Unit 12
Unit 12
Lecture Number 59
Track Maintenance I
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Stations
• Yards
• Level Crossing
2
Today’s Discussion
• Track Maintenance
– Maintenance categories
– Maintenance parameters
– Track Indices
3
Track Maintenance
• Ideal requirements
– It should show the health of the track
– It should be independent of the speed of recording
– It should not include design deviations as defects
– It should show the effect of loading also https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
– It should be recorded, keeping in view the purpose of
each types of results
4
Track Maintenance
6
Maintenance Limits: Speed up to 100 kmph
Parameter PML NBML UML UN – Unevenness
UN-1 SD 5.0 mm SD 6.8 mm AL – Alignment
Peak 20 mm SD – Standard
Vertical and Deviation of readings
UN-2 - - lateral
taken at every 30 cm
AL-1 SD 3.3 mm SD 4.0 mm acceleration peak
of 0.30g interval using TRC
Peak 15 mm
IRPWM 2020
AL-2 - -
Mean gauge over 200 m section over normal gauge
Straight - -8 mm to +10mm -10mm to +12mm
Curve R - -5mm to +14mm -7mm to +17mm
440m
7
Maintenance Limits: Speed up to 100 kmph
Parameter PML NBML UML Gauge: -5mm means
slack and +18mm means
Mean gauge over 200 m section over normal gauge
tight with respect to
Curve R< - -5mm to +18mm -7mm to +20mm 1676mm gauge;
440m
measured at every 30
Isolated defects – Nominal track gauge to peak values cm interval using TRC
Straight - -10mm to +12mm -12mm to +15mm IRPWM 2020
8
Maintenance Limits: Speed 100 to 110 kmph
Parameter PML NBML UML
UN-1 SD 3.8mm SD 5.5mm
Peak 17mm
UN-2 SD 5.4mm SD 7.5mm Vertical and
Peak 23mm lateral
https://iricen.gov.in/iricen/books_jquery/track_mo
AL-1 SD 2.5mm SD 3.9mm acceleration peak nitoring.pdf · PDF file
9
Maintenance Limits: Speed 110 to 130 kmph
Parameter PML NBML UML Twist = Relative
UN-1 SD 3.3mm SD 4.9mm movement of axle on
Peak 15mm left and right rail
UN-2 SD 5.1mm SD 7.4mm LL = Left low, left rail
Vertical and
Peak 22mm lateral lower than right rail
AL-1 SD 2.5mm SD 3.6mm acceleration peak RL = Right low, right
Peak 11mm of 0.25g rail lower than left rail
AL-2 SD 3.5mm SD 5.3mm
Peak 16mm
Mean gauge values are same as for speed up to 100 kmph
Twist TW-1 - 4mm/m 6mm/m
IRPWM 2020
10
Maintenance Limits: Speed 130 to 160 kmph
Parameter PML NBML UML Twist = (1-2 X-level) –
UN-1 SD 2.9mm SD 4.4mm Vertical and (3-4 X-level) / 3.6 or
Peak 13mm lateral 4.8 (i.e. length of
UN-2 SD 4.4mm SD 6.6mm acceleration peak bogie)
Peak 20mm of 0.20g Algebraic values are
AL-1 SD 1.9mm SD 3.6mm taken
IRPWM 2020
Peak 11mm
AL-2 SD 2.5mm SD 4.9mm
Peak 15mm
Mean gauge values are same as for speed up to 100 kmph
Straight - -6mm to +10mm -8mm to +12mm
11
Maintenance Limits: Speed 130 to 160 kmph
Parameter PML NBML UML
Curve R - -5mm to +13mm -7mm to +15mm
440m
Curve R< - -5mm to +18mm -7mm to +20mm
440m
Isolated defects – Nominal track gauge to peak values https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
Straight - -8mm to +12mm -10mm to +15mm IRPWM 2020
Standard chord
length for TRC on IR
is 7.2 m or 9.6 m;
done on side of rail
head
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
13
Track Maintenance: Measurement of Parameters
Twist/ alignment measurements are taken by
shifting the chord by 30 cm every time thus
resulting in 667 readings in 200 m distance
These are done for left and right rail
Thus, for all four parameters there will be
4000 readings for a block distance of 200 m
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
14
Track Maintenance: Track Indices
15
Track Maintenance: Track Indices
16
Track Maintenance: Track Indices
• Composite Track Record (CTR value)
– CTR = 75 – (ULA + URA + GA + TA + ALB + ARB)
– ALB = No. of peaks exceeding 5 mm in alignment on
7.2 m chord for left rail per km of track
– ARB = No. of peaks exceeding 5 mm in alignment on
7.2 m chord for right rail per km of track
https://iricen.gov.in/iricen/books_jquery/track_mo
– Unevenness peaks and alignment peaks of both the nitoring.pdf · PDF file
17
Track Maintenance: Track Indices
19
Track Maintenance: Track Indices
20
Track Maintenance: Track Indices
21
Track Maintenance: Track Indices
• Track Geometry Index (TGI value) TGI for a km = Average
– SDUm = (SDU2L + SDU2R)/2 – Average measured of TGI for 5 blocks in a
value of SD for unevenness km
– SDU2L = Measured value of SD of Unevenness of left
rail on 9.6 m chord
– SDU2R = Measured value of SD of unevenness of
right rail on 9.6 m chord https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
22
Track Maintenance: Track Indices
23
Track Maintenance: Track Indices
24
Track Maintenance: TGI values
parame Chord New Up to 110 kmph > 110 kmph < 130 Priority I: for UML
ter m track SD values mm kmph SD values Priority II: for PML
tolerance mm Bold values are used to
SD values
P II PI P II PI calculate UNI, TWI, GI
mm
and ALI
UN 3.6 1.2 2.5 3.3 2.3 3.0
https://iricen.gov.in/iricen/books_jquery/track_mo
9.6 2.5 6.5 7.4 5.1 6.2 nitoring.pdf · PDF file
26
Track Maintenance: Track Indices
27
Track Maintenance: Track Indices
https://iricen.gov.in/iricen/books_jquery/track_mo
0 for f < 0.5 Hz 0 for f < 0.5 Hz nitoring.pdf · PDF file
0.325 f2 for 0.5 < f < 5.4 Hz 0.8 f2 for 0.5 < f < 5.4 Hz
400/f2 for 5.4 < f =< 20.0 Hz 650/f2 for 5.4 < f =< 20.0 Hz
1 for f > 20 Hz 1 for f > 20 Hz
28
Track Maintenance: Track Indices
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
30
Track Maintenance: TRC Measuring Gauge
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
31
Track Maintenance: TRC – Measurement of Alignment
Accelerator
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
32
Track Maintenance: CFD Plots of Parameters
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
33
Track Maintenance: Blocks Requiring PM and UM
https://iricen.gov.in/iricen/books_jquery/track_mo
nitoring.pdf · PDF file
34
Today we started discussing the maintenance of tracks. We
discussed the classification of maintenance, tolerances
related to four parameters, their measurement process,
and track indices used to identify the maintenance
requirements.
Thank You
35
RAILWAY ENGINEERING
Lecture Number 58
Stations, Yards, Level Crossings
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
2
Today’s Discussion
• Stations
• Yards
• Level Crossing
3
Stations
• Purpose:
– Controls movement of trains
• Reception, Departure of trains, Crossing of trains,
Passing of faster trains
– Allows passenger and goods movement
– Provide facilities for enroute passengers
– Enable sorting of trains and wagons on sidings
– Provide maintenance facilities for rolling stock,
especially at terminal stations or junctions
– Facilitate movement or changeover of train crew
4
Stations
• Classification: Operational
– Block stations: Class-A, Class-B, Class-C
– Non-Block station: Class-D
– In the case of block station, the driver need an
authority to proceed enter the block section S1P.pdf (railnet.gov.in)
5
Stations
• A-Class Stations
– At these stations, the line shall not be considered
clear and Line clear shall not be given, unless:
• The whole of the last preceding train has arrived
completely
• All signals have been put back to ON position behind
the said train S1P.pdf (railnet.gov.in)
6
Stations
• A-Class Stations
– Conditions for line Clear:
• Where line clear cannot be given for a train unless
the line on which it is intended to receive the train
is clear for at least 400 m beyond the Home signal,
or up to the Starter signal S1P.pdf (railnet.gov.in)
7
Stations
• B-Class Stations
– Conditions for line Clear: for double line
• The whole of the last preceding train has arrived
completely
• All necessary signals have been put back to ON
position behind the said train and the line is clear
S1P.pdf (railnet.gov.in)
at stations equipped with MAS up to the
outermost facing points or the BSLB, if any
– Conditions for line Clear: for single line
• The whole of the last preceding train has arrived
completely
8
Stations
• B-Class Stations
– Conditions for line Clear: for single line
• The whole of the last preceding train has arrived
completely
• All necessary signals have been put back to ON
position behind the said train and the line is clear S1P.pdf (railnet.gov.in)
9
Stations
• C-Class Stations
– Conditions for line Clear: for single/double line
• The whole of the last preceding train has passed
completely at least 400 m beyond the Home signal
and is continuing its journey
• All signals taken OFF for the preceding train have
S1P.pdf (railnet.gov.in)
been put back to ON position behind the said train
• Provided that on a single line, the line is also clear
of trains running in the opposite direction towards
the block hut from the block station at the other
end
10
Station Signals
Class-B Station
Class-C Station
Class-A Station Railway Engineering by Chandra and Agarwal
11
Stations: Comparison
Class-A Class-B
Exist only in TAS Exist in TAS and MAS
Now obsolete Most stations are Class-B
No station section Definite station section
No shunting after LC given Shunting possible
LC cannot be given to both No such restriction S1P.pdf (railnet.gov.in)
side simultaneously
LC cannot be given unless No such restriction
reception line is clear
Obstruction is protected by 2 Obstruction is protected by 1
signals signal
12
Stations: Non-Block
• Halt:
– A simplest form with same shelter for booking of
tickets and waiting, platform is at rail level
• Flag station:
– Provided with a station building and staff; equipped
with a Morse telegraph or a control phone for
communication with nearby stations
• Wayside or Crossing station:
– Basic idea is to allow crossing of trains, especially on
single lines; mail/express trains stop at major
stations; deals with parcel traffic only; points and
13
Stations: Non-Block
14
Stations: Non-Block
• Junction station:
– Station with three or more lines merging/
diverging from/in different directions
15
Stations: Non-Block
• Terminal station:
– Station where a line or a branch line terminates; station
is equipped with facilities for passengers, wagons and
locomotives; usually FOB is not provided
16
Yards
• Types of Yards
– Coaching yard: It deals with reception and
dispatch of passenger trains; related facilities are
provided
– Goods yard: This deals with the reception,
stabling, loading, unloading and dispatch of goods
wagons; no sorting, marshalling and reforming is
done; separate goods sidings are provided
– Locomotive yard: This yard provides facilities
related to the locomotives; space is based on the
number of locomotives to be handles together
17
Yards
• Types of Yards
– Sick Line yard: This yard deals with the wagons
which are declared defective; repair related
facilities and workshop are provided
– Marshalling yard: This is a yard where goods
trains are received, sorted, new trains are
formed, and dispatched; deals with loaded and
unloaded wagons/trains; marshalling is done in
such a way that wagons can be conveniently
detached without mush shunting enroute at
wayside stations
18
Marshalling Yards
• Functions
– Reception of trains
– Sorting of trains
– Departure of trains
• Principle of Design:
– Trains should be received and dispatched as quickly
as possible
– Directional movement of wagons shall be
unidirectional
– There shall be no conflicting movement of wagons
and engines
19
Marshalling Yards
• Principles
– Lead for movement of wagons and trains should
be short as possible
– It should be well lighted
– Scope should be there for further expansion
• Types
– Flat yard: All tracks are laid almost at level and
the wagons are relocated using engines; require
frequent shunting; takes more time during back-
and-forth operations
20
Marshalling Yards – Types
• Flat yard: This is adopted when,
– There is limitation of space
– There is severe limitation of funds
– Number of wagons dealt are less
• Gravitational yard: Some tracks are laid at a gradient;
wagons move to sidings for sorting under action of
gravity; engine assistance is need for some operations
• Hump yard: A hump is provided, wagons are pushed
to hump by an engine, and they slide to the sidings
under gravity; topography of location plays an
important role in this
21
Marshalling Yards
Item Gradient to be adopted for Mechanized yard
Mechanical yard Non-mechanical uses retarders to
yard control the speed of
wagons on a
Rising gradient of 1 in 50 to 1 in 125 1 in 50 to 1 in 100 gradient and to stop
approach at specified location
Top of hump Level Level
First falling grade 1 in 17 to 1 in 20 1 in 25 to 1 in 35
after apex of hump
Intermediate grade 1 in 50 to 1 in 60 1 in 80m to 1 in
up to the point 200
where the train starts
22
Marshalling Yards
Item Gradient to be adopted for Non-Mechanized
Mechanical yard Non-mechanical yard uses hand
yard brakes to control the
speed of wagons on
Final falling gradient 1 in 200 to level 1 in 80 to 1 in 200 a gradient and to
up to clearance of stop at specified
points location
Gradient of the Down gradient Falling gradient 1
sidings eased off and then in 400 to 1 in 600
an up gradient
given to stop
wagons at the end
23
Marshalling Yards
Hump
Yard
24
Marshalling Yards
• Spacing: 400 km if lead is 500 km and train section is
100 km
• Length of a siding: 700 m for BG
• Number of sidings: based on 3-4 trains per siding
• Shunting neck: Longer than the longest train
• Average height of ordinary hump: 2.5 to 3 m
• Average height of mechanized hump: 3.5 to 6 m
• Average gradient from the hump to the end of
switching zone: 2% for empty and 1.5% for loaded
wagons
25
Level Crossings
26
Level Crossings
27
Level Crossings
• Classification is based on nature of road, number of
road vehicles passing and number of trains passing
• TVU (Train vehicle Unit) = No of trains × No of road
vehicles (both for 24 hours)
• Train, motor vehicle, bullock carts and tongues – 1
unit
• Cycle rickshaw and auto rickshaw – ½ unit
• Motorised two-wheelers: ¼ unit
• TVU over 20000 qualifies for interlocking
• Minimum TUV for ROB/RUB on cost sharing basis
should be 1 Lakh, with relaxation on suburban
sections
28
Level Crossings
Class Criteria TVU is more than 6000
Special TVUs greater than 50,000 of LC visibility is poor –
Convert un-manned
‘A’ Class TVUs from 50000 and up to 30000 or gate into Manned gate
Line capacity utilization 80% (on single line) and
number of road vehicles greater than 1000
‘B’ Class TVUs less than 30000 and up to 20000 and IRPWM 2020
number of road vehicles greater than 750
B1 Class: TVUs less than 30000 and up to 25000
B2 Class: TVUs less than 25000 and up to 20000
‘C’ Class All other level crossings for road, not covered in
above classes
29
Level Crossings
• Road and railway line should cross preferably at right
angles. Angle of crossing should not be less than 45o
• All interlocked LC shall be kept ‘Normally Open to
Road Traffic’
• In case of non-interlocked LC, the gates must
normally be kept closed. They can be kept open
IRPWM 2020
during the busy season with proper permission
• Height gauges should be located at a minimum 8 m
from gate posts at LC located at electrified sections
• LC should not fall within the breathing length of LWR
30
Level Crossings
• Rail joints should be avoided in check rails and on the
running rails, within the level crossings and 3 m on
either side from the end of level crossing
• In case of LWR, avoiding fish plated joint on the level
crossing and within 6 m from the end of level crossing
• On NH, SH and other important roads, only grade
IRPWM 2020
separators shall be provided instead of LC
• Visibility of manned gate shall be minimum 5 m and
gate post shall be 3 m from center of the track
• Fencing shall be done for 15 m parallel to the track on
either side
31
Level Crossings
IRPWM 2020
32
Level Crossings
34
RAILWAY ENGINEERING
Lecture Number 60
Track Maintenance II
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Track Maintenance
– Maintenance categories
– Maintenance parameters
– Track Indices
2
Today’s Discussion
• Track Maintenance
– Annual Maintenance Schedule
– Mechanised Track Maintenance
– Systematic packing
– Picking up slacks
– Through packing
3
Regular Track Maintenance
4
Regular Track Maintenance
5
Regular Track Maintenance
6
Regular Track Maintenance
IRPWM 2020
7
Mechanised Track Maintenance
IRPWM 2020
– Maintenance taken up are:
• Systematic tamping of plain track as well as Points
& Crossings
• Intermediate tamping of plain track as well as
Points & crossings
8
Mechanised Track Maintenance
IRPWM 2020
• Picking up and transportation of Material
• Mobile Maintenance Gang (MMG)
– One MMG has a jurisdiction on 70-80 km in single
line section and 30-50 km in double/multi-line
section
9
Mechanised Track Maintenance
IRPWM 2020
welding.
• Attention to SEJs.
• Scattered replacement of switches and crossing
components, glued joints, SEJs, etc.
• Rail cutting, drilling and chamfering
10
Mechanised Track Maintenance
spot attention.
• Driving of RBMV
– RBM vehicle carries all the equipment and
accessories required for maintenance works
11
Mechanised Track Maintenance
IRPWM 2020
weather patrolling, monsoon patrolling)
• Watching vulnerable locations
• Need-based attention to bridges, turnouts, SEJs, LC
• Greasing of ERCs, lubrication of joints, casual
changing of rubber pads, fittings
12
Mechanised Track Maintenance
IRPWM 2020
• Creep and gap adjustment not involving use of
machines
• Pre and post tamping attention
• Examination of rails, sleepers and fastenings
including measurement of toe load of ERCs
13
Mechanised Track Maintenance
IRPWM 2020
14
Track Maintenance
15
Track Maintenance
16
Track Maintenance
17
Track Maintenance
18
Track Maintenance
• Systematic Tamping (Plain track, P&C)
– The tamping depth i.e. gap between the top edge of
the tamping blade and the bottom edge of the
sleeper in closed position of the tamping tool should
be adjusted to 15 mm to 20 mm
– Tamping tools shall be inserted centrally between
the sleepers into the ballast (to avoid damage) Ballast Tamping Machine railgeelong.com
19
Track Maintenance
IRPWM 2020
20
Track Maintenance
• Picking Up Slacks
– Slacks usually occur on:
• Stretches of yielding formation
• High banks and cuttings
• Approaches of bridges, LC, SEJs, P&C zones, Glued Using Crowbar on track Storyblocks video
Joints
• Badly aligned curves, axle counter locations and
other electrical and S&T installations
• Locations where ballast is poor in quality or
quantity or where drainage is defective
IRPWM 2020
21
Track Maintenance
• Picking Up Slacks
– Attention shall be given as per the results of TRC /
OMS / Oscillograph car
– For spot attention, multi-purpose tampers or Off-
track handheld tampers or crowbars are used
– In the case of a low joint, the fishplates should be
slightly loosened and the joint tapped, so that the Off-track handheld tampers svjcorporation.com
22
Track Maintenance
• Picking Up Slacks
– If the affected length of the track is more than 1
km then track machines should be used
Defects Symbol Place of indication
Cross levels C-2 On the sleeper inside gauge face
Track Tamping Machine railway-supply
Loose packing H or P On the sleeper outside the gauge face
Gauge G± On the sleeper inside gauge face
Unevenness → On the rail web on gauge face side
Alignment → On the foot of the rail inside gauge
face IRPWM 2020
23
Track Maintenance
• Through Packing: Convention method
– Manual through packing is not done on concrete
sleeper tracks
– Steps:
• Opening of the road.
• Examination of rails, sleepers and fastenings.
• Squaring of sleepers. Manual maintenance rediff.com
24
Track Maintenance
25
Track Maintenance
26
Track Maintenance
• Through Packing: Convention method
– Squaring of sleepers
• Out-of-square sleepers are picked with pick end of
beaters, fastening loosened, and the sleepers are
levered and squared to position
• Squaring should be done using mechanical or
hydraulic spacer or using crowbars
– Slewing of track to correct alignment Manual maintenance thestatesman.com
27
Track Maintenance
28
Track Maintenance
30
Track Maintenance
31
Track Maintenance
32
Track Maintenance
33
Track Maintenance
be removed
• Cess should be maintained to the correct depth below
rail level according to the ballast-section and
formation profile. Too high a cess affects drainage; too
low a cess results in ballast-spread and wastage
IRPWM 2020
34
Today we continued discussion on track maintenance. We
discussed annual schedule of maintenance and regular
maintenance. Along with mechanized maintenance,
packing of ballast, picking up of slacks and through
packing we discussed.
Thank You
35
RAILWAY ENGINEERING
Lecture Number 61
Track Maintenance III
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Track Maintenance
– Annual Maintenance Schedule
– Mechanised Track Maintenance
– Systematic packing
– Picking up slacks
– Through packing
2
Today’s Discussion
• Track Maintenance
– Systematic overhauling
– Lubrication of rail joints
• Insulated rail joints
• Glued insulated rail joints
– Deep screening of ballast
• Manual and mechanical
– Lifting and Lowering of track
3
Track Maintenance
• Systematic Overhauling
– The overhauling should be done using SBCM for
cleaning of shoulder ballast
– The length of the section to be overhauled shall be
such that complete overhauling of track will be
accomplished within a specific period (normally 3 to
5 years) Shoulder ballast cleaning machine rail-news.com
4
Track Maintenance
• Systematic Overhauling
– Operations:
• Shallow screening and making up of ballast
• All items as done in through packing
• Making up the cess
– Shallow screening and making up of ballast
• For good drainage periodical screening of ballast is Shallow screening
essential
• The ballast in the shoulders opposite to the crib as
well as between the sleepers is removed to the full
depth
• A slope is given at the bottom sloping away from the
sleeper end
IRPWM 2020
5
Track Maintenance
• Systematic Overhauling
– Shallow screening and making up of ballast
• In case of manual overhauling, the crib ballast in the
shoulders should be opened out to a depth of 75 to
100 mm below the bottom of sleepers, sloping from
the center towards sleeper end
• The ballast is then screened and put back Shoulder ballast cleaning machine plassertheurer.com
6
Track Maintenance
• Systematic Overhauling
– Shallow screening and making up of ballast
• Where drains across the track exist, they should be
cleaned and filled with boulders or ballast to
prevent packing from working out and forming
slacks Shoulder ballast cleaning machine plassertheurer.com
7
Track Maintenance
• Systematic Overhauling
– Making up of cess
• Cess when high should be cut along with
overhauling and when low should be made up
• Overhauling should be completed before the end
of March Shoulder ballast cleaning machine plassertheurer.com
IRPWM 2020
8
Track Maintenance
9
Track Maintenance
10
Track Maintenance
• Lubrication of Rail Joint
– Procedure:
• The fishing surfaces of the rails and fishplates are then
lubricated
• The fish bolts are then put back in reverse position
and tightened using a standard fish bolt spanner, the
inner two bolts being tightened first
• While tightening overstraining of bolts shall be Lubrication of rail joint rail-system.net
avoided
• During all works such as relaying, rail renewals and
renewals of turnouts, etc. rail joints should be
lubricated
• Insulated joint fishplates should not be greased
IRPWM 2020
11
Track Maintenance
12
Track Maintenance
• Glued Insulated Rail Joints
– The ballast used in track in the vicinity of glued
insulated joints shall be clean to ensure efficient
packing and drainage.
– Ballast is clear of rails and rail fastenings.
– In glued joints, normally no relative movement occurs
between rails and fishplates.
– In case, failure of joints occurs by separation of rail,
Glued Insulated rail joint indiamart.com
13
Track Maintenance
• Deep Screening of ballast
– Track, on which deep screening is to be done, shall
be well drained
– Due to presence of bad formation, ballast attrition,
excessive rainfall and dropping of fines and ore,
ballast gets choked up and track drainage is
impaired
– In such situations, it becomes necessary to screen
the entire ballast right up to the formation level
/sub-ballast level
– Through screening restores the resilience and
elasticity of the ballast bed. This is called deep
screening
IRPWM 2020
14
Track Maintenance
15
Track Maintenance
16
Track Maintenance
IRPWM 2020
17
Track Maintenance
18
Track Maintenance
19
Track Maintenance
20
Track Maintenance
21
Track Maintenance
IRPWM 2020
22
Track Maintenance
23
Track Maintenance
24
Track Maintenance
25
Track Maintenance
26
Track Maintenance
27
Track Maintenance
28
Track Maintenance
29
Track Maintenance
• Lifting of Track
– This may be needed:
• During re-grading
• For elimination of minor sags (caused due to improper
maintenance or yielding formation)
• To maintain good levels
– Before starting lifting, level pegs should be fixed at
suitable intervals
– Lifting should not exceed 50 mm at a time. This
allows proper consolidation
IRPWM 2020
30
Track Maintenance
• Lifting of Track
– The easement gradient for the passage of trains should
not be steeper than 25mm in one rail length of 13 m
– Lifting should commence from the downhill end carried
out in the direction of rising grade in case of single line
– It should proceed in the opposite direction to traffic, in
case of double line, care being taken not to exceed the
easement grade
– While lifting the track under bridges and overhead
structures and in tunnels, it should be ensured that
there is no infringement of standard dimensions
IRPWM 2020
31
Track Maintenance
• Lifting of Track
– In case of curves, it is usual to set the inner rail to the
correct level and grade and to raise the outer rail to
give the required super elevation, care being taken to
see that the cant gradient is within the permissible
limit
– The operation should be repeated until the required
level is attained when the track should be finally
ballasted, through packed and boxed, the cess being
made up to proper level
– Heavy lifting should always be carried out under
suitable speed restriction
IRPWM 2020
32
Track Maintenance
• Lowering of Track
– Usually, it should not be done
– When lowering is to be done, trenches should be
made across the track at every 30 m to the final
level to give a continuous indication
– The ballast should be removed sufficiently far away
from the track to prevent it getting mixed up with
excavated material
– Lowering should be restricted to maximum of 75mm
at a time
IRPWM 2020
33
Track Maintenance
• Lowering of Track
– Grade for passage of trains should not exceed
25mm in a rail length of 13 m
– Lowering should be carried out in the direction of
the falling grade
– Procedure:
• Clear the spaces between the sleepers
• Slightly lift the track, break the packing beneath
and level it into the space between the sleepers
IRPWM 2020
34
Track Maintenance
• Lowering of Track
– Procedure:
• Remove the material, repeat the operation until
the final level is reached
• Then the track is ballasted, through packed and
boxed
• Cess is cut down to the proper level
IRPWM 2020
35
Today we further discussed the track maintenance. We
covered systematic maintenance, lubrication of rail
joints, insulated rail joints and glued insulated rail joints,
manual and mechanical deep screening of ballast, and
lifting and lowering of a track.
Thank You
36
RAILWAY ENGINEERING
Lecture Number 62
Track Maintenance IV
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Track Maintenance
– Systematic overhauling
– Lubrication of rail joints
• Insulated rail joints
• Glued insulated rail joints
– Deep screening of ballast
• Manual and mechanical
– Lifting and Lowering of track
2
Today’s Discussion
• Track Maintenance
– Measured Shovel Packing
– Track Circuited Areas
– Electrified Areas of Track
– Permanent Way Renewals
– Through Sleeper Renewals
3
Track Maintenance
4
Track Maintenance
5
Track Maintenance
6
Track Maintenance
7
Track Maintenance
8
Track Maintenance
9
Track Maintenance
10
Track Maintenance
11
Track Maintenance
12
Track Maintenance
13
Track Maintenance
14
Track Maintenance
• Track Electrified Areas
– Precautions to be taken:
• In case wires drop at a level crossing, the gatekeeper
shall immediately arrange to stop the traffic on the
track
• Precaution be taken to prevent possible damage to
the traction underground feeder cables which are
located near the running lines
• Vertical and horizontal clearances of the wires should
be adhered to with respect to the center line of the
track
• No tool or part of the body shall come within 2 m of
OHE
IRPWM 2020
15
Track Maintenance
16
Track Maintenance
17
Track Maintenance
IRPWM 2020
18
Permanent Way Renewals
• Track renewal categories
– CTR(P): Complete Track Renewal (Primary)
– CTR(S): Complete Track Renewal (Secondary)
– TRR(P): Through Rail Renewal (Primary)
– TRR(S): Through Rail Renewal (Secondary)
– TSR(P): Through Sleeper Renewal (Primary)
– TSR(P): Through Sleeper Renewal (Secondary)
– TRT: Through Turnout Renewal
– TFT: Through Fitting Renewal
– TWT: Through Weld Renewal
– TBST: Through Bridge Sleeper Renewal
– TBR: Through Ballast Renewal
IRPWM 2020
19
Permanent Way Renewals
• Track renewal categories
– CTR(P): Complete Track Renewal (Primary)
– CTR(S): Complete Track Renewal (Secondary)
– TRR(P): Through Rail Renewal (Primary)
– TRR(S): Through Rail Renewal (Secondary)
– TSR(P): Through Sleeper Renewal (Primary)
– TSR(P): Through Sleeper Renewal (Secondary)
– TRT: Through Turnout Renewal
– TFT: Through Fitting Renewal
– TWT: Through Weld Renewal
– TBST: Through Bridge Sleeper Renewal
– TBR: Through Ballast Renewal
IRPWM 2020
20
Permanent Way Renewals
• Primary renewals:
– Renewals in which only new material are used
• Secondary renewals:
– Renewals using released serviceable materials
• Scattered renewals:
– In this case, unserviceable rails, sleepers and
fastenings are replaced by identical sections of
serviceable and nearly the same vintage track
components in isolated locations and not more than
10 rails and/or 250 sleepers in a gang beat in a year
IRPWM 2020
21
Permanent Way Renewals
• Scattered renewals:
– Such renewals are part of normal maintenance
operations
• Casual renewals:
– In this case, unserviceable rails, sleepers and
fastenings are replaced by identical sections of
serviceable and nearly the same vintage track
components in isolated locations of continuous but
small stretches
– This is not a part of normal maintenance operations
IRPWM 2020
22
Permanent Way Renewals
23
Permanent Way Renewals
24
Permanent Way Renewals
• Wear on Rails:
– Limiting loss in rail section: 6% in 52 kg/m and 7%
in 60 kg/m rail section Vertical wear
25
Permanent Way Renewals
• Wear on Rails:
– Lateral wear limits: Lateral wear
• Curves: ‘A’ and ‘B’ routes 8mm; ‘C’ and ‘D’ routes New
Profile
10mm Wear measured
at a point 13-15
• Straight: ‘A’ and ‘B’ routes 6mm; ‘C’ and ‘D’ routes mm below rail Worn
table Profile
8mm
• Maintainability of track to prescribed standards
– Poor running quality of track in spite of extra
maintenance labour engaged
– Disproportionate cost of maintaining the portion of
track in safe condition
IRPWM 2020
26
Permanent Way Renewals
27
Permanent Way Renewals
28
Permanent Way Renewals
29
Permanent Way Renewals
30
Permanent Way Renewals
31
Permanent Way Renewals
32
Permanent Way Renewals
IRPWM 2020
33
Today we discussed other aspects related to track
maintenance. We discussed measured shovel packing,
maintenance precautions in track circuited areas and
electrified areas, permanent way renewals and through
sleeper renewals.
Thank You
34
RAILWAY ENGINEERING
Lecture Number 63
Track Renewals and Drainage
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Track Maintenance
– Measured Shovel Packing
– Track Circuited Areas
– Electrified Areas of Track
– Permanent Way Renewals
– Through Sleeper Renewals
2
Today’s Discussion
• Track Renewals
– Points and Crossings
– Track Renewal Train
• Track Drainage
– Requirements for a track
– Drainage between stations
– Drainage in station yards
– Drainage at platforms
– Sub-surface drainage
3
Permanent Way Renewals
4
Permanent Way Renewals
5
Permanent Way Renewals
6
Permanent Way Renewals
7
Permanent Way Renewals
IRPWM 2020
8
Track Renewal / Re-laying Train (TRT)
9
Track Renewal / Re-laying Train (TRT)
• TRT consists of:
– A set of BFRs, used to handle sleepers, works with a
speed of 720 m/h when in use
• Working of TRT
– Removal of fastenings (from old rails)
– Placement of new rails (at 1.5 m from the track)
– Positioning on the track (using guidance sled) siyasat.com
10
Track Renewal / Re-laying Train (TRT)
• Working of TRT
– Levelling and compaction of ballast bed (using
vibratory plough and compactor)
– Laying of new sleepers
– Laying of new rails plassertheurer.com
11
Track Drainage
12
Track Drainage
13
Track Drainage
• Sources of Water
– Gravity water: Water which collects due to
precipitation and moves into the subgrade under
gravity. This can be controlled by:
• Provision of surface drainage, say cross-falls, side
drains
• Lowering of cess
• Turfing of side slopes of embankments
– Capillary action: This is the water which moves up
from the ground water table or seepage water
under the action of capillary effect
• It can be controlled by providing a pervious layer
which acts as a capillary break
14
Track Drainage
• Sources of Water
– From adjacent areas: Water seeping from sources in
the vicinity into the subgrade. It can be controlled
by:
• Diverting the water from the source away from
embankment
• Providing effective paved catch water drain in sloped
areas
• Providing inverted filters and underground drains
– Hygroscopic action from atmosphere: Absorbing the
moisture present in the atmosphere. Being less it
has little effect of subgrade moisture
15
Track Drainage
16
Track Drainage
17
Track Drainage
18
Track Drainage
19
Track Drainage
20
Track Drainage
• Drainage in station yards
– Normally the drain top should not be above the cess
level for effective drainage in the ballast
– In case the above is not feasible, weep holes can be
provided at the assumed cess level
– The slope shall be aligned based on the location of
the outfall. If it is available at both the ends, then
the slope of the drain shall move away towards the
ends from the center in the yard
– A network of longitudinal and cross drains shall be
provided to carry away the water in the least
possible time
21
Track Drainage
22
Track Drainage
23
Track Drainage
• Sub-surface drainage
– Inverted filter:
• Thickness of the layer can be 300mm on a clayey soil.
It may be increased as per the soil properties
• It may contain plastic fines not exceeding 5% and non-
plastic fines not exceeding 12%
• In macadam form, the LL should not exceed 35 and PI
should be below 10
• The uniformity coefficient should be above 4
(desirably above 7)
• The coefficient of curvature should be between 1 and
3
24
Track Drainage
• Sub-surface drainage
– Depth of blanket layer:
• For GP/SP soil with Cu > 2, GM, GM-GC: 450mm
• For GC, SM, SC, SM-SC: 600mm
• ML, ML-CL, CL, MI, CI, rocks susceptible to
weathering: 1000mm
– Sand Piles
• Sand piles of diameter 200mm can be used to
improve the sub-surface drainage
• The total cross-sectional area of sand piles is kept
as 20% of the formation area
25
Track Drainage
• Sub-surface drainage
– Sand Piles
• The depth of sand piles may be 2 to 3 m
• The water rises through the sand piles to the surface
through capillary action and evaporates
– Cement Grouting
• Cement grouting is used if water pockets are created
in the subgrade
• The slurry of cement and sand is pumped into the
embankment by pneumatic injection
• The grout of cement and sand is made in the ratio of
1:2 to 1:6 and is injected under the pressure of 4.2
kg/cm2
26
Track Drainage
• Sub-surface drainage
– Cement Grouting
• Pumping is continued till the grout appears
through the ballast and reaches its top surface
• It helps in filling the cracks thus preventing the
water to flow into the subgrade
• This method is expensive
– Paved catch water drains can also be provided to
stop the water to enter the subgrade
27
Track Drainage
• Sub-surface drainage
– Water Pockets in ballast
• If water pockets are just formed, then deep
screening and provision of pervious layer can help
• Cement grouting can be used to seal off the pocket
if the stretch is small
• In case water gets trapped in the ballast due to an
impervious layer lying over a pervious layer, the
drainage can be improved by puncturing a hole in
the impervious layer
28
Track Drainage
• Sub-surface drainage
– Water Pockets in ballast
• Perforated pipes can be inserted to drain off the
water
• Counterfeit drains can be provided to drain the
water. These are usually 600mm wide and spaced
at an interval of around 10 m
29
Today we discussed other aspects related to track
maintenance. We have continued with permanent
way renewals and through sleeper renewals then we
discussed about Track renewals and Track drainage.
Thank You
30
RAILWAY ENGINEERING
Lecture Number 64
High Speed Tracks
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Track Renewals
– Points and Crossings
– Track Renewal Train
• Track Drainage
– Requirements for a track
– Drainage between stations
– Drainage in station yards
– Drainage at platforms
– Sub-surface drainage
2
Today’s Discussion
3
High Speed Tracks
4
High Speed Tracks
• Classification:
– High Speed tracks
• Speeds over 120 kmph and up to 250 kmph
– Super High-Speed Tracks
• Speeds above 250 kmph
• To achieve the above conditions, it is
required to:
– Modernize the tracks to higher standards
– Use modified / advanced traction efforts
IRPWM 2020
5
High Speed Tracks: Effects of High Speed
6
High Speed Tracks: Effects of High Speed
• Unbalanced weights
• Unsprung masses
• Suspension characteristics
• Wave formation
• Adhesion between wheel and rails
• Vibrational limitations
• Special problems on curves
• Power requirements
IRPWM 2020
7
High Speed Tracks: Wave Formation
8
High Speed Tracks: Wave Formation
9
High Speed Tracks: Wave Formation
10
High Speed Tracks: Wave Formation
11
High Speed Tracks: Adhesion between Wheels and Rails
12
High Speed Tracks: Adhesion between Wheels and Rails
13
High Speed Tracks: Adhesion between Wheels and Rails
IRPWM 2020
14
High Speed Tracks: Vibrations
15
High Speed Tracks: Vibrations
IRPWM 2020
16
High Speed Tracks: Curved Tracks
17
High Speed Tracks: Curved Tracks
18
High Speed Tracks
IRPWM 2020
19
High Speed Tracks
• Track components:
– Electric traction with higher power
– Heavy rail sections with higher wear resistance
(say 90 UTS / 110 UTS section)
– Use of SEJs with LWR/CWR
– Use of PSC sleepers
– Use of higher sleeper density as 1540, 1660 per
km or higher
– Ballast section as discussed for LWR/CWR
IRPWM 2020
20
High Speed Tracks
• Track components:
– Use of elastic fastenings
– Integrated track assembly with LWR/CWR
– Use of long curved switches as 1 in 16 and above
(on MAHSR it is 1 in 18)
– Higher cant deficiency
– Use of Cast Manganese Steel (CMS) rail for
crossings and curved switches
– Use of USFD to check flaws in rails before use
IRPWM 2020
21
High Speed Tracks
22
High Speed Tracks
• Track components:
– Strengthened formation as per requirement by:
• Providing topping layer with or without water
proofing membrane
• Providing sub-bullah piles
• Cement grouting of ballast pockets
• Lime treatment of formation
• Providing sub-bank or flattening of slopes
• Increase in depth of the ballast
IRPWM 2020
23
High Speed Tracks
• Traction Requirements
– Specific power, defined as the power required to
move 1 ton of passenger rolling stock, is correlated
with air resistance, gradient, speed and acceleration
– It is observed that with an increase in speed, the
requirement of power to overcome the resistance
and to accelerate the train goes up very steeply
– Tests indicated that at a speed of 300 kmph, air
resistance takes about 95% of the traction power
and only 5% of the power is devoted to suspension
and guidance
IRPWM 2020
24
High Speed Tracks
IRPWM 2020
25
High Speed Tracks: Super High-Speed Concepts
26
High Speed Tracks: Super High-Speed Concepts
27
High Speed Tracks: Super High-Speed Concepts
28
High Speed Tracks: Super High-Speed Concepts
29
High Speed Tracks: Super High-Speed Concepts
30
High Speed Tracks – Safety on Track
31
High Speed Tracks
32
High Speed Tracks
33
High Speed Tracks
34
Today we discussed the high-speed tracks. This included the
need for high-speed tracks, the effects of high speed and
the resulting restrictions on the permissible speeds,
modernization requirements, the concepts for super
high-speeds on tracks, and the safety features which can
be taken up on such tracks.
Thank You
35