100% found this document useful (1 vote)
3K views3 pages

Residential Building Estimate

Uploaded by

arvind.bemba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views3 pages

Residential Building Estimate

Uploaded by

arvind.bemba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

DETAILED ESTIMATE GROUND FLOOR

DETAILED ESTIMATION FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL BUILDING IN


GROUND FLOOR AT S.NO:370/28,PATTA NO:2418 AT VANNIMADAI VILLAGE,NENMENI PANCHAYAT,
SATTUR TALUK, VIRUDHUNAGER DISTRICT .
NAME OF APPLICANT:Mr. MARUTHU
Estimate amount: Rs.22,65,000 /-
Sl. No. Description of Work Nos L B D Qty. Remarks
Earth work excavation in all soils
1 except hard rock with initial lead
of 2mm deep of foundation
a. Columns 1 x 12 5.00 5.00 6.00 1800.00
b. Plinth beam-Cross wall 1 x 4 30.17 1.00 0.50 60.34
Plinth beam-Cross wall 1 x 1 4.00 1.00 0.50 2.00
Plinth beam-Long wall 1 x 2 30.00 1.00 0.50 30.00
Plinth beam-Long wall 1 x 1 24.00 1.00 0.50 12.00
1862.34 Cft
52.74256585 Cum
Plain cement concrete 1:5:10
mix using 40mm hard broken
2
stone including cost and
conveyance of all labour charges
a. Columns 1 x 12 5.00 5.00 0.33 99.00
b. Plinth beam-Cross wall 1 x 4 30.17 0.75 0.33 29.87
Plinth beam-Cross wall 1 x 1 4.00 0.75 0.33 0.99
Plinth beam-Long wall 1 x 2 30.00 0.75 0.33 14.85
Plinth beam-Long wall 1 x 1 24.00 0.75 0.33 5.94
129.86 Cft
3.677663551 Cum
Reinforced cement concrete
1:2:4 mix using 20mm hard
3
broken stone including cost and
conveyance of all labour charges
a. Footing mat 1 x 12 5.00 5.00 1.50 450.00
b. Column upto plinth beam 1 x 12 0.75 1.00 4.00 36.00
c. Plinth beam-Cross wall 1 x 4 30.17 0.75 1.50 135.77
Plinth beam-Cross wall 1 x 1 4.00 0.75 1.50 4.50
Plinth beam-Long wall 1 x 2 30.00 0.75 1.50 67.50
Plinth beam-Long wall 1 x 1 24.00 0.75 1.50 27.00

Column above plinth upto lintel


d. 1 x 12 0.75 1.00 10.00 90.00
level
Column above lintel upto roof
g. 1 x 12 0.75 1.00 3.00 27.00
beam
h. Roof beam-Cross wall 1 x 4 30.17 0.75 1.50 135.77
Roof beam-Cross wall 1 x 1 4.00 0.75 1.50 4.50
Roof beam-Long wall 1 x 2 30.00 0.75 1.50 67.50
Roof beam-Long wall 1 x 1 24.00 0.75 1.50 27.00
i. Roof slab 1 x 1 30.17 30.00 0.50 452.55
1525.08 Cft
43.19116398 Cum
Brick work in cement mortar 1:6
mix using first class bricks
4
including cost and conveyance of
all labour charges etc.
a. Cross wall 1 x 4 30.17 0.75 9.50 859.85
Cross wall 1 x 1 4.00 0.75 9.50 28.50
Long wall 1 x 2 30.00 0.75 9.50 427.50
Long wall 1 x 1 24.00 0.75 9.50 171.00
1486.85
Deduction:
Door MD 1 x 1 3.50 0.75 7.00 18.38
Door D1 1 x 2 3.00 0.75 7.00 31.50
Door D2 1 x 1 2.50 0.75 7.00 13.13
Window W 1 x 7 4.00 0.75 4.00 84.00
Ventilator V 1 x 1 2.00 0.75 2.00 3.00
150.00
1336.85 Cft
37.86023789 Cum
Plastering work in C.M 1:5 ,mix
over all wall surfaces including
5
cost and conveyance of all
labour charges etc.completely.
Outer:
a. Wall around 1 x 1 120.00 16.00 1920.00
Inner:
a. Wall around 1 x 1 185.00 11.00 2035.00
Deductions:
Door MD 1 x 1 3.50 7.00 24.50
Door D1 1 x 2 3.00 7.00 42.00
Door D2 1 x 1 2.50 7.00 17.50
Window W 1 x 7 4.00 4.00 112.00
Ventilator V 1 x 1 2.00 2.00 4.00
200.00
3755.00 Sqft
106.343812 Sqm
Earthfilling in basement by river
sand or gravel including cost and
6
conveyance of all labour charges
etc. completely.
a. Area 1 x 1 30.17 30.00 3.00 2715.30
2715.30 Cft
76.8988955 Cum
Flooring concrete 1:5:10 mix
using 40 mm hard broken stone
7
including cost and conveyance of
all labour charges etc.
a. Area 1 x 1 30.17 30.00 0.33 298.68
298.68 Cft
8.458878505 Cum
Finishing the floor with Ceramics
tiles including cost and
8
conveyance of all labour charges
etc. completely.
a. Area 1 x 1 30.17 30.00 - 905.10
905.10 Sqft
84.11710037 Sqm
Special ceiling plastering in C.M
1:3 mix of 10 mm thickness in
9
roof including cost and
conveyance of all labour charges
a. Area 1 x 1 30.17 30.00 905.10
905.10 Sqft
84.11710037 Sqm

10 Provision for Wooden works LUMPSUM


11 Weathering Coarse
12 Provision for Painting works LUMPSUM
Provision for Electrification&
13 LUMPSUM
Plumbing works
Provision for Septic tank
14 LUMPSUM
arrangement works
Provision for unforeseen and
15 LUMPSUM
contingencies items