CL 05

Inspection checklist for PRE-POURING SAFETY

Uploaded by

sanjutechteam3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION CHECKLIST FOR

PRE-POURING SAFETY
Project : Diplomatic Residences, Sector - 111, Gurgaon, Haryana WO Ref. No. : PCPL/PROJECTS/DR/2024/WO-009

Owner : M/s Puri Construction Pvt. Ltd. (PCPL) Reference No. : VCL/DIPLOMATIC/CL/SI/

Contractor : M/s Varindera Constructions Limited (VCL) Date :

Location :

Type of Structure :

Reference Document / Drawing No. :

Grid:

Status
S No. Acceptance Criteria Remarks
Yes No
PRE-POURING SAFETY INSPECTION CHECKLIST
Are all supports / props provided for the shuttering for slab of
1
adequate strength and properly fixed and braced?
2 Do all Props rest on the ground firmly?
Are all props property pinned, braced with ledgers, pipes and tied
3
with couplers?
4 Are edges of the slab property barricaded?
Have provisions been made to install edge protection (barricading/
5 vertical safety net etc.) once pour is completed i.e. inserting ≥ 20 mm
rebars, pipe etc. prior to casting?

6 Are all loose / free fall materials removed from the slab?

7 Is the vibrator cable connected to ELCB / RCCB?


Is the condition of the vibrator cable to be used while casting
8
acceptable / good?
9 Is lighting arrangement proper?
Is the condition of walk way challis provided to walk on reinforcement
10
while casting work acceptable/good?
Are the ladders providing access to the Slab securely fixed at the top
11
and bottom?
12 Are openings in working platform kept safely covered/ fenced?
13 Is there a provision of handrails for anchoring full body harness?
Is the concrete pipe line clean and properly secured / supported /
14 damped so as to ensure it is not touching erected scaffolding /
shuttering / formwork etc.?
Are horizontal safety nets provided wherever required i.e. just below
15
working platform?
16 Have all the workers been explained safe work procedures?
17 Are emergency resources (e.g. Ambulance, Driver, First-aider etc.)
Are the workers & staff engaged in concrete/casting work equipped
18 with mandatory PPE's like Safety Helmet, Safety Full body harness,
Safety Shoes Gumboot, Goggles, rubber gloves etc.?
Remarks :

Contractor's Representative Client's Representative

Name : Name :

Designation : Designation :

Signature : Signature :

Date : Date :