Graduation Project
Graduation Project
By
Graduation Project
2023
Acknowledgments
First of all, we deeply thank Allah for helping us accomplish this Project
and we devote it to our families, thanks to their encouragement, patience,
and assistance over the years.
We would like to thank many personnel for his support for the completion
of this work. Specially, our supervisor Prof. Dr. Mousa Abdallah.
Special thanks to Eng. Ahmed Metwally & Eng. Omar Saad & Eng.
Walid Fawzy Mohamed & Eng. Omar Hassan Taha & Eng. Ahmed
Moustafa Ahmed & Eng. Ahmed Dewidar & Eng. Seham Hamdy from
ELSEWEDY ELECTRIC T&D for their guidance along the technical
sessions.
Also, we would like to express our gratitude Smart Power Service (SPS)
for their continuous guidance and support specially Dr. Amr Kasem, Eng.
Mohamed Khaled, and Eng. Mahmoud Magdy.
ABSTRACT
This project aims to design a transformation substation meeting all the
required specifications and quality standards for safe and reliable
operation.
An electrical substation is a subsidiary station of an electricity generation,
transmission, and distribution system where voltage is transformed from
high to low or the reverse using transformers.
Electric power may flow through several substations between generating
plant and consumer and may be changed in voltage in several steps.
A substation receives electrical power from generating station via
incoming transmission lines and delivers electrical power via outgoing
transmission lines. Substations generally have switching, protection,
control equipment and transformers.
Our case study on Zahraa EL-Mokattam 220/22 KV GIS Substation
which includes the primary and secondary design of all the equipment
associated with this substation.
Table of Contents
CHAPTER 1 INTRODUCTION ............................................................................................... 18
1.1 Introduction ...................................................................................................................... 19
1.2 Sulfur Hexafluoride (SF6) ............................................................................................... 20
1.2.1 Introduction to Sulfur Hexafluoride ........................................................................... 20
1.2.2 Physical Properties ................................................................................................... 21
1.3 Classification of Substation ............................................................................................. 23
1.3.1 Classification based on voltage levels: .................................................................... 23
1.3.2 Classification based on Short Circuit level: ........................................................... 23
1.3.3 Classification based on Insulating Medium: .......................................................... 24
1.3.3.1 Air-insulated switchgear (AIS) ........................................................................ 24
1.3.3.2 Gas insulated switchgear (GIS) .......................................................................... 26
1.3.4 Classification based on Configuration .................................................................... 29
1.3.4.1 Single bus ........................................................................................................... 30
1.3.4.2 Double bus single breaker. ............................................................................... 30
1.3.4.3 Double bus double breaker. ............................................................................. 31
1.3.4.4 Ring bus ............................................................................................................. 32
1.3.4.5 Breaker and half breaker ................................................................................. 33
1.4 Project description ........................................................................................................... 34
CHAPTER 2 SLD & GLO ......................................................................................................... 35
2.1 SLD .................................................................................................................................... 36
2.1.1 Introduction SLD...................................................................................................... 36
2.1.2 Advantages of single line diagram .......................................................................... 36
2.1.3 Some of the standard symbols used to represent SLD .......................................... 36
2.1.3.1 Bus-bar: ............................................................................................................... 37
2.1.3.2 Power transformers: ............................................................................................ 37
2.1.3.3 Circuit breaker: ................................................................................................... 37
2.1.3.4 Isolators or Isolating switches:............................................................................ 38
2.1.3.5 Earth switch: ....................................................................................................... 38
2.1.3.6 Current transformers (CT): ................................................................................. 38
2.1.3.7 Potential transformers (PT): ................................................................................ 38
2.1.3.8 Lightning arresters(LA): ..................................................................................... 38
2.1.3.9 Coupling capacitor: ............................................................................................. 38
2.1.3.10 Wave trap: ......................................................................................................... 38
2.1.4 The project data ........................................................................................................ 39
2.1.5 Scope single line diagram ......................................................................................... 39
2.1.5.1 220 kV GIS Switchgear and Equipment: ............................................................ 39
2.1.5.2 220kV outdoor equipment: ................................................................................. 40
2.1.5.3 Supply, install and connect for 220k winding neutral point equipment of the
three phase power transformer: ....................................................................................... 41
2.1.5.4 Supply, install and connect for 22KV winding neutral point equipment of the
three phase power transformer: ....................................................................................... 41
2.1.5.5 22 kV switchgear: ............................................................................................... 41
2.1.6 Single Line diagram for 220/22 KV Substation ..................................................... 43
2.2 General Layout (GLO) .................................................................................................... 44
2.2.1 Introduction ................................................................................................................ 45
2.2.2 Substation Layout Arrangement ................................................................................. 45
2.2.3 Important parameters and considerations for substation design ................................. 46
2.2.3.1 Environmental Conditions .................................................................................. 46
2.2.4 Minimum Clearance ................................................................................................... 47
2.2.5 Factor of safety ........................................................................................................... 47
2.2.6 General Layout Design ............................................................................................... 48
2.2.6.1 Gantry Area ......................................................................................................... 48
2.2.6.2 GIS Building ....................................................................................................... 48
2.2.6.3 Transformer Area ................................................................................................ 49
2.2.6.4 Main Road ........................................................................................................... 49
2.2.6.5 Capacitor Bank Area ........................................................................................... 50
2.2.6.6 Control Building ................................................................................................. 50
2.2.6.6.1 Switchgear Room .................................................................................... 51
2.2.6.7 Control Room...................................................................................................... 51
2.2.7 General Layout ........................................................................................................... 52
2.2.8 First Layout................................................................................................................. 52
CHAPTER 3 SHORT CIRCUIT CALCULATIONS ............................................................. 53
3.1 Introduction ...................................................................................................................... 54
3.1.1 Causes of Short Circuit ............................................................................................... 54
3.1.2 Effects of Short Circuit ............................................................................................... 55
3.1.3 Important of Short-Circuit Calculations ..................................................................... 56
3.2 Definitions ......................................................................................................................... 57
3.2.1 Terms and Definitions ................................................................................................ 57
3.2.1.1 Symmetrical short circuit current (𝐼𝑘) ................................................................ 57
3.2.1.2 Initial symmetrical short circuit current (𝐼𝑘′′) .................................................... 57
3.2.1.3 Initial symmetrical short-circuit apparent power (𝑆′′𝐾) ..................................... 57
3.2.1.4 Peak short-circuit current (𝑖𝑝) ............................................................................. 57
3.2.1.5 Decaying Component Direct current aperiodic component (𝐼𝑑𝑐) .................... 57
3.2.1.6 Steady-state short-circuit current (𝐼𝑘)................................................................. 57
3.2.1.7 Symmetrical breaking current (𝐼𝑏) ..................................................................... 58
3.2.1.8 Nominal system voltage (𝑈𝑛) ............................................................................. 58
3.2.1.9 Equivalent voltage source (𝑐𝑈𝑛/3) .................................................................... 58
3.2.1.10 Voltage factor (c) .............................................................................................. 58
3.2.1.11 Far-from-generator short circuit ....................................................................... 58
3.3 Short-Circuit Current Analysis ...................................................................................... 59
3.3.1 Short-Circuit Path in the Positive-Sequence System .................................................. 60
3.4 Classification of Short-Circuit Types ............................................................................. 62
3.4.1 Symmetrical Fault....................................................................................................... 63
3.4.2 Unsymmetrical Fault .................................................................................................. 63
3.5 Methods of Short-Circuit Calculation ............................................................................ 64
3.5.1 Equivalent Voltage Source ......................................................................................... 65
3.6 Calculation Equations According (IEC 60909) ............................................................. 67
3.6.1 Impedance Equation ................................................................................................... 67
3.6.1.1 Network Feeder ................................................................................................... 67
3.6.1.2 Transformer Impedance ...................................................................................... 68
3.6.2 Short Circuit Current Equation ................................................................................... 69
3.6.2.1 Initial symmetrical short circuit current (𝐼𝑘′′) .................................................... 69
3.6.2.2 Peak short-circuit current (𝑖𝑝) ............................................................................. 69
3.6.2.3 Decaying Component Direct current aperiodic component (𝐼𝑑𝑐) .................... 70
3.6.2.4 Steady-state short-circuit current (𝐼𝑘)................................................................. 70
3.6.3 Symmetrical breaking current (𝐼𝑏) ............................................................................. 70
3.7 Short Circuit Calculation 220/22 kV GIS Substation ................................................... 71
3.7.1 Short Circuit Calculation Using MATLAB................................................................ 71
3.7.1.1 Substation Configuration (SLD) ......................................................................... 71
3.7.1.2 MATLAB Code .................................................................................................. 72
3.7.1.3 Input Data............................................................................................................ 74
3.7.1.4 Output Data From MATLAB (SC Calculation) ................................................. 75
3.7.2 Short Circuit Calculation Using ETAP ...................................................................... 78
3.7.2.1 Power Grid .......................................................................................................... 78
3.7.2.2 Transmission Line ............................................................................................... 79
3.8 Transformer...................................................................................................................... 80
3.9 Cable .................................................................................................................................. 81
3.10 RUN SC According IEC 60909 ..................................................................................... 82
3.10.1 Report from ETAP.................................................................................................... 82
CHAPTER 4 EARTHING SYSTEM ........................................................................................ 83
4.1 Earthing system:............................................................................................................... 84
4.2 Definitions: ........................................................................................................................ 85
4.3 Importance:....................................................................................................................... 87
4.4 Designing steps: ................................................................................................................ 88
4.4.1 Measurements of Soil Resistivity ............................................................................... 88
4.4.2 Determine the Surface Layer Derating Factor ............................................................ 89
4.4.3 Conductor sizing ......................................................................................................... 91
4.4.4 Calculation of tolerable step voltage and touch voltage: ............................................ 94
4.4.5 Calculation of the number of conductors and the way to implement them: ............... 95
4.4.6 Calculation of the Earthing Grid Resistance: ............................................................. 96
4.4.7 Calculation of Maximum Grid Current: ..................................................................... 97
4.4.8 Calculation of Ground Potential Rise (GPR): ............................................................ 98
4.4.9 Calculating Maximum Step voltage and Touch voltage: ........................................... 99
4.4.10 Comparing: ............................................................................................................. 100
4.5 Designing of Substation Grounding Grid (Case study) .............................................. 101
4.5.1 Soil Resistivity:......................................................................................................... 101
4.5.2 Surface Layer Derating Factor: ................................................................................ 101
4.5.3 Cross Sectional Area of Conductors:........................................................................ 101
4.5.4 Safe Limits of Step Voltage and Touch Voltage: ..................................................... 102
4.5.5 Number of Conductors: ............................................................................................ 102
4.5.6 Grid Resistance: ........................................................................................................ 103
4.5.7 Maximum Grid Current: ........................................................................................... 103
4.5.8 Ground Potential Rise (GPR): .................................................................................. 103
4.5.9 Calculate Actual Mesh and Step Voltages by using Etap ........................................ 104
4.6 Designing of Substation Grounding Grid Using ETAP ............................................. 104
4.7 Secondary earthing ........................................................................................................ 109
CHAPTER 5 Raceway .............................................................................................................. 113
5.1 Raceway: ......................................................................................................................... 114
5.1.1 Cable Trench: ........................................................................................................... 114
5.1.1.1 Cable trays and Classification:.......................................................................... 115
5.1.1.2 Ladder trays: ..................................................................................................... 116
5.1.1.3 Perforated Cable Tray ....................................................................................... 116
5.1.1.4 Solid Bottom Cable Tray (Duct) ....................................................................... 117
5.1.1.5 Basket-type Cable Tray (Wire Mesh): .............................................................. 118
5.1.2 Filling Ratio .............................................................................................................. 119
5.1.2.1 Conduit size for cable: ...................................................................................... 119
5.1.2.2 Conduit material: .............................................................................................. 120
5.1.2.3 Calculation the filling ratio of all cables inside conduit: .................................. 120
5.1.3 Duct Bank ................................................................................................................. 122
5.1.4 Spacing between conductor ...................................................................................... 123
CHAPTER 6 Overvoltage Protection ..................................................................................... 126
6.1 Introduction .................................................................................................................... 127
6.2 Causes of Overvoltage .................................................................................................... 128
6.2.1 Internal faults ............................................................................................................ 128
6.2.2 External faults ........................................................................................................... 128
6.3 Lightning Protection System (LPS) .............................................................................. 129
6.3.1 LPS Components ...................................................................................................... 129
6.3.2 LPS Design Methods ................................................................................................ 131
6.3.2.1 Fixed Angles Method ........................................................................................ 132
6.3.2.2 Empirical Curves Method ................................................................................. 133
6.3.2.3 Rolling sphere method ...................................................................................... 134
6.3.3 LPS Calculations ...................................................................................................... 137
6.4 Metal Oxide Surge Arrester (MOSA) .......................................................................... 139
6.4.1 Introduction .............................................................................................................. 139
6.4.2 Construction.............................................................................................................. 139
6.4.3 Operation .................................................................................................................. 141
6.4.4 ZnO Surge Arrester .................................................................................................. 143
CHAPTER 7 Switching devices ............................................................................................... 145
7.1 Puffer Type SF6 Circuit Breaker: ................................................................................ 146
7.1.1 Construction.............................................................................................................. 146
7.1.2 Working Principle..................................................................................................... 148
7.1.2.1 Normal Condition ............................................................................................. 148
7.1.2.2 Circuit Breaker Opening Operation .................................................................. 148
7.1.2.3 Circuit Breaker Closing Operation ................................................................... 150
7.1.3 Advantages of SF6 puffer type circuit breakers ....................................................... 150
7.1.4 Disadvantages of SF6 puffer type circuit breakers ................................................... 151
7.1.5 Nameplate Details of SF6 Circuit Breaker ............................................................... 151
7.1.5.1 Mandatory Parameters ...................................................................................... 153
7.1.5.1.1 Rated voltage ......................................................................................... 154
7.1.5.1.2 Rated frequency ..................................................................................... 154
7.1.5.1.3 Rated normal current ............................................................................. 154
7.1.5.1.4 Short circuit breaking current ................................................................ 155
7.1.5.1.5 Rated duration of short circuit ............................................................... 155
7.1.5.1.6 Rated peak withstand current or Rated making current ........................ 155
7.1.5.1.7 Rated short duration power frequency withstand voltage ..................... 156
7.1.5.1.8 Rated lighting impulse withstand voltage ............................................. 157
7.1.5.1.9 First pole to clear factor ......................................................................... 157
7.1.5.1.10 Rated operating sequence ...................................................................... 158
7.1.5.1.11 Switching duty: ...................................................................................... 160
7.1.5.1.12 Rated pressure of SF6 gas ..................................................................... 160
7.1.5.1.13 Total weight of SF6 gas ......................................................................... 160
7.1.5.1.14 Total weight of CB ................................................................................ 161
7.1.5.1.15 Rated control voltage ............................................................................. 161
7.1.5.2 Condition based parameters .............................................................................. 161
7.1.5.2.1 Rated switching impulse withstand voltage .......................................... 161
7.1.5.2.2 DC component of short circuit current .................................................. 162
7.1.5.2.3 Rated line charging current.................................................................... 162
7.1.5.2.4 Classification ......................................................................................... 162
7.1.5.3 Optional Parameters .......................................................................................... 163
7.1.5.3.1 Rated out of phase current ..................................................................... 163
7.1.5.3.2 Rated cable Charging............................................................................. 164
7.1.5.3.3 Rated single capacitor bank breaking current ........................................ 164
7.1.5.3.4 Rated back-to-back capacitor bank breaking current ............................ 164
7.1.6 Mechanical Operating Mechanism of Circuit Breaker ............................................. 165
7.1.6.1 The hydromechanical mechanism..................................................................... 165
7.1.6.2 Spring Operating Mechanism ........................................................................... 166
7.2 Disconnecting Switch ..................................................................................................... 168
7.2.1 Disconnecting Switch Function ................................................................................ 168
7.2.2 Disconnect Switch Status ......................................................................................... 170
7.3 Earth Switch ................................................................................................................... 171
7.3.1 Earth Switch Function .............................................................................................. 171
7.3.2 Earth Switch Construction ........................................................................................ 172
7.3.3 Earth Switch Status ................................................................................................... 172
7.4 High Speed Earth Switch ............................................................................................... 172
7.5 The sequence of operation ............................................................................................. 174
CHAPTER 8 Auxiliary power supply and transformer ....................................................... 175
8.1 Introduction .................................................................................................................... 176
8.2 Substation main low voltage load ................................................................................. 177
8.2.1 Lighting: ................................................................................................................... 177
8.2.2 Sockets ...................................................................................................................... 179
8.3 Complete load estimation of 220/22 KV substation .................................................... 182
8.4 Auxiliary Transformer .................................................................................................. 184
8.4.1 Auxiliary transformer sizing ..................................................................................... 184
8.4.2 Auxiliary transformer and its specs: ......................................................................... 184
8.4.3 The requirements of the auxiliary transformer: ........................................................ 186
8.4.3.1 General: ............................................................................................................. 186
8.4.3.2 Transformation ratio and connection: ............................................................... 186
8.4.3.3 Voltage control: ................................................................................................ 186
8.4.3.4 Tapping and Tap changing: .............................................................................. 186
8.4.3.5 Overload capacity: ............................................................................................ 187
8.4.3.6 Limits of Temperature Rise: ............................................................................. 187
8.4.3.7 Bushing: ............................................................................................................ 188
8.4.3.8 Accessories and Fittings: .................................................................................. 188
8.4.3.9 Transformer room: ............................................................................................ 189
8.4.4 Operation of substation auxiliary transformer .......................................................... 189
8.5 Circuit Breaker: ............................................................................................................. 190
8.5.1 Type of circuit breaker: ............................................................................................ 190
8.5.1.1 Miniature circuit breakers (MCB): ................................................................... 190
8.5.1.2 Molded-case circuit breaker (MCCB): ............................................................. 190
8.5.1.3 Air Circuit Breaker (ACB)................................................................................ 191
8.5.2 Circuit breaker selection: .......................................................................................... 191
8.6 Cables: ............................................................................................................................. 193
8.6.1 Cables and conductor types ...................................................................................... 193
8.6.1.1 Single core cable ............................................................................................... 193
8.6.1.2 Multi core cables: .............................................................................................. 193
8.6.2 Feeding cables requirements .................................................................................... 194
8.6.3 Cable Sizing Calculations ......................................................................................... 194
8.6.3.1 Ampacity: .......................................................................................................... 195
8.6.3.2 Derating factors ................................................................................................. 195
8.7 Voltage drop.................................................................................................................... 196
8.8 Short circuit: ................................................................................................................... 197
CHAPTER 9 DC AUXILARY SYSTEM ............................................................................... 198
9.1 Introduction .................................................................................................................... 199
9.2 Function of DC system:.................................................................................................. 200
9.3 Battery Types: ................................................................................................................ 201
9.3.1 Lead-acid batteries:................................................................................................... 201
9.3.2 Nickel-cadmium batteries: ........................................................................................ 202
9.4 DC system configuration: .............................................................................................. 203
9.4.1 Single 100% battery Low capital cost No standby DC and 100% charger System . 203
9.4.2 Semi-duplicate 2*50% batteries and 2 *100% chargers: ......................................... 204
9.4.3 Fully duplicate 2 * 100% batteries and 2 * 100% chargers: .................................... 204
9.5 DC system Voltage in substations:................................................................................ 205
9.6 DC Parameters: .............................................................................................................. 206
9.7 Design Factors: ............................................................................................................... 206
9.7.1 Temperature derating factor (Tt): ............................................................................. 206
9.7.2 Design margin factor: ............................................................................................... 207
9.7.3 Ageing factor: ........................................................................................................... 207
9.7.4 Capacity rating factor (Kt) ........................................................................................ 208
9.8 Load classifications: ....................................................................................................... 208
9.8.1 Continuous loads: ..................................................................................................... 208
9.8.2 Non-Continuous loads: ............................................................................................. 209
9.8.3 Momentary Loads: .................................................................................................... 210
9.9 Duty cycle diagram: ....................................................................................................... 211
9.10 Battery sizing Calculation "according to (IEEE-1115)": ......................................... 211
9.10.1 Number of cells calculation: ................................................................................... 213
9.10.2 Batteries Sizing methodology:................................................................................ 214
9.10.3 Ampere-hour sizing ................................................................................................ 216
9.11 Battery Charger............................................................................................................ 218
9.11.1 Definition ................................................................................................................ 218
9.11.2 Battery charger rating "according to (EUS-E16)": ................................................. 218
9.11.3 Battery charger calculation ..................................................................................... 219
CHAPTER 10 INSTRUMENT TRANSFORMERS ............................................................. 220
10.1 Introduction .................................................................................................................. 221
10.2 CURRENT TRANSFORMERS (CTs) ....................................................................... 222
10.2.1 Magnetization curve ............................................................................................... 223
10.2.2 Knee-point voltage ................................................................................................. 224
10.2.3 Difference Between Measuring and Protective CTs .............................................. 224
10.2.4 Core Material of CTs .............................................................................................. 225
10.2.5 CT Burden .............................................................................................................. 226
10.2.6 Technical Terms of CTs ......................................................................................... 228
10.2.7 Theory of Current Transformers............................................................................. 231
10.2.8 CT Errors ................................................................................................................ 232
10.2.9 Open-circuiting of the Secondary Circuit of a CT ................................................. 234
10.2.10 Class X current transformers ................................................................................ 235
10.3 VOLTAGE TRANSFORMERS (VTs) ...................................................................... 235
10.3.1 VT Errors ................................................................................................................ 236
10.3.2 Limits of VT Errors for Protection ......................................................................... 236
10.3.3 Type of VTs ............................................................................................................ 237
10.3.3.1 Electromagnetic Type VTs ............................................................................. 237
10.3.3.2 Coupling Capacitor Voltage Transformers (CCVTs) ..................................... 238
CHAPTER 11 Protection Systems and Schemes ................................................................... 240
11.1 Introduction .................................................................................................................. 241
11.1.1 Classification of Relays and Basic requirements ............................................... 242
11.1.2 Zones of protection ............................................................................................... 243
11.1.3 Main and backup protection ............................................................................... 244
11.1.4 Tripping circuits ................................................................................................... 245
11.1.5 Trip circuit supervision ........................................................................................ 245
11.2 Feeder Protection ......................................................................................................... 247
11.2.1 Distance Relay ....................................................................................................... 247
11.2.1.1 Step Distance protection ............................................................................... 248
11.2.1.2 Problems facing distance protection ........................................................... 249
11.2.2 Line Current Differential Relay .......................................................................... 251
11.2.3 Common communication schemes ...................................................................... 252
11.2.4 Relay and Metering of feeder bay ....................................................................... 253
11.3 Transformer Protection ............................................................................................... 254
11.3.1 Purpose of transformer protection ..................................................................... 254
11.3.2 Types of Faults Encountered in Transformers .................................................. 254
11.3.2.1 External Faults .............................................................................................. 254
11.3.2.2 Internal Faults ............................................................................................... 255
11.3.3 Considerations for selecting protection system.................................................. 256
11.3.4 Types of Transformer Protection ........................................................................ 257
11.3.4.1 Differential protection – ANSI 87T ............................................................. 257
11.3.4.2 Restricted earth fault protection ................................................................. 260
11.3.4.3 Overcurrent protection ................................................................................ 261
11.3.4.4 Over flux protection ...................................................................................... 263
11.3.4.5 Mechanical protection .................................................................................. 264
11.3.5 Relay and Metering of Transformer 220/22 KV................................................ 269
11.4 Busbar protection ......................................................................................................... 271
11.4.1 Bus-bar protection requirements ........................................................................ 271
11.4.2 Busbar protection types ....................................................................................... 271
11.4.2.1 Busbar differential protection ..................................................................... 272
11.4.2.1.1 Low impedance differential protection.................................................. 272
11.4.2.1.2 High impedance differential protection ................................................. 273
CHAPTER 12 Relay coordination study ................................................................................ 275
12.1 Over current protection ............................................................................................... 276
12.2 Purpose of OC protection: ........................................................................................... 277
12.3 Principles of time/current grading.............................................................................. 277
12.4 Standard IDMT overcurrent relay ............................................................................. 278
12.5 Overcurrent sitting ....................................................................................................... 280
12.5.1 ETAP program ..................................................................................................... 282
12.5.2 Time coordination Curve (TCC) ......................................................................... 289
12.5.3 calculation pickup Currents using EXCEL sheet.............................................. 290
CHAPTER 13 Substation Control & Monitoring ................................................................. 291
13.1 Introduction .................................................................................................................. 292
13.2 Basic Control System ................................................................................................... 292
13.3 Details of Conventional HMI ...................................................................................... 294
13.4 Details of Computer-Based HMI ................................................................................ 295
13.5 Local Control Cabinet ................................................................................................. 297
13.6 Bay Controller .............................................................................................................. 301
References .................................................................................................................................. 303
List of figures
Figure 1.1 Power System Elements .............................................................................................. 19
Figure 1.2 Molecular structure of sulfur hexafluoride SF6 .......................................................... 21
Figure 1.3 Arc current of SF6, with SF6 gas-to-air gas mixture and air ...................................... 22
Figure 1.4 Physical Properties of Sulphur Hexafluoride – SF 6 ................................................... 23
Figure 1.5 Gas insulated switchgear ............................................................................................. 26
Figure 1.6 Comparison between GIS & AIS Substations ............................................................. 29
Figure 1.7 Single Bus arrangement ............................................................................................... 30
Figure 1.8 Double bus–single breaker arrangement. .................................................................... 30
Figure 1.9 Double breaker–double bus arrangement .................................................................... 31
Figure 1.10 Ring Bus arrangement ............................................................................................... 32
Figure 1.11 Breaker-and-a-half arrangement ................................................................................ 33
Figure 2.1 single line diagram of 220/22KV substation ............................................................. 43
Figure 2.2 Gantry Area ................................................................................................................. 48
Figure 2.3 GIS Building ................................................................................................................ 49
Figure 2.4 Transformer Area ........................................................................................................ 49
Figure 2.5 Capacitor Banks Area .................................................................................................. 50
Figure 2.6 Control Building 1 ....................................................................................................... 50
Figure 2.7 Switchgear Room ....................................................................................................... 51
Figure 2.8 Control Room .............................................................................................................. 51
Figure 2.9 General Layout ............................................................................................................ 52
Figure 2.10 First Layout ............................................................................................................... 52
Figure 3.1 time behavior of the short-circuit current .................................................................... 59
Figure 3.2 Equivalent circuit of the short-circuit current path in the positive-sequence system .. 60
Figure 3.3 Switching processes of the short circuit ...................................................................... 62
Figure 3.4 Short Circuit types ....................................................................................................... 64
Figure 3.5 Equivalent Voltage Source method ............................................................................. 65
Figure 3.6 short circuit is fed from a network without Transformer. .......................................... 67
Figure 3.7 short circuit is fed from a network with Transformer. ................................................ 68
Figure 3.8 X/R Ratio ..................................................................................................................... 70
Figure 3.9 SLD.............................................................................................................................. 71
Figure 3.10 Input data (MATLAB) .............................................................................................. 74
Figure 3.11 Power Grid Data (ETAP) .......................................................................................... 78
Figure 3.12 Transmission Line Data (ETAP) ............................................................................... 79
Figure 3.13 Transformer Data (ETAP) ......................................................................................... 80
Figure 3.14 Cable Data From Elseewdy catalogue ....................................................................... 81
Figure 3.15 Cable Data (ETAP).................................................................................................... 81
Figure 3.16 Short Circuit Results (ETAP) .................................................................................... 82
Figure 3.17 Short Circuit Report (ETAP) ..................................................................................... 82
Figure 4.1 (Wenner method) ........................................................................................................ 89
Figure 4.2 (Maximum Grid Current) ........................................................................................... 97
Figure 5.1 Cable Trench ............................................................................................................. 115
Figure 5.2 Ladder tray................................................................................................................. 116
Figure 5.3 Perforated Cable Tray................................................................................................ 117
Figure 5.4 solid bottom cable tray .............................................................................................. 118
Figure 5.5 Basket type Cable Tray ............................................................................................. 118
Figure 5.6 filled by multiple cables. ........................................................................................... 119
Figure 5.7 specifications ............................................................................................................. 120
Figure 5.8 calculations of Filling ratio ........................................................................................ 122
Figure 5.9 filling ratio specifications .......................................................................................... 122
Figure 5.10 Duct Bank ................................................................................................................ 123
Figure 5.11 Spacing between conductor ..................................................................................... 124
Figure 5.12 Diameter of 630Sq.mm Cable ................................................................................. 124
Figure 5.13 Cable Trench ........................................................................................................... 125
Figure 6.1 Fixed angles for masts (IEEE-998) ........................................................................... 132
Figure 6.2 Fixed angles curve for masts (IEEE-998) ................................................................. 133
Figure 6.3 Empirical curve for masts and objects (IEEE-998) ................................................... 134
Figure 6.4 Principle of Rolling Sphere Method (IEEE-998) ...................................................... 135
Figure 6.5 Rolling Sphere Over an Object (NFPA-780) ............................................................ 135
Figure 6.6 Manual Calculations of GIS Building ....................................................................... 137
Figure 6.7 Protected GIS Building.............................................................................................. 138
Figure 6.8 Zoomed-in Protected GIS Building ........................................................................... 138
Figure 6.9 Construction of metal oxide surge arrester (MOSA) ................................................ 140
Figure 6.10 Metal oxide resistor disks ........................................................................................ 140
Figure 6.11 Microstructure of MOSA disk element (ZnO, Bi2O3) ........................................... 143
Figure 6.12 Equivalent circuit of MOSA element ...................................................................... 144
Figure 7.1. Construction of Puffer Type CB Interrupter. ........................................................... 147
Figure 7.2 SF6 CB Construction. ................................................................................................ 147
Figure 7.3. Operation of a Puffer Type SF6 Circuit Breaker. ..................................................... 149
Figure 7.4. Current and Voltage during Fault Clearing. ............................................................. 149
Figure 7.5 Short Circuit Making Current Waveform.................................................................. 156
Figure 7.6. Auto Reclosing System. ........................................................................................... 159
Figure 7.7 Main Technical Parameters of CB. ........................................................................... 160
Figure 7.8 Hydromechanical operation mechanism. .................................................................. 165
Figure 7.9 Section view of Hydromechanical operation mechanism. ........................................ 166
Figure 7.10 Closed position (Closing spring Charged ) ............................................................. 167
Figure 7.11 Open position (Closing spring Charged ) ................................................................ 167
Figure 7.12 Closed position (Closing spring Charged ) ............................................................. 168
Figure 7.13. Cross-section of an isolated-phase GIS disconnector. ........................................... 169
Figure 8.1 32 A rated voltage 380 V........................................................................................... 181
Figure 8.2 16 A rated voltage 380 V........................................................................................... 182
Figure 8.3 Load estimation of 220/22 KV substation ................................................................. 183
Figure 8.4 Auxiliary transformers parameters ............................................................................ 185
Figure 8.5 Miniature circuit breaker ........................................................................................... 190
Figure 8.6 Molded-case circuit breaker ...................................................................................... 191
Figure 8.7 Air circuit breaker...................................................................................................... 191
Figure 8.8 Ratings of circuit breaker .......................................................................................... 192
Figure 8.9 Single core cable........................................................................................................ 193
Figure 8.10 Multi core cable ....................................................................................................... 194
Figure 9.1 DC auxiliary system .................................................................................................. 200
Figure 9.2 Lead acid batteries ..................................................................................................... 201
Figure 9.3 Nickel-Cadmium Battery........................................................................................... 202
Figure 9.4 Single battery single charger ..................................................................................... 203
Figure 9.5 one battery two charges ............................................................................................. 204
Figure 9.6 Two batteries tow charges system ............................................................................. 205
Figure 9.7 Duty cycle .................................................................................................................. 211
Figure 9.8 Generalized duty cycle .............................................................................................. 214
Figure 9.9 DC load summary ...................................................................................................... 216
Figure 9.10 Duty cycle diagram.................................................................................................. 217
Figure 9.11Total AH of battery .................................................................................................. 217
Figure 10.1 Typical CT magnetization curve ............................................................................. 223
Figure 10.2 Magnetization characteristics of CT cores .............................................................. 226
Figure 10.3 Equivalent circuit of CT as viewed from secondary side ........................................ 231
Figure 10.4 Capacitance voltage divider .................................................................................... 238
Figure 11.1 Division of power systems into protection zones .................................................... 243
Figure 11.2 Typical relay tripping circuits ................................................................................. 245
Figure 11.3 Trip circuit supervision circuit ................................................................................ 246
Figure 11.4 Typical basic protection for sub-transmission feeder .............................................. 247
Figure 11.5 Distance protection Zones ....................................................................................... 248
Figure 11.6 Load Encroachment ................................................................................................. 249
Figure 11.7 Power Swing ............................................................................................................ 250
Figure 11.8 Line Current Differential Relay-Scheme................................................................. 251
Figure 11.9 RMOLD of feeder bay............................................................................................. 253
Figure 11.10 Transformer fault statistics .................................................................................... 255
Figure 11.11 Percentage differential protection for Y - ∆ connected ........................................ 257
Figure 11.12 Operating characteristic of percentage differential relay ...................................... 259
Figure 11.13 Bias setting of percentage differential relay .......................................................... 259
Figure 11.14 Earth fault protection of a power transformer ....................................................... 260
Figure 11.15 Connection of overcurrent protection devices on both sides of a power transformer
..................................................................................................................................................... 262
Figure 11.16 Coordination between HV & LV sides of Transformer ........................................ 262
Figure 11.17 characteristics of over flux protection ................................................................... 263
Figure 11.18 Buchholz Relay mounting arrangement ................................................................ 264
Figure 11.19 Sudden Pressure Rise Relay .................................................................................. 266
Figure 11.20 Oil Pressure Relief Relay ...................................................................................... 267
Figure 11.21Winding Thermometer ........................................................................................... 268
Figure 11.22 RMOLD of transformer bay ................................................................................. 270
Figure 11.23 The Differential protection for a bus-bar............................................................... 272
Figure 11.24 Low Impedance bus Differential Protection diagram ........................................... 273
Figure 11.25 High Impedance bus Differential Protection diagram ........................................... 274
Figure 12.1 Relay characteristics ................................................................................................ 279
Figure 12.2 ETAP MODEL ........................................................................................................ 282
Figure 12.3 Time Coordination Curve (TCC) ............................................................................ 289
Figure 13.1 an example of human machine interface locations................................................. 293
Figure 13.2 Indoor local control cabinet ..................................................................................... 297
Figure 13.3 Outdoor local control cabinet .................................................................................. 298
Figure 13.4 Mimic diagram ........................................................................................................ 299
List of Table
Table 2.1 220KV equipment's legend and symbols ...................................................................... 36
Table 2.2 22KV equipment’s and legend symbols ..................................................................... 37
Table 2.3 Environmental Conditions ............................................................................................ 46
Table 2.4 Minimum Clearance ..................................................................................................... 47
Table 2.5 Factor of safety ............................................................................................................. 47
Table 3.1 Voltage factor c, according to IEC 60909 .................................................................... 66
Table 3.2 Typical values of impedance voltage drop of three-phase transformer. ....................... 69
Table 3.3 Output Data (MATLAB) for HV Busbar ..................................................................... 76
Table 3.4 Output Data (MATLAB) for LV Busbar ...................................................................... 77
Table 4.1 Basic range of soil resistivity ........................................................................................ 88
Table 4.2 typical surface material resistivity ................................................................................ 91
Table 4.3: material constants ........................................................................................................ 93
Table 6.1 Maximum values of rolling sphere radius (IEC-62305-3).......................................... 136
Table 6.2 Final results of the manual calculations for all protection zones ................................ 138
Table 7.1 Nameplate of SF6 Circuit Breaker.............................................................................. 152
Table 10.1 CTR Errors ................................................................................................................ 233
Table 10.2 VTR Errors ............................................................................................................... 236
Table 11.1 Transformer categories Rating.................................................................................. 256
Table 11.2 Types of Mechanical Protection ............................................................................... 264
Table 11.3 RMOLD .................................................................................................................... 269
Table 12.1 Definitions of standard relay characteristics ............................................................ 279
CHAPTER 1 INTRODUCTION
18 | P a g e
CHAPTER 1 Introduction
1.1 Introduction
Generally, the power system consists of three main elements which are
generation, transmission and distribution Substation: is part of power system in
which the voltage is transformed from level to level for transmission, distribution,
transformation and switching. The electric power is produced at the power stations
which are located at favorable places, generally quite away from the consumers.
19 | P a g e
CHAPTER 1 Introduction
level in the grid to perform various tasks for example we transmit electrical power
at high voltage (220 KV, 132 KV, 66 KV) and sometimes extra high voltage (400
KV, 500 KV, 765 KV) and ultra-high voltage (more than 765 KV according to IEC
standard). Using high voltage for power transmission provides many benefits such
as decrease ohmic losses, decrease cross section area of conductors, increase power
transfer capability moreover transfer power for long distance. Addition benefit of
substation it is the core of unified utility electrical grid as the substation connect the
generation station from all over country through the transmission grid. The
substation provides the high reliability of the grid as through the substation we can
switch off the faulty sections of the grid and maintain the stability. The electrical
national grid through substations provides a very economic power system as we can
generate power in a place and transmit power to a distant place. The substations help
in the control of the electrical national grid as in case of increasing the loads in peak
times operators of the grid start of switching off less importance distribution
substations and decrease the current load to be suitable with the generation power
which maintain stability and prevent blackouts. Another strategy in case of high load
in peak times we can transfer electrical power in our national grid from substations
which is connected with other substations in different countries.
20 | P a g e
CHAPTER 1 Introduction
IEC 60480, 62271-203 for HV GIS, 62271-100 for circuit breakers and 62271-102
for disconnectors.
The main characteristic of SF6 useful for the design of high-voltage equipment
is the high dielectric withstand capability, which is about 3 times the dielectric
withstands of air. Used in high voltage equipment with gas pressures of up to 8 bar,
the size of equipment using SF6 can be reduced by up to ten times as compared to
equivalent air-insulated installations. SF6 gas also effectively quenches arcs in
circuit breakers, disconnectors, and ground switches. Pure SF6 increases strongly
the arc-quenching capability with increasing pressure, as shown in Figure 1.3. This
is the reason why the gas pressure in breaker compartments of a GIS has the highest
gas pressure compared to the bus bar gas compartment or to gas compartments of
disconnectors and ground/earth switches. If the SF6 gas is mixed with air, the
resulting arc-quenching capability is strongly reduced. The SF6 related arc currents
of air are much lower, as shown in Figure 1.3. The metal encapsulation of GIS makes
21 | P a g e
CHAPTER 1 Introduction
the equipment very safe to operate because all high voltage parts are contained and
properly insulated and the metallic enclosure is grounded and can be normally
touched without injury. The SF6 insulation gas inside the GIS does not show any
aging effects and is protected by the metal enclosure from ambient influences such
as humidity, dust, salt air, and others. Therefore, the maintenance required is very
low. Today’s state-of-the-art GIS have recommended maintenance cycles of 25
years. The main physical properties of SF6 to be used in high-voltage equipment are
shown in figure 1.4.
Figure 1.3 Arc current of SF6, with SF6 gas-to-air gas mixture and air
The data in Figure 1.4. is taken from different sources and in some cases the results
are found to be conflicting, possibly due to the variation in the chemical purity of
the gas tested. SF6 gas resembles C02 in many physical properties. Both these gases
are sublime and melt under a pressure of several atmospheres. Up to -50.8 C (melting
point). The SF6 gas is in equilibrium with the solid phase and liquid SF6 is
metastable. On the other hand, liquid SF6 cannot exist above 45.6 0 C, the critical
temperature.
22 | P a g e
CHAPTER 1 Introduction
• LV (up to 1000V).
• MV (1000V to 33kV).
• HV (33 KV and 220 kV).
• EHV (above 220KV).
• HVDC Substation
• 25 KA
• 31.5 KA
• 40 KA
• 50 KA
23 | P a g e
CHAPTER 1 Introduction
• 63 KA
• AIS
• GIS
The AIS uses air as the primary dielectric from phase to phase, and phase to
ground insulation. They have been in use for years before the introduction of GIS.
In Air Insulated Substation, air between phase-ground and phase-phase is used as
insulator. In spite of poor dielectric and statutory clearness of air more space is
required, and in urban populated area resources of area is very limited. Change in
ambient temperature such as humidity level, rain, pollutants in air cause the
insulation to deteriorate. Due to all these factors it’s required more space for
insulation of AIS in order to meet the specified requirements. The physical
infrastructure is venerable to continuous degradation due to atmospheric condition.
Any seismic instability can adversely affect the whole infrastructure. Because of all
above stated problems Air Insulated Substation require complex planning and more
execution time which increases its capital cost moreover its operational cost is also
high due to higher frequency of maintenance Undertaking all these facts an
insulation material is needed to decreases the size of substation. Using Gas Insulated
Substation is a solution to that. All equipment is enclosed in a gas filled chamber
which provides effective insulation in much less space as compared to Air Insulation
Substation. Special gas is used as insulation material whose properties are further
described in this paper. This gas is enclosed along with electric components such as
Bus-Bars, circuit breakers, switchgears… etc., in a chamber Using GIS not only
24 | P a g e
CHAPTER 1 Introduction
decreases our size but it also has many advantages in the form of cost and
maintenance.
Advantages
Disadvantages
The poor dielectric properties of air, as well as secondary factors such as humidity,
pollutants, moisture means that more space is required for efficacy.
25 | P a g e
CHAPTER 1 Introduction
Gas Insulated Substation is an electric power substation in which all live equipment
and bus bars are housed in grounded metal which is sealed and placed in a chamber
filled with gas. Isolated gas station by using sulfur hexafluoride (SF6), which has
superior dielectric properties used to moderate pressure to the phase to phase and the
ground insulation. In gas-insulated high voltage conductors, circuit breakers,
switches, current transformers, voltage transformers and surge protectors are
encapsulated in SF6 cans to the ground. Isolation in the gas is used when space is to
provide a high position in the big cities or permissions in normal positions between
phase to phase and phase to ground are very large. For this reason, a large space is
required for the sub-station or in normal air insulation (AIS). But the dielectric
strength of SF6 gas is higher relative to the air, necessary for phase to phase and
ground clearance for all equipment are much lower. Therefore, the overall size of
each team and the whole substation is reduced to about 10 % of the conventional air
insulation substations. Gas Insulated Substation (GIS) SF6 contains the same
compartments in conventional outdoor substations. All live parts are enclosed in
metal boxes filled with SF6 gas. The active parts are supported on insulators molten
resin. Some of these bushes are designed as barriers between adjacent modules such
26 | P a g e
CHAPTER 1 Introduction
that the gas does not pass through them. The entire system is divided into
compartments which are relative to the other gas-tight. Thus, the gas detection
system in each compartment can be independent and simpler. The housings are of
nonmagnetic materials such as aluminum or stainless steel and are connected to
ground. The gas seal is provided with 'O' static seal positioned between the machined
flanges. The “O – rings” are placed in the slots such that, after assembly, the “O-
ring” to shrink 20%. The quality of materials, the dimensions of grooves and “O –
rings” are important to ensure sealing performance of the gas-insulated gas station.
Gas Insulated station has a gas detection system. The gas inside of each compartment
should have a pressure in the range of the density of the gas in each compartment is
controlled 3kg/cm2 .The. If the pressure drops slightly, the gas is trapped
automatically. With new gas leaks, low pressure alarm is triggered or automatic or
shutdown.
Advantages of GIS
1. The earthed metal enclosure makes for a safe working environment for the
attending personnel.
2. Compartmentalized enclosure of the live parts makes for a very reliable
system due to reduced disruption of the insulation system.
3. By reducing the distance between active and non-active switchgear parts, less
space is required than in the normal AIS system: this comes in handy in
densely populated areas and unfavorable terrain (minimum requirements for
an AIS is about 47,000m2 , while GIS with the same power properties will
require approx.. 523m2 ). For the AIS, the highest element is approximately
28m, whereas for GIS you have 11m at the highest point for a 400kV
substation.
27 | P a g e
CHAPTER 1 Introduction
Disadvantages of GIS
28 | P a g e
CHAPTER 1 Introduction
1. Single bus.
2. Double bus single breaker.
3. Double bus double breaker.
4. Ring bus
5. Breaker and half breaker.
29 | P a g e
CHAPTER 1 Introduction
This is the simplest bus arrangement, a single bus and all connections directly to one
bus (Figure 1.7). Reliability of the single bus configuration is low: even with proper
relay protection, a single bus failure on the main bus or between the main bus and
circuit breakers will cause an outage of the entire facility. With respect to
maintenance of switching devices, an outage of the line they are connected to is
required. Furthermore, for a bus outage the entire facility must be de-energized. This
requires standby generation or switching loads to adjacent substations, if available,
to minimize outages of loads supplied from this type of facility. Cost of a single bus
arrangement is relatively low, but also is the operational flexibility; for example,
transfer of loads from one circuit to another would require additional switching
devices outside the substation.
30 | P a g e
CHAPTER 1 Introduction
The double bus-single breaker arrangement connects each circuit to two buses, and
there is a tie breaker between the buses. With the tie breaker operated normally
closed, it allows each circuit to be supplied from either bus via its switches. Thus
providing increased operating flexibility and improved reliability. For example, a
fault on one bus will not impact the other bus. Operating the bus tie breaker normally
open eliminates the advantages of the system and changes the configuration to a two
single bus arrangement (Figure 1.8). The double bus–single breaker arrangement
with two buses and a tie breaker provides for some ease in maintenance, especially
for bus maintenance, but maintenance of the line circuit breakers would still require
switching and outages as described above for the single bus arrangement circuits.
The double bus–double breaker arrangement involves two breakers and two buses
for each circuit (Figure 1.9). With two breakers and two buses per circuit, a single
bus failure can be isolated without interrupting any circuits or loads. Furthermore, a
circuit failure of one circuit will not interrupt other circuits or buses. Therefore,
31 | P a g e
CHAPTER 1 Introduction
As the name implies, all breakers are arranged in a ring with circuits connected
between two breakers. This arrangement affords increased reliability to the circuits,
since with properly operating relay protection, a fault on one bus section will only
interrupt the circuit on that bus section and a fault on a circuit will not affect any
other device (Figure 1.10). Protective relaying for a ring bus will involve more
complicated design and, potentially, more relays to protect a single circuit. Keep in
mind that bus and switching devices in a ring bus must all have the same ampacity,
since current flow will change depending on the switching device’s operating
position. From a maintenance point of view, the ring bus provides good flexibility.
A breaker can be maintained without transferring or dropping load, since one of the
two breakers can remain in-service and provide line protection while the other is
being maintained. Similarly, operating a ring bus facility gives the operator good
32 | P a g e
CHAPTER 1 Introduction
flexibility since one circuit or bus section can be isolated without impacting the loads
on another circuit. Cost of the ring bus arrangement can be more expensive than a
single bus, main bus and transfer, and the double bus–single breaker schemes since
two breakers are required for each circuit, even though one is shared. he ring bus
arrangement is applicable to loads where reliability and availability of the circuit is
a high priority.
33 | P a g e
CHAPTER 1 Introduction
Relay protection is similar to the ring bus, and due to the additional devices, is more
complex and costly than most of the previously reviewed arrangements.
34 | P a g e
CHAPTER 2 SLD & GLO
35 | P a g e
CHAPTER 2 SLD & GLO
2.1 SLD
2.1.1 Introduction SLD
A single line diagram also called the one-line diagram is a symbolic or
graphical representation of a three-phase power system. It has a diagrammatic
representation of all the equipment and connections. The electrical elements such
as circuit breakers, transformers, bus bars, and conductors, are represented using
standardized schematic symbols so that they can be read and understood easily. In
a single line diagram, instead of representing each of three phases with separate
lines, only a single conductor is represented using a single line. A single line
diagram makes it easy to understand an electrical system, particularly in the case of
complicated systems in substations. It helps in a detailed study and evaluation of
the system and its efficiency.
2.1.2 Advantages of single line diagram
• Helpful to identify when to perform troubleshooting and simplifies the
troubleshooting process.
• Meets compliance with applicable regulations and standards.
• Ensure a safer and more reliable operation of the facility
• Gives an overall understanding of the system and eases evaluation
• Accurate single line diagram will further ensure the safety of personnel
work.
2.1.3 Some of the standard symbols used to represent SLD
36 | P a g e
CHAPTER 2 SLD & GLO
2.1.3.1 Bus-bar:
When number of lines operating at the same voltage levels needs to be
connected electrically, bus-bars are used. Bus-bars are conductors made of copper
or aluminum, with very low impedance and high current carrying capacity.
2.1.3.2 Power transformers:
Power transformers are used generation and transmission network for
stepping-up the voltage at generating station and stepping-down the voltage for
distribution. Auxiliary transformers supply power to auxiliary equipment’s at the
substations.
2.1.3.3 Circuit breaker:
A circuit breaker is a circuit component that can open or close a circuit under
normal and fault conditions. It is designed such that it can be operated manually
under normal conditions and automatically under fault conditions. It is a special
type of switching device which can be operated safely under huge current carrying
conditions. It is used for timely disconnecting and reconnecting different parts of
the power system for protection and control.
37 | P a g e
CHAPTER 2 SLD & GLO
• One complete bay for bus coupler with rated current 2000A contains but not
limited to:
- One (1) three single phase GIS circuit breaker 2000A.
- Two (2) three single phase GIS disconnecting switches.
- Two (2) three single phase GIS maintenance earthing switches.
- Two (2) three single phase GIS current transformers.
- Local control panels.
39 | P a g e
CHAPTER 2 SLD & GLO
• Two complete transformer bays with rated current 1600A, each bay contains
but not limited to:
- One (1) three single phase GIS circuit breakers 1600A.
- Two (2) three single phase GIS disconnecting switches.
- Two (2) three single phase GIS maintenance earthing switches.
- One (1) three single phase GIS current transformers.
- One (1) three single phase bus ducts up to 220kV SF6 to air bushing
outside the GIS building.
- One (1) three single phase SF6 to air bushing at the end of the GIS
bus ducts.
- Local control panel.
• Two complete OHTL bays with rated current 1600A each bay contains but
not limited to:
- One (1) three single phase GIS circuit breaker, 1600A.
- Three (3) three single phase GIS disconnecting switches.
- Two (2) three single phase GIS maintenance earthing switches.
- One (1) three single phase GIS current transformers.
- One (1) three single phase high speed GIS earthing switches.
- One (1) three single phase bus ducts up to 220kV SF6 to air bushing
outside the GIS building.
- One (1) three single phase SF6 to air bushing at the end of the GIS
bus ducts.
- Local control panel.
2.1.5.2 220kV outdoor equipment:
• For OHTL bays, each bay shall contain:
- One (1) three single phase outdoor surge arrester.
- One (1) three single phase outdoor voltage transformers (1 coupling
capacitive voltage transformer + 2 capacitive voltage transformer), the
CCVT shall be erected on middle phase and shall be suitable for line
trap erection.
- One (1) line trap suitable to be erected on CCVT.
40 | P a g e
CHAPTER 2 SLD & GLO
2.1.5.3 Supply, install and connect for 220k winding neutral point
equipment of the three phase power transformer:
- One (1) single phase outdoor current transformer.
- One (1) single phase108kV outdoor surge arrester.
- One (1) single phase 123kV outdoor disconnector switch.
2.1.5.4 Supply, install and connect for 22KV winding neutral point
equipment of the three phase power transformer:
- One (1) single phase outdoor current transformer.
- One (1) single phase 15kV outdoor surge arrester.
- One (1) single phase 22kV outdoor disconnector switch.
- One (1) resistance 650A, 20 ohm, 30 sec.
2.1.5.5 22 kV switchgear:
The 22 kV switchgear single busbar with rated current 2500 A. one breaker
configuration shall be metal clad of indoor type with symmetrical short circuit
current of 31.5 kA for three seconds, withstand lightning impulse voltage 125
kVpeak, rated voltage 24 kVms and include but not limited to the followings as
specified herein and according to the attached single line diagram:
• Three (3) sections single phase bus bars of rated current 2500 A.
• Three (3) bus tie cells 2500 A each equipped with SF6 or vacuum circuit
breakers of rated current 2500 A as specified.
• Three (3) bus rise cells 2500 A each equipped with SF6 or vacuum circuit
breaker of rated 2500 A as specified interlocked with related bus tie circuit
Breaker.
• Three (3) incoming feeder cells 2500 A each equipped with SF6 or vacuum
circuit breaker of rated current 2500 A.
• Thirty-three (33) outgoing feeder cells 800 A each equipped with SF6 or
vacuum circuit breaker of rated current 800 A.
• Two (2) auxiliary transformer cells 800 A each equipped with SF6 or
vacuum circuit breaker of rated current 800 A.
• Three (3) for capacitor bank cells 1250 A each equipped with SF6 circuit
breaker of rated 1250 A as specified in the relevant sections in addition to
capacitor bank section.
41 | P a g e
CHAPTER 2 SLD & GLO
• Three (3) measuring cell each one contains three single phase voltage
transformer provided with H.R.C fuses.
• Nine (9) single phase lightning arresters of 24 kV, 2.5 kJ/kV for the three
sections (three for each section)
• All required AC and DC cable connections.
• All control, measuring and low voltage cables between the 22kV switchgear
and the control room panels.
• Control, measuring metering and protection equipment as specified in
relevant sections and SLD.
• 22 kV measuring transducers
• All other materials, equipment, switches, steel structure, cables and works
that may be required for completion and proper commercial operation of 22
kV switchgear.
42 | P a g e
CHAPTER 2 SLD & GLO
43 | P a g e
CHAPTER 2 SLD & GLO
44 | P a g e
CHAPTER 2 SLD & GLO
2.2.1 Introduction
General Layout of substations is the most important design considerations as
a every primary design drawing and some secondary drawings depends on the
layout and the included rooms in the substation. This chapter presents
studying the different substation rooms and shows every room function and
its importance.
2.2.2 Substation Layout Arrangement
1- Outdoor Switchyard
• Incoming Lines
• Outgoing Lines
• Busbars
• Transformers
• Insulators
• Capacitor banks
• Circuit-breakers, isolators,
• Earthing switches, surge arresters, CTs,
• VTs, neutral grounding equipment.
• Station cars parking
2- Control Building
• Low voltage AC Switchgear.
• Medium voltage switchgear.
• AC/ DC Room
• SCADA panel’s location
• Control Panels, Protection Panel
3- Battery Room
• D.C. Batteries system
• Washing latrine
45 | P a g e
CHAPTER 2 SLD & GLO
46 | P a g e
CHAPTER 2 SLD & GLO
47 | P a g e
CHAPTER 2 SLD & GLO
48 | P a g e
CHAPTER 2 SLD & GLO
49 | P a g e
CHAPTER 2 SLD & GLO
50 | P a g e
CHAPTER 2 SLD & GLO
51 | P a g e
CHAPTER 2 SLD & GLO
52 | P a g e
CHAPTER 3 Short Circuit
53 | P a g e
CHAPTER 3 Short Circuit
3.1 Introduction
Short-Circuit Currents are currents that introduce large amounts of destructive
energy in the forms of heat and magnetic force into a power system. A short circuit
is sometimes called a fault. It is a specific kind of current that introduces a large
amount of energy into a power system. It can be in the form of heat or in the form
of magnetic force. Basically, it is a low-resistance path of energy that skips part of
a circuit and causes the bypassed part of the circuit to stop working. The reliability
and safety of electric power distribution systems depend on accurate and thorough
knowledge of short-circuit fault currents that can be present, and on the ability of
protective devices to satisfactorily interrupt these currents. Knowledge of the
computational methods of power system analysis is essential to engineers
responsible for planning, design, operation, and troubleshooting of distribution
systems. Short circuit currents impose the most serious general hazard to power
distribution system components and are the prime concerns in developing and
applying protection systems. Fortunately, short circuit currents are relatively easy
to calculate. The application of three or four fundamental concepts of circuit
analysis will derive the basic nature of short circuit currents. These concepts will
be stated and utilized in a step-by step development. The three-phase bolted short
circuit currents are the basic reference quantities in a system study. In all cases,
knowledge of the three-phase bolted fault value is wanted and needs to be singled
out for independent treatment. This will set the pattern to be used in other cases.
54 | P a g e
CHAPTER 3 Short Circuit
• A fault with the insulation- if the circuit wire insulation is faulty, the current can
then pass to neutral wire, causing a surge in electricity and a short circuit. circuit
wire insulation can be negatively affected by age and use, as well as SC and nails,
and animals like rats.
• A fault with the appliance- when you plug an appliance into the circuit, it
becomes a circuit extension. And if the wiring is faulty, this can short the whole
circuit in your property
• A fault with the connections- a circuit needs strong connectors to keep the current
flowing. If the connector is loose, electricity will be able to pass to either neutral
wire, or a grounded part of the circuit, causing a short circuit.
The consequences are variable depending on the type and the duration of the
fault, the point in the installation where the fault occurs and the short-circuit
power, Consequences include.
Most of the failures on the power system leads to short-circuit fault and cause
heavy currents to flow in the system. The calculations of these short-circuit
currents are important for the following reasons.
56 | P a g e
CHAPTER 3 Short Circuit
3.2 Definitions
Average value of the upper and lower envelope curve of the short-circuit
current, which slowly decays to zero.
57 | P a g e
CHAPTER 3 Short Circuit
The effective value of the short-circuit current that flows through the contact
switch at the time of the first contact separation.
The voltage at the position of the short circuit, which is transferred to the
positive-sequence system as the only effective voltage and is used for the
calculation of the short-circuit currents.
Ratio between the equivalent voltage source and the network voltage, Un,
divided by √ 3.
58 | P a g e
CHAPTER 3 Short Circuit
59 | P a g e
CHAPTER 3 Short Circuit
For the same external conductor voltages, a three-phase short circuit allows
three currents of the same magnitude to develop among the three conductors.
Therefore, it is only necessary to consider one conductor in further calculations.
Depending on the distance from the position of the short circuit from the generator,
it is necessary to consider near-to-generator and far-from-generator short circuits
separately. For far-from-generator and near-to-generator short circuits, the short-
circuit path can be represented by a mesh diagram with an AC. voltage source,
reactances X, and resistances R (Figure 3.2). Here, X and R replace all components
such as cables, conductors, transformers, generators, and motors
Figure 3.2 Equivalent circuit of the short-circuit current path in the positive-sequence system
𝑑𝑖𝑘
𝑖𝑘 . 𝑅𝑘 + 𝐿𝑘 = 𝑢̂ sin( 𝜔𝑡 + 𝜓)
𝑑𝑡
where 𝜓 is the phase angle at the point in time of the short circuit. The
inhomogeneous first-order differential equation can be solved by determining the
homogeneous solution 𝑖𝑘 and a particular solution 𝐼′′ 𝑘 .
𝑖𝑘 = 𝑖′′𝑘 + 𝑖𝑘−
60 | P a g e
CHAPTER 3 Short Circuit
𝑳
The homogeneous solution, with the time constant 𝛕𝒈 = , yields the
𝑹
following.
−𝑢 𝑡⁄ sin( 𝜔𝑡−∅ )
τ𝑔 𝑘
𝑖𝑘 = 𝑒
√(𝑅2 + 𝑋 2)
−𝑢 𝑡⁄ sin( 𝜔𝑡+𝜓−∅ )
τ𝑔 𝑘
𝑖′′𝑘 = 𝑒
√(𝑅2 + 𝑋 2 )
−𝑢 𝑡⁄ sin( 𝜔𝑡−∅ )
τ𝑔 𝑘
𝑖𝑘 = [sin( 𝜔𝑡 + 𝜓−∅𝑘 ) − 𝑒
√(𝑅2 + 𝑋 2 )
𝑋 𝑋
∅𝑘 = arctan ( ) = tan−1
𝑅 𝑅
Figure 3.3 shows the switching processes of the short circuit. For the far-from-
generator short circuit, the short-circuit current is, therefore, made up of a constant
a.c. periodic component and the decaying d.c. aperiodic component. From the
simplified calculations, we can now reach the following conclusions.
61 | P a g e
CHAPTER 3 Short Circuit
II. The magnitude of the short-circuit current depends on the operating angle of
the current. It reaches a maximum at 𝛾 =90∘ (purely inductive load).This
case serves as the basis for further calculations.
III. The short-circuit current is always inductive.
62 | P a g e
CHAPTER 3 Short Circuit
Symmetrical faults are relatively simple to analyze; however, they account for
very few actual faults. Only about 5% of faults are symmetrical. Asymmetrical
faults are more difficult to analyze, but they are the more common type of fault.
1. Three-Phase Fault
• connection of all conductors with or without simultaneous
contact to ground
• symmetrical loading of the three external conductors
• calculation only according to single phase.
2. Three-Phase to ground Fault.
63 | P a g e
CHAPTER 3 Short Circuit
64 | P a g e
CHAPTER 3 Short Circuit
3- transient calculation.
Figure 3.5 shows an example of the equivalent voltage source at the short-
circuit location F as the only active voltage of the system fed by a transformer with
or without an on-load tap changer. All other active voltages in the system are short-
circuited. Thus, the network feeder is represented by its internal impedance, 𝑍𝑄𝑡
transferred to the LV side of the transformer and the transformer by its impedance
referred to the LV side. The shunt admittances of the line, the transformer, and the
nonrotating loads are not considered. The impedances of the network feeder and
the transformer are converted to the LV side. The transformer is corrected with 𝐾𝑇 ,
which will be explained later. The voltage factor c (Table 2.1) will be described
briefly as follows: If there are no national standards, it seems adequate to choose a
65 | P a g e
CHAPTER 3 Short Circuit
voltage factor c, according to Table 3.1, considering that the highest voltage in a
normal
66 | P a g e
CHAPTER 3 Short Circuit
In Figure (3.6) short circuit is fed from a network in which only the initial
symmetrical short-circuit current at the feeder connection point Q is known, then
the equivalent impedance 𝑍𝐾𝑛𝑒𝑡 of the network (positive sequence short-circuit
impedance) at the feeder connection point q should be determined by :
𝑐 ∗ 𝑈𝑛 𝑐 ∗ 𝑈𝑛 2
𝑍𝐾𝑛𝑒𝑡 = 𝐼𝑓 𝑆′′𝑛 𝑖𝑠 𝐾𝑛𝑜𝑤𝑛 → 𝑍𝐾𝑛𝑒𝑡 =
√3 ∗ 𝐼𝐾𝑛𝑒𝑡 𝑆′′𝑛
67 | P a g e
CHAPTER 3 Short Circuit
𝑐 ∗ 𝑈𝑛 2 𝑈𝑛−𝐿𝑉 2
𝑍𝐾𝑛𝑒𝑡 = ∗( )
𝑆′′𝑛 𝑈𝑛−𝐻𝑉
The impedance of the machine can be calculated with the nominal parameters
of the machine itself (rated voltage 𝑈𝑟𝑇 ; apparent power 𝑆𝑟𝑇 ; percentage voltage
drops 𝑈𝑘 ) by using the following formula:
𝑈𝑘 𝑈𝑟𝑇 2
𝑍𝑇𝑅 = ∗
100% 𝑆𝑟𝑇
68 | P a g e
CHAPTER 3 Short Circuit
Rated
primary
5…20 30 60 110 220 400
voltage
in KV
𝑐 ∗ 𝑈𝑛
𝐼′′𝐾 =
√3 𝑍 𝐾
𝑖𝑝 = 𝐾 ∗ √2 𝐼′′𝐾
69 | P a g e
CHAPTER 3 Short Circuit
𝐼𝐾 = 𝐼′′𝐾
𝐼𝑏 = 𝐼′′𝐾
70 | P a g e
CHAPTER 3 Short Circuit
71 | P a g e
CHAPTER 3 Short Circuit
Xknet= 0.995*ZKnet
Rknet = 0.1*Xknet
ZTR= (Uk*ULV^2)/(100*STr) % Transformer Impedance
RTr= (URr*ULV^2)/(100*STr) % Transformer Res
XTr= sqrt(ZTR^2-RTr^2) % Transformer Reactance
%------------------------------------------------------
Zsc=(ZKnet+ZTL)/4
XR_Ratio=Xknet/Rknet
K=1.02+0.98*exp(-3*(1/XR_Ratio))
%------------------------------------------------------
Ik_cmax= (Cmax*Un)/(sqrt(3)*Zsc)
Ik_cmin= (Cmin*Un)/(sqrt(3)*Zsc)
%------------------------------------------------------
ip= sqrt(2)*K*Ik_cmax
iDc= sqrt(2)*Ik_cmax*exp(-2*pi*50*t*(1/XR_Ratio))
%------------------------------------------------------
% MVSG Short Circuit
Rcable = 0.0414; %(Ohm/km)
Lcable = 0.3295; %(mH/km)
Lenghtcable = 20; %(m)
XL_cable = 2*pi*50*Lcable*0.02/4;
R_cable = Rcable*0.02/4;
Zcable=sqrt((R_cable^2 +XL_cable^2))
ZscM= (ZKnet* (ULV/UHV)^2 )+ (ZTR+ Zcable)/3
Ik_MVSG_cmax= (Cmax*ULV)/(sqrt(3)*ZscM)
Ik_MVSG_cmin= (Cmin*ULV)/(sqrt(3)*ZscM)
73 | P a g e
CHAPTER 3 Short Circuit
Un=...kV 220
Sn=...MVASC 8000
STr=...MVA 75
UHV=...kV 220
ULV=...kV 22
Uk=...% 13
74 | P a g e
CHAPTER 3 Short Circuit
ZTL =6.0531
ZKnet =6.6550
Xknet =6.6217
Rknet =0.6622
ZTR =0.8389
RTr =0.0032
XTr =0.8389
Zsc =3.1770
XR_Ratio =10
K = 1.7460
Ik_cmax =43.9779
Ik_cmin =39.9799
ip =108.5910
iDc =45.4267
Zcable =0.5100
ZscM =0.5162
Ik_MVSG_cmax = 27.0671
Ik_MVSG_cmin =24.6064
75 | P a g e
CHAPTER 3 Short Circuit
ZTL √𝑅𝐿 2 + 𝑋 2 Ω
6.0531
𝑐 ∗ 𝑈𝑛 2
𝑍𝑘𝑛𝑒𝑡 𝑍𝐾𝑛𝑒𝑡 = Ω
𝑆′′𝑛 6.655
Ω
𝑋𝑘𝑛𝑒𝑡 𝑋𝐾𝑛𝑒𝑡 = 0.955 ∗ 𝑍𝐾𝑛𝑒𝑡 6.6217
𝑰𝒌𝑪𝒎𝒂𝒙 𝒄 ∗ 𝑼𝒏 kA
𝑰′′𝑲 =
√ 𝟑 𝒁𝑲 43.978
𝐼𝑘𝐶𝑚𝑖𝑛 𝑐 ∗ 𝑈𝑛 kA
𝐼′′𝐾 =
√3 𝑍𝐾 39.98
𝑖𝑝 kA
𝐾 ∗ √2 𝐼′′𝐾 108.59
𝐼𝐷𝐶 𝑅 kA
′′ −2𝜋𝑓𝑡 𝑘
√2 ∗ 𝐼 ∗ 𝑒 𝑋𝑘 45.427
𝐾
76 | P a g e
CHAPTER 3 Short Circuit
𝑍𝐶𝑎𝑏𝑙𝑒 0.5176 Ω
𝑍𝑘𝑛𝑒𝑡 0.5187 Ω
𝑰𝒌𝑪𝒎𝒂𝒙 𝒄 ∗ 𝑼𝒏 kA
𝑰′′𝑲 =
√ 𝟑 𝒁𝑲 26.9353
LV Busbar 22 (kV)
𝐼𝑘𝐶𝑚𝑖𝑛 𝑐 ∗ 𝑈𝑛 kA
𝐼′′𝐾 =
√3 𝑍𝐾 24.4866
𝑖𝑝 kA
𝐾 ∗ √2 𝐼′′𝐾 108.59
𝐼𝐷𝐶 𝑅 kA
′′ −2𝜋𝑓𝑡 𝑘
√2 ∗ 𝐼 ∗ 𝑒 𝑋 𝑘 45.427
𝐾
77 | P a g e
CHAPTER 3 Short Circuit
78 | P a g e
CHAPTER 3 Short Circuit
79 | P a g e
CHAPTER 3 Short Circuit
3.8 Transformer
80 | P a g e
CHAPTER 3 Short Circuit
3.9 Cable
81 | P a g e
CHAPTER 3 Short Circuit
82 | P a g e
CHAPTER 4 Earthing System
83 | P a g e
CHAPTER 4 Earthing System
The design of an earthing system for a substation is critical to ensure the safety of
personnel and equipment. It must be designed to handle fault currents and lightning
strikes, and it must be installed and maintained in accordance with local codes and
standards which is IEEE. Regular testing and maintenance of the earthing system is
also essential to ensure its continued effectiveness.
So, it is required to make these work spaces less risky and as safer as possible to
allow the worker to do their job safely. Thus, there are number of things to apply to
ensure the safety of the workers such as:
_ Wearing safety gear (Helmet, Goggles, Gloves, and Boots).
_ Using better insulation materials. _ Earthing system.
_ Using high sensitivity protection devices.
In this chapter we will discuss earthing systems in substations, talk about its
importance, important measurements, and steps and show a study case.
84 | P a g e
CHAPTER 4 Earthing System
4.2 Definitions:
We have to keep in mind some important definitions to understand this chapter
which are:
• Earthing system: is circuitry which connects parts of the electric circuit with the
ground. It affects the magnitude and distribution of short circuit currents through
the system, and the effects it creates on equipment and people in the proximity of
the circuit.
• Grounding system: Comprises all interconnected grounding facilities in a
specific area.
• Ground: A conducting connection, whether intentional or accidental, by which
an electric circuit or equipment is connected to the earth or to some conducting
body of relatively large extent that serves in place of the earth.
• Grounded: A system, circuit, or apparatus provided with a ground(s) for the
purposes of establishing a ground return circuit and for maintaining its potential
at approximately the potential of earth.
• Ground current: A current flowing into or out of the earth or its equivalent
serving as a ground.
• Ground electrode: A conductor imbedded in the earth and used for collecting
ground current from or dissipating ground current into the earth.
• Ground mat: A solid metallic plate or a system of closely spaced bare
conductors that are connected to and often placed in shallow depths above a
ground grid or elsewhere at the earth’s surface, in order to obtain an extra
protective measure minimizing the danger of the exposure to high step or touch
voltages in a critical operating area or places that are frequently used by people.
• ground return circuit: A circuit in which the earth or an equivalent conducting
body is utilized to complete the circuit and allow current circulation from or to
its current source
• Ground potential rise (GPR): The maximum electrical potential that a
substation grounding grid may attain relative to a distant grounding point
assumed to be at the potential of remote earth. This voltage, GPR, is equal to the
maximum grid current times the grid resistance.
• Grounding grid: A system of horizontal ground electrodes that consists of a
number of interconnected, bare conductors buried in the earth, providing a
85 | P a g e
CHAPTER 4 Earthing System
86 | P a g e
CHAPTER 4 Earthing System
4.3 Importance:
Earthing a substation is crucial for several reasons, including:
_In case you are wondering why earthing of all things is what is used in
substations and in many fields too; Earthing is one of the main factors in electrical
systems to protect the humans from getting electric shock. Earthing is used in
almost every equipment.
And when designing a grounding system there are two main objectives:
• To provide means to carry electric currents into the earth under normal and
fault conditions without exceeding any operating and equipment limits or
adversely affecting continuity of service.
• To assure that a person in the vicinity of grounded facilities is not exposed to
the danger of critical electric shock.
87 | P a g e
CHAPTER 4 Earthing System
Its equation:
where
ρa is the apparent resistivity of the soil in Ω·m
R is the measured resistance in Ω
a is the distance between adjacent electrodes in m
b is the depth of the electrodes in m
89 | P a g e
CHAPTER 4 Earthing System
Where
ρs: the soil resistivity, in Ω-m
ρ: the thin layer material resistivity, in Ω-m
h s:the thin layer material thickness
90 | P a g e
CHAPTER 4 Earthing System
91 | P a g e
CHAPTER 4 Earthing System
Its equation:
Where
I = the r.m.s. current in kA
Amm² = the conductor cross-section in mm2
K0 =1/ɑ0 or (1/ɑr)
Tm = the maximum allowable temperature in °C
Ta = the ambient temperature in °C
Tr = the reference temperature for material constants in °C
α0 = the thermal coefficient of resistivity at 0 °C in 1/°C
αr = the thermal coefficient of resistivity at reference temperature Tr in 1/°C
ρr = the resistivity of the ground conductor at reference temperature Tr in µΩ cm
tc = the duration of current in s
TCAP = the thermal capacity per unit volume from Table 1, in J/ (cm3°C)
92 | P a g e
CHAPTER 4 Earthing System
Practical tests:
• The interruption time should not be less than half a second for safety.
• In some designs, the insulation melting temperature is considered, especially
when there are insulated parts in the earthing system, such as green and yellow
insulated wires. In this case, the temperature is not the melting temperature of
the earthing conductor, which can reach 1000 degrees Celsius, but it is
calculated as 200 degrees Celsius only. It is important to first confirm the
presence or absence of insulated conductors in the earthing system, as this can
affect the cross-sectional area of the conductor.
93 | P a g e
CHAPTER 4 Earthing System
94 | P a g e
CHAPTER 4 Earthing System
The previous equations for step and touch voltages can be also written as:
𝑅𝑓
Etouch = (RB + ). IB , Estep = (RB + 2Rf). IB
2
And the 1000 in the previous equations represent the resistance of the human body.
95 | P a g e
CHAPTER 4 Earthing System
In the case of horizontal conductors (or the network), the voltage value that arises
on the surface of the ground between two points in the area near the grounded body
due to the flow of fault current is small.
Therefore, you will always find in substations that we use a
grounding network consisting of horizontal conductors in the
form of squares with a side length ranging from 3-6 meters,
while the side length in grounding transmission and generation
stations ranges from 10 to 20 meters. This network is placed
under the ground of the substation to ensure a low value of Step
Voltage and Touch Volt, as shown in the diagram. Note that all
of these conductors are buried horizontally under the ground surface by
approximately one or half a meter. Then, we add vertical electrodes either at the
intersection points on the perimeter of the shape or at all intersection points.
Where;
Rg is the earthing grid resistance with respect to remote earth (Ω)
ρ is the soil resistivity (Ω.m)
𝐿 𝑇 is the total length of buried conductors (m)
A is the total area occupied by earthing grid (m2)
h is the depth of earthing grid (m)
And this one is the one that matters where it causes GPR:
GPR = IG RG
On the other hand, there is an additional part that can increase the current value due
to magnetic coupling, as well as the possibility of the presence of a DC component in
the fault, whose value depends on the Time Constant of the network and the location
of the fault, and this requires an approximation in its calculation. Generally, the ratio
of this addition is called the Decrement factor, Df, which is calculated from the
following equations:
IG = Ig Df
−2 𝑡𝑓
𝑇𝑎
Df = √1 + (1 − 𝑒 𝑇𝑎 )
𝑡𝑓
𝑋 1
Ta =
𝑅 2𝜋𝑓
Where;
IG represents only the second part of the fault current.
Ta is the dc time offset constant.
𝑡𝑓 is the duration of fault.
98 | P a g e
CHAPTER 4 Earthing System
GPR = IG Rg
Where;
99 | P a g e
CHAPTER 4 Earthing System
The calculations here take into account, in addition to the fault current value, the
spacing between the horizontal conductors, the depth of the vertical electrodes, the
total lengths of the horizontally buried conductors, and the total lengths of the
vertical electrodes. The original reference can be consulted for more details on these
constants.
4.4.10 Comparing:
To make sure that the system is secured and safe the values calculated in step
4.4.8 must be less than values calculated in step 4.4.4 where:
Em < Etouch
Es < Estep
And if any error were to be discovered we can check the design with some new
adjustments:
_ According to the giving the soil resistivity is 60 Ω.m. and the surface material
resistivity is 8534.4 Ω.m. the:
ρ
0.09(1− )
ρ𝑠
Cs = 1 -
2ℎ𝑠 +0.09
60
0.09(1− )
8534.4
Cs = 1 - = 0.918
2 ∗0.5 +0.09
Where;
𝑇𝑚 = 1083 °C
αr = 0.00393 °C-1
101 | P a g e
CHAPTER 4 Earthing System
ρ𝑟 = 1.72 µΩ.cm.
TCAP =3.422 jcm-3°C-1
tc = 1 sec
K0 = 234
Ta =40 °C
Then;
1∗𝑜.𝑜𝑜393∗1.72∗104
3√ 3.422
A = 50 ∗ 10 1083− 4𝑜 =177.4 mm2
ln(1+ )
234+40
Where;
Cs = 0.918
ρ𝑠 =8534.4 Ω.m.(gravel)
tc = 1 sec
Then.
0.157
Estep,70 =(1000 + 6 *0.918*8534.4 ) = 7537.17 V
√1
0.157
Etouch,70 = (1000 + 1.5 *0.918 * 8534.4) = 2002.04 V
√1
102 | P a g e
CHAPTER 4 Earthing System
Where;
ρ = 60 Ω.m.
𝐿𝑡 = (20*109+20*63+20*10) =3640
h = 0.5 m
A = 109*63=6867 m2
Then;
1 1 1
Rg = 60( + (1 + )) = 0.336 Ω
3640 √20∗6867 1+0.5√20/6867
−2𝑡𝑓
−2∗1
𝑇𝐴 0.03
Df = √1 +
𝑡𝑓
(1 − 𝑒 𝑇𝐴
) = √1 + 1
(1 − 𝑒 10 ) = 1.016
Therefore, GPR > Vstep, the design may be correct or incorrect, and the final
judgment depends on the detailed values of Step Voltage and Touch Volt that we
will calculate in the next step
103 | P a g e
CHAPTER 4 Earthing System
104 | P a g e
CHAPTER 4 Earthing System
❖ Then inputs concerning the conductor, grid and the rod size:
105 | P a g e
CHAPTER 4 Earthing System
❖ Case study
106 | P a g e
CHAPTER 4 Earthing System
107 | P a g e
CHAPTER 4 Earthing System
108 | P a g e
CHAPTER 4 Earthing System
3. Cables
Metallic cable sheath shall be effectively grounded to drain any induced
voltages to the ground
4. Control cables
The shield of control cables must be grounded at both ends to the grounding
grid. In certain situations, a separate conductor should be installed alongside
the control cable and connected to the two sheath ground points.
109 | P a g e
CHAPTER 4 Earthing System
5. Power Cables
Sheaths of single conductor power cables within a substation should be
grounded at one end, preferably at the source end, to reduce sheath current.
For longer cables, the sheath should be grounded at both ends and at each
splice. Power cable potheads should be case grounded via a mounting bolt,
and the grounding of sheaths for ring type CTs should not affect CT secondary
current.
6. Instrument Cables
instrument cables carrying milliamps, analog, or digital signals should have
their metallic screening grounded at one point using a PVC insulated
grounding wire. The grounding wire should be connected to a separate
instrument ground bar that is insulated from the cubicle ground.
7. signal Cables
All signal cables used in telemetering and communications shall have their
shield grounded at one end only to reduce interference from stray sources.
.
8. Cable Tray System
Cable tray system shall be grounded with bare copper conductor of
50 mm2 size at both ends and shall be bonded across gaps including
expansions gaps.
9. Control Building
The control building in a substation must be grounded using the same safety
criteria as the substation and should be encircled by a grounding conductor.
11.Metallic Conduits
All metallic conduits should be connected to grid at each manhole or at its
terminals using 50mm2 conductor.
110 | P a g e
CHAPTER 4 Earthing System
2. Instrument Transformers
Potential and current transformers shall be grounded at the grounding
terminals of CT & PT. The neutral point of the secondary connection of
CT&PT shall be grounded to the ground grid in the control/relay room to
reduce the transient over-voltages.
3. Surge Arrestor
surge arrestor with operation counter, the insulated lower end of the lightning
arrestor shall be connected to the operation counter with an insulated coated
copper conductor with cross section area not less than 50 mm2. The surge
arrestor ground terminal shall be connected to the ground grid via two
stranded copper conductors.
4. Shunt Capacitors and Reactors
Shunt capacitors and reactors are grounded when mounted on a metal
structure that is connected to the grounding grid.
112 | P a g e
CHAPTER 5 Raceway
CHAPTER 5 Raceway
113 | P a g e
CHAPTER 5 Raceway
5.1 Raceway:
Raceways are an important component in the design. A raceway (sometimes
referred to as a raceway system) is an enclosed conduit that forms a physical pathway
for electrical wiring. Raceways protect wires and cables from heat, humidity,
corrosion and general physical threats. The cable tracks located in the station is
starting from the GIS building, which contains the control and Protection cables and
the low voltage cables that should be transferred to the control rooms and AC/ DC
room, the path of these cables should be created, taking into consideration the cost
not to increase, the losses of information in communication cables and the length to
avoid the voltage drop, The medium voltage path must be created to enter in
MVSWGR in the control building , so we must know what are the methods used and
how to calculate them taking into account some considerations in mind.
Prior to the cable being laid, the cable trench must be dug and prepared
properly. This means that the trench must be of adequate size to allow for the cables
and ducting required. The trench width and depth also depend on the where the cable
trench is being dug. For instance, a cable being laid underneath a public footway will
not be laid as deep as one under arable land that is to be ploughed. When a trench is
to be dug, it should be sufficient to allow the installer to install the cables and ducting
at the correct depth for the cable being used. The cable should be installed within the
specified pulling dimensions and without damaging the cable sheaths. Cable trays
shall be fabricated from hot dip galvanized steel. Tray shall not sag more than 50
mm at midpoint between supports when loaded with cables. Space between supports
shall be according to the cable weight but not more than 2 meters.
114 | P a g e
CHAPTER 5 Raceway
115 | P a g e
CHAPTER 5 Raceway
Ladder trays generally get used where there are larger bundles or heavier
cables. The ladder cable tray has two side rails connected by cross members, or
rungs. The rungs provide convenient anchors for tying down the cables.
A perforated cable tray consists of a bottom that has openings, and 60% of the
flat area is used to support the cables, placed inside the longitudinal side rails. These
trays are used for instrumentation and power cables. They are perfect for organizing
large volumes of industrial power cables. Perforated cable trays can be installed on
any surface and improve the cables’ useful life. Cable trays such as these provide
greater security since they isolate cables completely. With a perforated cable tray,
there is no buckling or hanging. Additionally, the perforated design of the tray
ensures adequate ventilation for the cables, so one can maintain adequate
temperatures in a closed environment space.
116 | P a g e
CHAPTER 5 Raceway
117 | P a g e
CHAPTER 5 Raceway
The basket-type trays are welded wire structures that serve to support electrical
cables in an orderly way especially systems with cables of control and data. They
provide ideal support for data communication cables (coaxial and braided pairs).
These trays have the advantage of being versatile and can be used in many different
situations. Due to this, it is possible to work with accessories that vary horizontally
and vertically by cutting them as needed. They have other advantages, such as a light
structure and more open spaces. It provides better cooling, improves electrical
efficiency, and is fire-resistant. It can be used as a shield for cables.
118 | P a g e
CHAPTER 5 Raceway
Conduit Fill or Raceway fill is the percent of area inside the conduit taken up
by the cable. Another definition is the amount of a conduit's cross-sectional area
occupied, or filled, by a cable or multiple cables. Figure clear the definition. The fill
is based on the cable outside diameter (O.D.) and the conduit inside diameter (I.D.).
Conduits can be used for cable routing in floors, along walls, and for cable
entrance into the control house. Conduits are available in plastic, aluminum, and
steel. Each of these types may be used in control houses for wire containment to
convenience outlets, lighting fixtures, and other control house auxiliary power
equipment. A word before starting need to consider some factors when doing the
calculations:
119 | P a g e
CHAPTER 5 Raceway
supplier data can get each cable Nominal External diameter of cable and conduit
diameter. So, to calculate everything in the following:
• Get all cable size required for GIS panels which that coordinate with protection
engineer or the supplier of GIS can send excel sheets for all panels requirement,
but this is not recommended because maybe specification require special requests
for the substation.
• Calculate total area for conduit and cable to use it in filling equation.
• According to NEC should have 25% as spare in conduit and the conduit filling
don’t exceeds 40%.
• After that calculate total use sleeves required increase some sleeves as spare for
any reason lead to damage any conduit.
D2 cable
Filling ratio = 2
D conduit
The following table includes the calculations of Filling ratio for GIS building
opening sleeves.
121 | P a g e
CHAPTER 5 Raceway
And for cable trays filling ratio we have the same method of conduit sizing but in
many specifications have a special require in the project technical as in figure
Duct banks are groups of conduits designed to protect and consolidate cabling
to and from buildings. In a duct bank, data and electrical cables are laid out within
PVC conduits that are bundled together; these groupings of conduit are protected by
concrete and metal casings. Duct banks are often buried, allowing contractors to
consolidate the wiring for a building into centralized underground paths.
122 | P a g e
CHAPTER 5 Raceway
This construction method is designed to protect the cabling outside of the building
and consolidate it in one area, but not only protect the enclosed cables from damage
they also consolidate and conceal the building's series of wires. Bundling cables with
a duct bank also streamlines future construction projects because the cables are
consolidated and bundled to create a clear passageway. This consolidation allows
property owners to upgrade or repair existing wiring without undergoing lengthy
excavation projects. Duct banks are also useful for installing cabling underneath
roads, parking lots and other areas with existing structures. Duct banks also allow
property owners to replace, upgrade or repair existing underground wiring without
excavating the entire length of the lines.
Values given are averages for the cable types and range of conductor sizes
considered. Single conductor cables can be installed in a cable tray cabled together,
Where the cables are installed according to Elsewedy Electric.
123 | P a g e
CHAPTER 5 Raceway
124 | P a g e
CHAPTER 5 Raceway
125 | P a g e
CHAPTER 6 Overvoltage Protection
126 | P a g e
CHAPTER 6 Overvoltage Protection
6.1 Introduction
Overvoltage protection is a critical aspect of substation design and operation.
Substations are key components of electrical power systems, where they serve as
points of connection between different parts of the power grid, including
transmission lines, distribution networks, and customer facilities.
127 | P a g e
CHAPTER 6 Overvoltage Protection
• Resonance
Resonance can occur when there is an inductor and capacitor in parallel, which
creates a resonant circuit. When an AC voltage is applied to this circuit, the inductor
and capacitor store energy and release it back and forth. If the frequency of
the applied voltage matches the natural frequency of the circuit, the energy stored in
the circuit builds up and can cause the voltage in the circuit to increase beyond the
expected or rated voltage.
128 | P a g e
CHAPTER 6 Overvoltage Protection
When the electric charge within the cloud or between the cloud and the ground
becomes large enough, it can create an electric discharge which causes damage to
buildings, starting fires, and injuring or killing people.
A lightning mast, also known as a lightning rod or air terminal, is a tall, pointed
metal rod or object mounted on the roof or other high points of a building or structure
as part of a lightning protection system. The lightning mast is designed to attract
lightning strikes and provide a low-resistance path for the lightning current to flow
to the ground, thereby protecting the building or structure and its occupants from the
damaging effects of lightning strikes.
Lightning masts are typically made of conductive metals such as copper, aluminum,
or steel, and are designed to be taller than the surrounding objects to increase their
effectiveness in attracting lightning strikes. They are installed at regular intervals
around the perimeter of the building or structure, and are connected to a network of
conductors and grounding electrodes that provide a low-resistance path for the
lightning current to flow safely to the ground.
129 | P a g e
CHAPTER 6 Overvoltage Protection
• Copper wire
Copper wire is often used as the main conductor to connect the lightning rods or
air terminals to the grounding system. The wire is typically sized based on the
expected lightning current and voltage levels, and is installed in a straight path with
minimal bends or loops to minimize the resistance and voltage drop along the
conductor.
• Down conductors
The size and length of the down conductor is determined by the expected lightning
current and voltage levels, the height of the building or structure, and the distance to
the grounding system. The down conductor must be installed in a straight path with
130 | P a g e
CHAPTER 6 Overvoltage Protection
minimal bends or loops to minimize the resistance and voltage drop along the
conductor.
• Disconnecting link
A disconnecting link, also known as a disconnect switch or isolator, is a device
used in a lightning protection system to isolate a section of the system from the rest
of the system for maintenance, repair, or replacement. The disconnecting link is
typically installed in the down conductor or other conductors of the lightning
protection system, and is designed to provide a safe and reliable means of
disconnecting the lightning protection system from the power supply.
The disconnecting link is often used in conjunction with other components of the
lightning protection system, such as surge protectors and grounding electrodes, to
provide a comprehensive system for protecting the building or structure from
lightning strikes. When maintenance or repairs are required, the disconnecting link
can be opened to isolate the lightning protection system from the power supply,
allowing work to be performed safely and without risk of electrical shock or damage
to equipment. It can be manual or automatic, and can be operated either locally or
remotely.
There are several design methods that can be used in a lightning protection
system. Here are three main methods:
131 | P a g e
CHAPTER 6 Overvoltage Protection
132 | P a g e
CHAPTER 6 Overvoltage Protection
Class of lightning protection system is obtained from risk assessment, usually taken
class three in Egypt.
133 | P a g e
CHAPTER 6 Overvoltage Protection
The concept of this design method is that an imaginary sphere is being rolled
over the building, masts, or wires with radius (S) which is equal 46 meters. Any
object under the curve of sphere is being protected safely, if the object touches the
sphere or goes inside it that means that the object is in the risk of being struck by
lightning. The figures shown illustrates this concept,z
134 | P a g e
CHAPTER 6 Overvoltage Protection
135 | P a g e
CHAPTER 6 Overvoltage Protection
The following table shows the maximum value of rolling sphere radius
according to the class-level,
To calculate the radius of protection and overlapping protection zone this equations
are being used,
𝑟 = √𝑆 2 − (𝑆 − ℎ𝑚 )2 − √𝑆 2 − (𝑆 − ℎ𝑒 )2 (ℎ𝑚 < 𝑆)
𝑟 = √𝑆 2 − √𝑆 2 − (𝑆 − ℎ𝑒 )2 (ℎ𝑚 ≥ 𝑆)
Where,
𝑆 : Sphere radius
136 | P a g e
CHAPTER 6 Overvoltage Protection
𝑟 = √𝑆 2 − (𝑆 − ℎ𝑒 )2
𝑆 : Sphere radius
137 | P a g e
CHAPTER 6 Overvoltage Protection
138 | P a g e
CHAPTER 6 Overvoltage Protection
Surge arresters are installed in substations and in transmission lines with the
purpose of limiting both lightning and switching induced overvoltages to a specified
protection level, which is, in principle, below the withstand voltage of the equipment
in order to protect it from excessive overvoltages. The ideal surge arrester would
have a nonlinear voltage and current characteristic that starts to conduct at a specified
voltage level (switch-on), keeping a certain margin above its rated voltage, holds the
specified voltage level without variation for the duration of the overvoltage for
expected lifetime, and then ceases to conduct as soon as the voltage across the surge
arrester returns to a value below the specified voltage level (switch-off). Therefore,
surge arresters are fundamentally required to absorb the energy that is associated
with the overvoltages. We will talk about the metal oxide surge arrester (MOSA).
MOSA is often placed at the terminals of power transformers, at both ends of the
bus terminals, and at both ends of transmission lines to mitigate the overvoltage
levels imposed on equipment
6.4.2 Construction
Figure 6.9 shows the cross section of the design of a porcelain-housed unit of a
MOSA. The MO resister column and its supporting construction form the active part
of the arrester. The column consists of individually stacked MO resistors, almost
always cylindrical in shape as shown in Fig. 6.10. The resistor diameter determines
the energy absorption and current carrying capability. Diameters vary from
approximately 30 mm for distribution up to 100 mm and more for higher voltages.
When a MOSA has a length from 1.5 m to 2 m and higher, a grading ring is
139 | P a g e
CHAPTER 6 Overvoltage Protection
required. This is essential in controlling the voltage distribution from the top to the
bottom. This is unfavorably influenced by the earth capacitances that affect the
arrester. If the grading ring is not in place, the top, or high-voltage end, would be
140 | P a g e
CHAPTER 6 Overvoltage Protection
6.4.3 Operation
Surge arresters are generally connected in parallel with the protected equipment
and are subjected to the system voltage under normal operating conditions.
The voltage and current (V-I) characteristic of a typical metal oxide surge arrester
(MOSA) shows three distinctive regions: (I) MOSA can leak a small capacitive
current at continuous operating voltage levels up to the rated voltage; (II) MOSA
starts to conduct and the current increases rapidly with a slight voltage increase
showing a flat V-I characteristic in the breakdown region; (III) then the MOSA
increases voltage for large currents.
In order to reduce the power consumed by a metal oxide arrester during nominal
operation at system voltage, the continuous operating voltage of the arrester has to
be chosen such that the peak value of the resistive-current component is well below
1 mA and the capacitive-current component is dominant. This means that the voltage
distribution at operating voltage is capacitive and is thus influenced by stray
capacitance. The voltage-current characteristic of the metal oxide material offers the
nonlinearity necessary to fulfill the mutually contradicting requirements of an
adequate protection level at overvoltages and low current, i.e., low energy
141 | P a g e
CHAPTER 6 Overvoltage Protection
dissipation, at the system operating voltage. Metal oxide surge arresters are suitable
for protection against switching overvoltages at all operating voltages.
Porcelain-housed metal oxide surge arresters were used for performance satisfaction,
it is important that the units are hermetically sealed for the lifetime of the arrester
disks. The sealing arrangement at each end of the arrester consists of a stainless steel
plate with a rubber gasket. This plate exerts continuous pressure on the gasket,
against the surface of the insulator. It also serves to fix the column of the metal oxide
disks in place by springs. The sealing plate is designed to act as an overpressure
relief system. Should the arrester be stressed in excess of its design capability, an
internal arc is established. The ionized gases cause a rapid increase of the internal
pressure, which in turn causes the sealing plate to open and the gases to flow out
through venting ducts. Since the ducts are directed toward each other, it results in an
external arc, thus relieving the internal pressure and preventing a violent shattering
of the insulator.
142 | P a g e
CHAPTER 6 Overvoltage Protection
143 | P a g e
CHAPTER 6 Overvoltage Protection
When the current through the metal oxide varistor remains capacitive, the voltage
across the varistor elements is determined by their capacitance and thus influenced
by stray capacitances. Stray capacitances to earth cause a deviation from the linear
axial voltage distribution with higher voltage stress of the upper elements in the
arresters. This deviation is influenced by the physical parameter of the arrester such
as height, number, and length of arrester units and grading rings. With increasing
varistor temperature, the ohmic current component of the varistor contributes to a
more linear voltage distribution in the arrester. Insertion of grading rings as a passive
measure to improve the voltage distribution is the most effective.
144 | P a g e
CHAPTER 7 Switching Devices
145 | P a g e
CHAPTER 7 Switching Devices
7.1.1 Construction
Such SF6 circuit breaker has a fixed contact and moving contact. The moving
contact is hollow from inside having a cylinder that stores compressed SF6 gas as
shown in figure (7.1). The tip of the moving contact is designed in such a way to
form a nozzle that increases the speed of the gas when it passes through it. The fixed
contact is designed in such a way when it is in the closed position, it blocks the flow
of SF6 gas. When the contacts separate, the path for gas flow is opened which
releases a blast of SF6 gas. It has the same working operation as an air blast circuit
breaker except the gas is recombined, compressed and stored in the gas cylinder
again. Which makes it very complex and quite expensive gas system is required for
operation.
146 | P a g e
CHAPTER 7 Switching Devices
147 | P a g e
CHAPTER 7 Switching Devices
The movement of the puffer cylinder against the stationary piston leads to a decrease
in the puffer cylinder’s internal volume, which causes compression of the SF6 gas
inside the cylinder. Due to contact overlap, gas compression starts before any
contacts open. As the downward movement continues, the main contacts separate
and the current commutates to the arcing contacts which are still in the closed
position (due to their physically longer construction). During the course of further
opening, the arcing contacts start to separate and an arc is established between them.
148 | P a g e
CHAPTER 7 Switching Devices
As the arc flows it blocks the flow of SF 6 gas through the nozzle to some extent.
Thus, the gas pressure in the puffer cylinder continues to increase. When the
sinusoidal current waveform approaches zero, the arc becomes relatively weak and
the pressurized SF6 gas inside the puffer cylinder flows axially (through nozzle) over
the arc length. This blast of SF6 gas removes the thermal energy in the contact gap
and reduces the degree of ionization (electrical conductivity) such that the arc is
extinguished.
149 | P a g e
CHAPTER 7 Switching Devices
When the arc is interrupted, transient recovery voltage (TRV) starts to appear across
the contacts as shown in figure above the opening speed of the circuit breaker
contacts should be fast enough to create an adequate contact separation distance to
withstand this voltage stress. In case the contact gap’s dielectric strength is lower
than TRV stress, the arc will be re-established in a phenomenon which is commonly
called circuit breaker re-ignition or re-strike.
Whilst closing, a circuit breaker can sometimes experience an event known as pre-
strike. As the contacts move towards each other during closing, the contact gap’s
dielectric strength decreases. At some point, the voltage stress across the contact gap
exceeds its dielectric strength, thus producing a ‘pre-strike ‘arc which bridges the
contacts.
150 | P a g e
CHAPTER 7 Switching Devices
In most of the countries high & extra high voltage circuit breakers are
manufactured based on the IEC standard, i.e., IEC 62271-100. Parameters
mentioned on the nameplate of circuit breaker are also in line with the IEC 62271-
100. As per IEC, few parameters are mandatory, some are condition based, and some
of them are completely optional. In this chapter, we’ll look at the all parameters
mentioned on nameplate of SF6 circuit breaker which is shown in table below.
151 | P a g e
CHAPTER 7 Switching Devices
SIEMENS
Year of Manufacturing/ No.
Type 3AP1FI
2006/IND/07/2610
Rated voltage U 245KV
MADE IN INDIA
152 | P a g e
CHAPTER 7 Switching Devices
As the name suggest, these parameters are mandatory. All the manufacturer
producing circuit breakers must mention these parameters on the nameplate of
SF6 circuit breaker. But of course, some of these parameters may be skipped, if
it is mutually agreed between manufacturer and customer.
153 | P a g e
CHAPTER 7 Switching Devices
Unit: kV RMS
• 400 A
• 630 A
• 800 A
• 1250 A
• 1600 A
• 2000 A
• 3150 A
154 | P a g e
CHAPTER 7 Switching Devices
• 4000 A
Unit: Ampere
Unit: kA RMS
Unit: Seconds
155 | P a g e
CHAPTER 7 Switching Devices
It is generally 2.5 times the rated short circuit current. It is referred in kA peak,
as it remains for very short time.
Unit: kA Peak
And hence, breaker shall withstand power frequency voltage caused by these
reasons. IEC has defined the level of power frequency voltage that can appear across
156 | P a g e
CHAPTER 7 Switching Devices
breaker contact. So, for example, for 420kV CB the power frequency voltage defined
by IEC is 610kV rms. Circuit breaker has to undergo power frequency withstand
test, in which power frequency voltage is applied to the circuit breaker for 1 min.
Unit: kV RMS
Unit : kV Peak
So, on the nameplate we’ll find it is mentioned as 1.3 (or 1.5). This means, first pole
to open will have 1.3 times the normal system voltage across it, and the pole can
sustain that.
Unit: N/A
157 | P a g e
CHAPTER 7 Switching Devices
Operating sequence denotes the opening & closing operation breaker is capable of
performing under specified conditions.
As per IEC 62271-1 there are two alternatives for operating sequence:
O – t – CO – t’ – CO
CO – t’’ – CO
where,
O = Opening operation
C = closing operation
so auto reclosing works as follow: 90% of the faults (like) on the system are transient
in nature. Which remain in the system for a very short time and then the system goes
back to normal. In such cases, it is beneficial to put the system live again, and here
the auto reclosing system comes into picture.
158 | P a g e
CHAPTER 7 Switching Devices
We’ll consider the auto reclosing duty which is mentioned on our nameplate i.e. O-
0.3 SEC-CO-3 MIN-CO. So, let’s say there is fault on the system the breaker will
open then it will remain open for 0.3 sec. After 0.3 sec, it will close and if the fault
is cleared it will remain close. But, if the fault is still there then the breaker will open
immediately. Now breaker will remain in open condition for 3 mins. After 3 mins
the breaker will close again, and if the fault is cleared it will remain close. But if, the
fault is still there then the breaker will open immediately, and now breaker will
remain open until it is closed manually.
Unit: N/A
159 | P a g e
CHAPTER 7 Switching Devices
Unit: kg
160 | P a g e
CHAPTER 7 Switching Devices
Unit: kg
Unit: Volts
These were the mandatory parameters as per IEC. These parameters we’ll generally
find on every nameplate of high & extra high voltage SF6 circuit breaker.
It becomes important to test the breaker above 245kV voltage level for switching
surges. Switching surges are generally caused by energization of lines or switching
161 | P a g e
CHAPTER 7 Switching Devices
Unit: kV Peak
Unit: %
This is the highest amount of line charging current a circuit breaker is capable of
breaking. This type of current is generated because of the switching of loaded or
unloaded overhead lines. So, for 420kV CB IEC has defined the rating equal to
600A.
Unit: Ampere
7.1.5.2.4 Classification
Condition: If class in not E1 & M1
162 | P a g e
CHAPTER 7 Switching Devices
• M2 Class
These parameters are completely optional as per the IEC standard. And hence, it
can be or cannot be on the nameplate, depends upon the manufacturer.
This current gives the highest amount of transient recovery voltage across the
breaker contacts and hence it is one of the critical duties to break. Generally, out of
phase breaking current is 25% of rated short circuit breaking current. On the
nameplate you can see the out of phase current is 12.5kA which is 25% of rated short
circuit breaking current I.e., 50kA.
Unit: kV
Don’t get confused between line charging and cable charging both are different. Line
charging refers to overhead lines whereas, cable charging refers to underground
cables.
Unit: Ampere
Unit: Ampere
164 | P a g e
CHAPTER 7 Switching Devices
if the breaker is made for back to back capacitor bank switching, then you’ll find
this parameter on the nameplate of SF6 circuit breaker.
Unit: Ampere
So, these are the optional parameters we can find on the name plate of HV or EHV
circuit breaker.
165 | P a g e
CHAPTER 7 Switching Devices
166 | P a g e
CHAPTER 7 Switching Devices
The cam and the ratchet wheel engaged with the locking device, which is released
when the closing coil is energized, are rotated counterclockwise by the closing
spring. The lever is rotated clockwise, compressing the trip spring by torque from
the cam (Fig.7.10).
As soon as the closing sequence is completed, the closing spring is charged by the
ratchet linked to the motor (Fig.7.11).
167 | P a g e
CHAPTER 7 Switching Devices
Disconnect switches in a GIS installation are used for the same function as
those in an air insulated substation (AIS). They are applied to isolate different
elements of the substation, such as circuit breakers, transmission lines, transformer
banks, buses, and voltage transformers. Typically, they do not have big interrupting
capability except for small quantities of charging current associated with short pieces
of bus. Charging currents are in the range of 0.5 A to 2.0 A.
168 | P a g e
CHAPTER 7 Switching Devices
During the closing operation, this gap is bridged by the moving contact. The moving
contact is attached to a suitable drive, which imparts the desired linear displacement
to the moving contact at a pre-determined design speed.
A firm contact is established between the two contacts with the help of spring-loaded
fingers or the multi-lam contacts. The isolation gap is designed for the voltage class
of the isolator and the safe dielectric strength of the gas.
169 | P a g e
CHAPTER 7 Switching Devices
An insulator is used to drive the moving contact and to isolate the drive from the
high voltage components of the disconnector. The shape and size of the insulator are
controlled by the electrical and mechanical requirements of the isolator. In three-
phase ac systems, the individual phase isolators are ganged together to operate
simultaneously.
Leak-tight rotary seals are used in gas insulated isolators for transferring motion
from external drive to the gas. Disconnectors in high voltage GIS operate at SF6
pressures of 0.38 MPa to 0.45 MPa.
The operating speed of the disconnector moving contact ranges from 0.1 to 0.3
m/sec. The design of electrostatic shields on two fixed contacts and the earth side of
the drive insulator plays an important role in ensuring the satisfactory performance
of a gas insulated disconnector.
The disconnect switch status, open or closed, may be discovered by one or more of
the following:
Direct/camera view of the status of the switch blade through a viewport in the
earthed metallic enclosure. Where motorized disconnect or earthing switches are
installed, some utilities and end users, demand a knife switch to make sure the motor
mechanism is deenergized during maintenance. Also, the motor mechanism may
170 | P a g e
CHAPTER 7 Switching Devices
demand decoupling from disconnect operating arm. This has to be considered in the
initial design stages.
Commonly, during the initial design stages, a utility or new GIS end user will meet
with the GIS manufacturer to review their operating routines and functions.
earthing switches in a GIS installation are used for the same staff protection
purpose as those in an air insulated substation (AIS) similar to a portable personnel
earthing connection made with a hook stick. They are used to earth different de-
energized substation elements, such as circuit breakers and voltage transformers.
Typically, these earthing switches do not have fault-closing or induced current
interrupting ability, but are capable of conducting fault current when in the closed
position and a small quantity of continuous current for the purpose of testing circuit
breakers and current transformers that are out of service.
The fast earth switch, on the other hand, is used to protect the circuit-connected
instrument voltage transformer from core saturation caused by direct current flowing
through its primary as a consequence of remnant charge (stored online during
isolation/switching off of the line).
In such a situation, the use of a fast earth switch provides a parallel (low resistance)
path to drain the residual static charge quickly, thereby protecting the instrument
171 | P a g e
CHAPTER 7 Switching Devices
voltage transformer from the damages that may otherwise be caused. The basic
construction of these earth switches is identical.
1. Fixed contact, which is located at the live bus conductor and which forms a
part of the main gas insulated system;
2. Moving contact system mounted on the enclosure of the main module and
aligned to the fixed contact.
transmission lines, transformer banks, and main buses. In some GIS facilities high
speed ground switches are used to initiate protective relay functions. They are,
typically, not used to ground circuit breakers or voltage transformers. HSGS are also
designed and tested to interrupt electrostatically induced capacitive currents and
electromagnetically induced inductive currents occurring in de-energized
transmission lines in parallel and close proximity to energized transmission lines.
They can also remove DC trapped charges on a transmission line.
HSGS typically have motor operating mechanisms with spring assists for rapid
opening and closing of the switchblade. They typically use the same methods for
determining the switch position as disconnect switches. Figure show a HSGS
connected to a bus.
Normally, high speed earthing switches have motor operating mechanisms with
spring assists for quick opening and closing of the switch blade. Normally, they use
the same procedure for discovering the switch status as disconnect switches.
173 | P a g e
CHAPTER 7 Switching Devices
174 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
175 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
8.1 Introduction
Substation Auxiliary AC system is very important and critical in high voltage
substation. It is typically used to supply all low voltage loads.
Auxiliary power supply system shall be according to EUS-E16 specifications
comprise both AC and DC systems necessary for the substation to fed but not
limited to the following:
The AC auxiliary system can be also doubled. The doubled system would utilize
two separate auxiliary transformers, each supplying their own section in the main
distribution switchgear. The doubled system can be also constructed so that the
second supply is coming from an external source, often the surrounding low
voltage network using Automatic transfer switch.
The purpose of auxiliary power supply systems is to cater for the necessary energy
for the operation of primary and secondary devices at the substation. The auxiliary
power systems are normally divided in the main design requirements for typical
176 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
The auxiliary transformer is a transformer that convert medium voltage level (22
KV or 11 KV) to low voltage level 0.4 KV. The medium voltage may be from
medium voltage switchgear outgoing or in sometimes it may be come from power
transformer tertiary winding.
The main aims of AC auxiliary system design is to size the rating of auxiliary
transformer to be able to meet all low voltage loads in the substation. Not only the
current loads but also the future loads due to expansion in station.
177 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
• LED tube lamps shall be installed in all parts of the building except on
outside wall of the building where high-pressure Sodium lamps shall be
used.
3- Other Buildings and Areas:
• Rather than those items mentioned herein, the whole substation
structures illumination and all electrification works are a part of the
contractor's works. Such as residential building, parking area, ... etc.
4- Emergency lighting:
178 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
Emergency lighting shall be designed to give lux level not less than 5% of the
normal lighting lux level with minimum level of 10 lux.
Emergency exit signs are required at all exits and along escape routes.
Portable emergency lanterns which will be automatically light a pilot lamp in case
of AC supply failure shall be supplied.
8.2.2 Sockets
In General
• The various types of sockets should be provided with a switch and signal
lamp.
• All sockets shall be mounted at 0.4 m above floor level except in the kitchen
and the toilet which should be mounted at 1.2 m above floor level.
179 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
• Sockets with rated current higher than 16A - 380V should be provided with
a locking device to prevent insertion or removal of the plug if there is a
tension (voltage) on its terminals.
Each socket should be provided with its plug with the following ratings:
• All sockets shall be provided with separate earthing pins connected to the
yellow/green part in the feeder's cable.
• Sockets for l0A and with rated voltage not exceeding 250V shall be in
accordance with IEC 83 group C, international standard.
• Sockets for 16A with a rated voltage not exceeding 750V shall be in
accordance with IEC 309-1-2-309A.
• Sockets for 125A with a rated voltage not exceeding 750V, shall be in
accordance with IEC 309-1-2-309A.
• Sockets for 250A rated voltage not exceeding 750V, shall be in accordance
with IEC 309-1-2-309A.
• Sockets for 250A, rated voltage 380V shall be installed to each power
transformer to supply power to oil treatment plant.
• One socket 32A rated voltage 380V shall be installed outside each
marshalling box.
180 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
3- Other rooms:
• Sockets for 16A with rated voltage not exceed 250V shall be installed in
all rooms. Distance between sockets should not be more than 8 m, at least
two sockets in each room.
• Sockets for 16A with a rated voltage not exceeding 750V shall be each 4
meters, at least one socket in each room close to distribution boards, relay
boards and control boards.
• Sockets for 16A with a rated voltage 380V shall be installed close the AC
boards.
181 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
4- Basement
• Sockets for 63A, rated voltage not exceeding 750V one socket every 25 m at
least.
182 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
183 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
184 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
185 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
8.4.3.1 General:
• The auxiliary transformers shall comply with IEC 60067 standard and will
be 3 phase unit transformers oil immersed ONAN type which suitable for
indoor installation.
• The auxiliary transformers shall be connected by power cables to medium
and low voltage switchgears.
• The Transformer shall be designed with cable entry boxes for direct
connection of cables on the high and low voltage sides. Oil or compound
filled cable boxes are not permitted..
• The continuous rating of each transformer shall not be less than 500KVA
The power supply of the substation will fed from two auxiliary transformers have a
transformation ratio of 22/0.4 KV and the connection will be DELTA/STAR
(DYN11) with earthed low voltage neutral.
• Tapping shall be provided on the high voltage winding to give the no load
voltage variation specification in schedule of requirements.
186 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
• Tap changing shall be carried out with the transformer off-circuit by means
of an externally operated self-positioning tapping switch
• All phases of the tapping switch shall be operated by one hand wheel, which
shall be positively located and lockable at each tapping switch position
• Indication plates shall be fitted to show clearly the tap position number at
which the transformer is operating, switch position number one will
correspond to the maximum plus tapping.
The transformer shall be able to deliver its maximum continuous ratings with the
tap changer set at the middle tapping of the primary winding, without exceeding
the temperature rise limits:
• Ambient temperature 55 °C
• Oil temperature at top level 45 °C
• Winding temperature by resistance method 50 °C
• Hot spot 60 °C
187 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
8.4.3.7 Bushing:
• The 22kV and 0.4kV sides shall be completely insulated. All bushings shall
be designed that there will be no excessive stressing of any parts due to
temperature changes and adequate means shall be provided to accommodate
conductor expansion.
• The bushings on both sides shall be of the outdoor type and have a leakage
path not less than 2 cm/kV at 22kV.
• MV and LV bushings shall be replaceable without difficulty. Cemented in
bushings are not acceptable. Replacement shall not require removal of the
top cover.
• Sufficiently robust to withstand transports risks.
• The LV bushings shall be located on the top of the transformer tank, on the
side opposite the MV bushings. The LV phase and neutral bushings shall be
provided.
• The MV bushings shall be labeled (U, V, W) and L V bushings (u, v, w, n)
The marking of phase identification by adhesive stickers or painting is not
acceptable.
The Auxiliary transformers shall be supplied with all the necessary accessories
and fittings including but not limited to the following:
• Off load tap changer for external operation with clearly marked position
indication.
• Expanding vessel.
188 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
One of the two auxiliary transformer will feed the main distribution board.
• Abnormal operation:
189 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
If a fault arises on any transformer, the transition system shall connect the loads to
the other transformer.
8.5 Circuit Breaker:
It’s a device used to switch all currents up to the rated current during normal
operation and to interrupt the fault current when a short-circuit occurs.
190 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
can cause overload or short circuit. With a current rating of up to 2500A, MCCBs
can be used for a wide range of voltages and frequencies with adjustable trip
settings.
191 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
the proper selection of circuit breakers. They are the rated maximum voltage, rated
continuous current, and the short-circuit current rating.
The voltage rating of the circuit breaker should be not less than the maximum 1
operating voltage of the AC system. Typical low voltage AC circuit breaker
voltage ratings are 120, 120/240, 208Y/120, 240, 277, 347, 480Y/277, 480,
600Y/347, and 600 volts.
The short-circuit current rating is the maximum short circuit current that a circuit
breaker can successfully interrupt. The circuit breakers for an AC system should
have a current interrupting rating equal to or higher than the actual AC system
maximum fault current. Typical low voltage AC circuit breaker current
interrupting ratings are 7.5 kA, 10 kA, 14 kA, 18 kA, 20 kA, 22 kA, 25 kA, 35 kA,
42 kA, 50 kA, 65 kA, 85 kA, 100 kA, 125 kA, 150 kA, and 200 kA.
The circuit breaker rated continuous current should be not less than the maximum
circuit normal operation current. Typically, the rated circuit breaker current should
be 1 to 1.25 of calculated load current with 10% design margin.
192 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
In some cases, thermal trip units or electronic trip units should be selected based on
equipment protection requirements or the arc flash energy limitation requirements.
The trip unit setting should be clearly identified in the circuit breaker order and
design document.
So, The AC switchboard shall include one outgoing feeders with circuit breaker of
rated current not less than 150 A for feeding outdoor fence
The main AC board shall contain but not limited to the following circuit breakers:
8.6 Cables:
8.6.1 Cables and conductor types
8.6.1.1 Single core cable
It is used for lighting circuits. Insulation may be XLPE or PVC.
193 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
194 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
8.6.3.1 Ampacity:
All conductors should be initially sized based on the ampacity of the load(s)
they are supplying.
For single Phase Loads:
𝑃 𝑆
𝐼= =
𝑉 ∗ (cos ∅) 𝑉
For 3 Phase Loads:
𝑃
𝐼= = 𝑆/(√3 ∗ 𝑉)
√3 ∗ 𝑉 ∗ cos ∅
Where:
I: load current capacity
P: rated power (w)
V: system voltage
S: apparent power (VA)
Cos (ɸ): power factor
8.6.3.2 Derating factors
Are the factors which makes a cable current carrying capacity less than the
designed value. For example, ambient air temperature, soil temperature and laying
method of the cable.
For accurate design of cables and accurate specify capacity of cables we must
receive information about derating factors from cables suppliers so that we can
specify the cross-section area of cables more accurate.
195 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
Generally, The cable must have a current capacity more than the rated of the circuit
breaker connected to it because if the cable current capacity is less than the rated of
circuit breaker then an moderate overload may be happen and C.B doesn’t sense it
but this overload may damage the cable (we can say that circuit breaker is a
protection for cable).
196 | P a g e
CHAPTER 8 Auxiliary power supply and transformer
2
𝜃𝑓 + 𝛽
𝐼𝑎𝑑 𝑡 = 𝐾 2 𝑆 2 ln
𝜃𝑖 + 𝛽
𝐼𝑎𝑑 : Short circuit current calculated on adiabatic basis (amp).
K: constant depends on material of the current carrying component.
S: cross sectional area of conductor (𝑚𝑚2).
T: duration of short circuit (1 second).
ɵ𝑓: Final temperature = 2500𝑐
ɵ𝑖: Initial temperature = 900𝑐
𝛽: Temperature coefficient of resistance of the current carrying component.
197 | P a g e
CHAPTER 9 DC Auxiliary System
198 | P a g e
CHAPTER 9 DC Auxiliary System
9.1 Introduction
A DC system is the total assembly of components that is required to supply
direct current within preset limits of terminal voltage for a specified time. What is
the necessity of the DC system in a substation?
The function of the DC system is to supply auxiliary and operating power to
equipment designed for a DC supply, such as:
• Protection circuits
• Control circuits
• Emergency lighting
• Annunciation, alarms
• Communication panels
The typical system is normally supplied by an AC system and consists of a battery
and a battery charger. Voltage-dropping devices may also be installed between the
system output terminals and the load to be supplied
Generally, DC supply is preferred because it is a reliable source obtained from a
battery bank.
In case of power failure, we can determined the status of the breakers, like which
breaker is in on position or which one is in off and check the fault status of the
relay.
But in this case the AC supply cannot be use to check the status of the fault that is
why DC system is preferred to use.
199 | P a g e
CHAPTER 9 DC Auxiliary System
200 | P a g e
CHAPTER 9 DC Auxiliary System
• Voltage: The fully charged lead-acid cell has an open circuit voltage of
approximately 2.10 V, which varies as a function of cell specific gravity
and temperature. Open circuit voltage increases with specific gravity and
decreases with temperature, and may range from 2.06 to 2.15 V/cell.
Float voltages range from 2.15 to 2.40 V/cell, depending on their
individual cell design, temperature, and manufacture recommendation
201 | P a g e
CHAPTER 9 DC Auxiliary System
202 | P a g e
CHAPTER 9 DC Auxiliary System
voltage and the largest possible number of cells that will satisfy the
manufacturers charging recommendations.
➢ Advantages:
• Low capital cost.
➢ Disadvantages:
• No standby DC System outage for maintenance Need to isolate battery/
charger combination from load under boost charge conditions in order
to prevent high boost voltages appearing on DC distribution system
203 | P a g e
CHAPTER 9 DC Auxiliary System
➢ Advantages:
• Medium capital cost.
• Standby DC provided which is 100% capacity on loss of one charger.
• Each battery or charger can be maintained in turn.
• Each battery can be isolated, and boost charged in turn without
affecting DC output voltage.
➢ Disadvantages:
• 50% capacity on loss of one battery during AC source failure.
9.4.3 Fully duplicate 2 * 100% batteries and 2 * 100% chargers:
204 | P a g e
CHAPTER 9 DC Auxiliary System
➢ Advantages:
• Full 100% standby DC capacity provided under all AC source conditions
and single component (charger or battery) failure
➢ Disadvantages:
• High capital cost
• Greater space requirement Increased maintenance cost
9.5 DC system Voltage in substations:
• 220/110-volt DC 2-wire ungrounded system for control, protection,
emergency lighting, tripping coils, operating coils, contactors, relays,
Auxiliary relays indications and protection.
• 48 volt for communications system and SAS system
205 | P a g e
CHAPTER 9 DC Auxiliary System
9.6 DC Parameters:
Generally, the following parameters for DC systems as specified in "EUS-E16"
are:
• Nominal DC system voltage: 220 V
• Allowable minimum DC system voltage: 198 V
• Allowable maximum DC system voltage: 242 V.
• Rated discharge time hour: 5H
• Number of batteries for 220 V: 2 batteries
• Number of chargers for 220 V: 2 chargers
206 | P a g e
CHAPTER 9 DC Auxiliary System
Capacity decreases gradually during the life of the battery, with no sudden
capacity loss being encountered under normal operating conditions. Since the rate
of capacity loss is dependent upon such factors as operating temperature,
electrolyte specific gravity, depth, and frequency of discharge, an ageing factor
should be chosen based on the required service life. The choice of the ageing factor
is, therefore, essentially an economic consideration. An ageing factor of 1.25 is
used, meaning that the battery is sized to carry the loads until its capacity has
decreased to 80% of its rated capacity. For an application involving continuous
high temperatures and/or frequent deep discharges, it may be desirable to use a
factor of, say, 1.43, and replace the battery when its capacity falls to 70% of its
rated capacity.
207 | P a g e
CHAPTER 9 DC Auxiliary System
The capacity rating factor, Kt, is the ratio of rated ampere-hour capacity (at a
standard time rate, at 25 °C, and to a standard end-of-discharge voltage) of a cell,
to the amperes that can be supplied by that cell for t minutes at 25 °C and to a
given end of- discharge voltage. Kt factors are available from the battery
manufacturer or may be calculated from other published.
Published discharge data for nickel-cadmium cells are most commonly available in
tabular form, in which the current available from each cell type is stated for a given
discharge time and end-of-discharge voltage. For intermediate times and voltages,
it is necessary to interpolate between the known:
208 | P a g e
CHAPTER 9 DC Auxiliary System
209 | P a g e
CHAPTER 9 DC Auxiliary System
210 | P a g e
CHAPTER 9 DC Auxiliary System
211 | P a g e
CHAPTER 9 DC Auxiliary System
Operating conditions can change the available capacity of the battery. For
example:
a) Available capacity decreases as its temperature decreases.
b) Available capacity decreases as the discharge rate increases.
c) The minimum specified cell voltage at any time during the battery discharge
cycle limits the available capacity.
d) The charging method can affect the available capacity.
The battery capacity is determined by the drawings up a load profile, which
specifies the current load on the battery as a function of time. The necessary
battery rating is determined by means of the load profile plus 25% for future use by
Owner.
The factors specified below shall be taken into account in determining the rating of
the battery:
• Load profile as approved by Owner.
• Time during which the AC supply is not available (5 hours).
• Highest and lowest permissible pole voltage.
• Factor of safety to allow for ageing of the battery and incomplete charging.
• Battery type.
• Ambient temperature
212 | P a g e
CHAPTER 9 DC Auxiliary System
The minimum battery voltage equals the minimum system voltage plus any voltage
drop between the battery terminals and the load. The minimum battery voltage is
then used to calculate the allowable minimum cell voltage.
𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑏𝑎𝑡𝑡𝑒𝑟𝑦 𝑣𝑜𝑙𝑡𝑎𝑔𝑒
= 𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑐𝑒𝑙𝑙 𝑣𝑜𝑙𝑡𝑎𝑔𝑒
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑐𝑒𝑙𝑙𝑠
213 | P a g e
CHAPTER 9 DC Auxiliary System
Using the capacity rating factor for the given cell range and the applicable
temperature derating factor Tt, a cell size is calculated that will supply the required
current for the duration of the first period. For the second section, the capacity is
calculated assuming that the current A1 required for the first period is continued
through the second period; this capacity is then adjusted for the change in current
(A2 - A1) during the second period. In the same manner, the capacity is calculated
for each subsequent section of the duty cycle. This iterative process is continued
214 | P a g e
CHAPTER 9 DC Auxiliary System
until all sections of the duty cycle have been considered. The calculation of the
capacity FS required by each section S, where S can be any integer from 1 to N,
can be expressed mathematically as follows:
𝑃=𝑆
Where:
• S :is the section of the duty cycle being analyzed. Section S contains the first
S periods of the duty cycle (for example, section S5 contains periods 1
through 5)
• N: is the number of periods in the duty cycle
• P: is the period being analyzed.
• Ap: is the amperes required for period P.
• t: is the time in minutes from the beginning of period P through the end of
section S
• Kt: is the capacity rating factor for a given cell type, at the t minute
discharge rate, at 25 °C, to a definite end-of-discharge voltage.
• Tt: is the temperature derating factor at t minutes, based on electrolyte
temperature at the start of the duty cycle.
• Fs: is the capacity required by each section S
215 | P a g e
CHAPTER 9 DC Auxiliary System
216 | P a g e
CHAPTER 9 DC Auxiliary System
217 | P a g e
CHAPTER 9 DC Auxiliary System
𝑘𝐶
𝐴= + 𝐿𝑐
𝐻
Where:
A: Output rating of the charger in amperes.
K: Efficiency factor to return 100 percent of ampere-hours removed. Use 1.4 for
nickel-cadmium batteries.
C: Calculated number of ampere-hours discharged from the battery (calculated
based on duty cycle).
H: Recharge time to approximately 95 percent of capacity in hours. A recharge
time of 8 to 12 hours is usually recommended.
218 | P a g e
CHAPTER 9 DC Auxiliary System
219 | P a g e
CHAPTER 10 Instrument Transformer
220 | P a g e
CHAPTER 10 Instrument Transformer
10.1 Introduction
Current and voltage transformers (CTs and VTs) are collectively known as
transducers or instrument transformers. They are used to transform the power system
currents and voltages to lower magnitudes and to provide isolation between the high
voltage power system and the relays and other measuring instruments (meters)
connected to the secondary windings of the transducers. In order to achieve a degree
of interchangeability among different manufacturers of relays and meters, the ratings
of the secondary windings of the transducers are standardized. The standard current
ratings of the secondary windings of the current transformers (CTs) are 5 or 1
ampere. The secondary windings of the voltage transformers (VTs) are rated at 110
V line to line. The current and voltage ratings of the protective relays and meters are
same as the current and voltage ratings of the secondary windings of the CTs and
VTs respectively. The transducers should be able to provide current and voltage
signals to the relays and meters which are faithful reproductions of the corresponding
primary quantities. Although in most of the cases the modern transducers are
expected to do so, but they can’t be ideal and free from the errors of transformation.
Hence the errors of transformation introduced by the transducers must be taken into
account, so that the performance of the relays can be assessed in the presence of such
errors.
221 | P a g e
CHAPTER 10 Instrument Transformer
222 | P a g e
CHAPTER 10 Instrument Transformer
223 | P a g e
CHAPTER 10 Instrument Transformer
CTs which are used to step down the primary currents to low values suitable
for the operation of measuring instruments (meters) are called measuring or metering
CTs. Secondary of the measuring CTs are connected to the current coils of ammeters,
wattmeters, energy meters, etc. Since the measurements of electrical quantities are
performed under normal conditions and not under fault conditions, the performance
of measuring CTs is of interest during normal loading conditions. Measuring CTs
are required to give high accuracy for all load currents up to 125% of the rated
current. These CTs may have very significant errors during fault conditions, when
the currents may be several times their normal value for a short time. This is not
significant because metering functions are not required during faults. The measuring
CTs should get saturated at about 1.25 times the full-load current so as not to
reproduce the fault current on the secondary side, to avoid damage to the measuring
instruments. CTs used in association with protective devices i.e., relays, trip coils,
pilot wires etc. are called protective CTs. Protective CTs are designed to have small
errors during fault conditions so that they can correctly reproduce the fault currents
for satisfactory operation of the protective relays. The performance of protective
224 | P a g e
CHAPTER 10 Instrument Transformer
relays during normal conditions, when the relays are not required to operate, may
not be as accurate. When a fault occurs on a power system, the current tends to
increase and current and voltage tends to collapse. The fault current is abnormal and
may be 20 to 50 times the full-load current. It may have dc offset in addition to ac
component. The fault current for a CT secondary of 5A rating could be 100 to 250
A. Therefore, the CT secondary having a continuous current rating of 5A should
have short-time current rating of 100 to 250 A, so that the same is not damaged.
Since the ac component in the fault current is of paramount importance for the relays,
the protective CT should correctly reproduce it on the secondary side in spite of the
dc offset in the primary winding. Hence the dc offset should also be considered while
designing the protective CT. The protective CT should not saturate up to 20 to 50
times full-load current.
225 | P a g e
CHAPTER 10 Instrument Transformer
consider currents that are five times under the rated current, the core material made
from nickel-iron alloy fares batter.
Hot-rolled silicon steel has the lowest permeability. So, it is not suitable for CTs. In
order to achieve the desired characteristics, composite cores made of laminations of
two or more materials are also used in CTs.
10.2.5 CT Burden
The CT burden is defined as the load connected across its secondary, which is
usually expressed in volt amperes (VA). It can also be expressed in terms of
impedance at the rated secondary current at a given power factor, usually 0.7
lagging. From the given impedance at rated secondary current, the burden in VA can
be calculated. Suppose the burden is 0.5 Ω at 5 𝐴 secondary current. Its volt amperes
will be equal to 𝐼 2 𝑅 = 52 × 0.5 = 12.5 𝑉𝐴. The total burden on the CT is that of
the relays, meters, connecting leads and the burden due to the resistance of the
226 | P a g e
CHAPTER 10 Instrument Transformer
secondary winding of the CT. The relay burden is defined as the power required to
operate the relay. The burden of relays and meters is given by the manufactures or it
can be calculated from the manufacturer’s specifications as the burden depends on
their type and design. The burden of leads depends on their resistance and the
secondary current. Lead resistance is appreciable if long wires run from the
switchyard to the relay panels placed in the control room. Lead burden can also be
reduced using low secondary currents. Usually, secondary currents of 5 A are used,
but current of 2 A or even 1 A can be used to reduce the lead burden. Suppose, the
lead resistance is 5 Ω. Then lead burden at 5 𝐴 will be 52 × 5 = 125 𝑉𝐴. The burden
at 1 A is only 12 × 5 = 5 𝑉𝐴. The economy in CT cost and space requirement
demands shorter lead runs and sensitive relays. The rating of a large CT is 15 VA.
For a 5 A secondary current, the corresponding burden is 0.6 Ω, and for a 1 A
secondary current it is 15 Ω. If rated burden be PVA at rated secondary current 𝐼𝑆
amperes, the ohmic impedance of the burden Zb can be calculated as follows:
𝑃
𝑍𝑏 = 𝑜ℎ𝑚𝑠
𝐼𝑠2
If burden power factor is 𝑐𝑜𝑠 𝜙 , the values of resistance and reactance of the burden
can be calculated as follows:
𝑅𝑏 = 𝑍𝑏 𝑐𝑜𝑠 𝜙
𝑋𝑏 = √𝑍𝑏2 – 𝑅𝑏2
The impedance of the relay coil changes with current setting. The values of power
consumption of relays, trip coil etc. are given by their manufacturers. The CT of
suitable burden can be selected after calculating the total burden on the CT. When
227 | P a g e
CHAPTER 10 Instrument Transformer
the relay is set to operate at current different from the rated secondary current of the
CT, the effective burden of the relay can be calculated as follows:
𝐼𝑠 2
𝑃𝑒 = 𝑃𝑟 ( )
𝐼𝑟
The rated VA output of the CT selected should be the higher standard value
nearest to the calculated value. If the VA rating of the CT selected is very
much in excess of the burden, it makes the choice uneconomical and the CT
becomes unduly large.
The following are some of the commonly used terms for current transformers (CTs)
i. Rated primary current: The value of the primary current which is marked on
the rating plate of the transformer and on which the performance of the CT is
specified by the manufacturer.
ii. Rated secondary current: The value of the secondary current which is
marked on the rating plate of the transformer and on which the performance
of the CT is specified by the manufacturer.
iii. Rated transformation ratio: The ration of the rated primary current to rated
secondary current. It is also called nominal transformation ratio.
228 | P a g e
CHAPTER 10 Instrument Transformer
iv. Actual transformation ratio: The ratio of the actual primary current to the
actual secondary current.
v. Burden: The value of the load connected across the secondary of CT,
expressed in VA or ohms at rated secondary current.
vi. Rated burden: The value of the load to be connected across the secondary of
CT including connecting lead resistance expressed in VA or ohms on which
accuracy requirement is based.
vii. Rated short-time current: The r.m.s value of the a.c. component of the
current which the CT is capable of carrying for the rated time without being
damaged by thermal or dynamic effects.
viii. Rated short-time factor: The ratio of rated short-time current to the rated
current.
ix. Rated accuracy limit primary current: The highest value of primary current
assigned by the CT manufacturer, up to which the limits of composit error are
complied with.
x. Rated accuracy limit factor: The ratio of rated accuracy limit primary
current to the rated primary current.
xi. Composit error: The r.m.s. value of the difference (𝑁 𝑖𝑠 – 𝑖𝑝 ), given by
100 1 𝑇
𝐶𝑜𝑚𝑝𝑜𝑠𝑖𝑡 𝑒𝑟𝑟𝑜𝑟 = √ ∫ (𝑁𝑖𝑠 – 𝑖𝑝 )
𝐼𝑝 𝑇 0
229 | P a g e
CHAPTER 10 Instrument Transformer
xiii. Rated short-circuit current: The r.m.s. value of primary current which the
CT will withstand for a rated time with its secondary winding short-circuited
without suffering harmful effects.
xiv. Rated primary saturation current: The maximum value of primary
current at which the required accuracy is maintained
xv. Rated saturation factor: the ratio of rated primary saturation current to
rated primary current
230 | P a g e
CHAPTER 10 Instrument Transformer
231 | P a g e
CHAPTER 10 Instrument Transformer
10.2.8 CT Errors
In an ideal (perfect) CT, the secondary current is given by
𝐼𝑝
𝐼𝑠 =
𝑁
𝐼𝑝
𝐼𝑠 = – 𝐼0
𝑁
Thus, the actual CT does not reproduce the primary current exactly in secondary side
both in magnitude and phase due to exciting current I0. The exciting current I0 is the
main source of errors in both measuring and Protective CTs. The error in magnitude
is due to error in CT ratio which is called “ratio error” and the error in phase is
called “phase-angle error.”
𝑁𝐼𝑠 – 𝐼𝑝
𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑒𝑟𝑟𝑜𝑟 = × 100
𝐼𝑝
Is = Secondary current
Ip = Primary current
232 | P a g e
CHAPTER 10 Instrument Transformer
The ratio error of a CT depends on its exciting current. When the primary current
increases, the CT tries to produce the corresponding secondary current, and this
needs a greater secondary emf, core flux density and exciting current. A stage comes
when any further increase in primary current is almost wholly absorbed in an
increased exciting current, and thereby the secondary current hardly increases at all.
At this stage, the CT becomes saturated. Thus, the ratio error depends on saturation.
An accuracy of about 2% to 3% of the CT is desirable for distance and differential
relays, whereas for many other relays, a higher percentage can be tolerated.
According to standards followed in U.K., protective CTs are classified as S, T and
U type. The errors of these types of CT s are shown in Table 10.1
When the primary current increases, at a certain value the core commences to
saturate and the error increases. The value of the primary current at which the error
reaches a specified limit is known as its accuracy limit primary current or
saturation current. The maximum value of the primary current for a given accuracy
limit is specified by the manufacturer. The CT will maintain the accuracy at the
specified maximum primary current at the rated burden. This current is expressed as
a multiple of the rated current. The ratio of accuracy limit primary current and rated
primary current is known as the rated accuracy limit factor or saturation factor, the
standard values of which are 5, 10, 15, 20 and 30. The performance of a CT is given
233 | P a g e
CHAPTER 10 Instrument Transformer
at certain multiples of the rated current. According to BSS 3938, rated primary
currents of CTs are up to 75 kA and secondary currents 5 A or 1 A
234 | P a g e
CHAPTER 10 Instrument Transformer
2. Turns ratio
In addition, the error in the turns ratio shall not exceed ±0.25%.
235 | P a g e
CHAPTER 10 Instrument Transformer
10.3.1 VT Errors
The errors introduced by the use of voltage transformers are, in general, less
serious than those introduced by current transformers. like current transformers,
voltage transformers introduce an error, both in magnitude and in phase, in the
measured value of the voltage. The voltage applied to the primary circuit of the VT
cannot be obtained correctly simply by multiplying the voltage across the secondary
by the turns ratio K of the transformer. The divergence of the actual (true) ratio 𝑉𝑝 /𝑉𝑠
from nominal (rated) ratio K depends upon the resistance and reactance of the
transformer windings as well as upon the value of the exciting current of the
transformer.
236 | P a g e
CHAPTER 10 Instrument Transformer
237 | P a g e
CHAPTER 10 Instrument Transformer
238 | P a g e
CHAPTER 10 Instrument Transformer
porcelain housing. The performance of the voltage divider type capacitor VT is not
as good as that of the electromagnetic type. The performance of high-speed distance
relays is less reliable with capacitor type VTs. Hence, the decision regarding the
choice of a VT will depend whether economy in VT cost or relay performance is
more important for a particular power line. Errors of capacitor type VTs can be
reduced by reducing its burden. It is due to the fact that the series connected
capacitors perform the function of a potential divider if the current drawn by the
burden is negligible compared to the current flowing through the capacitors
connected in series. An electronic amplifier having high input impedance and VA
output high enough to supply the VA burden can be included in the capacitor type
VT arrangement. Such an arrangement gives a good transient response. Finally, it
can be concluded that the secondary voltage supply seldom creates any problem but
problems with secondary current supply arise frequently.
239 | P a g e
CHAPTER 11 Protection System and Schemes
240 | P a g e
CHAPTER 11 Protection System and Schemes
11.1 Introduction
The purpose of an electrical power system is to generate and supply electrical
energy to consumers. The system should be designed to deliver this energy both
reliably and economically. Frequent or prolonged power outages result in severe
disruption to the normal routine of modern society, which is demanding ever-
increasing reliability and security of supply. As the requirements of reliability and
economy are largely opposed, power system design is inevitably a compromise.
Many items of equipment are very expensive, and so the complete power system
represents a very large capital investment. To maximise the return on this outlay, the
system must be utilised as much as possible within the applicable constraints of
security and reliability of supply. More fundamental, however, is that the power
system should operate in a safe manner at all times.
The definitions that follow are generally used in relation to power system
protection:
241 | P a g e
CHAPTER 11 Protection System and Schemes
242 | P a g e
CHAPTER 11 Protection System and Schemes
• The boundaries of the protective zone are decided by the locations of the
transducers or the CT’s.
• In order to cover all power equipment by their protection systems, the zones of
protection must meet these requirements:
i) All power system elements must be covered by at least one zone.
ii) Zones of protection must overlap to prevent any system element from
being unprotected.
243 | P a g e
CHAPTER 11 Protection System and Schemes
244 | P a g e
CHAPTER 11 Protection System and Schemes
protection may be adequate. For EHV systems, where system stability is at risk
unless a fault is cleared quickly, multiple primary protection systems, operating in
parallel and possibly of different types (e.g. distance and unit protection), will be
used to ensure fast and reliable tripping. Back-up overcurrent protection may then
optionally be applied to ensure that two separate protection systems are available
during maintenance of one of the primary protection systems.
Back-up protection systems should, ideally, be completely separate from the primary
systems. For example, a circuit protected by a current differential relay may also
have time graded overcurrent and earth fault relays added to provide circuit breaker
tripping in the event of failure of the main primary unit protection. Ideally, to
maintain complete redundancy, all system components would be duplicated. This
ideal is rarely attained in practice.
• series sealing
• shunt reinforcing
• shunt reinforcement with sealing
245 | P a g e
CHAPTER 11 Protection System and Schemes
With the circuit healthy either or both of relays A and B are operated and energise
relay C. Both A and B must reset to allow C to drop-off. Relays A, B and C are time
delayed to prevent spurious alarms during tripping or closing operations. The
resistors are mounted separately from the relays and their values are chosen such
that if any one component is inadvertently short-circuited, tripping will not take
place.
The alarm supply should be independent of the tripping supply so that indication
will be obtained in case of failure of the tripping supply.
246 | P a g e
CHAPTER 11 Protection System and Schemes
247 | P a g e
CHAPTER 11 Protection System and Schemes
5. Quadrilateral Characteristic.
6. Reactance Type Characteristic.
7. Lenticular Characteristic.
1. Zone 1:
• Trips with no intentional time delay.
• Under reaches to avoid unnecessary operation for faults beyond remote
terminal.
• Typical reach setting range 80-90% of ZL.
2. Zone 2:
• Set to protect remainder of line.
• Overreaches into adjacent line/equipment.
• Minimum reach setting 120% of ZL.
• Typically, time delayed by 15-30 cycles.
3. Zone 3:
• Remote backup for relay/station failures at remote terminal.
• Reaches beyond Z2, may covers the whole adjacent line.
248 | P a g e
CHAPTER 11 Protection System and Schemes
249 | P a g e
CHAPTER 11 Protection System and Schemes
250 | P a g e
CHAPTER 11 Protection System and Schemes
Line current differential relays operate on a difference in current into the line
compared to the current out of the line. This is called current differential method.
The differential current can be measured in different ways:
• Magnitude comparison
• Phase comparison
• Phasor or Directional comparison (magnitude and angle)
Line differential relays basically operate on a difference in current into the line,
compared to the current out of the line. For an internal fault, the current will flow
into the line from both line terminals, with the polarity of the current transformers
as shown in Figure
The above figure shows this for a line with two ends. Each device measures the local
current and sends the information of measured currents and phase relation to the
opposite end.
251 | P a g e
CHAPTER 11 Protection System and Schemes
Two relays at each end of the cable separated by some distance with the
communication path between the two relays so that they exchange information
together.
252 | P a g e
CHAPTER 11 Protection System and Schemes
253 | P a g e
CHAPTER 11 Protection System and Schemes
• Protecting the transformer from external faults such as: various short circuits,
voltage surges, and overload.
• Protection of the electrical network connected to the transformer.
• Protecting the parts surrounding the transformer at the time of fault
• Observing and monitoring the operation of transformers in order to reduce
risks as much as possible at the time of fault occurrence.
254 | P a g e
CHAPTER 11 Protection System and Schemes
(i) Short circuits in the transformer winding and connections These are
electrical faults of serious nature and are likely to cause immediate
damage. Such faults are detectable at the winding terminals by unbalances
in voltage or current. This type of faults include line to ground or line to
line and interturn faults on H.V. and L.V. windings.
(ii) Incipient faults Initially, such faults are of minor nature but slowly might
develop into major faults. Such faults are not detectable at the winding
terminals by unbalance in voltage or current and hence, the protective
devices meant to operate under short circuit conditions are not capable of
detecting this type of faults. Such faults include poor electrical
connections, core faults, failure of the coolant, regulator faults and bad
load sharing between transformers.
255 | P a g e
CHAPTER 11 Protection System and Schemes
The protection methods used in transformers vary according to the power level
of each transformer. Transformers are usually categorized according to their ratings
as follows:
Small transformers may only use the fuse as their main protection, while the levels
of protection vary to more than five types in large transformers, including
differential protection, overcurrent protection, restricted earth fault protection and
others.
• Differential protection.
• Restricted earth fault protection.
• Overcurrent protection.
• Over flux protection.
• Mechanical protection.
256 | P a g e
CHAPTER 11 Protection System and Schemes
257 | P a g e
CHAPTER 11 Protection System and Schemes
O and R are the operating and restraining coils of the relay, respectively. The
connections are made in such a way that under normal conditions or in case of
external faults the current flowing in the operating coil of the relay due to CTs of the
primary side is in opposition to the current flowing due to the CTs of the secondary
side. Consequently, the relay does not operate under such conditions. If a fault occurs
on the winding, the polarity of the induced voltage of the CT of the secondary side
is reversed. Now the currents in the operating coil from CTs of both primary and
secondary side are in the same direction and cause the operation of the relay. To
supply the matching current in the operating winding of the relay, the CT which are
on the star side of the transformer are connected in delta. The CTs which are on the
delta side of the transformer are connected in star. In case of Y – ∆ connected
transformer there is a phase shift of 30° in line currents. Also the above mentioned
CTs connections also correct this phase shift. Moreover, zero sequence current
flowing on the star side of the transformers does not produce current outside the
delta on the other side. Therefore, the zero sequence current should be eliminated
from the star side. This condition is also fulfilled by CTs connection in delta on the
star side of the transformer.
The relay settings for transformer protection are kept higher than those for
alternators. The typical value of alternator is 10% for operating coil and 5% for bias.
258 | P a g e
CHAPTER 11 Protection System and Schemes
The corresponding values for transformer may be 40% and 10% respectively. The
reasons for a higher setting in the case of transformer protection are.
(i) A transformer is provided with on-load tap changing gear. The CT ratio
cannot be changed with varying transformation ratio of the power
transformer. The CT ratio is fixed and it is kept to suit the nominal ratio of
the power transformer. Therefore, for taps other than nominal, an out of
balance current flows through the operating coil of the relay during load
and external fault conditions.
(ii) When a transformer is on no-load, there is no-load current in the relay.
Therefore, its setting should be greater than no-load current.
259 | P a g e
CHAPTER 11 Protection System and Schemes
A simple overcurrent and earth fault relay does not provide good protection for
a star connected winding, particularly when the neutral point is earthed through an
impedance. Restricted earth fault protection, as shown in Fig. 11.14 provides better
protection. This scheme is used for the winding of the transformer connected in star
where the neutral point is either solidly earthed or earthed through an impedance.
The relay used is of high impedance type to make the scheme stable for external
faults.
260 | P a g e
CHAPTER 11 Protection System and Schemes
The overcurrent protection device, in addition to the restricted earth fault protection
device, is a backup protection against faults that occur outside the protection area in
the case of transformers with a capacity higher than 5 MVA.
And this protection is installed on the high voltage and low voltage sides of the
transformer. They are considered as backup protection for the differential protection
on the transformer. And it is necessary to make a time coordination between them
to ensure the speed of separation from the low voltage side first. And overcurrent
relays contain special high set (instantaneous) element with high standards that are
useful in cases of severe short circuits.
It is also necessary to ensure that this protection does not operate when an inrush
current passes. Fig. 11.15 shows the connection of overcurrent protection devices on
both sides of the high voltage and low voltage from the power transformer.
261 | P a g e
CHAPTER 11 Protection System and Schemes
Figure 11.15 Connection of overcurrent protection devices on both sides of a power transformer
It also shows the time coordination between them by choosing the appropriate time
curve for the protection devices on both sides of the power transformer, as shown in
Figure No. (). When a fault occurs that causes the passage of a current of a value,
the time taken to disconnect the secondary side breaker must be faster (less) than the
time taken to disconnect the breaker of the primary side.
262 | P a g e
CHAPTER 11 Protection System and Schemes
The magnetic flux increases when voltage increases. This results in increased
iron loss and magnetising current. The core and core bolts get heated and the
lamination insulation is affected. Protection against over fluxing is required where
overfluxing due to sustained overvoltage can occur. The reduction in frequency also
increases the flux density and consequently, it has similar effects as those due to
overvoltage. The expression of flux in a transformer is given by:
𝐸
∅=𝐾
𝑓
Therefore, to control flux, the ratio E/f is controlled. When E/f exceeds unity, it has
𝐸
to be detected. Electronic circuits with suitable relays are available to measure the
𝑓
𝐸
ratio. Usually 10% of overfluxing can be allowed without damage. If exceeds 1.1,
𝑓
overfluxing protections operates. Overfluxing does not requires high speed tripping
and hence instantaneous operation is undesirable when momentary disturbances
occur. But the transformer should be isolated in one or two minutes at the most if
overfluxing persists.
263 | P a g e
CHAPTER 11 Protection System and Schemes
Buchholz relay
264 | P a g e
CHAPTER 11 Protection System and Schemes
A typical Buchholz relay will have two sets of contacts. One is arranged to operate
for slow accumulations of gas, the other for bulk displacement of oil in the event of
a heavy internal fault. An alarm is generated for the former, but the latter is usually
direct-wired to the CB trip relay. The device will therefore give an alarm for the
following fault conditions, all of which are of a low order of urgency.
When a major winding fault occurs, this causes a surge of oil, which displaces the
lower float and thus causes isolation of the transformer. This action will take place
for:
An inspection window is usually provided on either side of the gas collection space.
Visible white or yellow gas indicates that insulation has been burnt, while black or
grey gas indicates the presence of, dissociated oil. In these cases, the gas will
probably be inflammable, whereas released air will not. A vent valve is provided on
the top of the housing for the gas to be released or collected for analysis.
Transformers with forced oil circulation may experience oil flow to/from the
conservator on starting/stopping of the pumps. The Buchholz relay must not operate
in this circumstance. Cleaning operations may cause aeration of the oil. Under such
conditions, tripping of the transformer due to Buchholz operation should be inhibited
for a suitable period. Because of its universal response to faults within the
265 | P a g e
CHAPTER 11 Protection System and Schemes
transformer, some of which are difficult to detect by other means, the Buchholz relay
is invaluable, whether regarded as a main protection or as a supplement to other
protection schemes. Tests carried out by striking a high voltage arc in a transformer
tank filled with oil, have shown that operation times of 0.05s-0.1s are possible.
Electrical protection is generally used as well, either to obtain faster operation for
heavy faults, or because Buchholz relays have to be prevented from tripping during
oil maintenance periods. Conservators are fitted to oil-cooled transformers above
1000kVA rating, except those to North American design practice that use a different
technique.
This device detects rapid rise of pressure rather than absolute pressure and
thereby can respond even quicker than the pressure relief valve to sudden abnormally
high pressures. Sensitivities as low as 0.07bar/s are attainable, but when fitted to
forced-cooled transformers the operating speed of the device may have to be slowed
deliberately to avoid spurious tripping during circulation pump starts. Alternatively,
sudden pressure rise relays may have their output supervised by instantaneous high-
set overcurrent elements.
266 | P a g e
CHAPTER 11 Protection System and Schemes
The simplest form of pressure relief device is the widely used ‘frangible disc’ that is
normally located at the end of an oil relief pipe protruding from the top of the
transformer tank. The surge of oil caused by a serious fault bursts the disc, so
allowing the oil to discharge rapidly. Relieving and limiting the pressure rise avoids
explosive rupture of the tank and consequent fire risk. Outdoor oil-immersed
transformers are usually mounted in a catchment pit to collect and contain spilt oil
(from whatever cause), thereby minimising the possibility of pollution. A drawback
of the frangible disc is that the oil remaining in the tank is left exposed to the
atmosphere after rupture. This is avoided in a more effective device, the sudden
pressure relief valve, which opens to allow discharge of oil if the pressure exceeds a
set level, but closes automatically as soon as the internal pressure falls below this
level. If the abnormal pressure is relatively high, the valve can operate within a few
milliseconds, and provide fast tripping when suitable contacts are fitted. The device
is commonly fitted to power transformers rated at 2MVA or higher, but may be
applied to distribution transformers rated as low as 200kVA, particularly those in
hazardous areas.
267 | P a g e
CHAPTER 11 Protection System and Schemes
Winding Thermometer
The winding thermometer, responds to both the top-oil temperature and the
heating effect of the load current. The winding thermometer creates an image of the
hottest part of the winding. However, the top-oil temperature can be measured, the
top-oil temperature may be considerably lower than the winding temperature,
especially shortly after a sudden load increase. This means that the top-oil
thermometer is not an effective overheating protection. Accordingly, the
measurement is further expanded with a current signal proportional to the loading
current in the winding. This current signal is taken from a current transformer located
inside the bushing of that particular winding.
268 | P a g e
CHAPTER 11 Protection System and Schemes
(87G) on LV side
Separate over flux Relay (24)
Tap Position
Trip circuit supervision Relay
indicator (TPI)
Lockout Relay (86)
269 | P a g e
CHAPTER 11 Protection System and Schemes
270 | P a g e
CHAPTER 11 Protection System and Schemes
The successful protection can be achieved subject to compliance with the following:
1. Stability 2. Selectivity
• Not to operate for faults outside • Trip only the faulted equipment
the zone • Important for busbars divided
• Most important for busbars into zones
3. Speed
• Limit damage at fault point
• Limit effect on fault stability
271 | P a g e
CHAPTER 11 Protection System and Schemes
The differential protection principal for high and low impedance differential
protection is based on the Kirchhoff’s Law, that all currents measured around a
protected element (line, transformer, generator, motor, bus) must under normal (non-
fault) condition sum up to zero.
A current sum unequal to zero would indicate a fault in the protected element. The
simplest way to obtain this current summation on a bus is by paralleling all current
transformer surrounding the bus zone. To be able to do this, all current transformers
need to have the same transformation ratio. As shown in figure 6.17, the sum of all
current can be measured and an overcurrent element would be sufficient to detect an
internal bus fault. On all external faults the measured current would be zero under
ideal measurement conditions. Basically, all differential protection algorithms are
based on this principle. However, the required “ideal measurement conditions” are
hard to achieve with inductive current transformer.
272 | P a g e
CHAPTER 11 Protection System and Schemes
makes this scheme to become attractive to most protection engineers because of its
advance algorithms for percent differential protection functions. Re-configuration of
bus-bar protection became less complex. Possibilities of replacing Data Acquisition
Units (DAU) in bays by utilizing distribution architectures have become
implementable.
273 | P a g e
CHAPTER 11 Protection System and Schemes
house and connected to the relay. The relay operates based on the rising voltage
which appears at the summing point when differential current flows through the high
impedance operate circuit.
The high-impedance input of the relay generally has an internal impedance of 1000
ohms or higher, depending on manufacturer, that is typically resistive. For non-fault
conditions, the currents are balanced sufficiently so that the voltage across the relay's
impedance is near zero. The weakest CT, fully saturated for an external fault, with
all other CTs operating normally should be calculated to establish the starting point
for the internal fault trip setting. This process is followed to prevent unwanted
operation for an external fault. For an internal fault, all CTs try to force the
differential current through the high-impedance input, creating the voltage drop used
to trip for the internal fault condition. At this point, the voltage which appears across
the relay is essentially the open-circuit voltage of the CTs. The resultant high voltage
is the signature for fault detection. High-impedance differential relays typically have
a means to control this high voltage to prevent CT, cable, and relay insulation
breakdown. The two main methods for controlling this high voltage are non-linear
impedances such as a Metal-Oxide Varistor (MOV), paralleling with stabilizing
resistance, and a static switching device such as a Silicon Controlled Rectifier
(SCR).
274 | P a g e
CHAPTER 13 Control & Monitoring
275 | P a g e
CHAPTER 12 Relay Coordination Study
• a one-line diagram of the power system involved, showing the type and rating
of the protection devices and their associated current transformers
• the impedances in ohms, per cent or per unit, of all power transformers,
rotating machine and feeder circuits
• the maximum and minimum values of short circuit
• currents that are expected to flow through each protection device
• the maximum load current through protection devices
• the starting current requirements of motors and the starting and locked
rotor/stalling times of induction motors
• the transformer inrush, thermal withstand and damage characteristics
• decrement curves showing the rate of decay of the fault current supplied by
the generators
• performance curves of the current transformers
The relay settings are first determined to give the shortest operating times at
maximum fault levels and then checked to see if operation will also be satisfactory
at the minimum fault current expected. It is always advisable to plot the curves of
relays and other protection devices, such as fuses, that are to operate in series, on a
common scale. It is usually more convenient to use a scale corresponding to the
276 | P a g e
CHAPTER 12 Relay Coordination Study
current expected at the lowest voltage base, or to use the predominant voltage base.
The alternatives are a common MVA base or a separate current scale for each system
voltage.
The basic rules for correct relay co-ordination can generally be stated as follows:
• whenever possible, use relays with the same operating characteristic in series
with each other.
• make sure that the relay farthest from the source has current settings equal to
or less than the relays behind it, that is, that the primary current required to
operate the relay in front is always equal to or less than the primary current
required to operate the relay behind it.
277 | P a g e
CHAPTER 12 Relay Coordination Study
must isolate only the faulty section of the power system network, leaving the rest of
the system undisturbed.
1. Discrimination by Time
2. Discrimination by Current
3. Discrimination by both Time and Current
The mathematical descriptions of the curves are given in Table 12.1, and the curves
based on a common setting current and time multiplier setting of 1 second are shown
in Figure 12.1.
The tripping characteristics for different TMS settings using the SI curve are shown
in Figure 12.1.
278 | P a g e
CHAPTER 12 Relay Coordination Study
279 | P a g e
CHAPTER 12 Relay Coordination Study
1. load bay
• The cable cross- sectional area for outgoing cell from specs (630𝑚𝑚2 )
• The current rating of 630𝑚𝑚2 cable is equal = 741 A
• The Derated current of cable is equal = 741 x 0.5 = 370.5A =𝐼𝑟𝑎𝑡𝑒𝑑
1.25∗370.5∗1
• Phase (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 1.1578125 𝐴
400
8∗370.5∗1
• Phase (Instantaneous) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 7.41 𝐴
400
0.1∗370.5∗1
• Ground (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.092625 𝐴
400
0.5∗370.5∗1
• Ground (Instantaneous) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.463125𝐴
400
280 | P a g e
CHAPTER 12 Relay Coordination Study
4. LV 75MVA TR bay
75 𝑥 106
• 𝐼𝑟𝑎𝑡𝑒𝑑 = = 1968.2395 𝐴
√3 𝑥 22 𝑥 103
1.25∗1968.2395
• Phase (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.98411 𝐴
2500
0.1∗1968.23∗1
• Ground (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.07872 𝐴
2500
5. HV 75MVA TR bay
75 𝑥 106
• 𝐼𝑟𝑎𝑡𝑒𝑑 = = 196.82395 𝐴
√3 𝑥 220 𝑥 103
1.25∗196.82395
• Phase (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.61507 𝐴
400
8∗196.82395 ∗1.1
• Phase (Instantaneous) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 4.3301 𝐴
400
0.1∗196.823∗1
• Ground (overcurrent) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.04920 𝐴
400
0.5∗196.82395∗1
• Ground (Instantaneous) → 𝐼𝑝𝑖𝑐𝑘𝑢𝑝 = = 0.2460𝐴
400
281 | P a g e
CHAPTER 12 Relay Coordination Study
282 | P a g e
CHAPTER 12 Relay Coordination Study
283 | P a g e
CHAPTER 12 Relay Coordination Study
284 | P a g e
CHAPTER 12 Relay Coordination Study
285 | P a g e
CHAPTER 12 Relay Coordination Study
286 | P a g e
CHAPTER 12 Relay Coordination Study
287 | P a g e
CHAPTER 12 Relay Coordination Study
Foult @ LV TR Side
288 | P a g e
CHAPTER 12 Relay Coordination Study
289 | P a g e
CHAPTER 12 Relay Coordination Study
290 | P a g e
CHAPTER 13 Control & Monitoring
291 | P a g e
CHAPTER 13 Control & Monitoring
13.1 Introduction
In order to operate the substation effectively, a control system which indicates
the status of all plant including alarms and indications of secondary system
equipment; shows analogue values for the key parameters such as voltage, current,
megawatts, and megavars; as well as provides digital outputs to close and open
switchgear, raise and lower taps on transformers, etc. is required. In addition to the
basic indications and controls, other functions such as synchronizing, voltage and/or
reactive control, interlocking for both safety and operational reasons, load control to
avoid frequency collapse, etc. may also be applied. Other functions such as
automatic closing or reclosing to optimize the performance of the network may be
needed, and in some instances-controlled switching, i.e., point on wave control of
closing or opening, may be used to reduce switching transients on the network.
At any moment, only one control point shall be in service, and the rules to switch
control points (control arbitration) are user-definable, but usually selection between
bay or station control will be from the bay control point and may be on an individual
292 | P a g e
CHAPTER 13 Control & Monitoring
equipment basis. Selection between station or network control will be from the
station control point and may be on a per-circuit basis. The facilities at each point
will vary in terms of the equipment being controlled, the indications, and the alarms
available. Alarms may be grouped for station and network control points to suit
individual requirements. Generally, alarms and indications necessary for the safe
and satisfactory operation of the substation should be provided at each control point.
Special facilities, such as synchronizing, may be available at the station or bay
control point. Reference should be made to Fig. 13.1 which illustrates the type of
equipment at the human machine interfaces. With the continued increase in the use
of equipment using digital technology, there is now a clear distinction between the
conventional and the computer-based human machine interfaces. Computer-based
HMI is commonly found at network control level but is becoming increasingly more
common in station control rooms. However, there are still some conventional HMIs
at the station level. HMI at bay level is often direct wire control and therefore
conventional.
293 | P a g e
CHAPTER 13 Control & Monitoring
294 | P a g e
CHAPTER 13 Control & Monitoring
A mimic display either in the form of a board for large substations or VDU “pages”
should be available. Operator consoles capable of operating the substation (at
substation level), or power system (network level), should be comprised of the
required components from the above list. The console should be capable of operating
in online, maintenance, training, and programming mode. Special software
interlocks should prohibit two or more consoles working “online” simultaneously.
VDUs should be of the full graphic, multicolor type designed for 24 h a day
continuous operation. The following information should be displayed:
295 | P a g e
CHAPTER 13 Control & Monitoring
296 | P a g e
CHAPTER 13 Control & Monitoring
The control cabinet is metal enclosed, free standing, made of sheet steel, and
provided with a lockable hinged door and door operated lights. The local control
cabinet has all necessary control switches, local/off/remote lockable selector
switches, close and open switches, measuring instruments, all position indicators for
circuit breakers, disconnect switches and grounding switches, alarms, mimic
diagram, AC and DC supply terminals, control and auxiliary relays, and so on. The
cabinet is fully designed as per IEC 60 439 or IEEE C37.123. The control cabinet is
designed in such a way as to facilitate full and independent control and monitoring
of the GIS locally.
297 | P a g e
CHAPTER 13 Control & Monitoring
All electronic components inside the bay control cabinet are designed to work
satisfactorily for the specified project requirement. At least 20% of each spare
contacts (NO (normally open) and NC (normally closed)) are provided with an
auxiliary relay for future use. All CT secondary taps should be wired to the local
control cabinet. The CT terminal block is such that it will provide isolation and
testing facilities of CT secondaries at the cabinet. For multiratio CTs the terminal
block is provided on the LCC as per IEEE C57.13 to facilitate connection of various
taps. Facility is provided in the LCC for shorting and grounding of secondary
terminals. Potential transformer (PT) secondary windings are terminated at the local
control cabinet through a terminal box. For PT wiring in the LCC, each phase of
each circuit is provided with a miniature knife switch and a high rupturing capacity
(HRC) fuse/supervised mini circuit breaker (MCB). Knife switches are located on
the PT side of fuses. Separate terminals are provided for PT fuse supervision. The
298 | P a g e
CHAPTER 13 Control & Monitoring
control cabinet is equipped with a mimic diagram on the front of the cabinet showing
(see Figure 13.4):
299 | P a g e
CHAPTER 13 Control & Monitoring
apparatus. All control power circuits are protected by miniature circuit breakers in
each cabinet. Other circuits supplying loads, such as heaters, receptacles, or lights,
have separate overload protection. The cabinet is grounded with a suitable copper
bus and the hinged door of the cabinet is grounded by a flexible grounding
connection. Alarm/annunciators are of the window type as per IEC 60 255 or IEEE
C37.1, with a minimum of 20% spare windows for use. The alarm/annunciator
system is designed for continuous operation of all alarms independently and
simultaneously.
• SF6 gas pressure Low–Low, Stage 1 alarm for each gas zone/section (in the
case of a single phase, an alarm is provided for each phase)
• SF6 gas pressure Low–Low, Stage 2 alarm for each gas zone/section (in case
of a single phase, the alarm is grouped for all phases)
• Excess run time of the motor for the circuit breaker, disconnecting switch, and
ground switch
• Spring overcharged for the circuit breaker mechanism
• Loss of DC for the trip and close circuit
• Circuit breaker trip
• VT supply fail (VT MCB trip)
• Loss of AC supply
• Circuit breaker mechanism failure
• Local/remote switch
• Pole discrepancy operated (for single-phase breaker)
• Trip circuit failure
• Loss of DC supply to circuit breaker motor
300 | P a g e
CHAPTER 13 Control & Monitoring
Bay level functions include data acquisition and data collection functionality in
bay control intelligent electronic devices (IEDs). The following basic functions
are included in the control unit:
301 | P a g e
CHAPTER 13 Control & Monitoring
302 | P a g e
References
REFERENCES
[1] MEHTA, V. K.; MEHTA, Rohit. Principles of Power System: Including
Generation, Transmission, Distribution, Switchgear and Protection: for BE/B.
Tech., AMIE and Other Engineering Examinations. S. Chand Publishing, 2005.
[2] MCDONALD, John D. Electric power substations engineering. CRC press,
2016.
[3]RANDOLPH, John. Electric Power Substations Engineering [Book Reviews].
IEEE Power and Energy Magazine, 2013,
[4] GUIDE, SF6 Recycling. International Council on Large Electric Systems
(CIGRE). Task Force, 2010, 23.01.
[5] Power system studies book for Dr/Mahmoud El-Gilany.
[6] IEEE Std 80-2013.
[7] Egyptian Code for earthing E27.
[8] IEEE Std. 998-1996. IEEE Guide for Direct Lightning Stoke Shielding of
Substations.
[9] Greenwood, A. Electrical Transients in Power Systems.
[10] Abdel-Salam, M., et al. High Voltage Engineering - Theory and Practice.
[11] Zipse, D. Lightning Protection Systems: Advantages and Disadvantages.
IEEE Transactions on Industry Applications, Vol. 30, No. 5, September/October
1994.
[12] AS/NZS 1768:2007 Lightning Protection.
[13] IEC 62305-1:2010 Protection Against Lightning.
[14] Anderson and A.J. Eriksson, Lightning Parameters for Engineering
Application, CIGRE Electra No. 69 (1980), p. 65-102.
[15] IEEE Std 80-2000
303 | P a g e
REFERENCES
[16] IEEE Std 141TM [B11]: [17] IEEE Std C57.12.00TM [B4]. [18] IEC 60949
[19] IEC 60076 [20] IEC 309-1-2-309A [21] IEEE 1115-2000 (Batteries for
Stationary Applications).
[22] IEEE 1184-1994 (Battery for UPS) .
[23] Electricity utilities specifications (EUS -E16).
[24] Transmission and Distribution Electrical Engineering, Third edition, Dr C. R.
Bayliss CEng FIET and B. J. Hardy ACGI CEng.
[25] IEEE Std 242-2001 IEEE Recommended Practice for Protection and.
Coordination of Industrial and Commercial Power Systems.
[26] IEEE Std C37.113-1999 IEEE Guide for Protective Relay Applications to
Transmission Lines.
[27] IEEE Standard C57.12.00-2015 categorizes the power transformers based on
their ratings.
[28] IEEE Std C37.234-2009 IEEE Guide for Protection Relay Applications to
Power System Buses.
[29] Network Protection & Automation Guide by Alstom.
[30] The art and science of protective relaying by C. Russell Mason.
[31] Protection and Switchgear by U.A.Bakshi.
[32] Comparison between high impedance and low impedance bus differential
protection. By Dr. Juergen Holbach.
[33] A Review of High-Impedance and Low-Impedance Differential Relaying for
Bus Protection by Suparat Pavavicharn and Gerald Johnson
[34] Roy E. Cosse, Jr., P.E., Donald G. Dunn, Robert M. Spiewak, P.E., “CT
SATURATION CALCULATIONS - ARE THEY APPLICABLE IN THE
MODERN WORLD
[35] Electrical protection book of Dr. Al-Gilany.
[36] EUS (C07).
[37] EUS (C06).
[38] IEEE C57.13 STANDARD FOR CURRENT TRANSFORMERS
304 | P a g e