BoQ E6X No Price

Uploaded by

Izhal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views4 pages

BoQ E6X No Price

Uploaded by

Izhal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

COO PEMBUATAN/MODIFIKASI TANGKI & SISTEM PIPING PAPUA FIELD

Bill of Quantity
PT. BORNEO MITRA SINERGI
28 Oktober 2024
Harga Satuan (Rp.) TOTAL HARGA
NO URAIAN PEKERJAAN VOL. TOTAL (Rp.)
UPAH BAHAN ALAT TRANSPORTASI SATUAN
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)=(9)x(3)
i Pekerjaan Persiapan Rp -
i.1 Pengurusan izin kerja 1.00 Lot/spk - -
i.2 Medical Check up 45.00 Org - -
i.3 Pembuatan Gudang Sementara / m2 150.00 m2 - -
i.4 Pembuatan Direction Kit / m2 (termasuk barak pekerja) 150.00 m2 - -
i.5 Tenaga Keamanan (1) 300.00 hari/org - -

ii Project Management dan Dokumen Rp -


ii.1 Management -
ii.1.1 HSE Officer 8.00 bulan/org - -
ii.1.2 Site manager 10.00 bulan/org - -
ii.1.3 Project Manager 12.00 bulan/org - -
ii.1.4 QA/QC Engineer (1) 10.00 bulan/org - -
ii.2 Survey & Engineering
ii.2.1 Survey 1.00 Lot/spk - -
ii.2.2 Drawing for Construction 1.00 Lot/spk - -
ii.2.3 Construction Report 1.00 Lot/spk - -
ii.2.4 Project Procedure 1.00 Lot/spk - -

iii Transportasi Kerja Rp -


Flowline
iii.1 Transportasi tenaga kerja
iii.1.1 Sewa Mobil 4WD Double Cabin (1) 300.00 hari - -
iii.2 Transportasi peralatan dan material
iii.2.1 Sewa Mobil Transport Material (1) 180.00 hari - -
iii.2.2 Sewa truck crane 5 Ton 100.00 hari - -
iii.2.3 Sewa truck crane 10 ton (1) 180.00 hari - -
iii.3 Sewa Alat Berat
iii.3.1 Excavator (1) 600.00 jam - -
iii.3.2 Dump Truck (1) 700.00 jam - -
Gasline
iii.4 Transportasi peralatan dan material -
iii.2.1 Sewa Mobil Transport Material (1) 30.00 hari - -
iii.2.2 Sewa truck crane 5 Ton 30.00 hari - -
iii.2.3 Sewa truck crane 10 ton (1) 30.00 hari - -
iii.5 Sewa Alat Berat
iii.3.1 Excavator (1) 120.00 jam - -
iii.3.2 Dump Truck (1) 120.00 jam - -
iv Pekerjaan Utama Flowline Rp -
iv.1 Pipa Utama Flowline
iv.1.1 Carbon Steel Pipe Ø 4" Sch.40 SRL, R1 Sch. 40, API 5L Gr. B/ A106/ A53,ERW BE SRL 963.00 Jts - -
iv.1.2 Ecer Pipa Ø4" Sch.40 @ 6 M / Jts 916.00 jts - -
iv.1.3 Menyablon pipa Ø4" @ 6 M / Jts 916.00 jts - -
iv.1.4 Memotong & Bevel Pipa Ø4" Sch.40 / Ttk 916.00 ttk - -
iv.1.5 Las pipa Ø4" Sch.40 @ 6 M / Jts 916.00 jts - -
iv.1.6 Stel & las Elbow Ø4" Sch.40 / Pcs 30.00 pcs - -
iv.1.7 Mendudukkan pipa Ø4" Sch.40 / Mtr 5,492.00 mtr - -
iv.1.8 Pipa Ø4" Sch.40 / Mtr 5,492.00 mtr - -
iv.1.9 Pasang Valve 4" - 300# / Pcs 1.00 pcs - -

Hal. 1 dari 4
COO PEMBUATAN/MODIFIKASI TANGKI & SISTEM PIPING PAPUA FIELD

Bill of Quantity
PT. BORNEO MITRA SINERGI
28 Oktober 2024
Harga Satuan (Rp.) TOTAL HARGA
NO URAIAN PEKERJAAN VOL. TOTAL (Rp.)
UPAH BAHAN ALAT TRANSPORTASI SATUAN
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)=(9)x(3)
iv.1.10 Pasang Valve 4" - 150# / Pcs 8.00 pcs - -
iv.1.11 Ball Valve Ø 4" 150# 8.00 pcs - -
iv.1.12 Ball Valve Ø 4" 300# 1.00 pcs - -
iv.1.13 Swing Check Valve Ø 4" 150# 4.00 pcs - -
iv.1.14 Spiral Wound Gasket Ø 4" 300# 3.00 pcs - -
iv.1.15 Spiral Wound Gasket Ø 4" 150# 21.00 pcs - -
iv.1.16 Flange WN Ø 4" 300# Sch.40 3.00 pcs - -
iv.1.17 Flange WN Ø 4" 150# Sch.40 21.00 pcs - -
iv.1.18 Hex Machine Bolt M 16 184.00 pcs - -
iv.1.19 Stel & las Flange Ø4" Sch.40 / Pcs 24.00 pcs - -
iv.1.20 Pengecatan External dan Asessories Tangki 1,720.20 m2 - -
iv.1.21 Stel & las Flange Ø4" Sch.40 / Pcs 24.00 pcs - -
iv.1.22 Lowering Pipa Ø4" Sch.40 / Mtr 5,492.00 Mtr - -
iv.2 Pemasangan pipe support - -
iv.2.1 Galian Tanah Biasa 157 m3 - -
iv.2.2 Ecer pipa 3" sch 40 @ 12 m 502.00 Jts - -
iv.2.3 Carbon Steel Pipe Ø 3" Sch.40 SRL, R1 502.00 Jts - -
iv.2.4 Potong dan bevel pipa 3" sch. 40 (Ttk) 1,025.00 Ttk - -
iv.2.5 Las Pipa 3" sch 40 @ 12 mtr (Jts) 1,025.00 Jts - -
iv.2.6 Potong plat baja (t +- 4 mm) 98.30 Mtr - -
iv.3 Road Crossing Pipa (Open Cut) @5 RC
iv.3.1 Galian tanah 879.80 m3 - -
iv.3.2 Timbunan Tanah didatangkan Termasuk Perataan dan Pemadatan 1,011.77 m3 - -
iv.3.3 Carbon Steel Pipe Ø 6" Sch.40 SRL, R1 42.00 Jts - -
iv.3.4 PIPE: VENTING, 2", SCH. 40, 0.154" THK, R-2, ASTM A-53 (GALVANIS) 10.00 Ea - -
iv.3.5 ELBOW: 90o, LR, 2", S-40, BW, A234WPB-W, ASME B16.9 30.00 Ea - -
iv.3.6 Pengeceran pipa 6" sch 40 (untuk casing) 42.00 Jts - -
iv.3.7 Potong dan bevel pipa casing 6" sch 40 (cross @ 20M) 42.00 Ttk - -
iv.3.8 Las Pipa Casing 6" Sch 40 @ 4 mtr (Jts) 42.00 Ttk - -
iv.3.9 CENTRALIZER: INNER f 4" 180.00 Ea - -
iv.3.10 Menyetel dan memasang sentralizer (1 pack @ 2 m panjang casing) 126.00 Pck - -
iv.3.11 END SEAL: 4" X 8" 42.00 Ea - -
iv.3.12 Pasang end seal (2 end seal @ 1 pipa) 84.00 Pck - -
iv.3.13 Pembalutan/wrapping pipa 4" dengan primer paste, 1st & 2nd layer and holiday test 5,492.00 mtr - -

iv.1 Pipa Utama Gasline


iv.1.1 Carbon Steel Pipe Ø 4" Sch.40 SRL, R1 Sch. 40, API 5L Gr. B/ A106/ A53, ERW BE SRL (Header) 192.60 Jts - -
iv.1.2 Carbon Steel Pipe Ø 2" Sch.40 SRL, R1 Sch. 40, API 5L Gr. B/ A106/ A53, ERW BE SRL (Branch) 87.60 Jts - -
iv.1.3 Ecer Pipa Ø4" Sch.40 @ 6 M / Jts 183.20 Jts - -
iv.1.4 Ecer Pipa Ø2" Sch.40 @ 6 M / Jts 87.60 Jts - -
iv.1.5 Menyablon pipa Ø2" @ 6 M / Jts 183.20 Jts - -
iv.1.6 Menyablon pipa Ø4" @ 6 M / Jts 87.60 Jts - -
iv.1.7 Memotong & Bevel Pipa Ø4" Sch.40 / Ttk 192.60 ttk - -
iv.1.8 Memotong & Bevel Pipa Ø2" Sch.40 / Ttk 87.60 ttk - -
iv.1.9 Las pipa Ø4" Sch.40 @ 6 M / Jts 192.60 jts - -
iv.1.10 Las pipa Ø2" Sch.40 @ 6 M / Jts 87.60 ttk - -
iv.1.11 Stel & las Elbow Ø4" Sch.40 / Pcs 4.80 pcs - -
iv.1.12 Stel & las Elbow Ø2" Sch.40 / Pcs 3.20 pcs - -
iv.1.13 Mendudukkan pipa Ø4" Sch.40 / Mtr 1,098.40 mtr - -
iv.1.14 Mendudukkan pipa Ø2" Sch.40 / Mtr 490.00 mtr - -

Hal. 2 dari 4
COO PEMBUATAN/MODIFIKASI TANGKI & SISTEM PIPING PAPUA FIELD

Bill of Quantity
PT. BORNEO MITRA SINERGI
28 Oktober 2024
Harga Satuan (Rp.) TOTAL HARGA
NO URAIAN PEKERJAAN VOL. TOTAL (Rp.)
UPAH BAHAN ALAT TRANSPORTASI SATUAN
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)=(9)x(3)
iv.1.15 Lowering Pipa Ø4" Sch.40 / Mtr 50.00 mtr - -
iv.1.16 Lowering Pipa Ø2" Sch.40 / Mtr 50.00 mtr - -
iv.1.17 Pasang Valve 4" - 300# / Pcs 0.20 pcs - -
iv.1.18 Ball Valve Ø 4" 300# 0.20 pcs - -
iv.1.19 Spiral Wound Gasket Ø 4" 300# 0.60 pcs - -
iv.1.20 Flange WN Ø 4" 300# Sch.40 A 105 0.40 pcs - -
iv.1.21 Flange WN Ø 2" 300# Sch.40 A105 2.00 pcs - -
iv.1.22 Hex Machine Bolt M 16 46.80 pcs - -
iv.1.23 Stel & las Flange Ø4" Sch.40 / Pcs 4.80 pcs - -
iv.1.24 Pengecatan External dan Asessories Tangki 344.04 m2 - -
iv.1.25 Stel & las Flange Ø4" Sch.40 / Pcs 4.80 pcs - -
iv.1.26 Stel & las Flange Ø2" Sch.40 / Pcs 1.60 pcs - -
iv.1.27 Tee Reducer Ø 4" x 4" x 2" Sch.40 0.20 pcs - -
iv.1.28 Reducer 4" x 2" Sch.40 0.60 pcs - -
iv.1.29 Stel & las Tee Reducer Ø4 x 2" Sch.40 / Pcs 0.20 pcs - -
iv.1.30 Pasang Valve 2" - 300# / Pcs 0.20 pcs - -
iv.1.31 Elbow Ø 2" 90° Sch.40 1.40 pcs - -
iv.1.32 Elbow Ø 2" 45° Sch.40 1.80 pcs - -
iv.1.33 Ball Valve Ø 2" 300# 0.40 pcs - -
iv.1.34 Swing Check Valve Ø 2" 300# 'A216 WCB 0.40 pcs - -
iv.1.35 Spiral Wound Gasket Ø 3" 300# ASME B 16.20 1.60 pcs - -
iv.1.36 Elbow 4" 45derajat Sch 40 4.80 pcs - -

iv.2 Pemasangan pipe support -


iv.2.1 Galian Tanah Biasa 27 m3 - -
iv.2.2 Ecer pipa 3" sch 40 @ 12 m 86.40 Jts - -
iv.2.3 Carbon Steel Pipe Ø 3" Sch.40 SRL, R1 86.40 Jts - -
iv.2.4 Potong dan bevel pipa 3" sch. 40 (Ttk) 205.00 Ttk - -
iv.2.5 Las Pipa 3" sch 40 @ 12 mtr (Jts) 205.00 Jts - -
iv.2.6 Potong plat baja (t +- 4 mm) 19.66 Mtr - -
iv.3 Road Crossing Pipa (Open Cut) @5 RC
iv.3.1 Galian tanah 175.96 m3 - -
iv.3.2 Carbon Steel Pipe Ø 6" Sch.40 SRL, R1 9.60 Jts - -
iv.3.3 PIPE: VENTING, 2", SCH. 40, 0.154" THK, R-2, ASTM A-53 (GALVANIS) 2.00 Ea - -
iv.3.4 ELBOW: 90o, LR, 2", S-40, BW, A234WPB-W, ASME B16.9 6.00 Ea - -
iv.3.5 Pengeceran pipa 6" sch 40 (untuk casing) 8.40 Jts - -
iv.3.6 Potong dan bevel pipa casing 6" sch 40 (cross @ 20M) 8.40 Ttk - -
iv.3.7 Las Pipa Casing 6" Sch 40 @ 4 mtr (Jts) 8.40 Ttk - -
iv.3.8 CENTRALIZER: INNER f 4" 36.00 Ea - -
iv.3.9 Menyetel dan memasang sentralizer (1 pack @ 2 m panjang casing) 25.20 Pck - -
iv.3.10 END SEAL: 4" X 8" 8.40 Ea - -
iv.3.11 Pasang end seal (2 end seal @ 1 pipa) 19.20 Pck - -
-
v Pekerjaan Pengujian Rp -
Flowline
v.1 Radiography Pipa Dia. Ø 4" / Jts 1,890 jts - -
v.2 Penetrant Test Pipa 2" - 6" 395.00 m - -
v.3 Pengujian Hydrostatic Test 30.00 hari - -
v.4 Pigging 1.00 lot - -
v.5 Commisioning 1.00 lot/spk - -

Hal. 3 dari 4
COO PEMBUATAN/MODIFIKASI TANGKI & SISTEM PIPING PAPUA FIELD

Bill of Quantity
PT. BORNEO MITRA SINERGI
28 Oktober 2024
Harga Satuan (Rp.) TOTAL HARGA
NO URAIAN PEKERJAAN VOL. TOTAL (Rp.)
UPAH BAHAN ALAT TRANSPORTASI SATUAN
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)=(9)x(3)
v.6 Holiday Test pipa 2"-6" 395.00 m - -
Gasline
v.1 Radiography Pipa Dia. Ø 4" / Jts 549.00 jts - -
v.2 Penetrant Test Pipa 2" - 6" 57.52 m - -
v.3 Pengujian Hydrostatic Test 6.00 hari - -
v.4 Nitrogen Purging 0.20 lot - -
v.5 Pigging 0.20 lot - -
v.6 Commisioning 0.20 lot/spk - -
v.7 Holiday Test pipa 2"-6" 79.00 m - -
SubTotal Rp -

Diajukan oleh,
PT Borneo Mitra Sinergi

Pandu Dwijaya
Direktur Utama

Hal. 4 dari 4