Date Tracking Gantt Chart2

Uploaded by

jmrnocedal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views5 pages

Date Tracking Gantt Chart2

Uploaded by

jmrnocedal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

ABOUT THIS GANTT CHART

Visualize and track your projects using this Gantt chart template. To start, enter the tasks you're work
milestone description section and then enter details for each task. The data will automatically update
insert new tasks or use the scrollbar to scroll through the timeline.

• Use the progress column to add how much of the project you finished by adding a percentage num
• Add the day you started your project in the start date column
• Finish your calculations by filling in the number of days you need to complete your project in the da
Project: Green
Contoso, Ltd.
Riku Nakano
Project start date: 11/15/2024 Scrolling increment: 13

Milestone marker: 1
November December January
28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Milestone description Assigned to Progress Start Days T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Project development

Project charter 25% 11/18/2024 3

Research 11/23/2024 1

Projections 50% 11/15/2024 10

Stakeholders 12/8/2024 1

Review 10% 11/24/2024 6

Contracts

Proposals 60% 11/24/2024 13

Document review 50% 11/25/2024 9

Bid date 33% 12/3/2024 11

Award date 12/12/2024 1

Finalize 12/13/2024 24

Design

Feasibility study 12/3/2024 4

Submit permit applications 12/7/2024 14

Design proposal 12/23/2024 6

Materials 1/5/2025 3

Equipment 12/28/2024 19

Testing

Environment 12/25/2024 15

System test 12/17/2024 5

Issues/bugs 2/6/2025 5

Task 4

Task 5

To add more data, Insert new rows ABOVE this one


PROPOSED MANILA INLAND CONTAINER DEPOT
MEDLOG PHILIPPINES INC.

AN-TREL REALTY INC. Scrolling increment: 13

Project Start D Wed,20-Nov-2024 November December January February March April


20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Milestone Description Progress Start End Days W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

1.0 PRE-CONSTRUCTION PHASE

1.1 Revision and Finalization of Complete Drawing Plans 11/20/2024 11/29/2024 10

1.2 Application of Permits and Clearances 11/30/2024 12/29/2024 30

1.3 Site Survey ((Topographic Survey, Staking and Markings) 11/25/2024 11/26/2024 2

2.0 CONSTRUCTION PHASE

2.1 Mobilization 12/26/2024 12/27/2024 2

2.2 Construction of Temporary Fence and Barracks 12/27/2024 1/2/2025 7

2.3 Demolition Works (removal of existing structures such as


12/27/2024 1/9/2025 14
fence, container vans, existing electrical post and etc.)

2.4 Site Development Works

2.4.1 Clearing and Grubbing 12/27/2024 12/31/2024 5

2.4.2 Site Drainage and Plumbing System 12/31/2024 1/19/2025 20

2.4.3 Soil Leveling and Backfilling of Base and Sub-


1/2/2025 3/2/2025 60
Base Coarse Aggregates

2.4.4 Construction of Concrete Pavements 1/8/2025 2/26/2025 50

2.5 Construction of Proposed Buildings, Fence and Tanks

2.5.1 Construction of Container Office 1/21/2025 2/4/2025 15

2.5.2 Construction of Admin Building 2/8/2024 3/8/2024 30

2.5.3 Construction of Underground Rainwater


2/10/2025 2/19/2025 10
Detention Tank (Reinforced Concrete)
2.5.4 Construction of Underground Cistern Tank
2/13/2025 2/22/2025 10
(Reinforced Concrete)
2.5.5 Construction of Material and Recovery Facility
2/17/2025 3/8/2025 20
(MRF)
2.5.6 Construction of Retaining Walls and erimeter
1/26/2025 2/14/2025 20
Fence inlcuding Barrier

2.5.7 Construction of Two Guardhouses 2/6/2025 2/25/2025 20

2.6 Refurbishment and Pump Rooms

2.6.1 Powerhouse 2/28/2024 3/18/2024 20

2.6.2 Installation of Ventillation 3/1/2025 3/20/2025 20

2.6.3 Construction of Fire Pump Room 3/2/2025 3/24/2025 23

2.6.4 Refurbishment of Existing Warehouse 3/6/2025 3/25/2025 20


Project: Purple
Contoso, Ltd.
Hayden Cook
Project start date: 11/15/2024 Scrolling increment: 14

Milestone marker: 1
November December January
29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Milestone description Assigned to Progress Start Days F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Title 1

Task 1 25% 11/18/2024 3

Task 2 11/23/2024 1

Task 3 50% 11/15/2024 10

Task 4 12/8/2024 1

Task 5 10% 11/24/2024 6

Title 2

Task 1 60% 11/24/2024 13

Task 2 50% 11/25/2024 9

Task 3 33% 12/3/2024 11

Task 4 12/12/2024 1

Task 5 12/13/2024 24

Title 3

Task 1 12/3/2024 4

Task 2 12/7/2024 14

Task 3 12/23/2024 6

Task 4 1/5/2025 3

Task 5 12/28/2024 19

Title 4

Task 1 12/25/2024 15

Task 2 12/17/2024 5

Task 3 2/6/2025 5

Task 4

Task 5

To add more data, Insert new rows ABOVE this one