two cycle is not acceptable), using commercial grade diesel fuel, mounted on a welded structural
steel base with its radiator and alternator, forming a semi-portable unit.
B.Governor: Solid state Isochronous type with adjustable droop factory-set regulating frequency to 50 Hz
plus 1/2 Hz at steady state load conditions from full load to no load generator output, with frequency at
constant load remaining within steady state bandwidth of ±0.25 percent of rated frequency and with
frequency modulation less than 1 cycle per second, and shall include load sharing as well as load
shedding features
1.Acceptable manufacturers:
a.Woodward or equal.
C.Sensors monitoring lube oil pressure; high coolant temperature, and low coolant temperature.
D.Two-Stage Safety Switches: Automatic resetting, controlled by low lube oil pressure, high engine
coolant temperature, and to work with automatic control system. First stage to provide "Pre-Shutdown"
signal.
E.Lubrication System: With gear driven oil pump, full flow replaceable element oil filter(s). Provide a
duplex oil filter system with transfer device to allow replacement of an oil filter without an engine shut
down and shall include an external electric Pre-Lube auxiliary oil pump with TEFC motor.
F.Air Cleaner: Heavy duty dry type suitable for use in extreme dust conditions.
G.Coolant Pump: Engine mounted, gear or belt driven.
H.Terminal blocks for wiring connections made to engine mounted devices.
I.Water jacket heater.
2.4 ALTERNATOR
A.Alternator shall be a rated for continuous duty @ 2600KVA (3,3KV) & 2000KVA (415V), 1500 RPM, 50
Hz and capable of running at 0.94 power factor.
B.A minimum Class "H" insulation system. Temperature rise to be rated for Class F. Alternator shall be
suitable for continuous operation at ambient temperatures of 50°C.
C.Exciter: Brushless type with rotating rectifier bridge. The exciter shall develop its own power for
excitation and be isolated from harmonic distortions and irregularities on the generator output.
D.Voltage Regulator: Solid-state, volts-per-hertz type with screwdriver operated voltage adjustment, cross
current compensation and internal protection against excessive field currents and alternator output
voltage;
E.Waveform Quality: Not exceeding NEMA values for telephone influence factor (TIF) and with a
waveform deviation factor less than ten percent line to line.
B. A thermostatic bypass valve shall provide fast warm up and maintain engine operating temperature.
Coolant temperature shall be internally regulated to disconnect external cooling systems until
operating temperature is achieved. The generator cooling shall be controlled by a separate control
valve system.
C. Coolant shall consist of clean water/glycol solution with a rust inhibitor.
D. Redundant jacket water heater(s) in different water circuits shall be provided to work with the
thermostatic bypass to maintain coolant temperature of 86 degrees F (min.) while the engine is off. An
electric immersion heater (230VAC volt, single phase rated) and thermostatic control shall maintain the
coolant in the engine jacket at not less than 30 degrees C.
E. Isolation valves shall be installed on both sides of the heater element to facilitate servicing.
F. Heat exchangers shall be provided with temperature, pressure gauges, service valves, at both the inlet
and outlet connections, vent and drain connections.
2.10 EXHAUST SYSTEM
A.Silencer: Designed for "Residential" silencing with drain fitting at outlet end and bolted flange
connections at inlets and outlets. Silencer to have side inlet and opposite end vertical outlet except as
detailed. Maxim, Nelson, or approved equal.
B.Flexible Connection: Stainless steel, flexible, seamless pipe(s), with mechanical connections for
attachment to exhaust manifold and silencer.
Installation of the exhaust piping, flexible connection, flashing, and silencer. Provide a stainless steel
roof/wall thimble for the exhaust pipe.
PART 3 - EXECUTION
3.1 EXAMINATION
A.Examine areas and conditions under which Work is to be performed and identify conditions detrimental
to proper or timely completion. Do not proceed until unsatisfactory conditions have been corrected.
3.2 INSTALLATION - GENERAL
A.Verify concrete base is provided in compliance with Division 3.
B.Comply with manufacturer's recommendations.
C.Install engine generator systems indicated with necessary equipment, support and control systems, and
building construction features (e.g., concrete pads). Dimensions indicated are limiting dimensions for
project and must be verified with actual equipment used. Equipment with dimensions or weights
exceeding those indicated may only be used if approved and related additional costs borne by Contractor.
Equipment requiring additional mechanical services (e.g., exhaust, cooling air or liquid) or electrical
services (e.g., suppression filters, circuit wiring or over current protection) may only be used if approved
and related additional costs borne by Contractor.
D.Ground non-current carrying conductive parts of engine generator sets to main service ground via
conduit raceway systems unless indicated otherwise. Bonding generator neutrals to generator housings
is not acceptable
E.Verify that generator phase sequence matches system phase sequence and correct if necessary.
F.Install storage batteries in racks with required cables to engine and to battery charger.
1. Anchor battery rack to floor.
2. Wall mount battery charger adjacent to engine generator set.
G.Install fuel tank assembly per manufacturer's recommendations and at height recommended by
generator manufacturer.
1. Anchor fuel tank assembly to floor.
2. Do NOT support fuel tank from generator assembly.
H.Coordinate the installation of fuel and exhaust lines, including flex connectors and exhaust silencer, fuel
tank fill and vent lines and radiator discharge duct.
I.Connect unit control wiring. Identify wires to match manufacturer's designations.
1. Identify wires using conductor color coding and Brady (or other) numbered identification tape with
identification corresponding to wiring schematic submitted with Shop Drawings.
2. Connect battery charger alarms to unit control panel to indicate high and low battery voltage.
3. Connect fuel tank float switches to unit control panel, to indicate high and low fuel levels, and to the
fuel oil pump controls.
4. Install and connect remote audible alarm where shown.
5. Interconnect engine start, load bank shunt trip and transfer controls between the engine control panel
and each of the transfer switches and the fire pump controller.
6. Extend auxiliary control power circuit to location shown. Auxiliary control devices and wiring are
described in Plant Controls.
7. Connect emergency off switch into control panel.
8. Interconnect the inlet solenoid and safety valves to operate when float switch is actuated.
Interconnect the high level float switch to close safety valve when actuated and open when level
drops.
J.Coordinate connection of auxiliary devices, remote monitoring and fuel transfer pump control as
described in Plant Controls.
K.Field adjust voltage regulator and governor, and tune engine at site for optimum system performance.
Verify lubricating oil, engine coolant, and storage battery cells are full. Fill as required.
3.3 FUEL SYSTEM
A.Day Tank:
1. Install plumb using shims and bolt to floor with using concrete inserts.
2. Install level switches per manufacturer’s recommendations and adjust switch actions for the specified
elevations above the floor.
3. Provide temporary drain piping between day tank drain and overflow.
4. Simulate actual operating conditions to prove proper operation of controls.
B.Make electrical connections under this Division, including pumps and starters, float switches, solenoid
valves, etc.
1. Solenoid valves: Make electrical connections under this Division and control as recommended by
engine generator set suppliers.
2. Day tank: Make electrical connections to float switches.
3. Fuel transfer pump: Make electrical connections and control with float switches in day tank.
4. Storage tank: Connect low supply alarm float switch to control panel.
5. The minimum electric and overall efficiency acceptable shall not be less than 37,5 %. This efficiency
based on the net electric power output and low heating value of diesel fuel energy equivalent
consumed when engine operates at site conditions.
6. A penalty clause of US $ 30,000 will apply for every 1 % deficit in the efficiency for the generator
continuous 2444 KW (3,3KV @ 2,600KVA 0.94 pf) & 1880KW (415V @ 2000KVA 0,94 pf) ratings.
7. The above stated values shall be guaranteed by the engine manufacturer through testing at 0 %
tolerance.
E.Test reports: Upon completion of the standard test procedures, submit three sets certified test report
demonstrating compliance to these test procedures with all data recorded as required. In addition, an oil
sample will be taken during the test at full and partial load, thereafter analyzed for signs of unusual wear.
All testing shall be performed on the actual serial number generator sets assigned for delivery to the job
site for this project.
3.7 FIELD QUALITY CONTROL
A.Refer to General Requirements for responsibilities of Field Quality Control Requirements.
B.Coordinate testing date with Owner and Architect to determine date acceptable to all. Provide for engine
generator set manufacturer's authorized personnel to operate equipment during this testing and to verify
details of the installation.
C.Before start-up and loading of the unit, check and correct the following:
1. Alignment of engine and generator shafts.
2. Adjustments of voltage regulator and governor.
3. Fluid levels for lubricating oil, engine coolant, and storage battery cells.
4. Match of generator phase sequence with the main distribution system.
D.After all equipment has been installed at the job site, and after all pre-start checks and procedures have
been completed, a full system test shall be performed to demonstrate operational capability. This shall
include the following:
1. Paralleling of all generator sets on their associated bus segments to demonstrate load sharing and
generator set capacity for a minimum of 6 hours at rated load. After all bus segments have been
tested, the tie breakers (if applicable) will be closed and the segments shall be connected and tested
with full load. At this point all operational modes of the generator switchgear shall be demonstrated.
Load shall be provided by the Plant load or by the use of load banks for a minimum of one week
during mode of operation testing. Provide cabling for load banks as required.
2. During the field operation and load test the appropriate data and information will be documented as
noted below:
a. Upon completion of field testing, the dealer shall submit (5) copies of certification of installation
and testing in compliance with the specifications and manufacturer's guidelines.
E.Field test each engine generator set after final installation and under the total specified steady-state
load. Building loads normally connected to the system, temporary connections to other utility building
loads or portable load banks shall be used to bring the total test load on the engine generator set to its
design value for not less than four hours, or longer as required, to verify the stability of operation of
components in the system. Do not begin test until engine generator set has been inoperative for at least
24 hours and verify the ten second start time in the preheated condition.
1. Record volts and amperes on each phase, hertz, room temperature (two locations), and engine
operating temperature and oil pressure every 15 minutes during test run.
2. Demonstrate the proper operation of all indicators, instruments, devices and system functions for the
equipment specified. Coordinate this work with the installing contractor. Make all corrections required
to achieve proper equipment operation.
F.After successful completion of each unit's steady-state load test, perform two successful tests: one "test
without load" and one "test with load" both of which will require synchronizing (with other Generators).
Record seconds to synchronization of each unit, volts amps, and hertz. Each test shall be no shorter than
30 minutes in duration. Demonstrate load sharing capability.
G.After successful completion of system testing under parallel operation (with other Generators), test the
entire system by simulating a peak-shaving start. Record the synchronization times, volts, amps, and
hertz on each unit. Each test shall be no shorter than 20 minutes in duration.
H.With the engine at standby temperature, perform a battery test consisting of four (4) cranking cycles of
twenty seconds "on" and ten seconds "off" with engine fuel system disabled. Verify battery storage
capacity is adequate for 4 cycles of 30 second minimum cranking.
I. Repeat until satisfactory conclusion.
1. Replace batteries if they do not recharge to full value after test.
J.In addition, provide and verify the following load tests, namely
1. Bring three (3) generators to running speed in order to start one (1) chiller pair.
2. Bring six (6) generators to running speed in order to start the third (3) chiller pair. This test shall be
done while chiller pairs 1 & 2 are running 100%.
3. Bring all six (6) generators to running speed in order to start the four (4) chiller pairs.
Chiller loads might need to be reduced in order to successfully complete this test. Once initial starting
conditions have passed, chillers can be loaded once again.
Upon completion of the tests, a general inspection shall be made for leaks in the engine, piping, etc.
Remove a minimum of two oil filters and oil (within filter assembly) and examine for metal and abrasive
foreign particles. Oil analysis shall be completed by an independent test lab. If such particles are found,
supplier shall change oil and filters and run engine under load for a period of eight additional hours. Re-
examine oil and filter as specified above, and make all corrective measures as required until oil remains
free of such contaminants. Engine oil analysis shall be completed again one month prior to end of first
year warranty.
K.Provide or replace all fuel and oil used in testing.
L.Submit test results to Owner and Engineer.
3.8 DEMONSTRATION
A.The dealer shall provide five sets of the following documentation (at least 2 weeks prior to scheduled
Owner training):
1. Engine operation manual:
a. Service manual.
b. Spare parts books.
c. Generator operation and maintenance manual.
d. Copy of approved submittals including catalog cut sheets on all components.
e. As-built engine generator set drawings.
f. As-built control system schematics and wiring diagrams.
g. Warranty statement.
B.The dealer shall provide training to provide operating personnel with operational knowledge and
complete preventative maintenance capability of the system. This shall include, as a minimum, one week
classroom job site training by factory certified instructors and switchgear manufacturer's engineers. Topics
to be addressed shall include:
1. System operation in all modes.
2. Individual component operation and maintenance.
3. System preventative maintenance procedures.
4. Component preventative maintenance procedures.
5. System test procedures.
6. Component test procedures.
7. Reading of control schematics and trouble shooting.
C.Training shall be held at the job site and classroom training at the local dealer's facilities. During the first
year of operation, the dealer and a representative of the switchgear manufacturer shall return to perform
follow-up training at the convenience of operating personnel.
D.Demonstrate actual starting of chiller, as previously described, and record all data. Testing and starting
of chiller shall be accomplished after chillers, pumps, fans, etc. are installed and fully operational. The
chiller starting tests shall be completed after, and separate from, the engine generator paralleling tests as
previously discussed.
E.Demonstrate operation and maintenance procedures to Owner.
END OF SECTION