Final Report (1) - 1
Final Report (1) - 1
BY
(HCE076BCE01) AASHISH NEUPANE
(HCE076BCE05) AKRITI YOGI
(HCE076BCE18) BISWAS ADHIKARI
(HCE076BCE26) JYOTI BHATT
(HCE076BCE31) LALIT BABU JOSHI
February, 2024
APPROVAL
This project report entitled “Suitability analysis of landfill site & design of MRF in Nuwakot,
Nepal” submitted by Aashish Neupane, Akriti Yogi, Biswas Adhikari, Jyoti Bhatt, Lalit Babu
Joshi in partial fulfillment of the requirement for the degree of Bachelor in Civil Engineering has
been examined and is being recommended for the acceptance and approval.
………………………………….
Supervisor: Dr. Er. Shanti Kala Subedi
Himalaya College of Engineering
………………………………….
Project Coordinator: Er. Ujjwal Marasini
Himalaya College of Engineering
………………………………….
Head of Department: Er. MD Abrar Alam
Himalaya College of Engineering
…………………………………..
External Examiner: Shukra Raj Poudel
Pulchowk Campus, Civil Department
February, 2024
1|Page
ACKNOWLEDGEMENT
We would like to express our special thanks to our supervisor Dr. Er. Shanti Kala Subedi for
her guidance, encouragement and critical suggestion throughout the course of this study without
whom, this research couldn’t achieve this state of work. We highly appreciate her scholastic
attitude and pragmatics thinking over this project.
We are also very thankful to Department of Civil Engineering, Himalaya College of Engineering
for their support throughout this project. We are also thankful to Sishir Dahal sir for his ideas
and encouragement to successfully complete this work up to this stage. Also, our field and
academic knowledge for the research have been broadened by the assistance of our colleagues
and we want to give them special thanks for it.
In addition, we would like to thank all the teachers and staff of Himalaya College of Engineering
for helping us in carrying out my field work by providing us with sampling materials. Also, we
would like to thank our family members for their moral support and encouragement throughout
this research period.
We would like to extend further thanks to all individuals for their direct and indirect help.
2|Page
Table of Contents
APPROVAL ..................................................................................................................................................................1
ACKNOWLEDGEMENT .............................................................................................................................................2
Table and Figures ..........................................................................................................................................................4
1. Introduction ...............................................................................................................................................................5
1.1 Background .........................................................................................................................................................5
1.2 Problem Statement ..............................................................................................................................................5
1.3 Objectives............................................................................................................................................................6
1.3.1 General Objective ........................................................................................................................................6
1.3.2 Specific Objectives ......................................................................................................................................6
2. Literature Review ......................................................................................................................................................6
2.1 Status of Solid Waste Generation in Nepal .........................................................................................................6
2.2 Suitability Analysis .............................................................................................................................................7
2.3 Analytical Hierarchy Process ..............................................................................................................................7
2.4 Weighted Overlay Method ..................................................................................................................................8
2.5 Material Recovery Facility (MRF) ......................................................................................................................9
2.6 Payback Period .................................................................................................................................................. 10
3. Materials and Methods ............................................................................................................................................ 11
3.1 Study Area ......................................................................................................................................................... 11
3.2 Present Condition of Bidur Municipality .......................................................................................................... 11
3.3 Methodology ..................................................................................................................................................... 12
3.3.1 Primary Methods ........................................................................................................................................ 12
3.3.2 Secondary Methods .................................................................................................................................... 13
3.4 Methodology for Material Recovery Facility .................................................................................................... 15
4. Result and Discussion .............................................................................................................................................. 16
4.1 Survey on viewpoints of locals ......................................................................................................................... 16
4.2 BOD Test .......................................................................................................................................................... 17
4.3 Calculation of Waste Generation Rate .............................................................................................................. 17
4.3.1 Waste Generation Rate............................................................................................................................... 17
4.3.2 Current waste generation rate of Bidur Municipality ................................................................................. 18
4.3.3 Determination of required landfill area ...................................................................................................... 19
4.4 Landfill Site Suitability ..................................................................................................................................... 19
4.5 Feasibility of Material Recovery Facility in Bidur Municipality ...................................................................... 29
5. Conclusion & Recommendation .............................................................................................................................. 33
APPENDIX: Photographs ........................................................................................................................................... 34
References ................................................................................................................................................................... 38
3|Page
Table and Figures
Figures
FIGURE 1: STUDY AREA FOR LANDFILL SITE SELECTION ---------------------------------------------------------- 12
FIGURE 2:FRAMEWORK OF THE STUDY TO SELECT A SUITABLE SANITARY LANDFILL SITE IN BIDUR
MUNICIPALITY ----------------------------------------------------------------------------------------------------- 15
FIGURE 3: CHART SHOWING RESULTS OF HOUSEHOLD SURVEY ------------------------------------------------- 17
FIGURE 4: BOD SAMPLE COLLECTION SITE----------------------------------------------------------------18
FIGURE 5: SLOPE MAP--------------------------------------------------------------------------------------------------- 22
FIGURE 6: ROADWAYS MAP ------------------------------------------------------------------------------------------23
FIGURE 7: ROADWAYS BUFFER MAP ---------------------------------------------------------------------------------- 23
FIGURE 8: WATERWAYS MAP ---------------------------------------------------------------------------------------- 23
FIGURE 9: WATERWAYS BUFFER MAP -------------------------------------------------------------------------------- 23
FIGURE 10: FOREST MAP--------------------------------------------------------------------------------------------- 24
FIGURE 11: FOREST BUFFER MAP ------------------------------------------------------------------------------------24
FIGURE 12:CROPLAND BUFFER MAP -------------------------------------------------------------------------------- 25
FIGURE 13:SOIL MAP ---------------------------------------------------------------------------------------------------- 25
FIGURE 14:SOIL SETTLEMENT MAP -------------------------------------------------------------------------------- 26
FIGURE 15:SOIL SETTLEMENT BUFFER MAP ----------------------------------------------------------------------26
FIGURE 16:RANGELAND MAP --------------------------------------------------------------------------------- 27
FIGURE 17:RANGELAND BUFFER MAP------------------------------------------------------------------------ 27
FIGURE 18:BUILT-UP AREA MAP ------------------------------------------------------------------------------------ 27
FIGURE 19:BUILT-UP AREA BUFFER MAP --------------------------------------------------------------------------- 27
FIGURE 20: LANDFILL SITE SUITABILITY MAP------------------------------------------------------------29
FIGURE 21: CHART SHOWING SUITABILITY AREA ------------------------------------------------------29
FIGURE 22: PIE CHART SHOWING WASTE COMPOSITION OF STUDY AREA----------------------31
Tables
TABLE 1: PAIRWISE COMPARISON SCALE IN AHP -------------------------------------------------------------------- 8
TABLE 2: INTENSITY OF IMPORTANCE IN WEIGHTED OVERLAY METHOD FOR ARCGIS ------------------------ 8
TABLE 3:TABLE SHOWING DATA SOURCES OF VARIOUS CRITERIA ---------------------------------------------- 13
TABLE 4:FACTORS CRITERIA FOR LANDFILL SITE SELECTION SUITABILITY, CLASS & RANK---------------- 20
TABLE 5: PAIRWISE COMPARISON MATRIX (DECISION MATRIX) ----------------------------------------------- 27
TABLE 6: WEIGHTAGE FOR THE CRITERIA --------------------------------------------------------------------------- 27
TABLE 7:DESCRIPTION OF WASTE COMPONENT CATEGORIES ---------------------------------------------------- 29
TABLE 8: PRICES OF RECYCLABLE MATERIALS OF NUWAKOT DISTRICT AS OF JAN 2024 ------------------ 30
TABLE 9: PAYBACK PERIOD ANALYSIS ------------------------------------------------------------------------------ 32
4|Page
1. Introduction
1.1 Background
Solid waste management (SWM) is a crosscutting issue that impacts various areas of sustainable
development. Around the world, waste generation rates are rising. Annually, our planet becomes
home to about 2.01 billion tons of municipal solid waste and this number is expected to reach up
to 3.40 billion tons of waste by 2050 (Khanal, 2023). Compared to those in developed nations,
over 90% of waste generated in developing countries is often open dumped or burned. The
average waste generation in Asia was 0.52kg/capita/d, which was lower than the global of
0.74kg/capita/din 2016 (Khanal, 2023). In the context of Nepal, 1 million tons of waste is
generated in Nepal per year. A total of 389,983 tons of emitted garbage is sent to landfill sites,
315,069 tons dumped on riverbanks while 22,075 tons of garbage is burnt down (CBS, 2019).
Landfills are one of the as a major sources of methane emission, which ultimately adds up to
increased greenhouse gasses. As a developing nation, there is constantly increase in municipal
waste generation in Nepal. This waste gives rise to extreme conditions caused due to emission of
greenhouse gasses which could increase the risk of fire, endanger the human health, destroy the
vegetation mass around the landfill, pollute and degrade the groundwater resources, affect the
climate changes worldwide and produce unfavorable odors (Saleem, 2014). A sanitary landfill is
a pit with a protected bottom where trash is buried in layers and compressed to make it more
solid. Sanitary landfills help to prevent environmental contamination and to protect public health
by collecting and storing waste in the safest manner possible.
The history of solid waste management in Nepal goes back to 1919 after the establishment of
Safai Adda in Kathmandu. Solid waste management national policy of Nepal was issued in 1996,
which had emphasized on the minimization of waste by integrating the private sector. However,
due to unstable government and awareness, Surveys have shown that many municipalities in
Nepal do not follow sanitary solid waste practices. There are many reasons why these
communities have not taken steps to protect the health and welfare of their citizens from the
hazards associated with the inadequate and insanitary collection and disposal of solid wastes.
Predominate among the basic causes, is the belief that adequate service is too expensive, and a
lack of information on how to establish and operate a satisfactory system. (Gupta, et al., 2018).
5|Page
landfill is a must for proper management of solid waste. A proper siting of waste disposal
location by using GIS based Multi Criteria Decision Analysis uses logical procedures
incorporating different factors and criteria that address the biophysical and ecological aspects of
environment.
1.3 Objectives
1.3.1 General Objective
To calculate waste generation rate of study area and conduct suitability study of landfill site.
2. Literature Review
6|Page
This has caused numerous clashes between the locals and the government resulting in strikes and
stoppages of vehicular movement to the dumping location.
A fuzzy logic site suitability analysis is an analysis method that is used when data is continuous,
and does not adhere to discrete boundaries. It assigns membership values to locations that range
from 0 to 1. 0 indicates non-membership or an unsuitable site, while 1 indicates membership or a
suitable site. Fuzzy logic site selection is different from other site selection methods because it
represents a possibility of an ideal site, rather than a probability and it is commonly used to find
ideal habitat for plants and animals or other sites that are not specifically chosen by a user or
developer.
Weighted site selection analysis is an approach that allows users to answer questions or solve
problems that are impacted by many factors and assign varying weights to each of the criteria.
Criteria Weights can be defined as a value assigned to an evaluation criterion which indicates its
importance relative to other criteria under consideration. (Kirkwood, 1997) There are four
different techniques of assigning the weights, namely, ranking, rating, pairwise comparison and
trade of analysis methods. Calculating weight for the criteria using the method of pairwise
comparison method has major advantages that two criteria had to be considered at a time and
also, it can be easily incorporated into GIS based decision making procedures.
7|Page
pairs of sub-criteria (pairs of sub criteria, etc.), and pairs of alternatives. The AHP uses a
fundamental 9-point scale measurement to express individual preferences or judgments, creating
a matrix of pairwise comparisons (Table 1). These pairwise comparisons allow independent
evaluations of each factor’s contribution, thereby simplifying the decision-making process.
(Bozdağ, et al., 2016)
TABLE 1: PAIRWISE COMPARISON SCALE IN AHP
8|Page
Intensity of importance Definition
5 Not suitable
3 Less suitable
3 Moderately suitable
2 Highly suitable
1 Very Highly suitable
The very highly suitable sites are those which possess the optimum quality and characteristics for
sustainable solid waste disposal.
9|Page
While MRFs cannot be examined in isolation from the other components of the SWM system
due to their integration, comprehensive standalone MRF process models are necessary to
effectively simulate the life-cycle impacts of complete SWM systems. Decision-makers involved
in solid waste management are more attentive to recyclable materials found in solid waste since
recycling solid waste can help achieve goals connected to sustainability, such as resource
recovery, decreased energy use, and lower emissions. Only limited work has been done to
systematically characterize MRF operations and the resulting emissions.
Globally, average material use has increased from 5.0 tons to 10.3 tons per capita per annum
between 1950 and 2010 due to population growth, industrialization and an increase in socio-
economic power. (Krausmann, et al., 2014) In context of Nepal, Material recovery facilities
receive a low priority both at the national and local level. Lack of financial resources, human
resources capacity, waste management technology, and infrastructure are often cited as the
common barriers to waste management and MRF. A rapid assessment of solid waste
management (SWM) practices was conducted in 16 selected municipalities across seven
provinces of Nepal in mid-2018, The average composition of MSW was: organic (43.6%), paper
and paper products (22.7%), plastic (13.8%), glass (6.4%), metals (2.7%), textile (3%), rubber
and leather (1.3%), and others (6.6%) (Khatoon, 2020).
There are many organizations working in Nepal involved in solid waste management and
material recovery facilities such as Doko recyclers, Upcycle Nepal, Tyre Treasures, Smart Paani,
as well as municipal government offices and local recycling companies generating good revenue
and positive contribution in waste management and environment with their work. These
companies also provide services such as Shredding, Composting, E-waste and workshops. One
of the first MRF plant established in Nepal was in the village of Mulkharka - a buffer zone inside
the protected area of Shivpuri-Nagarjun national park which was designed to be a clean type of
MRF plant, (Dhakal, 2015).
10 | P a g e
3. Materials and Methods
11 | P a g e
With regards to waste disposal, our survey showed approximately 4 tons of waste is produced
every day in Bidur. Based on information gathered from site surveys, the Bidur Municipal
Government's environment and health departments are in charge of handling solid trash in the
area. Workers that are qualified for the job primarily gather and carry waste. In the city,
curbsides serve as waste collection sites. Locals can place their trash on the side of the road, and
government-employed cleaners will come pick it up. The city employs 12 temporary cleaners,
each of whom is equipped with 11 trolleys, 8 wheelbarrows, and 1 trailer. Waste is loaded into
wheelbarrows and trolleys once they are filled with waste. There are no projects running in the
municipality promoting recycling of solid waste. Waste is generally composted at household and
community levels. Although there are hospitals, health care facilities, schools and industries in
Bidur municipality, they are not separated and dumped with municipal waste similarly, they have
no system to collect other special types of waste and segregation process are rarely practiced in
the municipality.
3.3 Methodology
The management of waste generated by the households as well as other individual bodies is very
crucial for a quality of life in communities as well as environmental protection. Proper waste
management allows us to explore various positive outcomes like waste to energy, improves
aesthetics, recovery and reuse of valuable resources along with income generation opportunities.
In order to collect the waste generation following methods can be used:
12 | P a g e
The characterized wastes are then studied for various beneficiary purposes such as reselling, bio-
gas generation, reusing, etc. to the scrap dealer or plastic and paper mills after its volume or
weight has been measured. The wastes are studied in multiple ways for its reuse ability along
with income generation potentials.
f) Application of GIS and landfill site selection
The remote sensing technologies like Geographic Information System (GIS) is used to study
efficient waste collection routes as well as locating landfills and MRF plants.
Studying and analyzing the published articles, reports, books, data, etc. in order to accumulate all
the necessary information and knowledge required for the waste management and MRF site
selection. Collection of the demographic data from the concerned authorities and calculate the
total waste generation in accordance to sample survey conducted.
DEM USGS
Soil-Settlement ICIMOD
13 | P a g e
2. Determining siting criteria
There are numerous environmental, social, and economic criteria to consider while choosing a
landfill site. Based on data availability and significance, factors such as distance to roads,
distance from water sources, distance from residence, land use and land cover, elevation, slope,
landfill size, and wind direction will be considered in this study for the analysis of a suitable
landfill site. (Asefa, et al., 2021) After reviewing works of literature, the criteria are to be
selected with fixed suitable buffer. These criteria are then ranked relative to its importance with
other values from a set {1, 2, 3, 4, 5, 6, 7, 8, 9}. (ibid)
3. Land suitability assessment
Secondary data are processed using a suitable model in ESRI Arch GIS software. Each criterion
is to be reclassified as unsuitable, least suitable, moderately suitable, suitable, and highly suitable
by the Euclidean distance and reclassify spatial tool. Then the reclassified criteria are overlaid by
a weighted overlay spatial tool to produce a potential landfill site for solid waste disposal in
Bidur Municipality, Nuwakot. Field visits will also be conducted to validate the final site
selected landfill obtained using the methodology used in this study interval.
FIGURE 2: FRAMEWORK OF THE STUDY TO SELECT A SUITABLE SANITARY LANDFILL SITE IN BIDUR MUNICIPALITY
14 | P a g e
population growth, and density of the compressed landfill material are to be considered. (MM &
MTU, 2020) (Singh, 2013) To calculate the volume of landfill area, landfill height is chosen
accordingly to the groundwater depth of site. All calculations are performed using equations
given below;
𝒗𝒘 = 𝑡𝑜𝑡𝑎𝑙 𝑤𝑎𝑠𝑡𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑖𝑛 ′𝑁′ 𝑦𝑒𝑎𝑟𝑠(𝑡𝑜𝑛𝑠)/𝑟𝑎𝑡𝑒 𝑜𝑓 𝑐𝑜𝑚𝑝𝑎𝑐𝑡𝑖𝑜𝑛(𝑘𝑔/𝑚3),
where, 𝑣𝜔 𝑖𝑠 𝑡ℎ𝑒 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑠𝑡𝑒(𝑚3/𝑦𝑒𝑎𝑟𝑠)
𝒗𝒄 = 𝟎. 𝟐𝟓𝒗𝒘 , 𝑤ℎ𝑒𝑟𝑒 𝑣𝑐 𝑖𝑠 𝑡ℎ𝑒 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑓𝑜𝑟 𝑙𝑖𝑛𝑒𝑎𝑟 𝑎𝑛𝑑 𝑓𝑖𝑛𝑎𝑙 𝑐𝑜𝑣𝑒𝑟
𝑨𝒊 = 𝑪𝒊 ⁄𝑯𝒊 , 𝑤ℎ𝑒𝑟𝑒 𝐴𝑖 𝑖𝑠 𝑡ℎ𝑒 𝒍𝒂𝒏ⅆ𝒇𝒊𝒍𝒍 𝒂𝒓𝒆𝒂(𝒉𝒂) & 𝐻𝑖 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑎𝑛𝑑𝑓𝑖𝑙𝑙 ℎ𝑒𝑖𝑔ℎ𝑡 (𝑚)
15 | P a g e
4. Result and Discussion
Yes/No questions
YES NO
20
17 17 16
14
12
9 9 10
6
Since they use the biodegradable solid waste for farming, the general people were mostly aware
of the need to separate the two types of waste (degradable and non-degradable). However, some
people about 25% don't use their bio waste, which was evident in the dump site, generating an
unpleasant stench and leachate that ultimately has an impact on the residents of the Bidur
municipality's quality of life.
The main issue was their knowledge with the current dumping area and how the site disposes of
the gathered rubbish. The location of the dump site, as well as its drawbacks and issues, are
unknown to 65% of the general public. People in the know discussed the transient nature of the
solution and how it will impact the neighboring river. They talked about the need to relocate as
soon as possible.
In order to improve the quality of life for the residents of Nuwakot, the new location for the
dumping zone must be able to address all the shortcomings of the existing dumping zone.
16 | P a g e
4.2 BOD Test
BOD, or Biochemical Oxygen Demand, is a critical parameter used to assess the quality of water
in terms of its organic pollution levels. It measures the amount of dissolved oxygen consumed by
microorganisms as they break down organic matter in water. Essentially, BOD indicates how
much oxygen is needed to sustain aquatic life and provides insights into the health of water
bodies, making it a fundamental tool in environmental monitoring and management.
The BOD of the Trishuli River was found to be 5 mg/L. This value indicates the amount of
dissolved oxygen that is consumed by microorganisms as they decompose organic material in the
water sample. The considerably low BOD values, suggesting that the water contents have a
relatively low level of organic pollution and that the water quality is relatively good. This might
be because of the early stages that the landfill site is in; however, in the long run, the source of
water will be greatly affected due to the limited distance from the landfill site.
4.3 Calculation of Waste Generation Rate
4.3.1 Waste Generation Rate
The waste generation rate refers to the amount of waste produced over a specific period of time,
usually measured in terms of weight or volume. This includes various types of waste, such as
municipal solid waste, industrial waste, or hazardous waste.
17 | P a g e
Waste generation rates help in assessing the environmental impact of human activities.
Authorities and researchers can gain a better understanding of the scope of environmental
concerns and work towards practical solutions by quantifying the amount of waste created. It
informs the formulation and evaluation of waste management policies and also provides a
baseline for monitoring the effectiveness of waste reduction initiatives over time. It encourages
sustainable consumption and waste reduction practices. Waste generation rate helps raise
awareness about the environmental impact of consumer choices. Identifies and mitigates
potential health hazards associated with improper waste disposal.
The waste generation rate has various applications across different sectors and disciplines. Here
are some key applications:
• Guides infrastructure development and land use planning for effective waste
management.
• Assists in environmental impact assessments and biodiversity conservation efforts.
• Informs the development of waste management regulations and incentive programs.
• Aids in budget planning and personnel deployment for waste management.
• Sets targets for reduction and supports educational campaigns.
• Identifies opportunities for material recovery and influences product design.
• Guides businesses in assessing and reducing waste in supply chains.
• Addresses health risks associated with improper waste disposal and supports community
health programs.
• Facilitates global comparisons and harmonization of waste management policies.
18 | P a g e
Limitation of the result
As the sample size is small, it does not fully represent the whole population and hence the results
might not be actual results. Sample was taken among the household only which restricts the data
and the actual waste generation rate of study area might vary. So, large sample size is preferred
that includes unique sample to get the actual waste generation rate.
4.3.3 Determination of required landfill area
Here,
𝒗𝒘 = 𝑡𝑜𝑡𝑎𝑙 𝑤𝑎𝑠𝑡𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑖𝑛 ′𝑁′ 𝑦𝑒𝑎𝑟𝑠(𝑡𝑜𝑛𝑠)/𝑟𝑎𝑡𝑒 𝑜𝑓 𝑐𝑜𝑚𝑝𝑎𝑐𝑡𝑖𝑜𝑛(𝑘𝑔/𝑚3),
3610.181∗1000
or, 𝑣𝜔 = (m3/years)
400
𝒗𝒄 = 𝟎. 𝟐𝟓𝒗𝒘 , 𝑤ℎ𝑒𝑟𝑒 𝑣𝑐 𝑖𝑠 𝑡ℎ𝑒 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑓𝑜𝑟 𝑙𝑖𝑛𝑒𝑎𝑟 𝑎𝑛𝑑 𝑓𝑖𝑛𝑎𝑙 𝑐𝑜𝑣𝑒𝑟
𝑣𝑐 = 0.25 ∗ 9025.45 = 1805.09m3/year
𝑨𝒊 = 𝑪𝒊 ⁄𝑯𝒊 , 𝑤ℎ𝑒𝑟𝑒 𝐴𝑖 𝑖𝑠 𝑡ℎ𝑒 𝒍𝒂𝒏ⅆ𝒇𝒊𝒍𝒍 𝒂𝒓𝒆𝒂(𝒉𝒂) & 𝐻𝑖 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑎𝑛𝑑𝑓𝑖𝑙𝑙 ℎ𝑒𝑖𝑔ℎ𝑡 (𝑚)
or, 𝐴𝑖 = 11733.08⁄25
or, 𝑨𝒊 = 𝟒𝟔𝟗. 𝟑𝟐𝟑 𝒉𝒂
A study done by (Dangi, et al., 2011) in kathmandu city reveled that an average waste density of
for the Kathmandu metropolitan area was 400 kg/m3. As for the landfill height, it ranges from
10m to 30m throughout the landfill sites in nepal. (Shrestha, 2019) suggested that 25m of landfill
height provides a extended lifespan to the landfill site. The result shows that 469.323 hacters of
land is required to cater the supply of 3610.181 metric tonnes of waste per year.
19 | P a g e
assessment has to be done regarding the characteristics of the sites and potential for engineered
systems to overcome site deficiencies in terms of methods of operation proposed for the site and
social and cultural issues. Therefore, criteria are formulated to select the appropriate landfill
location for solid waste disposal. Factors are identified depending on the environmental, socio-
economic and surface conditions of the study area. Table 3 shows the criteria along with its
suitability ranking used during this suitability analysis.
TABLE 4:FACTORS CRITERIA FOR LANDFILL SITE SELECTION SUITABILITY, CLASS & RANK
20 | P a g e
The selected criteria for the operation are:
1. Slope
Slope is correlated with ground variation, making it a crucial component in determining whether
a landfill is suitable for a given use. It controls both groundwater infiltration and surface runoff.
The Bidur municipality's slope was determined to be between 0 and 69.1%, which is regarded as
extremely inappropriate for the development of any landfill site. Economically speaking,
building will cost more in places with steep and high slopes than in areas with medium slopes.
Consequently, a stable slope is needed to reduce expenses and surface runoff. (Ayo & Basu,
2011) states that the preferred areas for waste disposal are those with medium slope of not more
than 20%. (Fidelis, et al., 2019) confirmed that areas with slopes ranging from 0% to 5% are
highly suitable for landfill site. Hence area with uniform or even slope was more preferred
during this analysis.
21 | P a g e
FIGURE 6: ROADWAYS MAP FIGURE 7: ROADWAYS BUFFER MAP
22 | P a g e
4. Distance from Forest Area
A forest area is defined as terrain covered by naturally occurring or artificially planted stands of trees
that are at least five meters in situ, regardless of their productivity. Because there is a possibility of
soil contamination, which would lower the productivity and fertility of the land where forests are
found and ultimately causing harm to the ecosystem, the landfill site shouldn't be located too
close to any forest areas. It was determined that a distance of (600–1000) meters was unsuitable
for the construction of a landfill site, while a distance of (100–300) meters was thought to be
extremely acceptable and would cause the least amount of environmental disruption with more
area available for landfill site.
23 | P a g e
FIGURE 12:CROPLAND BUFFER MAP
6.Soil type
Bidur Municipality has four main types of soil: Eutric cambisols, Gleyic cambisols, Chromatic
luvisols, and Chromatic cambisols. where the majority of the municipality is covered in soil of
the Chromic Cambisols type. Due to their superior drainage qualities and greater load carrying
capacity, chromic luvisols are typically a better choice for landfill site construction. Additionally,
their relatively low susceptibility to waterlogging and erosion can contribute to the long-term
stability and integrity of landfill site which is denoted by green color in the map below.
24 | P a g e
7. Soil Settlement
The map below indicates the areas with a higher likelihood of soil settlements along with a
buffer. Compaction and other geological processes can cause soil settlement areas to sink and
subside, making them unsuitable for landfill sites since they shorten their life lifetime and cause
unintended hazards. Building a landfill site is deemed appropriate if it is at least 1000–1500
meters away from the soil settlement area.
25 | P a g e
FIGURE 16:RANGELAND MAP FIGURE 17:RANGELAND BUFFER MAP
26 | P a g e
Due to the complex nature of the data, AHP was used to interpret all criteria and find out the best
locations for landfills in the study area. The algorithm adopted for the current research study was
the AHP in which a comparison matrix was prepared and the importance of each criterion over
the other criteria was categorized and weighted (Table 5).
TABLE 5: PAIRWISE COMPARISON MATRIX (DECISION MATRIX)
Matrix Built- Slope Road River Soil Settlement Croplands Rangelands Forest
up type
Built-up 1 7.00 7.00 7.00 9.00 9.00 7.00 8.00 8.00
Slope 0.14 1 8.00 8.00 9.00 9.00 9.00 8.00 8.00
Road 0.14 0.12 1 0.17 8.00 8.00 8.00 6.00 7.00
River 0.14 0.12 6.00 1 8.00 9.00 7.00 7.00 7.00
Soil Type 0.11 0.11 0.12 0.12 1 2.00 0.14 0.14 0.14
Settlement 0.11 0.11 0.12 0.11 0.50 1 0.14 0.12 0.12
Croplands 0.14 0.11 0.12 0.14 7.00 7.00 1 0.50 7.00
Rangelands 0.12 0.12 0.17 0.14 7.00 8.00 2.00 1 9.00
Forest 0.12 0.12 0.14 0.14 7.00 8.00 0.14 0.11 1
The highest score in the AHP comparison matrix was given to the built-up area, slope, river
stream and roads because the study area is heavily covered by built-up and it is expensive to
relocate a large population. Roads affect the operational and construction cost of landfill sites by
providing the accessible routes for waste transportation during all weather conditions and are
also important for their aesthetic value. The weightage of the different criteria developed using
the AHP method is shown in (Table 6).
TABLE 6: WEIGHTAGE FOR THE CRITERIA
27 | P a g e
Suitability Map
The suitable waste disposal site selection was done on the basis of weighted overlay method.
Based on criteria and their zones, buffer map for all the individual criteria was created. These
maps were then reclassified based on the suitability ranking as per the table 3. These reclassified
maps were considered for generation single suitability ranking map with the help of weighted
overlay tool in ArcMap. Figure 20 shows the suitability map for landfill site in Bidur
municipality.
The generated suitability map was classified as not suitable area, moderately suitable and very
highly suitable land which respectively occupy 56% (6945.25 ha), 28.83% (3576.5 ha) and
15.17% (1881.6 ha) of the total study area. The chart below shows the suitability area for the
study site.
6945.25
3576.5
28 | P a g e
4.5 Feasibility of Material Recovery Facility in Bidur Municipality
A Material Recovery Facility (MRF) is a utility area built close to a sanitary landfill site with the
intention of recycling and reusing municipal solid waste in order to preserve the environment and
lengthen the landfill's useful life. Overall, MRF's plays a vital role in promoting sustainability,
resource efficiency, and environmental step wardship.
Category Description
29 | P a g e
Waste composition and price of recyclables
The prices of key recyclable materials, such as plastics, metal, paper, and glass, are affected by
the global economy and demand from the manufacturing sector. Common recyclables generated
at households, commercial establishments, and institutions (e.g., polyethylene terephthalate
[PET] bottles, white paper, and newspaper) sell at good prices. The waste composition of our
study shows that a major part from total waste contributes to food waste i.e. 58%. Waste such as
metals, glasses and special waste were not observed during our study as the sample size was
limited to households only. The chart below shows the current waste composition of the study
area.
Waste Composition
Plastics
26%
Paper
58% 16%
Food waste
As per our study, about 42% of the total waste generated in study area is recyclable. This shows
that current total population of Bidur municipality i.e. 59227 (Census, 2021) produces 4.15 tons
of recyclable waste per day that possess high value in the market. Table 8 shows the current price
list of recyclable materials in the study area. For design year of 20 years, with current population
growth rate of 1.7% per annum, it is estimated that a projected population of 82973 will produce
a total of 5.81 tons of waste per day or 2120.65 tons/year. To recycle this waste, a MRF with a
capacity of 5-10 tons per day is most suitable.
TABLE 8: PRICES OF RECYCLABLE MATERIALS OF NUWAKOT DISTRICT AS OF JAN 2024
Recyclable Material Junk Shop Price (per Factory Price (per ton)
ton)
Mineral water bottles Rs. 20000 Rs. 22000
Glass bottles Rs. 3000 Rs. 5000
Plastics Rs. 10000 Rs. 12000
Cartoon boxes Rs. 10000 Rs. 12000
Electronic Items Rs. 5000 Rs. 7000
Shoe sole Rs. 12000 Rs. 14000
Jute bag Rs. 5000 Rs. 7000
Iron Rs. 35000 Rs. 37000
Tin Rs. 20000 Rs. 22000
30 | P a g e
Materials Recovery Facility Construction and Operation & Maintenance Cost
The establishment of an MRF will entail cost in the following items:
1) Feasibility study
2) Environmental permitting
3) Lot acquisition
4) Site development
5) Facility construction
6) Equipment acquisition
7) Training of operations personnel (ADB, 2013)
The cost of each item, as well as permit requirements, varies according to the location of the site.
The price also varies, depending on the desired size of the facility. Site development cost also
vary and will depend on particular features such as terrain, land use, vegetation, and
accessibility. Low areas will need backfilling, while rolling terrain requires leveling and
earthmoving to attain the desired flat level. The cost of construction of MRF structure will vary
depending upon the location as the value of land is not stationary throughout. The cost of the
equipment has a big role in the development cost of the MRF facility. The type of MRF plant
(Manual, Semi-automatic, automatic) that is being constructed will influence the equipment cost.
The basic equipment, even for a manual operation, would include sorting tables, weighing scales,
a baler, and payloader.
A semi-automatic MRF plant with a capacity to process 1.5 tons of waste per hour is estimated to
cost about NRP 78 lakhs in Nepal (excluding land acquisition cost). Semi-automated have lower
cost for labor but require higher skills for Operation & Maintenance (O&M) of equipment,
facility, and utilities. In general O&M cost is placed at 5%-10% of the total investment and it
should not exceed the revenue from the sales of recyclables.
This research showed that 4.15 tons/day of recyclable waste (plastic and paper) is produced in
Bidur municipality that results to a total of 1514.75 tons of waste per year. As per (ADB, 2013)
the collection efficiency is 70% for urban areas and 30% for rural areas. As the municipality is in
early stages of development and most of the population practice self-disposal techniques like
burning and buying of the produced waste, the total waste collection efficiency is taken as 30%
and the recovery percentage ranges about 40-50% of collected waste. The calculations are as;
𝑇𝑜𝑡𝑎𝑙 𝑟𝑒𝑐𝑦𝑐𝑙𝑎𝑏𝑙𝑒 𝑤𝑎𝑠𝑡𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 = 1514.75 𝑡𝑜𝑛𝑠/𝑦𝑒𝑎𝑟
𝑊𝑎𝑠𝑡𝑒 𝑐𝑜𝑙𝑙𝑒𝑐𝑡𝑒𝑑 = 454.425 𝑡𝑜𝑛𝑠/𝑦𝑒𝑎𝑟
𝑅𝑒𝑐𝑦𝑐𝑙𝑎𝑏𝑙𝑒 𝑤𝑎𝑠𝑡𝑒 = 181.77 𝑡𝑜𝑛𝑠/𝑦𝑒𝑎𝑟
Considering the cost of equipment required on the material recovery facility to be around NRP
48 lakhs and the cost of construction to be NRP 30 lakhs, we require an initial investment of
NRP 78 lakhs. Taking the locally obtained salvage value rate of NRP 10 per kg the total revenue
from the material recovery facility can be NRP 1817700 while considering a 10% of operation
and maintenance cost. The payback period for the project is shown in table below:
31 | P a g e
TABLE 9: PAYBACK PERIOD ANALYSIS
The table shows that the estimate payback period of a MRF project that can handle the current as
well a future supply of waste in Bidur municipality is 5.9 years. This demonstrates that the
construction of a material recovery facility in the study area is feasible from both environmental
and economic perspective.
32 | P a g e
5. Conclusion & Recommendation
Conclusion
The research paper on "Suitability analysis of landfill site and design of MRF in Nuwakot,
Nepal" at the Bidur municipality of Nuwakot district has been finalized by the team of civil
engineering students. The present-day issue of municipal solid waste and its rightful
management in the research area are the primary subjects of this essay. The current landfill,
which is adjacent to the Trishuli river, is in dire shape and could soon present a number of
environmental challenges. We performed a survey to learn about the current conditions and
public sentiment regarding the landfill site and how it may influence the quality of the Trishuli
river's water in the future. We additionally carried out bod tests from two distinct sources within
close proximity to the landfill site, and the results indicated a modest impact, nevertheless it
could get worse.
On a weekly basis, we retrieved solid waste samples from two distinct wards. A total of 20
household were selected by random sampling. After three weeks of data analysis, we estimated
the aggregate quantity of solid trash generated in the area and utilized that information to
estimate the total area required for the construction of a sanitary landfill. We created several
geographical and analytical maps for the study area through GIS-based software, and we used
the weighted overlay technique for deciding which area is the most appropriate for the sanitary
landfill.
Similarly, we also carried out a feasibility study of MRF in Bidur municipality considering other
projects from different parts of the world. If we are to construct a material recovery facility in
Bidur, our study concluded that a semi-automatic plant is best suitable which will require an
initial investment of around NRP 78 lakhs with the cost of equipment NRP 48 lakhs. The
payback period was also calculated to be 5.9 years which is according to the present
circumstances and can definitely be increased with proper collections and segregation processes.
Construction of a material recovery facility along with the landfill site can be beneficial to the
municipality in terms of economic growth as well as environmental betterments.
Recommendation
33 | P a g e
APPENDIX: Photographs
34 | P a g e
WEIGHTING WEEKLY SAMPLE FOR STUDY AREA
35 | P a g e
CENTRAL JAIL NEAR DUMPING SITE TRISHULI RIVER NEAR CURRENT DUMPING SITE
SAMPLE COLLECTION FOR BOD TEST SATELLITE IMAGE OF SAMPLE COLLECTION SITE
36 | P a g e
FIELD VISIT OF BIDUR MUNICIPALITY
37 | P a g e
References
ADB, 2013. Material Recovery Facility Toolkit, Mandaluyong City: Asian Devlopment Bank.
Al-Ansari, Al-Anbri, M., Thameer, M. Y. & Nadir, 2018. Landfill site selection by weighted
overlay technique: case study of AL-kufa, Iraq. sustainability, p. 999.
Asefa, E. M., Damtew, Y. T. & Barasa, K. B., 2021. Landfill Site Selection Using GIS Based
Multicriteria Evaluation Technique in Harar City, Eastern Ethiopia. Environmental Health
Insight.
Ayo, B. & Basu, I., 2011. Selection of Landfill Sites for Solid Waste Treatment in Damaturu
Town-Using GIS Techniques. Journal of Environmental Protection, Volume 2, pp. 1-10.
Balew, A., Alemu, M., Leul, Y. & Feye, T., 2022. Suitable landfill site selection using GIS-
based multi-criteria decision analysis and evaluation in Robe town, Ethiopia. GeoJournal,
Volume 87, pp. 895-920.
Behera, D. K., Ahire, V., Ahire, V. & Saxena, M. K., 2022. Potential landfill site suitability
study for environmental sustainability using GIS-based multi-criteria techniques for nashik and
environs. Environmental Earth Sciences, p. 15.
Bista, R. G. & Prakriti, 2016. Crop diversification improves pH in acidic soils.. Journal of Crop
Improvement, pp. 657-667.
Bozdağ, A., Yavuz, F. & Dönertaş, A., 2016. AHP and GIS based land suitability analysis for
Cihanbeyli, Turkey. Article in Environmental Earth Sciences, pp. 1-15.
CBS, 2019. Statistics of Nepal, Kathmandu: Central Beareu of Statistics.
Census Nepal, 2011. Population And Housing Census of Nuwakot Aministrative of Nepal,
Nuwakot: s.n.
Census, 2021. National Population and Housing Cencue, Nepal: National Statistics Office.
Dangi, M. B. et al., 2011. Municipal solid waste generation in Kathmandu, Nepal. Journal of
Environmental Management, 92(1), pp. 240-249.
Dar, S. N., Ahmed, S., Skinder, S. & Wani, M. A., 2019. Identification of suitable landfill site
based on GIS in Leh, Ladakh Region. GeoJournal, Volume 84.
Dhakal, A., 2015. CGED-Nepal. [Online].
Doyuran, S. B., Lufti, S. & Vedat, 2006. Landfill site selection by using geographic information
system. Environment Geology, pp. 376-388.
Dubanowitz, A. J., 2000. Design of a material recovery facility (MRF) for processing the
recyclabe materials of new work city's municipal solid waste. Columbia University, p. 43.
38 | P a g e
Fidelis, O. A. et al., 2019. Combining multicriteria decision analysis with GIS for suitably siting
landfills in a Nigerian state. Environmental and Sustainability Indicators, Volume 3-4.
Gupta, N. et al., 2018. Automatic Waste Segregation. New York, s.n., pp. 1688-1692.
Karwan, A., Salahalddin, S. A., Nadhir, A.-A. & Jan, L., 2020. Landfill Site Selection Using GIS
and Multi-Criteria Decision-Making AHP and SAW Methods: A Case Study in Sulaimaniyah
Governorate, Iraq. Scientific Research Publishing, Volume 12, pp. 254-268.
Khanal, A., 2023. Forecasting municipal solid waste generation using linear regression
analysis, kathmandu, Nepal: Multidisciplinary jornal section.
Khatoon, A., 2020. Waste Management- A Case Study in Nepal. Solid waste policies and
strategies:Issues,Challenges and Case Studies, pp. 185-196.
Kirkwood, C., 1997. Strategic Decision Making: Multi Objective Decision Analysis with
Spreadsheets, Belmont, Australia: Duxbury Press.
Krausmann, et al., 2014. The global metabolic transition: Regional patterns and trends of global
material flows,. Global Environmental Change, pp. 87-97.
Majid, M. & Mir, B. A., 2021. Landfill site selection using GIS based multi criteria evaluation
technique. A case study of Srinagar city, India. Environmental Challenges.
MM, H. & MTU, R., 2020. Landfill area estimation based on solid waste collection prediction
using ANN model and final waste disposal options. J clean Prod.
Mohammad, A. A., Nadhir, A.-A. & Hadeel, K. J., 2014. GIS and Multicriteria Decision
Analysis for Landfill Site Selection in Al-Hashimyah. Natural Science, Volume 6, pp. 282-304.
OAG, 2015. Evironment Audit Report, Kathmandu: Office of Auditor General.
Saleem, D. U. &. S., 2014. Sustainability modelling and assesment of product recovery system-
an engineering approach to sustainable future, s.l.: .
Shrestha, K. K., 2019. Sustainable Management of Solid Waste in Nepal: Comparative Study of
Landfills in Kathmandu and Pokhara, Pokhara: .
Singh, A. O. &., 2013. GIS based environmental decision support system for municipal landfill
site selection. Manage Environmentl Qual.
WPDI & WLSP, 2017. Intergrated Development Planning of Bidur Municipality, Bidur: .
39 | P a g e