Arif Knitspin Substation
Data Collection
GAS GENERATOR
Capacity Max Load Present Running Load
No Voltage V pf
KW kW kW Amps
G1 1972 406 0.92 1650 1415 2149
G2 1972 409 0.94 1650 1425 2272
G3 1972 409 0.94 1650 1400 2200
G4 (overhaul) 0 0 0 0 0 0
G5 (emergency) 0 0 0 0 0 0
*Gas Consumption: 0.25 m3/kWh
From Main LT Outgoing Load
Run Run Load
Item Load (A) (kW)
Utility 320 182
LT1 680 435
LT3 1000 660
LT4 2000 1174
LT6 1200 780
LT china chiller 1000 555
Compressor LT 670 450
**1300 kW taken from NRG Vortex S/S due generator overhauling when required
Note:
LEDtube light 1270 Nos
A/C 76 kW
VFD+Servo 242+171 Nos
Pfi 5425 kVAR
Machine wise load
Total Load
Run Amps/ Run kW/
No. Machine Qty
Machine Machine kW A
1 Blow Room TRZSIR (set) 1 112 60 60 112
2 Blow Room RIETER (set) 1 54 30 30 54
3 Carding TRZSIR (Nos) 12 18 12.2 108 220
4 Carding RIETER (Nos) 18 13 8 144 234
5 Draw Frame BRK 6 10 6 36 60
6 Draw Frame FNS 6 6 3 18 36
7 Simplex 13 12 7 91 156
8 Ring Frame 58 46 28 1624 2668
9 Auto Coner 17 25 13 325 425
10 Xorella Yarn Condition 1 94 52 52 94
11 Combing 20 8 5.5 110 160
12 Hi Lap 3 13 7 21 39
13 AC plant 1 + FDP (set) 1 405 241 241 405
14 AC plant 2 (set) 1 165 90 90 165
15 AC plant 3 (set) 1 350 168 168 350
16 AC plant 4 (set) 1 360 177 177 360
17 AC plant 5 (set) 1 180 103 103 180
18 New FDP (set) 1 220 122 122 220
19 Lighting (set) 1400 N/A 46 40 N/A
20 QC lab + others N/A N/A N/A 100 N/A