Sabp P 063
Sabp P 063
                                             Contents
                                         1     Scope ................................................................ 2
                                         2     References........................................................ 2
                                         3     Definitions ......................................................... 3
                                         4     Design Criteria .................................................. 3
                                         5     Cable Sizing According to IEC .......................... 9
                                         6     Cable Sizing According to NEC ...................... 11
                                         7     Some Examples for Cable Sizing.................... 13
                                         Revision Summary................................................. 17
1 Scope
1.1 Purpose
                  The purpose of this document is to provide guidance for Saudi Aramco engineers
                  on how to properly size electrical power cables, considering short circuit
                  withstanding current, ampacity calculations under actual site installation
                  conditions, and voltage drop limitations using IEC and NEC methods for both low
                  voltage and high voltage (as defined in SAES-P-100) up to 34.5 kV.
1.2 Disclaimer
                  This Best Practice is not mandatory. In the event of a conflict between this Best
                  Practice (BP) and other Mandatory Saudi Aramco Engineering Requirements
                  (MSAER), the Mandatory Saudi Aramco Engineering Requirements take
                  precedence.
2 References
3 Definitions
4 Design Criteria
4.1 General
                  The selection of the specific type and size of power cable should be based on the
                  following:
                  4.1.2     Installation requirements such as duct banks, direct burial, conduit, cable
                            tray and thermal resistivity of soil & backfill material.
                  4.1.4     Selecting three core cable or trefoil configuration for single core cable as
                            a preferred option for cable length more than 0.5 km.
                            4.2.1.2       In general, the ampacity and voltage drop will be higher for
                                          three single conductor cables when compared with a similar
                                          size of three conductor cable.
                            4.2.1.3       For a very long cable installation, three core cable or three
                                          single core cable (trefoil configuration) is recommended, to
                                          reduce the effect of circulating currents and induced voltage.
                                          Design of cable, lay out, arrangements, and penetration to
                                          equipment shall minimize induced voltage and circulating
                                          currents to safe limits as specified in SAES-P-104.
         4.3      According to SAES-P-104, cable sizing shall be based on NEC, IEEE, or IEC.
                      ANSI manufactured cables, ampacity calculations and cable sizing shall be
                       based on the NEC, or from the tables in IEEE 835.
                      IEC manufactured cables, ampacity calculations and cable sizing shall be
                       based on the IEC 60364 and IEC 60502-2 series standards.
                      The Cable Derating Program of the Electrical Transient Analyzer Program
                       (ETAP) or other power simulation software are permitted to be used to
                       calculate ampacities, as an alternative to the NEC, IEC, or IEEE 835 tables.
                  The short-circuit withstand rating of cables is based on ensuring that the conductor
                  size is large enough to carry the short-circuit current for a sufficient time duration
                  (until the short-circuit protective device interrupts and clears the fault current)
                  before the cable insulation is damaged by the heat rise within the cable.
                  The minimum cable size to comply with a short-circuit current (Isc) for duration
                  of time (t) is therefore given by:
                                                                𝐼𝑠𝑐 × √𝑡
                                                           𝑆≥
                                                                    𝑘
                  Where:
                       k = Constant applicable to type of conductor and insulation
                           (143 for XLPE insulated copper conductors)
                       S = Cable cross-sectional area of the cable (mm2)
                       t = Fault duration
                                          Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved                                                        Page 5 of 17
Document Responsibility: Electrical System Design and Automation Standards Committee           SABP-P-063
Issue Date: 18 March 2019
Next Planned Update: 18 March 2029                                            Electrical Power Cable Sizing
                  According to SAES-P-104, for cable sizing adjustment for fault conditions, the
                  fault location shall be assumed to be at the load end of the cable.
                  -    For low voltage cables, fault duration time shall be a minimum of 110% of
                       the clearing time of the protective device providing primary protection to the
                       cable (maximum total clearing time in the case of fuses).
                  -    For medium voltage cables, fault duration time shall be a minimum of 110%
                       of the clearing time of the protective device providing backup protection to
                       the cable and this time shall not exceed 1.0 second.
                  The following basic parameters shall be used to evaluate the ampacities to fulfill
                  the load requirements:
                            LV Motor feeder cables should be rated at 125% of motor full load current
                            (service factor 1.15 or greater) and 115% for motors over 1,000 Volts,
                            Nominal (refer to NEC article 430) as a good engineering practice or as
                            per the trip current of overcurrent (overload) relays or other motor
                            protective devices. Other cables shall be rated for 100% load factor as per
                            SAES-P-104.
                  4.5.3     According to SAES-P-104, for the basis of sizing a feeder ampacity rating
                            which supplies distribution equipment, shall be equal to the lower of:
                            a)   The continuous current rating of the distribution equipment main bus
                            b)   The site rating of the upstream transformer
                            Exception:
                            Cable installation method should be taken into account when cable sizing
                            calculation to provide accurate cable sizing. Calculation results should
                            be verified against actual vendor equipment data and against protection
                            coordination study for final cable selection.
                            When sizing cables, the designer should pay attention to the overall
                            derating factor that takes into account the differences in the cable’s
                            actual installation and operating conditions from the base conditions.
                                          Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved                                                             Page 7 of 17
Document Responsibility: Electrical System Design and Automation Standards Committee           SABP-P-063
Issue Date: 18 March 2019
Next Planned Update: 18 March 2029                                            Electrical Power Cable Sizing
                                                                   𝐼 ′ = 𝐼𝐹
                            Where,
                                (I’) Derated Ampacity at actual installation conditions.
                                (I) Base Ampacity
                                (F) Overall Derating Factor.
𝐹 = 𝐹𝑓 × 𝐹𝑡 × 𝐹𝑡ℎ × 𝐹𝑔 × 𝐹𝑐
                            Where,
                                Ff = Derating factor for fire coating: As per SAES-P-104, Ff = 0.85
                                     when cables are fireproofed by coating or wrapping with a
                                     compound or other material. If not, then Ff equal to 1.0.
                                Ft = Derating factor to account for the differences in ambient and
                                     conductor temperatures. You may refer to SAES-P-104 for
                                     ambient temperature consideration associated with different
                                     installation conditions.
                                Fth = Derating factor for underground soil thermal resistance (only
                                     for Directly Buried cables). As per SAES-P-104, Earth Thermal
                                     Resistivity (RHO) for Land: 1.2 K-m/watt, Concrete (for Duct
                                     Banks): 1.0 K-m/watt, and Sea Bottom: 0.8 K-m/watt
                                Fg = Derating factor for cable grouping.
                                Fc = Derating factor for A/G tray covers (only for cables installed in
                                     covered Tray). Fc is assumed = 0.95
                            Duct bank de-ratings is considered where such duct runs exceed 3 meters
                            and overall cable ampacity will be based on the duct portion of the entire
                            run.
                  The voltage drop in power cables shall comply with sections 6.2 and 6.3 of
                                          Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved                                                        Page 8 of 17
Document Responsibility: Electrical System Design and Automation Standards Committee           SABP-P-063
Issue Date: 18 March 2019
Next Planned Update: 18 March 2029                                            Electrical Power Cable Sizing
                            If more insulated conductors are installed in the same group, the group
                            reduction factors specified in tables B.52.17 to B.52.21 will be applied.
         5.2      MV Power Cables as defined in IEC 60502-2, (6 /10 kV for 4.16 kV cables,
                  12 /20 kV for 13.8 kV cables and 18/30 (Insulation Thickness: 345 mils or
                  9 mm) for 34.5 kV cables).
                  Note: All tables referenced below were extracted from IEC 60502-2.
                            If more insulated conductors are installed in the same group, the group
                            reduction factors specified in tables B.18 to B.23 will be applied.
                                                         28 ∗ √0.5
                                                    𝑎=             = 138.5𝑚𝑚2
                                                          0.143
                       The Minimum Cross Section (𝑚𝑚2 )= 150 𝑚𝑚2
                                          Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved                                                       Page 13 of 17
Document Responsibility: Electrical System Design and Automation Standards Committee           SABP-P-063
Issue Date: 18 March 2019
Next Planned Update: 18 March 2029                                            Electrical Power Cable Sizing
                      Cable Ampacity
                                                                                𝐾𝑉𝐴
                                 𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 = 𝐼 = (                      ) = 646𝐴
                                                                              √3 ∗ 𝐾𝑉
                                                                 𝐼 ′ = 𝐼𝐹
                       Where: (I’) is De-rated Ampacity, (I) is Base Ampacity and (F) is Overall
                       Derating Factor.
                       Referring to the suitable IEC 60502-2 Table B.2, we will select: 2-3 - 1/C
                       150 mm2 has a base ampacity of 2*481 (flat touching formation as shown
                       below) which will be suitable for motor load.
                       Where the cables are assumed to be spaced at least 0.5 times the cable
                       diameter from cable tray edge.
                       Where,
                            Ff = Derating factor for fire coating.
                            Ft = Derating factor to account for the differences in ambient and
                                 conductor temperatures according to Table B.10 of IEC-60502-2.
                            Fth = Derating factor for underground soil thermal resistance (only for
                                  Directly Buried cables).
                            Fg = Derating factor for cable grouping.
                       Therefore,
                            Ff =1 (considering that the cable is not fire-rated)
                            Ft = 0.82 (at air ambient temperature of 50°C for shaded cable tray
                                  installation)
                       %V.D. = 0.04%
                       Hence, voltage drop across the selected cable is less than 2.5% of the System
                       Nominal Voltage.
                       %V.D. = 0.033%
                       Hence, voltage drop across the selected cable is less than 2.5% of the System
                       Nominal Voltage.
Revision Summary
18 March 2019            New Saudi Aramco Best Practice that provides guidance for Saudi Aramco engineers on
                         how to properly size electrical power cables, considering short circuit withstanding current,
                         ampacity calculations under actual site installation conditions, and voltage drop limitations
                         using IEC and NEC methods.