Technical Specification
Technical Specification
For the purpose of this Clause, the following terms are defined as follows:
1.1 OWNER
1.2 ADMINISTRATION
The Procuring Entity is the party who employs the Contractor to carry out the Works
stated in the Special Conditions of the Contract.
1.4 ENGINEER
The word "Engineer'' refers to the individual or firm authorized by the Administration to
oversee the execution of the Contract and approve the Works; acting either indirectly,
directly or through its property authorized agents, each agent acting only within the
scope of authority delegated to him by the _______________.
1.5 CONTRACTOR
The word "Contractor" refers to the party entering into the Contract for the
performance of the work required, its legal representative and/or its duly appointed
agent.
1.6 SUBCONTRACTOR
The word "Subcontractor'' refers to any person, firm, or corporation entering into
agreement with the Contractor for the performance of any part of the Contractor’s
obligation under the Contract.
1.7 CONTRACT
The word "Contract" refers to the Contract Documents and shall include the Contract
Agreement entered into by the Owner and the Contractor for the performance of the
Works described in the Contract Documents and shown on the Drawings, together with
1 | Technical Specifications
the Invitation for Bids, Information for Bidders, the Bid Form, information Required of
Bidders, Basic Contract, the General Conditions, the Special Provisions, the General
Technical Specification, the Drawings, Appendices, Annexes, Schedules, all Addenda
issued by _______ with respect to the foregoing prior to the opening ofbids and all
Change Orders issued by the Engineer with the approval of_______ and signed by the
Contractor pertaining to the Contract after the same has been awarded.
1.8 SPECIFICATIONS
The word "Specifications" refers to the Special Provisions and the Technical
Specifications of the Contract, together with all addenda andchange orders issued with
respect thereto.
1.9 DRAWINGS
The words "Drawings" or "Contract Drawings" refer to those drawings accompanying the
Specifications and subsequently approved drawings, which show the locations, nature,
extent, and form of the Works, together with applicable detail.
1.10 WORK
The word 'Work" refers to labor, materials, equipment, transportation and all incidental
costs necessary to complete the Contract.
The words "Constructional Plant" refer to all appliances orthings of whatsoever nature
required for the execution, completion and maintenance of the Works or Temporary
Works (as hereinafter defined) but donot include materials or other things intended to
form or forming part of the Permanent Works.
The words "Temporary Works" refer to all works or structures of every kind which are
impermanent in nature or intended to serve/exist for a limited time only, required or the
execution, completion or maintenance of the Works.
1.13 SITE
The word "Site" refers to the lands and other places on, under, in or through which work is to
be executed or carried out and any other lands or places provided by the Owner for the
purposes of the Contract together with such other places as may be specifically designated In
the Contract as forming part of the Site.
1.14 APPROVAL
2 | Technical Specifications
The word "Approval" refers to concurrence including subsequent written confirmation of
previous verbal approval by the Engineer or _____________.
The term "Working Day'' refers to working days in the Government service. The term
"Calendar Day" refers to the days in a week, including Saturdays, Sundays and holidays.
Whenever the word "day" is used, it shall refer to calendar day.
1.16 ABBREVIATIONS
Whenever the following abbreviations are used, they shall have the meaning indicated:
3 | Technical Specifications
2 – SPECIFICATIONS, DRAWINGS AND RELATED DATA
a. The intent of the Specifications and Drawings is that the Contractor shall furnish all
the required construction plant, equipment, appliances, tools, labour, materials and
services unless otherwise specifically provided for.
b. The Specifications and Drawings are complementary and what is called for in one
shall be as binding as if called for in both.
i. Contract Agreement;
ii. Instructions to Bidders;
iii. Addenda to the Bidding Documents;
iv. Specifications
v. Drawings
vi. Special Condition of Contract
vii. Any other document listed in the SCC asforming part of this Contract.
b. All shop drawing submittals shall be accompanied by a transmittal form using the
format bound with the Contract Documents. Any shop drawing submittal not
accompanied by such form, or where all applicable items on the form are not
4 | Technical Specifications
completed, will be returned for re-‐submittal. The Contractor may authorize a
material or equipment supplier to deal directly with the ______ with regard to
shop drawings; however, ultimate responsibility for the accuracy and completeness
of the information contained in thesubmittal shall remain with the Contractor.
c. A separate transmittal form shall be used for each specific item or class of material
or equipment for which a submittal is required. Transmittal of shop drawings on
various items using a single transmittal form will be permitted only when the items
taken together constitute a manufacturer's "package" or are so functionallyrelated
that expediency indicates review of the group or package as a whole. At hisoption
the Contractor may obtain from ________ quantities of the shop drawing
transmittal form at reproduction cost.
d. Within fifteen (15) calendar days after receipt of said prints, the Engineer will return
prints of each drawing to the Contractor with his comments noted thereon.
Whenever a re-‐submittal is required. the Contractor shall make a complete
acceptable submittal to ________ within ten (10) days from receipt of the returned
shop drawings. Non-‐compliance hereof will give rise to the administration right to
either (a) cancel the award, or (b) withhold the money due the contractor, to cover
additional cost of the Engineer’s review beyond the second submission. Such failure
may be considered a factor against Contractor's competence in future biddings to
be conducted by theAdministration.
e. If three (3) prints of the drawing are returned to the Contractor marked "NO
EXCEPTIONS TAKEN," formal revision of said drawing will not be required.
f. If three (3) prints of the drawing are returned to the Contractor marked "MAKE
CORRECTIONS NOTED," formal revision of the drawing will not be required.
g. If one (1) print of the drawings is returned to the Contractor marked "AMEND- ‐
RESUBMIT," the Contractor shall revise the drawing and shall resubmit eight (8)
copies of the revised drawing to the Engineer.
h. If one (1) print of the drawings is returned to the Contractor marked "REJECTED - ‐
RESUBMIT, the Contractor shall revise the drawing and shall resubmit eight (8)
copies of the revised drawing to the Engineer.
i. Fabrication of an item shall not be commenced before the _____ has reviewed the
pertinent shop drawings and returned copies to the Contractor marked either "NO
EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED." Revisions indicated on the
shop drawings shall be considered as changes necessary to meetthe requirements
of the Contract Drawings and Specifications and shall not be taken as thebasis of
5 | Technical Specifications
claims for extra work. The Contractor shall have no claim for damages or extension
of time due to any delay resulting from the Contractor having to make the required
revisions to shop drawings (unless review by ____ of the drawings is delayed
beyond a reasonable period of time and unless the Contractor can establish that the
_______ delay in review actually resulted in a delay in the Contractor's
Construction schedule. The review of the drawings by ______ will be limited to
checking for general agreement with the Specifications and Drawings, and shall in
no way relieve the Contractor of responsibility for errors or omissions contained
therein nor shall such review operate to waive or modify any provision contained in
the Specifications or Contract Drawings. Fabricating dimensions, quantities of
material, appllcab1e code requirements, and other Contract requirements shallbe
the Contractor's responsibility.
All cost involves in making laboratory test of the sample submitted as substitute for the
specified material shall be borne by the contractor.
The Owner will furnish the Contractor with three (3) sets of Specifications together with
reduced drawings (if any) and three (3) sets of full- ‐scale drawings. Additional quantities
of the Specifications and Drawings will be furnished at reproduction cost.
6 | Technical Specifications
3 – EARTHWORKS
3.1 GENERAL
The Contractor shall perform all earthworks required and shown on drawings.
3.3 EXCAVATION
a. General
Except when specifically provided to the contrary, excavation shall include the
removal of materials of whatever nature encountered, including all obstructions of
any nature that would interfere with the proper execution and completion of the
work. The removal of said materials shall conform to the lines and grades shown or
ordered. Unless otherwise provided, the entire construction site shall be stripped of
all vegetation and debris, and such materials shall be removed from the site prior to
performing any excavation or placing any fill. The Contractor shall furnish, place and
maintain all supports and shoring that may be required for the sides of the
excavations, and all pumping, ditching, or other approved measures for the removal
or exclusion of water, including taking care of storm water and waste water reaching
the site of the work from any source, so as to prevent damage to the work or
adjoining property.
The walls and faces of all excavations in which workers are exposed to danger from
unstable ground shall be guarded against by a shoring system, sloping of the
excavation, or some other acceptable method. The Contractor shall furnish, install,
and maintain such sheeting, bracing, etc, as may be necessary to protect the workers
and to prevent any movement of earth which could injure or delay the work or
endanger adjacent structures. In excavations where workers may be required to
enter, excavated or other materials shall be effectively stored and retained at least
600mm or more from the edge of the excavation. All excavation and trenching
operations shall conform to any and all national,provincial and local requirements.
7 | Technical Specifications
slab. Where shown, or ordered, areas beneath proposed structures shall be over-‐
excavated. When such over-‐excavation is shown on the Drawings, both over- ‐
excavation and subsequent backfill to the required grade shall be performed by the
Contractor at his own expense. When such over- ‐excavation is not shown, but is
ordered by the Engineer, such over- ‐ excavation and any resulting backfill will be
paid for under a separate unit price bid item if such bid item has been established;
otherwise, payment will be made in accordance with negotiated prices. After the
required excavation or over-‐excavation has been completed, the exposed surface
shall be scarified to a depth of 150 mm (6 in.) brought to optimum moisture content,
and rolled with heavy compaction equipment to ninety- ‐five percent (95%) of
maximum density.
Excavation under areas to be paved shall extend to the bottom of the aggregate base,
if such base is called for; otherwise, it shall extend to the bottom of paving. After the
required excavation, has been completed, the exposed surface shall be scarified,
brought to optimum moisture content, and rolled with heavy compaction equipment
to ninety percent (90%) of maximum density.
1. General
Unless otherwise shown or ordered, excavation for pipelines shall be open- ‐cut
trenches. The bottom of the trench, including any shoring, shall have a minimum
width equal to the outside diameter of the pipe plus 300 mm (12in.) and a
maximum width equal to the outside diameter of thepipe plus 600 mm (24 in.).
Except when otherwise shown or ordered by the Engineer, the bottom of the
trench shall be excavated uniformly to the grade of the bottom of the pipe. The
trench bottom shall be given a final trim using a string line for establishing grade,
such that each pipe section when first laid will be wholly in contact with the
ground or bedding along the extreme bottom of the pipe. Rounding out the
trench to form a cradle will not be required. The maximum length of open trench
permitted at any one time and in one location shall be 300 meters, or the length
necessary to accommodate the amount of pipe installed in single day, whichever
is greater. All newly laid pipes shall be backfilled at least 150 mm (6 in.) above the
top of the pipe at the end of each day. The remainder of the trench shall be
backfilled not later than the following day. Barricades and warning lights
satisfactory to the Engineer shall be provided and maintained for all trenches left
open overnight except at intersections and driveways in which case heavy steel
plates, adequately braced bridges or other type of crossing capable of supporting
vehicular traffic shall be furnished as directed by the Engineer.
8 | Technical Specifications
The trenches shall be over-‐excavated where shown, to the depth shown, then
backfilled to the grade of the bottom of the pipe with suitable selected granular
material or with sand. Said backfill shall be broughtto the optimum moisture
content and compacted to ninety- ‐five percent (95%) of maximum density under
proposed structures, and ninety percent (90%) elsewhere.Work specified in this
Clause shall be performed by the Contractor at his own expense.
Any over-‐excavation carried below the grade ordered, specified, or shown shall
be refilled to the required grade with suitable selected granular material by the
Contractor at his own expense. Such material shall be moistened as required and
compacted to ninety-‐five percent (95%) of maximum density under structures
and ninety percent (90%) elsewhere.
The Contractor shall remove and dispose all excess excavated material at his
own expense and in a manner approved by the Engineer.
9 | Technical Specifications
g. Excavation in Lawn Areas
Where pipeline excavation occurs in the lawn area, the sod shall be carefully
removed and stockpiled to preserve it for replacement. Excavated material from
the trench may be placed on the lawn provided a drop cloth or other suitable
method is employed to protect the lawn from damage. The lawn shall not remain
covered for more than seventy- ‐two 72) hours. Immediately after completion of
backfilling and testing of the pipeline, the sod shall be replaced in a manner so as
to restore the lawn as near as possible to its original condition.
Except where trees are shown on the drawings to be removed, trees shall be
protected from injury during construction operations; and no tree is to be
removed without written permission from the Engineer. No tree roots over
50mm (2in.) in diameter shall be cut without the permission from the Engineer.
Trees shall be supported during excavation as may be directed by the Engineer.
i. Rock Excavation
Rock excavation shall include removal and disposal of any kind of rock which
cannot be excavated without blasting or the use of rippers, and all boulders or
other detached stones each having a volume of 0.25 cubic meter or more as
determined by physical measurements by the Engineer.
After the reservoir area has been stripped of all vegetation and debris as
specified in Clause (a) herein, loam and topsoil from the top 60 cm (24 in.) of
excavated soil shall be removed and stockpiled for possible lateruse as fill on or
around the reservoir and for miscellaneous topsoil. Excavation under the
reservoir shall extend to tile bottom of the drain rock layer. After such excavation
has been completed, the exposed surface shall be rolled with heavy compaction
equipment to provide a, reasonably smooth surface for the placement of the
drain rock. Areas under the reservoir upon which earth fill is to be placed shall be
scarified to a depth of 15cm (6 inch) brought to optimum moisture content and
compacted to ninety five percent (95%) of maximum density.
3.4 BACKFILL
a. General
Backfill shall not be dropped directly upon any structure or pipe. Materials used for
backfill shall be selected material, free from grass, roots, brush or other vegetation.
or rocks having maximum dimension larger than 150 mm (6 in.). Material placed
within 150 mm (6 in.) of any structure or pipe shall be free of rocks or unbroken
10 | Technical Specifications
masses or earth materials having maximum dimension larger than 75 mm (3 in.).
Backfill shall not be placed around or upon any structure until the concrete has
attained sufficient strength to withstand the loads imposed. Backfill around water-‐
retaining structure shall not be placed until the structures have been tested, and the
structures shall be full of water while backfill is being placed.
1. Pipeline trenches shall be backfilled to a level of 150 mm (6 inch.) above the top
of the pipe with selected material obtained from the excavation; if, in the
Engineer's opinion, said material is unsuitable for backfill purposes, borrow
material having the sand equivalent value of not less than twenty (20) (ASTM,D-‐
2419) shall be used for this portion of the trench backfill. Borrow material,
when ordered by the Engineer, will be paid for under a separate unit price item if
such bid item has been established otherwise, payment will be made in
accordance with a negotiated price. Selected material shall first be brought up to
mid-‐diameter of the pipe and compacted; then the remainder of the backfill to
150 mm (6 in.) above the pipe may be placed and compacted. Such material shall
be compacted to ninety-‐five percent (95%) of maximum density where the
trench is located under proposed structures, and ninety percent (90%) of
maximum density elsewhere. Compaction shall be obtained by tamping in not
more than 150mm (6 in.) layers or by using excess water and passing a concrete
vibrator between the pipe and side of trench, in case of sand formation as
determined and allowed by the Engineer.
2. After the initial portion of backfill has been placed as specified above, the
remainder of the trench shall be backfilled. When compaction of the initial
portion of backfill is obtained with excess water, not less than four (4) hours shall
have elapsed between the placement of initial backfill and subsequent backfill.
The remainder of the backfill shall be selected material obtained from the
excavation and shall be placed in horizontal layers. Each layer shall be no more
than 150 mm (6 in.) in depth. Layers shall be moistened, tamped, puddled, rolled,
or otherwise compacted to:
11 | Technical Specifications
i. Ninety-‐five percent (95%) of maximum density where the trench is located
under proposed structures;
ii. ninety percent (90%) of maximum density where trench is located under
existing or proposed asphalt or concrete surface;
iii. eighty percent (80%) of maximum density where the trench is located under
unpaved shoulders, gravel roadways or dirt roads;
iv. one hundred percent (100%) of the natural density of the surrounding areas
where the trench is located in unimproved right-‐of-‐way.
If the backfill material is sandy or granular in nature and the trench is not located
under a structure, the layer construction may be eliminated; and compaction may be
obtained by flooding and jetting, provided this latter method is approved by the
agency having jurisdiction over the highway or street. If flooding and jetting are
permitted, the remaining backfill shall be placed in layers not exceeding 900 mm (36
in.) thickness. Each layer shall be flooded, jetted and rodded to secure complete
saturation of the material before placing the next layer.
When shown on the drawings, drain rock shall be provided in accordance with the
following provisions:
2. Drain rock shall be clean gravel or crushed stone and shall be durable and free
from slaking or decomposition under the action of alternate wetting and drying.
It shall be uniformly graded and of such size that the percentage by weight, as
determined by the "Standard Method of Test for Sieve Analysis of Fine and
Coarse Aggregates" (ASTM C136), shall conform with the following grading:
The drain rock shall have a sand equivalent of not less than seventy-‐five (75)
as determined by ASTM D-‐2419.
12 | Technical Specifications
3. The drain rock shall be thoroughly moistened and compacted with at least two
(2) passes using approved plate or roller type vibratory compacting equipment.
The surface of the drain rock immediately beneath the reservoir shall be
stabilized with hot applied liquid asphalt after the surface of the drain rock has
been finish graded. The Contractor shall use, at his option, one of the two types
of asphalt listed below.
Type 1 Type 2
Designation MC 70 MC 250
Spray Temperature 57–79 74–93
Coverage 2.3L/m2 2.3L/m2
Backfill around reservoir walls shall consist of selected material obtained from the
excavation, and shall be placed in uniform layers not more than 200 mm (6 in.) in
thickness before compaction where compaction is attained by means of sheepsfoot
rollers, pneumatic type rollers or any approved heavy compaction equipment. Where
the use of this equipment is impractical, the layers shall not exceed 150 mm (6 in.) in
thickness before compaction shall be attained by means of hand-‐operated power-‐
driven tampers. The backfill shall be brought up evenly with each layer moistened
and compacted by mechanical means to ninety percent (90%) of maximum density.
Flooding, ponding, or jetting will not be permitted. Backfill around the reservoir walls
shall not be placed until after the reservoir has been tested for leakage. The reservoir
shall remain filled with water while said backfill is being placed. Loaded carryalls or
vehicles weighing more than 4,500 kg (9,900 lb) when loaded shall not be permitted
closer to the walls than a horizontal distance equal to the depth of the fill at that
time.
Fill shall not be deposited on the roof of the reservoir earlier than thirty (30) days
after the entire roof slab has been placed. The earth shall be placed in layers. Mobile
equipment weighing more than 4,500 kg (9,900 lb) when loaded will not be permitted
to travel over the completed roof. Fill on the roof shall be moistened as required and
compacted to a maximum density of ninety percent (90%) using a roller weighing not
more than 3,600 kg. Vibrating compaction equipment shall not be used on the
reservoir roof. The top 150 mm (6 in.) of fill on the reservoir roof shall consist of
loamy earth, free of rocks larger than 25 mm (1 in.) in maximum diameter.
g. Embankment Fill
13 | Technical Specifications
thickness, as measured before compaction, where compaction is attained by means
of sheepsfoot rollers, pneumatic type rollers or any approved heavy compaction
equipment. Where the use of this equipment is impracticable, the layers shall not
exceed 150 mm (6 in.) in thickness before compaction; and compaction shall be
attained by means of hand-‐operated power-‐driven tampers. The backfill shall be
brought up evenly with each layer moistened and compacted by mechanical means
to ninety-‐five percent (95%) of maximum density under proposed structures, and
ninety percent (90%) of maximum density elsewhere. The top 500 mm (20 in) of
backfill or embankment shall consist of loamy earth free of rocks larger than 25mm
in maximum dimension.
Unless otherwise specified, all embankment slopes steeper than three (3) units
horizontal to one (1) unit vertical shall be stabilized by sodding as directed by the
Engineer. Strips of sod not less than 300 mm (12 in.) wide shall be placed along
sloped banks.
Sods shall be taken only from fields not less than three (3) years old and have been
previously rolled and mowed at least once. Sods taken from wild field that have not
been mowed will not be acceptable. Sod shall be of sufficient thickness to prevent
excessive breakage and shall be stripped in the largest practicable widths and
lengths. It shall be tamped in place, properly leveled and immediately well-‐
sprinkled. All sods not in good condition after being tamped in place shall be
removed and replaced.
Immediately after setting of grass sod, sod shall be covered with 6 mm (0.24 in.) of
screened topsoil which has been well- ‐mixed with 460 grams (1 lb) of grass seed per
100 square meters (1,076 ft2). Sod shall be replaced with the same kind of surfacing
or better in accordance with the latest specifications; re- ‐sodding shall continue until
acceptance.
14 | Technical Specifications
4 – REINFORCED CONCRETE
The work to be undertaken under this Clause shall include all labor, materials, equipment,
plant and other facilities and the satisfactory performance of allwork necessary to complete
all concrete work shown on the Drawings and specified herein. All work included under this
Clause shall be subject to the General Conditions accompanying these specifications. The
Contractor is required to refer especially thereto.
4.2 MATERIALS
a. Cement
b. Concrete-‐Aggregates
2. The maximum size of the aggregates shall not be larger than one- ‐fifth (1/5) of
the narrowest dimension between forms and not larger than three- ‐fourths
(3/4) of the minimum clear spacing between individual reinforcingbars, or
bundles of bars, and in no case larger than 38 mm (1- ‐1/2 in.) in diameter except
that larger diameters may be allowed in massive concreting with written
permission from the Engineer.
c. Water
Water used in mixing concrete shall be clean and free from injurious amounts of oils,
acids, alkali, organic materials, or other substances that may be deleterious to
concrete or steel. ·∙
d. Reinforcing Steel
All reinforcing steel bars used shall be of deformed type, new, free from rust, oil,
defects, greases, or kinks. They shall conform with the latest edition of theNational
Structural Code for Buildings with a minimum grade equal to 275. MPa unless
otherwise shown on the plans.
e. Admixture
15 | Technical Specifications
At the Contractor's option or at the request of the Engineer, but in either case at tile
expense of the Contractor, an admixture may be added to the concrete to control the
set, effect water reduction, and increase workability. Such admixture may be either a
hydroxylated carboxylic and acid type or a hydroxylated polymer type, but shall
contain no calcium chloride. The required quantities of cement shall be used in the
mix regardless of whether or not any admixture is used. The quantity of admixture
used and the method of mixing shall be in accordance with the manufacturer’s
instruction. Where the air temperature at the time of placement si expected to be
consistently over 26.7oC, (80°F), such admixture shall be Super Concrete Emulsions
"Plastiment", ''Master Builders's", "Pozzolith 300R", or substitute
f. Calcium Chloride
Except as otherwise specified for Architectural finish, the use of calcium chloride in
concrete will not be permitted.
a. Concrete for structural elements, including slabs on grade within water- ‐retaining
structures and stairs shall develop a minimum 28- ‐day compressive cylinder
strength of20.68 megapascal (3,000 psi), unless otherwise specified in the plans.
16 | Technical Specifications
c. Leveling concrete under reservoir base slabs/foundations shall have a minimum 28-‐
day cylinder strength of 14 MPa (2,000) psi.
The Contractor shall submit design mixes and test results of samples made in
accordance with "Standard Method of Making and Curing Concrete Compression and
Flexure Test Specimens in the Laboratory" (ASTM C- ‐192-‐Latest Revision) and
"Standard Method of Test for Compressive Strength of Molded Concrete Cylinders"
(ASTM Designation C-‐39) for each strength required, stating the proposed slump
and the proportional weights of cement, saturated surface dry aggregates, and
water. These mixes shall be proved by preliminary tests thirty (30) days before
concreting and shall show a 28- ‐day strength of fifteen percent (15%) higher than the
ultimate strength required. No substitution shall be made in the materials or mixed
without additional tests to show that the quality of concrete is satisfactory.
a. The methods of measuring concrete materials shall be such that the proportions
can be accurately controlled and easily checked at any time during the work.
Measurement of materials for ready-‐mixed concrete shall conform to the
"Standard Specifications for Ready- ‐mixed Concrete" (ASTM C-‐94, Latest
Revision) where applicable.
b. Aggregates shall be measured out by weight and to within one percent (1%).
Cement shall conform to 40 kg (88 lb) per bag and this is to be verified from time
to time. Water shall be measured by weight or volume to within one and one-‐
half percent (1-‐1/2 %).
c. The water shall in no case exceed 21.24 litres, and 25.67 litres (5.62 and 6.79 US
gallons) per bag of cement for all concrete with specified strength of fc=20.68
MPa (3000 psi) and 17.25 MPa (2500 psi), respectively. Slumps shall be within the
following limits:
17 | Technical Specifications
d. The minimum cement content for 20.68 MPa (3000 psl) concrete shall be 8.39
sacks per cubic metre of concrete.
e. Job mix adjustments on water content shall be allowed only with Engineer's
permission and provided that cement is also added to maintain the original
water-‐cement ratio of the design mix.
No concrete shall be placed in any structure until all water entering the space to be
filled with concrete has been properly cut off or has been diverted by pipes, or other
means, and carried out of the forms, clear of the work. No concrete shall be
deposited under water without the explicit permission of the Engineer, and then only
in strict accordance with his directions; nor shall the Contractor, without explicit
permission, allow still water to rise on any concrete until the concrete has attained its
initial set. Water shall not be permitted to flow over the surface of any concrete in
such manner and at such velocity as will injure the surface finish of the
concrete. Pumping or other necessary dewatering operations for removing ground
water, if required, will be subject to the approval of the Engineer.
b. The mixer shall be of an approved size and type which will insure a uniform
distribution of material throughout the mass, It shall be equipped with a device
for accurately measuring and controlling the amount of mixing water in each
batch.
c. The first batch of concrete materials placed in the mixer shall contain a sufficient
excess of cement, sand, and water to coat the inside of the drum without
reducing the cement of the mix to be discharged.
d. Retempering, i.e. remixing with the addition of water to concrete that has been
partially hardened will not be permitted.
a. Earth surfaces shall be thoroughly wetted by sprinkling prior to the placing of any
concrete, and these surfaces shall be kept moist by frequent sprinkling up to the
time of placing concrete thereon. The surface shall be free from standing water,
mud, and debris at the time of placing concrete.
18 | Technical Specifications
b. Concrete surfaces upon or against which concrete is to be placed, where the
placement of the old concrete has been stopped or interrupted so that, in the
opinion of the Engineer, the new concrete cannot be incorporated integrally with
that previously placed, are defined as construction joints. The surfaces of
horizontal joints shall be leveled with a wooden float to provide a reasonably
smooth surface. A surface consisting largely of coarse aggregate shall be avoided.
Except where the drawings call for joint surfaces to be painted, the joint surfaces
shall be cleaned of all laitance, loose or defective concrete and foreign material.
Such cleaning shall be accomplished by sandblasting followed by thorough
washing. All pools of water shall be removed from thesurface of construction
joints before the new concrete is placed. After the surfaces, have been prepared
to the satisfaction of the Engineer, all approximately horizontal construction
joints shall be covered with a layer of mortar approximately 25 mm (1 in.) thick.
The mortar shall have the same proportion of cement and sand as the regular
concrete mixture, unless otherwise directed by the Engineer. The water- ‐cement
ratio of the mortar in place shall not exceed that of the concrete to be placed
upon it, and the consistency of the mortar shall be suitable for placing and
working in a manner hereinafter specified. The mortar shall be spread uniformly
and shall be worked thoroughly into all irregularities of the surface, and wire
brooms shall be used where possible to scrub the mortar into the surface.
Concrete shall be placed immediately upon the fresh mortar.
c. When the placing of concrete is to be Interrupted long enough for the concrete
to take a set, the working face shall be given a shape by the use of forms or other
means that will secure proper unionwith subsequent work, provided that
construction joints shall be made only where approved by the Engineer.
a. Concrete which upon or before placing is found not to conform with the
requirements specified herein shall be rejected and immediately removed from
the work. Concrete which is not placed in accordance with these specifications,
or which or which is of inferior quality asdetermined by the Engineer, shall be
removed and replaced by and at the expense of the Contractor. No concrete shall
be placed except in the presence of a duly authorized representative of the
Engineer. Concrete shall not be placed when unsuitable heat or wind conditions
will prevent proper placement and curing as determined by the Engineer. Prior to
placing any concrete, the Contractor shall give the Engineer twenty- ‐four (24)
hours written notice.
c. Placing of concrete with a free drop or fall more than 1.20meters (4 ft) shall not
be allowed, except when approved by the Engineer and when approved sheet
19 | Technical Specifications
metal conduits, pipes, or "elephant trunks" are employed. When employed,
these conveyors shall be kept full of concrete and the ends kept buried in the
newly placed concrete as pouring progresses.
4.12 FORMS
a. General
The Contractor shall provide forms to confine the concrete and shape it to the
required lines. Plastering, in general, shall not be allowed. The Contractor shall
assume full responsibility for the adequate design of all forms. However, forms
which in the opinion of the Engineer are unsafe or inadequate in any respect may
at any time be condemned by the Engineer; and the Contractor shall promptly
remove the condemned forms from the work and replace them at his own
expense. A sufficient number of forms of each kind shall be provided to permit
the required rate of progress to be maintained. Whenever, in the opinion of the
Engineer, additional forms are necessary to maintain the progress schedule, such
additional forms shall be provided by the Contractor at his own expense. The
design and inspection of concrete forms, falsework, and shoring shall comply with
applicable safety regulations, and as may be specified in the General Condition£
of these Specifications.
b. Materials
All forms shall be smooth surface forms and shall be of the following materials:
20 | Technical Specifications
d. All girder, beam, and slab centerlines shall be crowned 6.3 mm in all directions
for every 4.5-‐meter span. However, cambers from all cantilevers shall be as
indicated on the plans or obtained from the Engineer by the Contractor.
For exposed corner columns and /or piers, control joint grooves andother
conspicuous lines:
3. Footings
4. Variation in steps:
In a flight of steps
Rise 3.2 mm (1/8”)
21 | Technical Specifications
Rise 1.6mm (1/16”)
Tread 3.2mm (1/9”)
When required for another work, or when requested bby the Owner or his
Engineer, the Contractor shall remove or relocate shoring; but existing
shoring shall not be disturbed until new shores are set in position.
f. Design
1. All forms shall be true in every respect to the required shape and size shall
conform to the established alignment and grade and shall be at sufficient
strength and rigidity to maintain their position and shape under the loads
and operations incident to placing and vibrating the concrete. Suitable and
effective means shall be provided on all forms for holding adjacent edges
and ends of panels and sections tightly together and in accurate alignment
so as to prevent the formation of ridges, fins, or offsets, or similar surface
defects in the finished concrete. Plywood, 16.0 mm (5/8 in.) and greater in
thickness, may be fastened directly to studding if the studs are close
enough to prevent visible deflection marks in concrete. The forms shall be
light so as to prevent the loss of water, cement, and fins during placing and
vibrating of the concrete. Adequate clean-‐out holes shall be provided at
the bottom of each lift of forms. The size, number, and location of such
clean-‐outs shall be subject to the approval of the Engineer.
4. Reservoir forms and falsework supporting the roof slab shall be designed
for a minimum additional live load or 0.96 KPa (20 psf).
g. Form Ties
Form ties with integral water stops shall be provided with a cork or other
suitable means for forming a conical hole to ensure that the form- ‐tie may be
broken off back of the face of the concrete. The maximum diameter or
removable cones for rod ties, or of other removable form- ‐tie fasteners having
a circular cross-‐section, shall not exceed 38 mm (1- ‐1/2in.) and all such
fasteners shall be such as to leave holes of regular shape for reaming. Holes
22 | Technical Specifications
left by the removal of fasteners from the ends of snap- ‐ties or form-‐ties all be
reamed with suitable toothed reamers so as to leave the surfaces of the holes
clean and rough before being filled with mortar as provided in Clause 4.20.
Wire ties for holding forms will not be permitted. No form tying device or part
thereof, other than metal, shall be left embedded in the concrete, nor shall any
tie be removed in such manner as to leave a hole extending through the interior
of the concrete member. The use of snap-‐ties which cause spalling of the
concrete upon form stripping or lie removal will not be permitted. If steel panel
forms are used, rubber grommets shall be provided where the ties pass through
the form in order lo prevent loss of cement paste. Where metal rods extending
through the concrete are used to support or to strengthen forms. the rods shall
remain embedded and shall terminate not less than 25 mm (1 in.) back from the
formed face or faces of the concrete. Form ties or metal rods left embedded in
concrete of water-‐ retaining tanks shall be equipped with an integral metal
waterstop of not less than 38 mm (1-‐1/2 in.) in diameter.
h. Vertical Surfaces
i. Maintenance of Forms
23 | Technical Specifications
surfaces of hydraulic structures, unused tie rod holes shall be covered with
metal caps or shall be filled by other methods approved by the Engineer.
j. Removal of Forms
a. General
24 | Technical Specifications
designated to receive a sealant fillet shall be thoroughly cleaned, as outlined for
the tapered grooves, prior to application of the sealant. The sealant shall be
polyurethane polymer designed for bonding to concrete which is continuously
submerged in water. No material will be acceptable which has an unsatisfactory
history as to bond or durability when used in the joints of hydraulic structures.
Prior to ordering the sealant material, the Contractor shall submit to the
Engineer for approval sufficient data to show general compliance with the
specification requirements. The material shall meet the following
requirements:
3. Following the curing period, the gap between blocks shall be widened to
31.7 mm (1-‐1/4 in.). Spacers shall be used to maintain this gap for
twenty-‐ four (24) hours prior to inspection for failure.
25 | Technical Specifications
c. Waterstops
2. Qualification Samples
26 | Technical Specifications
Engineer for approval. These samples shall be fabricated so that the
material and workmanship represent in all respects the fittings to be
furnished under this Contract. Field samples of fabricated fittings (crosses,
tees, etc.) will be selected at random by the Engineer for testing by a
laboratory at the Owner's expense. When tested, they shall have tensile
strength across the joints equal lo at least 4.14 MPa (600 psi). Field splices
and joints shall be made in accordance with the waterstop manufacturer’s
instruction using a thermostatically-‐controlled heating iron.
4. Flat-‐Strip Waterstop
Where expansion joint filler is indicated on the drawings, the material shall be of
the performed non-‐extruding type joint filler which may be constructed of open
cellular sponge rubber, or closed cellular sponge rubber of firm texture.
Bituminous fiber type will not be permitted. All non- ‐extruding and resilient-‐
type performed expansion joint filers shall conform with the requirements and
tests set forth in "Specifications for Preformed Sponge Rubber and Cork
Expansion Joint Fillers for Concrete Paving and Structural Construction," Type
(ASTM Designation D-‐1752), except as otherwise provided herein.
Pipes, conduits, dowels and other ferrous items required to be embedded in concrete
construction shall be so positioned and supported prior to placement of concrete
that there will be a minimum of 50 mm (2 in.) clearance between said items and any
part of the concrete reinforcement. Securing such items in position by wiring or
welding these to the reinforcement will not be permitted.
a. The order of placing concrete in all parts of the work shall be subject to the
approval of the Engineer. In order to minimize the effects of shrinkage, the
27 | Technical Specifications
concrete shall be placed in units as bounded by construction joints shown on the
drawings. The placing of units shall be done by placing alternate units in a
manner such that each unit placed shall have cured at least seven (7) days before
the contiguous unit or units are placed except that vertical walls shall be placed
until the wall footings have cured at least fourteen (14) days, and the corner
sections of vertical walls shall not be placed until all the adjacent wall panels
have cured at least fourteen (14) days.
b. The surface of the concrete shall be level whenever a run of concrete is stopped.
To insure a level, straight joint on the exposed surface of walls, a
wood strip at least 19.0 mm (0.75 in.) thick shall be tacked to the forms on these
surfaces. The concrete shall be carried about 13.0 mm (0.50 in.) above the
underside of the strip. About one hour after the concrete is placed, the strip shall
be removed and any irregularities in the edge formed by the strip shall be leveled
with trowel.
b. Care shall be used in placing concrete around waterstops. The concrete shall be
carefully worked by rodding and vibrating to make sure that all air and rock
pockets have been eliminated. Where flat- ‐strip type waterstops are used, the
concrete shall be worked under the waterstops by hand, making sure that all air
and rock pockets have been eliminated.
c. Concrete in walls shall be internally vibrated and at the same time rammed,
stirred, or worked with suitable appliances, tamping bars, shovels, or forked tools
until it completely fills the forms or excavations and closes snugly against all
surfaces. Subsequent layers of concrete shall not be placed until the layers
previously placed have been worked thoroughly as specified. Except in special
cases where their use is deemed impracticable by the Engineer, the Contractor
shall use internally vibrated, high speed power vibrators not less than 8000 rpm
of an approved immersion type in sufficient numbers, with standby units as
required, to accomplish the results herein specified within fifteen (15) minutes
after concrete of the prescribed consistency is placed in the forms. The vibrating
head shall be kept from contact with the surfaces of the forms. Care shall be
taken not to vibrate concrete excessively or to work it in any manner that causes
segregation of its face.
a. General
28 | Technical Specifications
All concrete shall be cured for not less than fourteen (14) days after placing, in
accordance with the methods specified herein for the different parts of the
work, and described in detail in the following Clauses.
b. Method 1
Wooden forms shall be wetted immediately after concrete has been poured and
shall be kept wet with water until removed. If forms are removed within
fourteen (14) days of placing the concrete, curing shall be continued in
accordance with the applicable method for the particular structure as set out in
Methods 2, 4, 5 and 6 below.
c. Method 2
The surface shall be covered with burlap mats which shall be kept wet with water
for the duration of the curing period, until the concrete in the walls has been
placed. No curing compound shall be applied to surfaces cured under Method 2.
d. Method 3
The surface shall be covered with moist earth, not less than four (4) hours nor
more than twenty-‐four (24) hours after the concrete is placed.
e. Method 4
1. The surface shall be sprayed with a liquid curing compound which will not
affect the bond of paint to the concrete surface. It shall be applied in
accordance with the manufacturer's instructions at a maximum coverage
rate of 4.91 m /L (200 fl /gal) in such manner as to cover the surface with a
uniform film which will seal thoroughly.
29 | Technical Specifications
2. Where the curing compound method is used, care shall be exercised to avoid
damage to the seal during the curing period. Should the seal be damaged or
broken before the expiration of the curing period, the break shall be repaired
immediately by the application of additional curing compound over the
damaged portion.
f. Method 5
Immediately after the concrete has been troweled, it shall be given 3 coat of
curing compound in accordance with Clause (e) herein. Not less than one (1)
hour or more than four (4) hours after the coat of curing compound has been
applied, the surface shall wetted with water delivered through fog nozzle and
concrete curing blankets shall be placed on the slabs. The curing blankets shall
consist of one of the following two types:
1. Sheets of clear polyethylene having a thickness of not less than six (6) mils
laid with edges butted together and with the joints between sheets sealed
with 25 mm (1 in.) wide strips or acetate tape.
The curing blankets shall be left in place during the 14- ‐day curing and shall not
be removed until after concrete for adjacent work has been placed. Should the
curing blankets become torn or otherwise ineffective, the Contractor shall
replace damaged sections. During the first seven (7) days of the curing period, no
traffic of any nature and no depositing, temporary or otherwise, of any materials
shall be permitted on the curing blankets. During the remainder of the curing
period, foot traffic and temporary depositing of materials that impose light
pressure will be permitted only on top of plywood sheets 16 mm (5/8 in.)
minimum thickness laid over the curing blanket.
g. Method 6
30 | Technical Specifications
Application shall be in two coats. The first coat shall be diluted to 1/2
strength by the addition of water and shall be sprayed on so as to provide a
maximum coverage rate of 2.45 m /L (100 ft /gal) of dilute solution. The
second coat shall consist of an application of the specified material
undiluted, and hall be sprayed on to surface so as to provide a maximum
coverage rate of 2.45 m /L (100 ft /gal).
The Contractor shall protect all concrete against Injury or damage from excessive
heat, lack of moisture, overstress, or any other cause until final acceptance by
the Owner. Particular care shall be taken to prevent drying of concrete and to
avoid roughening or otherwise damaging the surface. Any concrete found to be
damaged or which may have been originally defective, or which becomes
defective at any time prior to the final acceptance of the complete work, or
which departs from the established line or grade, or which for any other reason
does not conform with the Specifications, shall be satisfactorily repaired or
removed and replaced with acceptable concrete at the Contractor's expense.
a. All finished or formed surfaces shall conform accurately with the shape, alignment,
grades and sections as indicated on the plans or as prescribed by the Engineer.
Surfaces shall be free from fins, bulges, ridges, offsets, honey- ‐combing, or
roughness of any kind, and snail present a finished, smooth, continuous hard surface.
a. As soon as forms are removed, all exposed surfaces shallbe carefully examined
and any irregularities shall be immediately rubbed or ground in a satisfactory
manner in order to secure a smooth, uniform, and continuous surface. Plastering
or coating of surfaces to be smoothed will not be permitted. No repairs shall be
made until after inspection by the Engineer, and then only in strict accordance
with his directions. Concrete containing voids, holes, honeycombing, or similar
depression defects shall be completely removed and
31 | Technical Specifications
replaced; provided that where required or approved by the Engineer, defects
shall be repaired with gunite or with cement mortar placed by an approved
compressed air mortar gun. In no case will extensive patching of honeycombed
concrete be permitted. All repairs and replacements herein specified shall be
promptly executed by the Contractor at his own expense.
c. Holes left by the tie-‐rod cones shall be reamed with suitable toothed reamers so
as to leave the surfaces of the holes clean and rough. These holes then shall be
repaired in an approved manner with dry- ‐packed mortar. Holes left by form- ‐
typing devices having a rectangular cross-‐section and other imperfections
having a depth greater than their least surface dimension shall not be reamed
but shall be repaired in an approved manner with dry-‐packed mortar.
d. All repairs shall be built up and shaped in such a manner thatthe completed work
will conform with the requirements of Clause 4.19 using approved methods
which will not disturb the bond, cause sagging or horizontal fractures. Surfaces of
said repairs shall receive the same kind and amount of curing treatment as
required for the concrete in the repaired section.
All prominently exposed exterior, vertical, above ground concrete surfaces shall be
given an architectural finish.
32 | Technical Specifications
b. Ready-‐mixed concrete shall be delivered to the site of the work, and discharge
shall be completed within one hour after the addition of the cement to the
aggregates or before the drum has been revolved 250 revolutions, whichever is
first. In hot weather, or under conditions contributing to quick stiffening of the
concrete, or when the temperature of the concrete is 29.44°C (85°F) or above,
the time between the introduction of the cement to the aggregated and
discharge shall not exceed forty-‐five (45) minutes.
c. Truck mixers shall be equipped with electrically- ‐actuated counters by which the
number of revolutions of the drum or blades may be readily verified. The counter
shall be of the resettable, recording type and shall be mounted in the driver's
cab. The counters shall be actuated at the time of starting mixers at mixing
speeds.
d. Each batch of concrete shall be mixed in a truck mixer for not less than seventy
(70) revolutions of the drum or blades at tile rate of rotation designated by the
manufacturer of the equipment. Additional mixing, if any, shall be at the speed
designated by the manufacturer of the equipment as agitating speed. All
materials including mixing water shall be in the mixer drum before actuating the
revolution counter for determining the number of revolutions of mixing.
e. Truck mixers and their operation must be such that the concrete throughout the
mixed batch as discharged is within acceptable limits of uniformity with respect
to consistency, mix and grading. If slump test taken at approximately the ¼ and ¾
points of the load during discharge give slumps differing by more than 25mm (1
in) when the specified slump is 76mm (3 in) or less, or if they differ by more than
50mm (2 in) when the specified slump is more than 76mm (3 in) the mixer shall
not be used on the work unless the causing condition is corrected and
satisfactory performance is verified by additional slump test. All mechanical
details of the mixer, such as water measuring and discharge apparatus, condition
of the blades, speed rotation, general mechanical condition of the unit, and
clearance of the drum, shall be checked before a further attempt ot use the unit
will be permitted.
g. The use of non-‐agitating equipment for transporting ready- ‐mixed concrete will
not be permitted. Combination truck and trailer equipment for transporting
ready-‐mixed concrete will not be permitted. The quality and quantity of
materials used in ready-‐mixed concrete and in batch aggregates shall be subject
to continuous inspection at the batching plant by the Engineer.
33 | Technical Specifications
a. General
The use of slip form in concrete work is optional for this project. However,
should the Contractor decide to adopt slipform in concreting, the
procedures/guidelines outlined below shall be followed.
b. Form Material
c. Depth of Forms
The effective depth of any slip form shall be a minimum of 1.00 m (39 in.) and a
maximum of 2.00 m (78 in.).
d. Yokes
The Contractor shall provide adequate bracing which shall be a part of the
working platform. Plywood not less than 19 mm (O.75 in.) thick may be used as
the working platform. The top of the working platform shall be in the same level
as the tops of the inside forms, to permitdirect shoveling of concrete from the
deck into the forms.
f. Jacking System
The Contractor shall use hydraulic lifting gear with hydraulic jacks bearing against
rods buried in the concrete. Alternately, the forms may be lifted by winches and
cable, rack and pinion, or hung from steel rods. Hydraulically operated jacks with
capacities ranging from 3000, 4500 and 600D kilograms shall be used. Jacks shall
be cylindrical in shape with a hole in the center through which the jack rod
passes, with two sets of jaws which alternately lift and grip.
g. Jack Rods
The Contractor shall use 25mm (1 in) diameter mild steel bars with threaded
ends for easy coupling for extension. Jack rods shall remain in place as part of the
reinforcement. Unsupported length of jack shall not be more than 0.60m on
maximum load. Where rods pass through large formed openings, they must be
braced adequately.
34 | Technical Specifications
A suitable process distribution system from a control hydraulic pump shall be
used. The Contractor shall operate all jacks at the same speed to give uniform
lift, care being taken that the jacks carry the same loads. All jacks shall be
provided with the same hydraulic pressure to avoid cases where some will lift
more slowly than the others.
To control the level of the forms during the jacking process, plastic pipes with
colored water may be used, care being taken to purge outor remove entrapped
air in the plastic pipe.
As jacking proceeds, provisions shall be made to limit any deviations from the
vertical. A plumb bob shall be used during the entire operation.
j. Reinforcement
The Contractor shall employ special techniques to form openings for doors, for
connections of beams and floors, and for provisions of nibs and haunches.
Toothed or dovetailed connections shall be used.
l. Handling Concrete
The Contractor shall use the common method for slipforming structural cores by
depositing the concrete on the working platform and shoveling it into its final
position. Crane and bucket or hoist and barrows may be used.
After the slip process has started, the workmen shall place the concrete
continuously around the structure in 150 mm to 220 mm (6 in. to 8.8 in.) layers
by shovelling same into forms. On ceasing concreting, the forms shall be kept
35 | Technical Specifications
moving to prevent formation of excessive adhesion. The "hack off ' process shall
involve jacking at a decreasing rate, about 2- ‐3 hours after placing or until the
freeboard is about 450 mm to 500 mm (18 in. to20 in). When concreting, the
workmen shall jack forms up about 25mm to 50mm (1 in. to 2 in.) before pouring
concrete.
After concreting has ceased, the exposed forms must be cleaned and oiled. Care
should be taken to prevent coating of reinforcing steel and spillage onto the set
concrete.
1. Finishing
Where small holes and depressions occur, a spongefloat to fill small holes shall
be used to improve the overallappearance of the finished surface.
2. Curing
Potable water shall be used for curing. Wherever possible, water shall be sprayed
directly onto the surface. The Contractor shall provide suitable and adequate
water supply at the working platform. Workers shall apply water to the concrete
surface intermittently. Where the finished structure is to be exposed to the
elements, the wetting action of rain to complete the cement hydration may be
used as a curing method.
Covering of the interior and exterior surfaces of the formed structure with plastic
sheets to keep the moisture always in contact with the concrete surface will be
an acceptable method of curing.
a. All reinforcement shall be placed in accordance with the plans furnished by the
Engineer. In case of any doubt or ambiguity in placing of steel, the Contractor
shall consult with the Engineer whose decision shall be final in such cases.
b. All loose rust or scale, all adhering materials, and all oil or other materials which
tend to destroy bond between the concrete and the reinforcement shall be
removed before placing the steel and before concreting begins.
36 | Technical Specifications
nor less than one and one- ‐third (1-‐1/3) times the maximum size of the coarse
aggregate. Where bars are used in two or more layers, the bars in the upper
layers shall be placed directly above those in the lower layers at a clear distance
of not less than 25 mm (1 in.).
d. Bends for stirrups and ties shall be made around a pin having a diameter not Jess
than six(6) times the minimum thickness of the bar, except that for bars larger
than 25 mm (1-‐in.), the pin shall not be less than eight {8) times the minimum
thickness of the bar. All bars shall be bent cold.
b. Where changes in the cross-‐section of a column occur, the longitudinal bars shall
be offset in a region where lateral support is afforded. Where offset, the slope of
the inclined portion of the bar with the axis of the column shall not be more than
one in six; in the case of tied columns, the ties shallbe spaced not over 76 mm (3
in.) on center for a distance of 300 mm (12 in.) below the actual point of offset
unless otherwise shown on the plans.
a. The Owner or the Engineer may require a reasonable number of tests on the
concrete to be made during the progress of the work. Not less than four (4)
cylindrical specimens shall be made for each test of which at least two (2) shall be
reserved for 28-‐day test. Not less than one test shall be made for every fifty
(50) cubic metres of concrete and in no case less than one test for each day's
concreting. Samples shall be secured and molded in accordance with "Standard
Method of Sampling Fresh Concrete" (ASTM C- ‐172 -‐ Latest Revision) and
"standard Method of Making and Curing Test Specimens in the Field" (ASTM C-‐
31 -‐ Latest Revision). Strength test shall be made in accordance with the
"Standard Method of Test for Compressive Strength of Cylindrical Concrete
Specimens" (ASTM C-‐39 -‐ Latest Revision).
37 | Technical Specifications
b. The Contractor shall provide the samples to be taken at the place of deposit and
as specified by the Engineer and shall also box samples for shipment, packing
them to prevent damage from sharp blows. The Owner or his duly authorized
representative shall transport the test cylinders to a laboratory for testing. The
owner shall pay costs of said transportation and testing of the samples.
d. Should the test fail to give the required strength, the Owner shall have the right
to order a change in the proportions or in the procedures of curing of the
concrete for the rest of the structure.
For failure to meet the specified strengths of concrete which has been designed,
prepared, and deposited by the Contractor, the Contractor shall pay the Owner as
liquidated damages, not: as Penalty or forfeiture, the following schedule applied on
the amount of concrete represented by the samples.
a. For concrete less than one hundred percent (100%) but greater than or equal to
ninety percent (90%) of specified strength, payment of ten percent (10%) of the
unit bid cost per cubic metre of concrete.
b. For concrete, less than ninety percent (90%) but greater than or equal to eighty
percent (80%) of specified strengths, payment of fifteen percent (15%) of the
unit bid cost per cubic metre of concrete.
c. For concrete, less than eighty percent (80%) of the specified strength, removal of
the concrete so deposited and the replacement of same at the expense of the
Contractor.
1. In any case of failure to meet specified strength, the Contractor may, at his
expense, obtain concrete core samples from the poured concrete and the
compressive strength of same, as determined by a competent testing
authority, shall be taken as conclusive evidence of its strength and integrity,
provided the coring will not impair the safety of the structure and can be
satisfactorily replaced.
2. To determine adequacy of affected parts, the Owner shall have the option to
order load tests on parts of the structure where concrete strength tests are
below eighty percent (80%) of specified. These tests shall be in
38 | Technical Specifications
accordance with ACl-‐318, latest revision; recommendations and their costs
shall be borne by the Contractor.
39 | Technical Specifications
5 -‐ STEEL AND MISCELLANEOUS METAL WORKS
5.1 GENERAL
a. The Contractor shall furnish, fabricate, and install all steel and miscellaneous
metalwork as specified herein and as shown in the drawings. Miscellaneous
metalwork is defined as all items required to be fabricated from structural steel
shapes, plates, bars, and their products. He shall provide the necessary labor,
supervision, tools, materials, supplies, and appurtenances for the proper
construction and operation of the elevated steel reservoir. The Contractor shall
accomplish the work in a complete and finished manner and insure the highest
quality of workmanship in accordance with the drawings and specifications and to
the satisfaction of the Engineer.
b. Structural steel straps, plates, bars and their products shall conform with the
"Standard Specifications for Structural Steel" (ASTM Designation A36).
d. All materials to be used shall be new, previously unused, and in first class condition.
Steel materials of unidentified analysis may be used, provided they are tested and
properly certified by a qualified testing laboratory.
g. Shop drawings for all steel and miscellaneous metalwork shall be submitted to the
Engineer for review in accordance with Clause ___ -‐ Shop Drawings.
h. The work and equipment to be provided by the Contractor under this Contract shall
conform with the U.S. Standards as mentioned in. the following clauses or with any
International Standards of equal value.
5.2 MATERIALS
a. Structural Shapes
40 | Technical Specifications
All structural shapes for use shall be produced by the open- ‐hearth, basic oxygen, or
electric-‐furnace process. Open or non-‐tubular structural shapes shall conform with
ASTM A36. When structural shapes are fabricated from steel plates, the plates shall
conform with Item (b).
b. Plates
1. The Contractor shall furnish and set all bolts, anchor bolts, rods and reinforcing
steel. Except where otherwise shown or specified, all bolts, anchor bolts,
washers, and nuts shall be steel, galvanized after fabrication in accordance with
Clause 5.3.
2. Except as otherwise provided herein, steel for bolts, anchor bolts, and cap
screws shall be in accordance with "Specifications for Low Carbon Steel
Externally and Internally Threaded Standard Fasteners," Grade B (ASTM
Designation A307), or "Specifications for Carbon Steel Bars Subject to Mechanical
Property Requirements" (ASTM Designation A306) or threaded parts of ASTM
A36 and shall meet the following additional requirements: (1) the nut material
shall be free-‐cutting steel, and(2) the nuts shall be capable of developing the full
strength of the bolts. Threads shall be Coarse Thread Series conforming with the
requirements of the American Standard for Screw Threads. All bolts and cap
screws shall have hexagon head and nuts shall be Heavy Hexagon Series.
3. Threads of galvanized bolts and nuts shall be formed with suitable taps and dies
such that they retain the normal clearance after hot-‐dip galvanizing.
4. Unless otherwise shown, all bolts, anchor bolls, and nuts which are buried,
submerged, or inside a covered hydraulic structure shall be Hot- ‐Dip galvanized
per TS-‐20 and then coated with two coats of coal tar epoxy after installation.
d. Ladders
All ladders shall be fabricated of carbon steel and galvanized after fabrication.
Steel pipe handrails shall be standard 38 mm (1- ‐1/2) in.) black steel pipe made up by
welding. Railing shall be shop- ‐fabricated into easily handled units and hot- ‐dip
galvanized after fabrication. Field welding of pipe handrail joints will be permitted
only if approved by the Engineer, and then only in accordance with his instructions.
41 | Technical Specifications
Submerged steel pipe shall be coated with two coats of coal tar epoxy after
installation.
f. Pipe Columns
Pipe column steel shall conform with the "Specifications for Welded and Seamless
Steel Pipe," (ASTM A53}, Grade B. Pipe columns that would be submerged shall be
coated with two coats of coal tar epoxy. ·∙
g. Metal Decking
Metal decking shall be of the size and gage shown in the drawings and shall meet the
requirements of the Specification for the "Design of Light Gage, Cold-‐formed Steel
Structural Members" of the American Iron and Steel Institute. The steel shall be
galvanized after fabrication.
Aluminum safely stair treads 100 mm (4 in.} wide shall be provided on all stairs, and
elsewhere where shown.
1. General
Metal grating and floor hatches shall be of the design, sizes, and types shown.
Aluminum in contact with other metals or concrete shall be painted with one (1)
coat of zinc chromate and two (2) coats of approved aluminum metal-‐and-‐
masonry paint.
2. Metal Grating
3. Floor Hatches
42 | Technical Specifications
j. Iron Castings
Iron castings shall conform with the "Specifications for Gray Iron Casting" (ASTM
A48), unless otherwise shown.
Seat angles for grating shall be aluminum or steel as shown and of a size as shown.
Guides for slide gates shall be steel, of a size shown, hot- ‐dip galvanized after
fabrication.
5.3 GALVANIZING
All structural steel places, shapes, bars, and fabricated assemblies required to be
galvanized shall, after the steel has been thoroughly cleaned of rust and scare, be
galvanized in accordance with the "Specification for Zinc (Hot- ‐Galvanized) Coatings
on Products Fabricated from Rolled, Pressed and Forged Steel Shapes,Plates , Bars
and Strip" (ASTM A123). Any galvanized part that becomes warped during the
galvanizing operation shall be straightened. Bolts, anchor bolts. nuts, and similar
threaded fasteners, after being properly cleaned, shall be galvanized in accordance
with the "Specifications for Zinc Coating (Hot Dip) on Iron and Steel Hardware"
(ASTM A153). Field repairs to galvanizing shall be made using "Galvano," ''Galvo-‐
Weld," or approved equal.
a. General
All work required of the Contractor shall the of the highest quality workmanship.
Laying out of shop fabricated material shall be done only by experience workmen.
b. Straightening
Any required straightening of materials shall be done by methods that will not harm
the steel material. Minor cold straightening may be performed by hammering or
preferably by rolling or pressing. Heat may be used in straightening for more severe
deformations.
The plate edges to be welded may be universal mill edges or they may be prepared
by shearing, machining, chipping, or by mechanically guided oxygen or plasma arc
cutting. Edges of irregular contour may be prepared by manually guided oxygen or
plasma arc cutting.
1. Oxygen or plasma arc cutting. When edges ofplates are oxygen or plasma arc cut,
the surface obtained shall be uniform and smooth and shall be cleared of
43 | Technical Specifications
slag accumulation before welding. All cutting shall follow closely the lines
prescribed.
d. Rolling
e. Double-‐Curved Plates
Plates that are curved in two directions may be pressed either cold or hot or may be
dished with a "mortar and pestle" die by repeated application.
f. Milling of Columns
The ends of columns shall be milled to provide a satisfactory bearing unless the
design calls for sufficient welding to resist the total calculated loads.
g. Shop Assembly
Double-‐curved tank bottoms, shells, and roofs shall be assembled in the shop, if
necessary, to ensure that they will fit properly in the field.
h. Shipping / Transporting
All materials shall be loaded, transported to the site, unloaded and stored in such a
manner as to prevent damage.
5.5 WELDING
a. General
All welding shall be the shielded arc method and shall conform with the AWS “Code
for Arc and Gas Welding in Building Construction." Qualification of welders shall be
in accordance with the specifications for Standard Qualification Procedure of the
AWS.
b. Butt Joints
1. Subject to primary stress due to weight or pressure of the tank contents, Butt
Joints subject to primary stress such as longitudinal joints of cylindrical tanks
shells and all joint s below the point of support in suspended bottoms of elevated
tanks shall have complete joint penetration welds, which may be double welded
from both sides or welded from one side only using a backing strip or equivalent
means to ensure complete joint penetration welds. Butt
44 | Technical Specifications
joints may be used for all thickness permitted to be welded under this
specification.
3. Butt joints may be used for welding all thickness of material permitted to be
welded under this specification.
c. Lap Joints
1. Subject to primary stress due to weight or pressure of tank contents: Lap joints
subject to primary stress, such as longitudinal joints of cylindrical tank shells and
all joints below the point of supports in suspended bottoms of elevated tanks,
shall have continuous full fillet welds on both edges of the joints. The maximum
thickness permitted for this type shall be 12 mm (1/2 in.).
3. In any case, welded lap joints, except when shown on the plans, shall be lapped
not less than five times the nominal thickness of the thinner plate joined (5T);
but in double-‐welded lap joints, the lap need not exceed 50 mm(2 in.) and in
single-‐welded lap joints, the lap need not exceed25 mm (1 in.).
d. Plates
The maximum thickness of plates, except structural components and base plates
permitted to be welded under the specification shall be 50 mm (2 in.) or otherwise as
shown in the plans.
e. Roof Plates
45 | Technical Specifications
For roof plates which me not subject to hydrostatic pressure from tank contents, lap
joints may be welded on the top side only with continuous full fillet welds. Butt
joints shall be in single groove welds, using suitable backing or equivalent means to
ensure at least ninety percent (90%) joint penetration.
1. Fillet Welds: Plates 5 mm (3/16 in.) and less in thickness shall have full fillet welds.
Plates more than 5 mm (3/16 in.) thick shall have welds of a size not less than
one-‐ third the thickness of the thinner plate al the joint, with a minimum of 5
mm (3/16 in.).
The minimum length of any weld shall be four times the size but not less than 38 mm
(1-‐ 1/2in.), or else the size of the weld shall be considered not to exceed one- ‐
fourth of its length.
The effective length of a fillet weld shall not include the length of the tapered ends. A
deduction of at least 6.35 mm (1/4 in.) shall be made from the overall length as an
allowance for tapered ends.
h. Intermittent Welding
Intermittent welding shall not be used on tank shell plating in contact with tank
contents or on surfaces exposed to external weathering. Intermittent groove welds
shall not be used.
1. Length: The length of any segment of intermittent weld shall not be less than
four limes the weld size but never less than 38 mm(1-‐1/2 in.).
2. Seams: All seams that are to have intermittent weld shall have continuous length
of welds at each end for a distance of at least 150 mm (6 in.).
46 | Technical Specifications
Procedures shall conform with ANSI 249.2 (NFPA 518) for the prevention of fire and
property damage.
a. General
The Contractor shall furnish all labor, tools, falsework, scaffolding and other equipment
necessary and shall erect the tank so that it is completely ready for use.
b. Welds
All welds in the tank and structural attachments shall be made in a manner ensure
complete fusion with the base metal within the limits specified for each joint, and in
accordance with the qualified procedure.
1. Weather Conditions: Welding shall not be performed when the surfaces of the
parts to be welded are wet from rain or when rain is falling on such surfaces, or
during periods of high winds, unless the welder or welding operator and work are
protected properly.
3. Contour: The surface bends shall merge smoothly intoeach other in all welds.
5. Gouging: Gouging at the root of the welds and gouging of welds to remove defects
may be performed with a round-‐nosed tool or by arc or oxygen gouging.
Surfaces to be welded shall be free from loose scale, slag, heavy rust, grease, paint, and
any other foreign material, except tightly adherent mill scale. A light film of
deoxaluminate or equivalent spatter film compound may be disregarded. Such surfaces
shall be smooth, uniform, and free from fins, seams, and other defects that adversely
affect proper welding. A fine film of rust adhering on cut or sheared edge after wire
brushing need not be removed.
d. Tack Welds
47 | Technical Specifications
Tack weld used in the assembly of joints subject to primary stress from the weight or
pressure of the tank contents shall be thoroughly cleared of all welding slag, but need not
be removed, provided they are visually inspected for soundness (no cracks, complete
fusion. filled craters, and acceptable profiles) and metal.
e. Tank Assembly
All shell, bottom and roof plates subjected to stress by the weight or pressure of the
contained liquid shall be assembled and welded in such a manner that the proper
curvature of the plates in both directions is maintained.
1. Clips, jigs, and lugs: Clips, jigs, or lugs welded to the steel plates for erection purposes
shall be removed without damaging the plates, and any portion of the weld beads
remaining shall be chipped or ground smooth.
2. Bottom plates for elevated tanks: The bottom plates for elevated tanks shall be
assembled and welded together by a procedure that will result in a minimum of
distortion from weld shrinkage.
3. Tank Shell: For welding in the vertical position, the progression of welding shall be
either upward or downward.
4. The shell plates shall be joined by welding the joints in sequence that the Contractor
has found to result in the last distortion due to shrinkage of the weld and that will
avoid kinks at the longitudinal joints.
f. Matching Plates
1. Lap Joints: The plates forming a lap joint shall be held in as close contact as possible
during welding and in no case shall the separation be more than 1.6 mm (1/16 in.).
Where separation occurs, the size of the weld shall be increased by the amount of
separation.
2. Butt joints under primary stress: In butt joints subject to primary stress from weight
or pressure of tank contents, the adjoining plates shall be aligned accurately and
retained in position during welding, so that in the finished joint, the centerlines of
adjoining plates edges shall not have an offset from each other at any point in excess
of ten percent (10%) of the plate thickness (using the thickness of the thinner plate if
of different thickness) or 1.6 mm (1/16 in.) whichever is smaller.
3. Butt joints under secondary stress: In butt joints subject to secondary stress, the
adjoining plates shall be aligned accurately and retained in the position during
welding so that in the finished joint, the thinner plate of one is thinner than the
other) shall not project beyond its adjoining plate by more than twenty percent
(20%) of the plate thickness (using thickness of thinner plate if of different thickness)
or 3 mm (1/8 in.) whichever is smaller.
48 | Technical Specifications
4. Cleaning of Welds: The Contractor's crew shall remove weld scale or slag, spatter,
burrs, and other sharp or rough projections in a manner that will leave the surface
suitable for the subsequent cleaning and painting operation. Weld seams neednot be
chipped or ground, provided they may be satisfactorily cleaned and painted.
After the tank has been completely erected and ''trued up," a minimum of 25 mm (1
in.) space between the column and riser bases and the foundation shall be provided
for grouting. The space shall be wetted thoroughly and fitted with a 1:15 cement-‐
sand grout, which is forced under the base plates until the space is filled completely.
The Contractor shall furnish materials and labor forgrouting.
49 | Technical Specifications
6 – PIPING
6.1 GENERAL
a. The Contractor shall furnish and install all pipes, fittings, closure pieces, supports,
bolts, nuts, gaskets, jointing materials, and appurtenances as shown and specified,
and as required for a complete and workable piping system. Shop drawings of all
piping systems shall be furnished in accordance withClause ___ "Shop Drawings".
b. All bolts, nuts, and studs in the assembly of piping shall conform with the
requirements of Clause 5 -‐ Steel and Miscellaneous Metalwork.
c. All exposed piping shall be adequately supported with devices of appropriate design.
Where details are shown, the supports shall conform thereto and shall be placed as
indicated; provided that support for all piping shall be complete and adequate
regardless of whether or not supporting devicesare specifically shown.
Unless otherwise shown, galvanized steel pipe in sizes less than 100 mm (4 in.) in diameter
and smaller shall conform with the requirements of the "Specifications for Black and Hot-‐
Dipped Zinc-‐Coated (Galvanized) Welded and Seamless Steel Pipe for Ordinary Uses" (ASTM
A-‐120) and shall be Schedule 40. Galvanized steel pipe shall not be cement mortar- ‐lined
unless otherwise shown. Fittings for galvanized steel pipe shall be of galvanized malleable
iron. Galvanized and black steel pipe shall not be used for buried service, except where
shown on the Drawings.
Galvanized steel pipe for service connections shall be allowed only as specifically shown on
the Drawings. The pipe shall be wrapped with a 500 micron thick PVC tape to a total
thickness of 1000 microns, with half width overlapping. PVC tape shall be of a type approved
by the Engineer and shall be applied in accordance with the manufacturer’s
recommendation.
This standard specifies the requirements for unplasticized polyvinyl chloride (uPVC) pipes
with nominal outside diameter of75 mm to 150 mm intended for the conveyance of potable
water under pressure and of temperatures up to 45°C for use below ground.
The pipe shall conform with the requirements of the Philippine National Standard
Specification for Unplasticized Polyvinyl Chloride (uPVC) Pipes for Potable Water Supply (PNS
65:1993) except as otherwise specified herein.
a. Definitions
For the purpose of this standard, the following definitions shall apply:
50 | Technical Specifications
1. nominal pressure (PN) -‐ The normal maximum internal pressure that the pipe
can sustain in continuous use. This is expressed in megapascals (MPa) at 28°C.
2. design maximum induced stress -‐ The estimated maximum tensile stress on the
wall of the pipe along the transverse axis due to internal pressure to which the
pipe can be subjected continuously without failure. This is used in calculating the
wall thickness of the pipe. For the purpose of this standard, the maximum
induced stress is 8.5 MPa at 28°C.
3. pipe series (s) -‐ It is used in classifying the pipe, which is the ratio of the design
maximum induced stress to the nominal pressure of the pipe. The pipe series
number may be rounded off to the nearest whole number.
6. rework material -‐ PVC plastics from a processor's own production that has been
reground, pelletized or solvated after having been previously processed.
b. Classification
Pipes shall be classified in accordance with the pipe series and/or the nominal
pressure as follows:
In designing the maximum nominal pressure of the uPVC pipe under ambient
temperatures other than 28°C, Table 1 -‐ Maximum Induced Stress for Other
Temperatures may be utilized in arriving at the maximum induced stress to be used.
The said table may also be used in derating the nominal pressures of the pipe
specified in this standard.
Table 1
51 | Technical Specifications
c. Requirements
1. Materials
i The material from which the pipes are made shall consist substantially of
polyvinyl chloride that conforms with PNS 291, to which may be added only
those additives necessary to facilitate the manufacture of quality pipes of
good surface finish and sound physical, mechanical and chemical properties.
iii. The use of the manufacturer's own clean rework material produced during
the manufacture and production testing of products conforming with this
standard is permissible. No other rework material shall be used.
2. Dimensions
ii. Dimension and Tolerances -‐ The outside diameters, socket depths, socket
diameters, minimum wall thicknesses, effective lengths of the different pipe
series/nominal pressures and the tolerances are indicated inTable 2.
iii. Length -‐ Unless otherwise specified by the purchaser, the length of the pipe
shall be taken to mean the effective length, Le, as shown in Figure 1. The
minimum effective lengths are indicated inTable 2. A tolerance of +20 mm is
allowable.
3. Physical Characteristics
ii. Color -‐ The color of the pipe shall be blue nearest to RAL 5012 and shall be
uniform throughout the entire surface of the pipe.
iii. Effect of Materials on Water Quality -‐ When used under the conditions for
which they are designed, non- ‐metallic materials in contact with, or likely to
come into contact with potable water shall not constitute a toxic hazard,
52 | Technical Specifications
shall not support microbial growth and shall not give rise to unpleasant taste
or odor, cloudiness or discoloration of the water.
53 | Technical Specifications
Figure 1 - Standard Configuration of Unplasticized Polyvinyl Chloride (uPVC)
Pipes with Elastomeric Sealing Ring Socket Ends (63 mm to 500mm)
54 | Technical Specifications
55 | Technical Specifications
Table 3 -‐ Maximum Levels of Toxic Substances
Extraction Total
Toxic Substances 1 st
3 rd Concentrations of 3
Extracts
Lead, mg/L 1.00 0.05
Di-‐alkyl Tin, C4
and other higher
monologues 0.02
measured as tin,
mg/L
Cadmium, mg/L 0.01
Mercury, mg/L 0.001
iv. Physical Properties -‐ The pipe shall conform with the physical properties
specified in Table 4.
vi. Resistance to Sulfuric Acid -‐ The mass of the specimen shall not increase
by more than 0.316 g nor decrease by more than 0.013 g when tested in
accordance with PNS 979/ISO 3473. The effect of the acid on the surface
appearance of the specimen (roughening, bleaching or blackening) shall
be ignored.
4. Mechanical Properties
The pipe shall conform with the applied pressure for the hydrostatic pressure
tests indicated in Table 5 of PNS 65:1993 when tested in accordance with PNS
509/ISO 1167.
56 | Technical Specifications
Table 5 -‐ Applied Pressure for Pressure Test at 280 Unit: MPa
Series 10 8 7 5
Burst Pressure 3.80 4.56 5.49 7.10
Short Term 3.60 4.30 5.20 6.70
Pressure
Long Term 2.50 3.00 3.60 4.65
Pressure
For specific calculation, the following formula for deriving the applied pressure
may be used:
P= 2 x S x t min
Dm -‐ tmin
where:
i. Burst Pressure -‐ The pipe shall withstand the applied pressure for at least 60
seconds without failure. The value for the induced stress used in calculating
pressure requirement is 37.5 MPa at 28°C.
ii. Short Term Pressure -‐ The pipe shall withstand the applied pressure for at
least one hour without failure. The value for the induced stress used in
calculating pressure requirement is 35.7 MPa at 28°C.
iii. Long Term Pressure -‐ The pipe shall withstand the applied pressure for at
least 1000 hours without failure. The value for the induced stress used in
calculating pressure requirement is 24.6 MPa at 28°C.
iv. Resistance to External Blows -‐ The true impact rate of the batch at 28°C
shall not exceed 10% when tested in accordance with PNS 967/ISO 3127.
NOTE -‐ The true impact rate is the total number of broken test pieces
divided by the total number of blows, expressed as percentage as if the
whole batch had been tested. In practice, test pieces are drawn at random
from the batch and only estimate of the true impact rates are obtained.
v. Flattening -‐ The pipe shall not show evidence of splitting, cracking and breaking
when flattened to a minimum of 40% of its outside diameter when tested in
accordance with PNS 800/ASTM D2241.
vi.
5. Joints
57 | Technical Specifications
Elastomeric sealing ring type joints shall be usedfor sizes 63 mm up to 500 mm.
The elastomeric sealing ring shall conform with PNS 1008/ISO 4633.
1. At least one piece or set (depending on the quantities specified by the test
method) of sample/s per production batch (one production run or one
production shift, whichever is shorter) shall be taken at random for testing in
accordance with the methods and procedures specified in this standard.
2. The pipes shall be tested in accordance with the methods prescribed in this
standard.
f. Marking
The pipe shall be clearly marked with the following information spaced at intervals of
not more than one metre:
1. Name of Product
2. Nominal outside diameter, mm
3. Series and/or Nominal pressure, MPa
4. Manufacturer's name and/or its recognized trademark
5. The words "Made in PHL" or "Made in the Phil."
6. The words "For Potable Water"
REFERENCES
The following standards through reference in the text form part of this national
standard. At the time of publication of this PNS, the editions indicated were valid.
PNS 509/ISO 1167-‐1973, Plastic pipes for the transport of fluids -‐ Determination of
the resistance to internal pressure
PNS 800/ASTM D 2241 -‐ 1980, Standard Specification for Polyvinyl Chloride (PVC)
Pressure-‐Rated Pipe (SDR Series)
PNS 952/ISO 2507-‐1982, Unplasticized polyvinyl chloride (PVC) pipes and fittings -‐
Vicat softening temperature -‐ Test methods and specification
58 | Technical Specifications
PNS 953/ISO 2508-‐1981, Unplasticized polyvinyl chloride (PVC) pipes -‐ Water
absorption -‐ Determination and specification
PNS 966/ISO 3114-‐1977, Unplasticized polyvinyl chloride (PVC) pipes for potable
water supply -‐ Extractability of lead and tin -‐ Test method
PNS 967/ISO 3127-‐1980, Unplasticized polyvinyl chloride (PVC) pipes for the
transport of fluids -‐ Determination and specification of resistance to external blows
PNS 1008/ISO 4633-‐1983, Rubber seals -‐ Joint rings for water supply, drainage and
sewerage pipelines -‐ Specification for materials
PNS 1027/ISO 6992-‐1986, Unplasticized polyvinyl chloride (PVC) pipes for drinking
water supply -‐ Extractability of cadmium and mercury occurring as impurities
ABBREVIATIONS
59 | Technical Specifications
6.4 PE (POLYETHYLENE) PLASTIC PIPES
a. Materials
b. Effect on water quality -‐ When used under conditions for which they are designed,
materials in contact with or likely to come into contact with drinking water shall not
constitute a toxic hazard, shall not support microbial growth and shall not give rise to
unpleasant taste or odor, cloudiness or discoloration of the water.
60 | Technical Specifications
Designation of MRS at 50 yrs and Maximum allowable
Materials o
20 C, Mpa hydrostatic design
stress, Mpa
PE 100 10 8
PE 80 8 6.3
PE 63 6.3 5
when the lower confidence limitδLCL for the compound is determined in accordance
with ISO/TR 9080 and this δLCL is classified in accordance with ISO 12162 to obtain
the MRS.
d. Melt flow rate and density-‐ When measured In accordance with ISO 1133, the_
melt flow rate shall conform to the following conditions:
1. The melt flow rate of the compound shall not deviate by more than +/-‐ 30%
from the value specified by the manufacturer.
2. The change in MFR caused by processing, i.e. the difference between the
measured value for material from the pipe and the measured value for the
compound, shall not be more than 25%.
e. Geometrical Characteristics
For polyethylene pipes PE 100 (PE 3408) with design stress δs of 8Mpa
25 2.3
-‐ -‐
61 | Technical Specifications
For polyethylene pipes PE80 (PE 2406) with design stress δs of 6.3 Mpa
25 2.3 2.8
-‐ -‐ -‐
4. The minimum diameter of a drum ofcoiled pipe shall be 18 xdn and in any
case, such that kinking of the pipe is prevented.
5. The length of straight pipes and coils shall not be less than that agreed
between the supplier and user.
62 | Technical Specifications
f. Mechanical Properties
1. Hydrostatic Strength -‐ When tested in accordance with ISO 1167, the pipes
shall conform to the following requirements:
2. Retest in cases of failure at 80°C – A brittle fracture in less than 165h shall
constitute a failure. If, in the 165h test, a test piece fails in a ductile mode in less
than 165h, a retest shall be performed at a lower stress. The new stress, and the
new minimum failure time, shall be selected from the line through the
stress/time points given below:
PE 63 PE 80 PE 100
Stress Minimum Stress Minimum Stress Minimum
Failure Failure Failure
Mpa Time, Mpa Time, Mpa Time,
h h h
3.5 165 4.6 165 5.5 165
3.4 285 4.5 219 5.4 233
3.3 538 4.4 283 5.3 332
3.2 1000 4.3 394 5.2 476
4.2 533 5.1 688
4.1 727 5.0 1000
4.0 1000
g. Physical Characteristics
63 | Technical Specifications
3. Weathering of non-‐black pipes -‐ To determine the effects of weathering, pipes shall be
exposed to outdoor conditions in accordance with the procedures
adopted by the Bureau off Product Standards and described in ISO 4607. After
2
exposure to a total solar energy of at least 3.5 GJ/M the pipe shall
conform to the following requirements:
-‐ Hydrostatic strength, when determined with f.1 at 80oC for at least 165h,
i. Marking – All pipes shall be indelibly marked at maximum interval of 1.0m. The
marking shall indicate at least the following information:
-‐
The manufacturer’s name and/or trademarks
-‐
the Bureau of Product Standards “Q”check mark
-‐
the number of this PNS standard
-‐
the dimensions (nominal outside diameter x normal wall thickness) the
outside diameter tolerance (A or B)
-‐
the designation of the pipe material (e.g. PE 100, PE 80, PE 63) the nominal
pressure (PN)
-‐
the pipe series (S or SDR)
-‐
the production period (date or code)
-‐
the number of the national standard
-‐
the words "potable water" have to be included if the pipe is intended for
drinking water
-‐
other markings that may be specified by the owner
j. Sampling and Testing Schedule – The manufacturer shall adhere to the following
sampling and testing schedule as specified by PNS ISO 4427: 2002 Annex 8 as follows:
General Requirements
1. Diameter and wall thickness Per roll/hourly
2. Length Every 8 hours
3. Appearance Every 8 hours
64 | Technical Specifications
Type Test
1. Material Every 6 months or every change of
material brand / pipe
2. Carbon Black -‐do-‐
3. Weathering & Thermal Stability -‐do-‐
4. Effect of Material on Water -‐do-‐
Quality
5. Density -‐do-‐
6. Melt Flow Rate -‐do-‐
MRS Test
Brand
Hydrostatic Strength
brand
2. 165hr test -‐do-‐
3. 1000hr test -‐do-‐
Quality Control Test
a. Materials
The service line piping 50mm and smaller shall be made of polyethylene tubing as
specified herein and sizes shown on the Drawings. Service piping having diameters
larger than 50 mm (2”) shall be constructed of the same materials approved for
water mains of similar sizes.
Small tubing-‐size service lines shall have plastic or brass fittings using compression
type connections with compressive force applied on the outside surface of the
tubing. However, stainless steel or brass inserts may be utilized for bigger sizes.
Plastic fittings shall be injection-‐molded, compression type and suitable for use with
Polybutylene (PB) or Polyethylene (PE) tubings conforming in dimensions and
tolerances to ISO 161/I and ISO 3607, respectively.
65 | Technical Specifications
suitable for potable water by the Food and Drugs Administration (FDA) or any
accredited testing laboratories.
All plastic fittings shall meet the requirements of the National Testing Laboratories
for Potable Water and shall be designed to hold a working pressure of 1.1 MPa and
resist a minimum pull-‐out force of 20 kg.
The fillings shall be clearly and neatly finished and free fromburrs or other defects
likely to damage or score the pipe, and the bore shall be free from irregularities which
restrict the free flow of fluid. The internal and external surfaces of fittings shall be
clean and free from grooves, pinholes, or other defects likely to affect the
performance and service of the system.
Where saddles are required, as shown on the Drawings, they shall conform with the
provisions of Clause 6.12.
Welded outlets on steel pipe shall be insulated from brass fittings with nylon
bushings approved by the Engineer.
All plastic fittings shall he free of cracks or other injurious defects and shall be
smooth and clean before inspection.
For every 100 pieces of any size of fittings, at least three pieces shall chosen at
random and subjected to a pressure of 1.1 MPa at 23 oC. If any sample tested cracks
or leaks, the lot represented will be rejected.
c. Installation
66 | Technical Specifications
laid in a serpentine fashion along the service trench bottom to resist pull- ‐out.
Galvanized steel pipe for service lines shall be installed only where specifically shown
on the standard drawings. Galvanized steel pipe and PVC tape shall be in accordance
with Clause 6.3.
Where service lines are located under the roadbeds or in stony or rocky ground, sand
bedding shall be provided. The sand bedding shall be of adequate thickness to
provide a depth of cover of 0.15 m.
Unless otherwise directed, all service lines shall beinstalled prior to the hydrostatic
test of the water main, and they shall be tested with pressure test of the water main.
Each stopcock valve shall be operated to thoroughly flush the service and remove any
accumulated air present prior to the hydrostatictest.
a. Materials
Where saddles are required as shown on the Drawings, they shall be constructed of
one or a combination of the following materials and complying with the requirements
as hereunder indicated.
1. Brass
2. Bronze
3. Ductile Iron
4. Cast Iron
5. Plastics
All the materials used in the manufacture of clampsshall meet the requirements of
applicable ASTM, AWWA, ISO or other internationally accepted standard
specification.
67 | Technical Specifications
b. Manufacture
2. Double or single strap, as shown on the Drawings, each with a width not less than
20 mm (3/4 in.).
3. Straps or clamps shall be made of any of the materials listed aboveor of 18-‐8
stainless steel.
All parts of the service saddle including the clamp or strap shall comply with the
following minimum thickness requirements:
Saddles shall be shaped to the various outside pipe diameters to which they are to be
fitted and shall be provided with an approvedresilient neoprene rubber gasket with a
minimum bearing width of 12 mm (1/2 in.).
The tapping thread shall be at least 30 mm deep and drilled in accordance with iron
pipe (I.P.) thread dimensions.
4. Shop drawings for plastic service saddle shall be first submitted for approval
prior to manufacture.
Mechanical-‐type couplings shall be designed for a water working pressure not less
than the design pressure of the pipe on which they are to be installed, and shall be
equipped with Grade H rubber gaskets. Couplings shall be Gustin- ‐Bacon or Victaulic
Style 44 when pipe ends are banded, and Gustin- ‐Bacon or Victaulic Style 77 when
pipe ends are grooved
SLEEVE-‐TYPE COUPLINGS
Sleeve-‐type couplings shall he provided where shown and shall be Smith- ‐Blair,
Style 411 or Style 412, equivalent styles manufactured by Dresser, or approved
substitute.
68 | Technical Specifications
Couplings shall be of steel with steel bolts, without pipe stop, .1nd shall be of sizes to
fit the pipe and fitting shown. The middle ring shall be not less than 6 mm (1/4 in.) in
thickness and shall be 125 to 175 mm (5 in. to 7 in.) long forstandard steel couplings
and 400mm (16 in.) long-‐sleeved couplings. Bolts for exposed couplings shall be hot
dip galvanized. Buried bolts and sleeved couplings shal be coated in accordance with
Clause 10.13) (c) (3) (gg). Paints and Coatings.
a. Except as otherwise provided, gaskets for flanged joints shall be 1.5mm (1/16 in.)
thick laminated asbestos fiber.
b. Wherever blind flanges are shown, the gaskets shall consist of 3mm (1/8 in.) thick
cloth-‐ inserted rubber sheet which shall be cemented to the surface of the blind
flange.
Pressure gages shall have 89 mm (3- ‐1/2 in.) dials, 6 mm (1/4 in.) threaded connections
and shut-‐off cocks. Gages shall be calibrated to read 1.0 MPa (150 psi), unless otherwise
shown on the Drawings. The pressure element of the gage shall be protected against
excessive pulsations and surges by an external pressure snubber.
The Contractor shall furnish and install drain pipes where shown on the Drawings.
Concrete drain pipes shall conform with the Standard Specifications for Concrete Drain
Pipes of the Department of Public Works and Highways.
The Contractor shall furnish and install steel casing where shown on the Drawings. Steel
casings shall be of welded steel pipe of the diameters and plate thickness shown. Joints
In steel casings may be either butt-‐welded; lap welded, or welded using butt straps. No
protective coating need be applied to casings. Casings shall be installed as required in
accordance with details as shown, and subject to the approval of the agency having
jurisdiction.
a. Material
The Contractor shall furnish and install for each pipe above or equal to 50 mm an
Alu-‐Foil warning/detection tape (minimum width is 5 cm) (2") with the words
"Attention Water Main" marked in a continuous manner.
6.12 Installation
69 | Technical Specifications
The tape shall be laid flat on top of an intermediate layer of backfill, after compaction of
same and prior to backfilling and compacting, the final top layer. The depth of laying the
tape will therefore be about 0.30 m (1 foot) from the finish surface or at about:
-‐
0.45m from top of pipes with sizes equal to or under 250 mm diameter
except for Asbestos Cement Pipes.
-‐
0.60m above the top of pipes with sizes equal to or larger than 300 mm
diameter.
70 | Technical Specifications
7 – VALVES
7.1 GENERAL
a. The Contractor shall furnish and install all valves as specified herein and as shown on
the Drawings. All valves shall be new and of current manufacture.
b. Flanged valves may be plain faced with serratedgasket surface or raised. Flanges of
valves for water working pressure of 1.2 MPa (175 psi) or less shall be faced and
drilled to 125-‐lb American Standard dimensions; flanges of valves for water working
pressures greater than 1 .2 MPa (175 psi) shall be faced and drilled to 250- ‐lb
American Standard dimensions.
c. Each valve body shall be tested under a test pressure equal to twice its design water
working pressure.
d. All valves shall be provided with an exterior protective coating in accordance with the
provisions of Clause 10 -‐ Painting and Coatings.
e. When the operating nut of a buried valve is located more than 1.5 metres (5 ft) below
the ground surface, the Contractor shall provide and install in the valve box a stem
extension. The bottom of the extension shall be securely fastened to the operating
nut of the valve, and the top of the extension shall be centered in the valve box.
f. The Contractor shall furnish a minimum of six (6) tee- ‐handle valve keys. of variable
lengths sufficient to permit operation of all buried valves regardless of depth, by
operators of average height working in normal position. Where the number of valves
to be provided exceeds thirty (30) units, the Contractor shall provide one (1) valve
key for every five (5) additional valves or a fraction thereof.
h. Shop drawings for all valves shall be furnished in accordancewith Clause ___ -‐ Shop
Drawings.
a. Valves
This Clause applies to gate valves 50 mm (2 in.) through 300 mm (12 in.) in size. All
valves shall conform with the "Standard for Resilient Seated Gate Valves" (AWWA
C509). Gate valves where the pipeline design pressure is 1.0 MPa (150 psi) or less
shall be designed for a minimum water working pressure of 1.0 MPa (150 psi) and
shall be cast iron bodied, with resilient seats applied to the body or gate. Discs shall
be cast iron with bronze disc rings, and the seat ring shall be bronze and replaceable.
The valve shall be non-‐rising stem with a minimum of two "O" ring
71 | Technical Specifications
seals (at least one above the stem collar), or rising stem when shown on the
Drawings. The valves shall have a 50 mm (2 in.) square operating nut with a cast
arrow showing direction in which the nut is to be turned to open the valve. Valves
shall be constructed to permit the replacement of the "O" rings above the stem collar
under full working water pressure with the valves in the full open position. The valves
shall be coated in accordancewith Division 27 -‐ Painting and Coatings.
b. Testing Requirements
1. Shell Test
A hydrostatic lest pressure equal to twice the rated working pressure of the
valve shall be applied to the body with the gate in the open position . The test
shall show no leakage through the metal, flanged joints, or stem seals.
2. Seat Test
A test shall be made at rated working pressure to prove the sealing ability of each
valve from both directions of flow. The lest shall show no leakage through the
metal, pressure-‐containing joints, or past the seat.
3. Hydrostatic Test
One prototype valve of each size and class of a manufacturer's design shall be
hydrostatically tested with twice the specified rated pressure applied to one side
of the gate and zero pressure on the other side. The tes is to be made in each
direction across the gate. Under this hydrostatic test, the manufacturer may
make special provisions to prevent leakage past the seats. No part of the valve or
gate shall be permanently deformed by the test.
4. Torque Test
A prototype of each size should be over torqued in the closed and open positions
to demonstrate no distortion of the valve stem or damage to the resilient seat as
evidenced by failure to seal at rated pressure. The applied torque shall be 250 ft--
‐lb for 3 and 4 NRS valves, and 350 ft- ‐lb for 6, 8, 10, and 12 NRS valves (1.0 ft- ‐lb
= 0,736 Newton-‐metre = 0.66kg.m)
5. Leakage Test
Two prototype valves of each size chosen by the quality control inspector to
represent the extremes of seal compression shall be fully opened and closed to a
seal for 500 complete cycles with sufficient flow that the valve is at 200 psi
pressure differential at the point of opening and closing. The valves shall be drop
tight under rated pressure differential applied alternately to each side of the gate
after completion of the tests.
6. Pressure Test
One prototype of each valve size shall be tested to 500 psi with the closure
member in the open position. There shall be no rupture or cracking of the valve
body, valve bonnet, or seal plate. Leakage at pressure-‐containing joints shall not
be a cause for failure of the test.
72 | Technical Specifications
7.3 AIR-‐VACUUM AND AIR RELEASE VALVES
Air vacuum and air release valves shall have threaded connections. The bodies shall
be of high-‐strength cast iron, and the float shall be of stainless steel. Float guides,
bushings, lever pens and all other internal parts shall be constructed of stainless steel
or bronze. Seat washers and gasket shall be of a material insuring water-‐ tightness
with a minimum of maintenance. Valves shall be designed for a water working
pressure of not less than 1.0 MPa (150 psi). All valves shall be designed to
automatically operate so that they will: (a) positively open under atmospheric
pressure (as water drains from the body of the valve, it will allow air to flowntoi the
pipe while it is being emptied); (b) positively close as water, under low head, fills the
body of the valve; (c) not blow-‐shut under high velocity air discharge; and (d) permit
the escape of accumulated air under pressure while the pipe is in operation.
73 | Technical Specifications
7.8 PLUG VALVES
Plug valves shall be lubricated 50mm (2in.) semi- ‐steel straightway valves with a
working pressure of 175 lb. The valves shall be wrench- ‐operated, two-‐bolt cover
type with screwed ends. A complete locking device assembly shall be provided for
each valve where indicated on the Drawings.
74 | Technical Specifications
8 -‐ PRESSURE AND LEAKAGE TESTING AND DISINFECTING
8.1 GENERAL
The Contractor shall furnish all equipment, labor and materials, including taps, valves
and bulkheads as required and exclusive of water and water meter for testing and
proper disinfection of the pipelines and reservoir. The water and any water meter used
for testing shall be furnished by the Owner, but the Contractor shall provide the facilities
necessary to convey the water from the Owner- ‐designated source to the points of use.
All testing and chlorinating operations shall be done in the presence of the Engineer.
The pipeline shall be prepared for testing by closing valves when available, or by
placing temporary bulkheads in the pipe and filling the line slowly with water. During
the filling of the pipe and before the application of the specified test pressure, all air
shall be expelled from the pipeline. To accomplish this, taps shall be made, if
necessary, at points of highest elevation and after completion of the test; and taps
shall be tightly plugged unless otherwise-‐specified. After the line or section thereof
has been completely filled, it shall be allowed to stand under a slight pressure for a
minimum of forty-‐eight (48) hours to allow the escape of air from any air pockets
and to allow the pipe or mortar lining to absorb as much water as possible.
75 | Technical Specifications
During this period, all exposed pipes, fittings, valves, joints and couplings shall be
examined for leaks. If found to be cracked or defective, these shall be removed and
replaced by the Contractor with sound material at his own expense. The pipeline
shall then be refilled and all bulkheads, joints and connections shall be examined for
leaks. If any are found, these shall be stopped. The test shall consist of holding the
test pressure on each section of the line for a period of two (2) hours. The test
pressure at the lowest point shall be 690 Kpa or 1.0 MPa according to the class of
pipe installed, class 100 or class 150, and as approved by the Engineer. Pressure
gauges shall also be provided at all ends of the section tested. The water necessary to
maintain the pressure shall be measured through a meter or by other means
satisfactory to the Engineer. The leakage shall be considered the amount of water
metering the pipeline during the two- ‐hour test period. The allowable leakage for
cast iron pipe or ductile pipe shall not exceed the values listed in Table 3 of the
AWWA Standard for installation of Cast Iron Water Main (AWWA C600). All other
types of pipes shall have an allowable leakage not exceeding 1.85l/mm of diameter
of pipe per kilometer per day. Should any test of a section of pipeline disclose joint
leakage greater than that permitted, the contractor shall, at his own expense, locate
and repair or replace the defective pipe, fitting, joint, coupling or other
appurtenance. The test shall be repeated until the leakage is within the permitted
allowance.
Closure pieces between newly installed and existing mains shall be tested after the
pipe has passed the pressure and leakage test specified above. The test shall include
subjecting the joint to a pressure of 345 KPa (50 psi) for a period of five (5) minutes
and visually checking for leakage. All visible leaks shall be repaired by the Contractor
at no expense to the Owner.
76 | Technical Specifications
The preferred point of application of the chlorinating agent is at the beginning of the
pipeline extension or any valved section and through a corporation stop inserted on
the top of the laid pipes.
Should the initial treatment fail to result in the conditions stipulated above, the
chlorination procedures shall be repeated until satisfactory results are obtained,
Where connections are to be made to existing water mains, HTH shall be added at
points of interconnections as directed by the Engineer.
77 | Technical Specifications
twenty-‐ four (24) hours. After the chlorine- ‐treated water has been retained for the
required time, the chlorine residual in the reservoir and in the lines shall be at least
25 mg per litre. All valves shall be operated while the lines are filledwith the heavily
chlorinated water.
f. Final Filling of Reservoir
After the chlorine residual has been in accordance with Clause (d), the water level in
the reservoir shall be raised uniformly to approximately 30 cm (1 ft.) below the
overflow level by the addition of potable water. Before final filling is commenced, the
quantity of heavily chlorinated water remaining in the reservoir after filling the piping
shall be sufficient when the water level is raised to its final elevation to produce a
chlorine residual of between 1 mg per litre and 2 mg per litre. After the reservoir has
been filled, the strength of the chlorinated water in thereservoir shall be determined
by the Engineer. If the chlorine residual is less than 1 mg per litre, an additional
dosage shall be applied to the water in the reservoir. If the chlorine residual is greater
than 2 mg per litre in the reservoir, the reservoir shall be partially emptied and
additional potable water added.
In no case shall water be released through the drain lines prior to the expiration of
the required retention period.
g. Leakage Allowance of Concrete Reservoir
After the reservoir has been filled continuously for a period of thirty (30) days, if
leakage is such that the water surface drops more than 5.10 cm (2 in) in a 30 day
period, the Contractor shall empty to permit close examination for evidence of any
cracking or other conditions that might be responsible for the leakage. Any crack
shall be “vee’d” and sealed with rubber sealant in accordance with Clause 8.13 (b).
Any evidence of leakage through the joints shall be repaired tothe satisfaction of the
Engineer. Following these operations, the Contractor shall again sterilize the
reservoir in accordance with this Clause, exclusive of the sprayingoperation.
78 | Technical Specifications
9 – SURFACE RESTORATION AND PAVING
9.1 GENERAL
The Contractor shall furnish all materials, labor, plant, and equipment for the removal of
all pavement, sidewalks, curbs and gutters, fences, poles, driveways, walks, other
property, and surface structures that are necessary for the proper prosecution of the
work, but only upon approval of the parties having jurisdiction thereof and of the
Engineer. Unless otherwise shown, the Contractor shall restore at his own expense all
property removed or destroyed by his operation at least equal to conditions prior to
work under this Contract or to the satisfaction of the property owner:
a. In cutting or breaking up street surfacing required for the performance of the work,
the Contractor shall not use equipment which will damage the adjacent pavement.
All concrete pavement surfaces to be removed shall be scored with concrete sawing
equipment; provided, that any Portland cement concrete based under an asphaltic
mix surface will not be required to be scored by sawing. Asphaltic- ‐concrete
pavement shall be removed to dean straight lines.
The Contractor shall remove the pavement and road surfaces as part of the trench
excavation, and the amount removed shall not exceed the maximum width of trench
for pipelines as indicated on the Drawings, unless otherwise ordered in writing by the
Engineer.
The width and length of the pavement area required to be removed for the
installation of valves, valve chambers, spirals, or other structures shall not exceed the
maximum linear dimensions of such structures by more than 0.30 metres on each
side.
The width of the pavement area required to be removed for the installation of
service connections shall not exceed the maximum width as shown on the Drawings.
Except where shown on the drawings or otherwise specified, any pavement, trees,
shrubbery, fences, poles or other property and surface structures which have been
damaged, removed, or disturbed by the Contractor, whether deliberately or through
failure to carry out the requirements of the Contract Documents, municipal
79 | Technical Specifications
ordinances, or the specific directions of the Engineer, or through failure to employ usual
and reasonable safeguards shall be replaced or repaired at the expense of the
Contractor.
Except where shown on the drawings, the Contractor shall restore all private property
and surface structures removed or disturbed as a part of the work to a condition equal
to that before the work began. He shall also furnish all labor and materials incidental
thereto at his own expense. No payment shall be allowed for dirt road restoration.
9.6 PAVING
a. General
b. Borrow
80 | Technical Specifications
When sufficient suitable material is not available from the roadway excavations,
additional "borrow" materials shall be obtained from other sources. This "borrow"
material shall be in accordance with Item 107 of the referenced Standard
Specification.
c. Sub-‐grade Preparation
This item shall consist of the preparation and conditioning of the sub- ‐grade to the
full width of the roadbed in accordance with Item 112 of the referenced Standard
Specifications and in conformity with the lines, grades, and cross- ‐ sections shown on
the plans. ThisClause supersedes applicable Clauses in Clause 7.
This item shall consist of a foundation for the surface course, composed of gravel or
crushed stone and filler materials in accordance with Item 200 of the referenced
Standard Specifications. Grading shall be as indicated in Table 200- ‐1. This shall be
applied to the gravel roadway and parking area.
81 | Technical Specifications
10 – PAINTINGS AND COATINGS
10.1 GENERAL
The work included in this Clause consists of the furnishing of all labor, materials,
apparatus, scaffolding, and all appurtenant work in connection with painting and
coating in accordance with these Specifications. Any subcontractor for painting and
coating shall be approved by the Engineer.
10.2 SCOPE
The following surfaces are to be painted, except where otherwise specified or shown:
a. Ferrous metals having approved plating or factory applied final paint finishes;
b. Non-‐ferrous metals; unless otherwise noted or indicated; galvanized metal shall not
be considered a non-‐ferrous metal; and
c. Equipment with factory finished surface unless otherwise noted.
In no case shall any concrete, wood, metal, or any other surface requiring protection be
left unpainted even though not specifically defined herein.
No exterior painting or interior finishing shall be done under conditions which may
jeopardize the appearance or quality of the painting or finishing in any way. The Engineer
shall have the right to reject all material or work that is unsatisfactory, and require the
replacement of either or both at the expense of the Contractor.
82 | Technical Specifications
The Contractor shall take the necessary steps to protect thework of others during the time
his work is in progress. The Contractor shall be responsible for any and all damage to the
work. Paint shall be applied only during period of favorable weather.
10.5 WORKMANSHIP
All work shall be first class and in accordance with best standard practices of the
trade.
The Contractor shall examine carefully all surfaces to be painted and, before beginning
any of his work, shall see that the work of other trades has been left or installed in
workmanlike condition to receive paint.
Metal surfaces shall be clean and free from mil scale, rust, grease, oil, or any other
substances which could affect the quality of the painting.
Each coat of paint shall be applied at proper consistency and brushed evenly, free of
brush marks, sags, runs, and with no evidence of poor workmanship. Care shall be
exercised to avoid lapping of paint on glass or hardware. Paint shall be sharply cut to
lines and finished paint surfaces shall be free from defects or blemishes.
Protective covering shall be used to protect floors, fixtures, and equipment. Care shall
be exercised to prevent paint from being spattered onto surfaces which are not to be
painted. Surfaces from which such paint cannot be removed satisfactorily shall be
painted or repainted, as required, to produce a finish satisfactory to the Engineer.
All painting materials shall be used in strict accordance with manufacturer's directions,
spread or flowed on smoothly with proper film thickness and without runs, sags, or
other defects.
The Contractor shall store all painting materials and equipment not in immediate use in
a room approved by the Engineer for that purpose. The receiving and opening of all
paint materials and mixing shall be done in this room.
Necessary precautions shall be taken to prevent fire. Rags, waste, etc., soiled with paint
shall be removed from the premises at the end of each day's work,or stored in metal
containers with metal covers.
Paint containers shall be delivered to the job site in the manufacturer's unopened
containers and shall be opened only when required for use. Paint shall be mixed only in
83 | Technical Specifications
the designated room or space in the presence of Owner's representative. Paint shall be
thoroughly stirred or agitated to a uniformly smooth consistency suitable for proper
application. Unless otherwise specified or approved, no materials shall be reduced,
changed, or used except in accordance with manufacturer's label or tag on the
container. In all cases, paint shall be prepared and handled in a manner to prevent
deterioration and inclusion of foreign matter.
The Contractor shall leave on the job site a minimum of four (4) litres (1 gal.) of each
type and color of finish paint used in the project. Each gallon shall be properly labeled
for identification.
10.9 CLEAN UP
Upon completion of his work, the Contractor shall remove all surplus materials. All paint
spills shall be removed and the entire premises shall be free from rubbish, debris, etc.,
caused by his work. He shall presentthe work clean and free from blemish so that it is
acceptable in every way. All glass shall be cleaned of paint spots and polished, and the
job made ready for occupancy by the Owner
10.10 MATERIALS
a. Materials
The Contractor may substitute either paint materials for those specified in Clause
14.13 provided he first received written approval from the Engineer stating that said
proposed substituted materials are equal to that specified and are approved for use.
The painting material shall be delivered to the job site in original containers properly
labeled without evidence of tampering, substitution of contents, or of deterioration.
A complete list of material proposed for use shall be submitted for Engineer’s
approval.
All finish colors shall be as selected by the Owner. In multi- ‐coat work using color
pigmented paints, each coat shall have sufficient variation of color to easily
distinguish it from preceding coat. Using specified or approved materials, three (3)
sample panels of each finish, including all coats thereof shall be prepared and
submitted for the Owner's approval. Completed work shall match approved colors
and samples.
84 | Technical Specifications
a. General
Except as otherwise specified, surfaces to be painted shall be clean, smooth, and dry.
The Contractor shall report to the Engineer in writing any surface which cannot be
properly prepared for painting. If work is commenced before defects have been
reported and corrected, any unsatisfactory finish shall be rectified by the Contractor
at no cost to the Owner.
All concrete and masonry surface shall cure thirty (30) days prior to painting. Dirt,
dust, oil, grease, efflorescence, and other deleterious matter shall be removed and
surface roughened when necessary to insure good paint adhesion. The method of
surface preparation shall be left to the discretion of the Contractor, provided results
obtained are satisfactory to the Engineer. Before application of resin emulsion paint,
surfaces shall be prepared in accordance with manufacturer's directions. Before
application of oil base or latex paints, surfaces shall be tested for presence of alkali. If
alkali is present, surface shall be neutralized as recommended by the manufacturer
of the paint materials to be applied.
c. Plaster
Dirt, dust, loose plaster, and other deleterious matter which wouldprevent good
paint adhesion shall be removed. All holes, cracks, and depressions shall be neatly
filled with patching plaster mixed and applied to match the existing plaster. Patches
shall be sanded flush and smooth and properly sealed before applying prime coat.
After priming surfaces, suction spots shall be touched up with additional prime coat
material until surfaces evidence a uniform coating.
d. Metal
Dirt, scale, and rust shall be removed by scrapping, wire brushing, and sanding or
sandblasting as required. Mill scales shall be completely removed from fabricated
parts of the new elevated steel tank either in the shops or in the field. Mill scales can
be can be removed in the shop either by cleaning or pickling. In such case, the steel
must be painted before rusting or surface soiling occurs with zinc, dust, phenolic
primers to effect proper adhesion of the first field coat. If mill scales are removed in
the field prior to welding, all welded joints should be cleared of slag and weld spatter
by using either by nozzle or with spot blasting equipment. Where
85 | Technical Specifications
blasting is not available, grinding, sanding or brushing may be used provided
satisfactory degree of cleaning is obtained.
Oil and grease shall be removed with mineral spiritsor appropriate solvent. Before
painting, ferrous metal surfaces, including galvanized ferrous metal surfaces, shall be
pretreated with approved phosphoric acid etching cleaner in accordance with
manufacturer's direction to produce a chemically clean surface. Unless already
performed in accordance with specifications of other sections, abrasions and bare
spots in shop prime coatings shall be touched up with metal primer matching shop
coatings. Enamel undercoats shall be sandpapered by hand (with No. 00 sandpaper)
and dusted clean before applying succeeding coats.
e. Woodwork
a. General
All painting and finishing shall be performed by skiled craftsmen. Each coat of paint
shall be applied at proper consistency, evenly, and free of laps, sags, and runs and
cut sharply to required lines. Except as otherwise specified or required, paint shall be
applied only under dry and dust- ‐free conditions that will insure properly finished
surfaces, free of defects and blemishes. Paint shall not be applied when temperature
is likely to be above 32°c (90°F). Sufficient time shall be allowed between coats to
insure proper drying. All primer and intermediate coats shall be unscarred and
completely integral at lime of application of each succeeding coat. The Engineer shall
be notified when each coal has been applied and is ready for inspection. Until each
coat is inspected and approved by Engineer, no succeeding coats shall be applied.
Whenever two coats of a dark- ‐colored paint are specified, the first coal shall contain
sufficient powdered aluminum to act as an indicator for proper coverage when
applying the second coat.
b. Methods of Application
86 | Technical Specifications
Except as otherwise specified or when, in the opinion of the Engineer, a particular
method would produce unsatisfactory results, paint maybe applied by brush, spray,
or other application method at the option of the Contractor.
1. Priming
2. Back Painting
Woodwork millwork, and casework to be installed against concrete, masonry, or
plaster shall be back painted with one coat of exterior oil paint.
87 | Technical Specifications
11 – SECURITY FENCING
11.1 GENERAL
The Contractor shall furnish and install the fencing as shown and specified. Fencing shall
be topped with three (3) lines of barbed wire unless otherwise shown. Fencing shall be
1.83m (6 ft) high unless otherwise shown.
a. Materials
1. Fabric shall be 63.5 mm (2-‐1/2 in.) diamond, type A, No. 11 gage wire.
2. Fabric ties shall be No. 9 gage galvanized steel wire, spaced 0.35m (14 in.) apart
on posts and 0.61m (2 ft.) aparton rails. Aluminum ties will not be permitted. A
continuous No. 7 gage galvanized steel wire shall be interlaced with the fabric
along the extreme bottom of the fence, and shall be pulled taut.
3. Line posts shall be standard weight 63.0 mm (2-‐1/2 in.) OD pipe, 5.44 kg per
metre (3.65 lb per foot).
4. End and corner posts shall be 76.0 mm (3 in.) OD pipe, 8.63 kg per metre (5.79
lb per foot).
5. Gate posts shall be 102 mm (4 in.) OD pipe, 13.56 kg per metre (9.1 lb per foot).
6. Top rail and braces shall be 41.3 mm (1-‐5/8 in.) OD pipe, 3.38 kg per metre
(2.27 lb per foot).
7. Nuts, bolts, and screws shall be of galvanized steel, minimum size 9.5 mm (3/8
in.)
8. Swing gate frames, if any, shall be constructed of pipe at least as heavy as the
top rails for the fence and shall be fabricated by welding. Each gate lead shall be
provided with at least one diagonal brace. Frames shall be galvanized after
fabrication. Galvanized malleable iron fittings for latching the gate shall be
provided. Fabric shall match the fabric used in fence. Each, pair of gates shall be
provided with heavy drop rod latch assembly with a locking device for a padlock.
9. Concrete shall have minimum compressive strength of 13.8 Mpa (2000 psi) at
the age of twenty-‐eight (28) days.
88 | Technical Specifications
b. Installation
1. Post shall be set plumb and shall be centered inconcrete encasement. The top
surfaces of the concrete encasement shall be sloped outward to shed water and
shall have a neat appearance. Line posts shall be spaced not more than 3.0 m (10
ft.) apart and shall be set in the ground to a depth of 0.91 m (3 ft.). Post shall be
set in concrete bases not less than 0.30 m (12 in.) in diameter.
2. Bracing shall be provided at all end, gate and corner posts, the latter in both
directions. Horizontal brace rails shall be set midway between top rail and
ground running from the corner end and or gate post to 1 st line post. Diagonal
tension members shall connect tautly between posts below horizontal braces.
Barbed wire shall be 2-‐strand, 4 point, No. 12-‐1/2 gage galvanized steel wire with 14
gage barbs spaced at 13 cm on centers.
a. Materials
When part of fence is made of CHB, it shall be of 100 mm (4") CHB unless shown
otherwise on the Drawings. Masonry works shall conform with the requirement of
Clause 19 -‐ Concrete Masonry.
b. Columns
Gate columns and fence columns sizes and details shall be as shown on the
Drawings. Concrete works shall conform with the requirement of Clause 4 -‐
Reinforced Concrete.
Gates and frames shall be fabricated and of sizes indicated on the Drawings and
shall be of the quality and workmanship acceptable to the Engineer. The Contractor
shall guarantee the gates and frames against any defect due to fabrication and
installation. Before fabrication of the gate and frames, the inside surfaces shall be
shop painted with one coat of an approved rust-‐inhibitive
89 | Technical Specifications
synthetic primer. Fabric shall be the same as specified above and welded evenly
throughout the frame. The Contractor shall provide all necessary hardware which
shall conform with the requirements Clause 5 -‐ Steel and Miscellaneous metal
work.
d. Installation
The Contractor shall erect the fence as shown on the Drawings so that the finished
fence is plumb, taut, true to line and grade, and complete in all details. The
Contractor shall stake down fence where required. Columns shall be spaced and
constructed as shown on the Drawings.
The Contractor shall submit, for the Engineer's approval, complete shop drawings which
shall include all details requested by the Engineer. The Engineer shall approve these
drawings before installation.
90 | Technical Specifications
91 | Technical Specifications
12 – ELECTRO-‐MECHANICAL EQUIPMENT
12.1 GENERAL
a. The Contractor shall furnish, deliver, install, test and commission at site all
mechanical/electrical equipment specified herein. He shall provide the necessary
supervision, tools, materials, supplies and appurtenances for the proper installation,
testing and operation of the completely assembled equipment.
b. All equipment furnished and installed shall be brand new and non- ‐obsolete (at most
three years’ ex-‐stock), unused and guaranteed from defects in material, design
and/or workmanship. Importation papers of ex- ‐stock equipment shall be submitted.
No equipment or material shall be delivered for installation on site prior to the
return of acceptable shop drawings submitted by the Contractor in accordance with
Clause 2. The Contractor shall submit, together with the shop drawings, a
certification of the availability of spare parts and service locally in case of system
breakdown for a period of five (5) years.
c. The work under this Contract shall be done in accordance with the requirements of
the latest edition of the Philippine Electrical Code, the rules, regulations and
requirements of electrical and telephone utilities as far as their permanent services
are concerned, and the government ordinances enforced in the locality. In case of
conflict with these specifications or the drawings, the preceding clause shall govern.
d. The Contractor shall be responsible for securing all necessary permits from the
appropriate government authorities at his own expense both for the electrical and
mechanical construction and for the operation of the system upon completion of the
work. The Contractor shall furnish the Owner with the approved Certificate of Final
Electrical and Mechanical Inspection.
f. The Contractor shall coordinate and work with all the other parties with whose
apparatus he shall connect part/s of the work required herein. The Contractorshall
prepare drawings or details of the equipment he supplied, location of sleeves,
conduits and supports that may be required by other trades and shall furnish the
Owner with at least five (5) copies of these drawings, for the information of all
parties concerned. The approval of such drawings shall not relieve the Contractor in
any way from the responsibility of properly locating and/or coordinating his work
with those of other parties involved.
92 | Technical Specifications
g. The minimum efficiencies specified herein are the minimum laboratory efficiencies
for a completely staged unit. The Contractor shall furnish copies of certified non- ‐
witnessed performance test for the imported equipment. In the absence of such
certification and for locally-‐manufactured/assembled equipment, a local laboratory
testing shall be conducted on the equipment in the presence of authorized
representatives. In no case shall the Contractor be allowed to deliver and install the
unit until a satisfactory laboratory test is attained. The cost of making the test shall
be borne entirely by the Contractor.
h. The contractor shall be responsible for all components, and for satisfactory
installation and operation of the completely assembled unit, including the motors,
motor controllers and pumps.
i. The equipment and installation shall be guaranteed for a period of at least one (1)
year of operation. The Contractor shall furnish and replace, without cost to the
Owner, any equipment or part that is defective or shows undue wear within one (1)
year after acceptance of the contract work. A warranty certificate shall be issued to
the Owner, effectivity date of which shall start on the same day until has/have been
accepted. A duplicate copy of the same shall be furnished to the Engineer. All
incidental expenses relative to the warranty work shall be borne entirely by the
Contractor.
j. All mechanical and electrical equipment shall be tested to the satisfaction of the
Engineer before any facility is put into operation. Tests shall be made to determine
whether the equipment has been properly assembled, aligned, adjusted and
connected. Any changes, adjustments or replacements required to make the
equipment operate as specified shall be carried out by the Contractor as part of the
work. In addition to the mentioned testing conditions, the following field test
requirements should be considered for electrical equipment, materials and
components.
1. System Test -‐ Each panel board shall be tested with the power equipment
connected, circuit breakers closed and all loads and fixtures permanently
connected for their intended operation for a minimum of 24 hours continuous
operation in the presence of the Engineer, at the expense of the Contractor. The
entire installation shall be free from any ground fault and from any short circuit.
In no case shall the insulation resistance be less than that allowed by PEC
regulations for Electrical Equipment of Buildings and/or manufacturers'
recommendations. Failures shall be corrected in a manner satisfactory to the
Engineer.
93 | Technical Specifications
k. Upon completion of the contract work, the Contractor shall arrange that a field-‐
testing be conducted on the electro- ‐mechanical equipment by the Engineers/s in his
presence. The test shall be made to show that the installed equipment satisfies its
specifications and operational requirements. The contract work will not be accepted
and final payment will not be recommended until satisfactory test has been made. In
the event of failure of the equipment to meet the guaranteed efficiencies or to
operate to the Engineer's satisfaction during the first official field test, the Contractor
shall make such modifications and repairs and shall receive no additional
compensation therefore. Failure of the equipment to meet the contract
requirements in three (3) official field tests shall be a ground for rejection. Expenses
to be incurred, including the travel expenses of Engineers, during the second and last
official field test shall be charged to the Contractor. The test run shall be made within
thirty (30) days upon receipt of the Contractor's request for such testing. Provided,
however, that if the Engineer fail to make tile test within the said period, the field
test shall not further delay the acceptance of the work.
Above field test shall be made only after the Contractor has furnished the Engineer/s
a copy of satisfactory results of his initial or preliminary; tests on the equipment as
part of his work and without cost to the Owner.
During the testing of the equipment, the Contractor shall arrangeto have available
qualified persons who shall instruct the plant personnel in the operation and care
thereof. Only after all the equipment has been tested and adjusted shall the new
facilities be put into operation. Acceptance testing of equipment shall not include
initial start-‐up and adjustment of equipment. All equipment shall be tested for
proper operation and undergo initial adjustment prior to acceptance.
l. Before the acceptance of the work, Contractor shall furnish, for each piece of
equipment supplied, two (2) complete bound sets giving information listed below (in
English Language):
1. Clear and concise instruction for the operation, adjustment and lubrication and
other maintenance of the equipment.
2. Parts list of the equipment with catalog numbers and other data necessary for
ordering replacement parts in the future.
4. Where materials of construction are not specified, the Supplier shall use first class
commercial grades best suited for the particular use for which they are
employed.
94 | Technical Specifications
12.2 MECHANICAL EQUIPMENT
a. Scope of Work
The Contractor shall furnish, deliver, install, test and commission in accordance with
these Specifications and drawings submersible/vertical/horizontal centrifugal pump
and motor set, complete with motors controller, discharge elbow/head, discharge
piping with valves and fittings; standby diesel generating set/industrial type, diesel
engine complete with combination right angle gear drive, chlorinating equipment
and other appurtenances as specified herein and shown on the drawings.
b. Submersible Pump
Descriptions
i. Number of units
ii. Minimum capacity at design head, L/S
iii. Design head, TDM, m
iv. Minimum pump laboratory efficiency at design head exclusive of pump
column friction, Percent
v. Nominal size of column pipe, mm
vi. Length of column pipe (from bottom of discharge elbow lo top of bowl
assembly), m
vii. Design speed, rpm
viii. Maximum diameter of motor/pump bowl including cable guard, mm
ix. Length of submersible cable, m
x. Maximum Motor Horse power, HP
There shall be no point within the operating range of the pump wherein the
required horsepower exceeds the rated motor horsepower. Inaddition to the
above requirements, the design point shall be located within the best efficiency
range of the pump. Efficiency range shall be within the - ‐5% of the pump’s peak
efficiency.
2. Pump Construction
i. Pump Element -‐ The impellers shall be of the semi- ‐open or enclosed type,
constructed of bronze or stainless steel, accurately fitted, smoothly finished,
and dynamically balanced at normal pump speeds. Impellers constructed of
thermoplastic material may be used only when the computed down thrust at
design condition is less than 2000 lbs., with a motor rating not to exceed 5
HP. They shall have removable wearing rings and lateral seal rings mounted
on their companion cases. The bowl cases shall be constructed of closed
grained cast iron or stainless steel. Cast iron bowls shall be provided with
non-‐toxic epoxy or glass enamel lining. Pump bearings shall be at least
95 | Technical Specifications
2-‐1/2 times the diameter of the shaft. The pump shaft shall be of type 416
stainless steel.
ii. Column Pipe -‐ The column pipe for the deepwell pump shall be seamless
black iron not lighter than schedule 40, furnished in 3.0 metres (10 ft)
maximum length, and shall be connected with threaded couplings. The pump
suction shall include a stainless steel strainer. The inlet area shall be equal to
at least five (5) times the impeller inlet area. A non- ‐leak check valve shall be
provided and installed at the top portion of the bowl assembly.
iii. The pump shall have a nameplate showing the serial number of the
equipment and the name of the manufacturer. The nameplate shall show the
capacity in liters per second, TDH in metres and rated speed in revolutions
per minute. Such other information as the manufacturer may consider
necessary for complete identification shall be shown on the plate. The
nameplate of the distributing agent shall not be acceptable. The nameplate
shall be securely fastened to the equipment in a location affording easy
viewing.
Descriptions:
i. Number of units
ii. Minimum capacity at design head, L/S
iii. Design head, TDH, M
iv. Minimum pump laboratory efficiency at design head exclusive of
pump column friction, percent
v. Nominal size of column, pipe, mm
vi. Length of column pipe (from bottom to top of bowl assembly), M
vii. Design speed, RPM
96 | Technical Specifications
viii. Maximum bowl diameter, mm
ix. Maximum Motor Horse power, HP
There shall be no point within the operating range of the pump wherein the
required horsepower exceeds the rated motor horsepower. In addition to
the above requirements, the design point shall be located within the best
efficiency range of the pump. Efficiency range shall be within the- ‐5% of the
pump's peak efficiency (0.05 x PPE).
2. Pump Construction
ii. Column Pipe and Line Shaft -‐ The column pipe for the vertical
turbine pump shall not be lighter than schedule 40 seamless steel
pipe, furnished in 3.0 metres (1O ft) maximum length, and shall be
connected with threaded couplings. The joints shall be butted to
insure perfect column alignment after assembling. The shaft shall be
furnished in interchangeable section not over three (3) metres (10 ft)
in length. It shall be coupled with extra- ‐strong threaded coupling
machined from solid steel bar and shall have a diameter capable of
transmitting the required power carrying the necessary weight and
thrust without vibration. The line shaft shall be type 416 stainless
steel. The vertical turbine pump shall be provided with stainless steel
cone type strainer which shall have a net inlet opening area of not
less than three (3) times the cross-‐sectional area of the suction pipe.
iv. Discharge Head -‐ The discharge head shall be of the above surface
type of either cast iron or steel and shall include a 16 mm (5/8") thick
sole plate to be grouted in place after the pump has been aligned.
The well shall be sealed using rubber gasket between the discharge
head and the sole plate as shown on the drawings. The discharge
flanges shall be sized as specified and shall meet the requirements of
ANSI specifications B16-‐5. The stuffing box shall be
97 | Technical Specifications
constructed with bronze bearing or bushing below the packing and
shall be readily accessible.
The stuffing box leakage can be collected and drawn off through a
pipe connected to the discharge head.
v. The pump shall have a nameplate showing the serial number of the
equipment and the name of the manufacturer. The nameplate shall
show the capacity in litres per second, TDH in metres and rated
speed in revolutions per minute. Such other information as the
manufacturer may consider necessary for complete identification
shall be shown on the plate. The nameplate of the distributing agent
shall not be acceptable. The nameplate shall be securely fastened to
the equipment in a location affording easy viewing.
3. Motor – The contractor shall provide and install a vertical hollow shaft motor in
the proposed pumping station as shown on the drawings. The motor shall be
rated as per operating requirements schedule and shall be of the squirrel cage,
induction type with non-‐reversing ratchet mechanism, rated at ________
(460/230) volts, _______ 1/3 phase, 1800 rpm, 60 HZ AC with 1.15 service
factor. The motor shall be NEMA design B with drip- ‐proof enclosure. Motor
shall have Class B or Class F insulation with temperature rise as specified by
NEMA standard for class of insulation used. It shall be fitted with a permanent
non-‐ corrosive nameplate in which all NEMA standard motor data are
stamped/engraved in English and Metric units.
1. General -‐ The horizontal centrifugal pump shall be used to pump water from the
impounding reservoir to the distribution system, and shall be of the split case,
end suction or multi-‐stage horizontal type as required.
Descriptions:
i. Number of units
ii. Minimum capacity at design head, Us
iii. Design head, TOH, m
iv. Minimum pump laboratory efficiency at design head exclusive of pump
column friction, percent
v. Nominal size of column pipe, mm
vi. Required Net Positive Suction Head, m
vii. Location of pump suction strainer, m
viii. Design speed, rpm
ix. Maximum Motor Horsepower, HP
98 | Technical Specifications
There shall be no point within the operating range of the pump wherein the
required horsepower exceeds the rated motor horsepower. In addition to
the above requirements, the design point shall be located within the best
efficiency range of the pump. Efficiency range shall be within the- ‐5% of the
pump's peak efficiency (0.05 x PPE).
ii. Impellers – The impellers shall be enclosed type of bronze or stainless steel
accurately fitted, smoothly finished and dynamically balanced at normal
pump speeds.
iii. Pump Shaft – The shaft shall be designed to have adequate diameter
considering the power transmission, pump thrust, critical velocity and
deflection and shall be precisely fabricated and finished. The pump shall be
manufactured of stainless steel and shall be provided with bronze or
stainless sleeves that are easily replaceable.
v. Motor -‐ The motor shall be squirrel cage, induction type, rated ______
(460/230) volts, ______ (1/3) phase, 3600 rpm/1800 rpm, 60 HZ AC with
1.15 minimum service factor. The motor shall be either a NEMA design B, or
JEC B or its equivalent with drip- ‐proof enclosure. Motor shall be of class B
or Class F insulation with temperature rise as specified by NEMA standards
for class of insulation used. It shall be fitted with permanent non- ‐corrosive
nameplate on which all standard data shall be stamped/engraved in English.
e. Chlorinating Equipment
99 | Technical Specifications
ii. (a) Vacuum-‐operated Gas Chlorinator
(iii) Pump Construction -‐ The pump shall be of high head, low capacity,
centrifugal, end-‐suction type that should satisfy the operational
requirements of the system chlorine ejector supplied herewith. It shall
be close-‐coupled, factory aligned to a heavy duty motor and mounted
together on a common steel or cast-‐iron base. The suction and
discharge connections shall be cast integral with the casing. The casing
and bearing housings shall be of 30,000 pound tensile cast- ‐iron. Pump
impellers shall be of enclosed type constructed of bronze, stainless steel
or thermoplastic or any other materials suited for the particular
application, mechanically and hydraulically balanced, securely fastened
to the shaft with keys, taper bushings and locknuts. The motor shall have
a horsepower (Hp) rating as specified in the contract documents, 230v,
(1/3) phase, 60 Hz, 3450/1750 RPM and with minimum service factor of
1.15. The motor shall be interconnected with the well pump motor
control so that they will start and stop simultaneously.
(4) Motor Control for Booster Pump -‐ The motor controller shall be of
the full voltage magnetic starter type with circuit breaker, overload
protective device and on/off buttons suited for the booster pump to be
supplied.
The pressure feed type gas chlorinator shall only be used for application
where there is either no electricity to run a booster pump or no
pressurized water supply offering a sufficient differential for vacuum
operation and shall be operated by the inside pressure of the chlorine
cylinder. Back pressure at the point of application shall not exceed 10 psi.
iv. Chlorine Test Kit -‐ The test kit shall be of colorimetric type and the residual
chlorine shall be determined by a simple visual comparison between
permanent color standards of known value and sample color. The test kit
shall be capable of analyzing for total chlorine using orthotolidine solution
method. The unit shall have a range of 0- ‐5 mil or ppm with increments of
0.1 mg/L or ppm. Orthotolidine solution shall be provided with the test kit.
v. Chlorine Gas Mask -‐The Contractor/Supplier shall furnish one canister type
gas mask with full face lens for the proposed pumping station complete with
canister suitable for working condition for short periodsof time in the
presence of less than one percent (1%) chlorine concentration. The mask
shall be provided with carrying case, manufacturer's instruction manual,
two (2) extra canisters and shall be of the type recommended by the
Chlorine Institute Standard.
2. Hypochlorination Equipment
ii. Capacity -‐ The feed pump shall have a maximum operating capacity in
gal/day (gpd) of hypochlorite solution, as specified in the contract
documents and shall be equipped with manually operated knob control
mounted on top of the pump suitable for the above maximum feed rate. A
feed indicator shall permit visual monitor of fluid rate at any lime.
iii. Operation -‐ The rate of hypochlorite solution feed shall be set manually
and shall remain constant until manually changed. Feed rate adjustment
shall be permitted while the unit is in operation. The hypochlorite feed
pump shall be rated 230 VAC, single phase and 60Hz.
v. Powder Chlorine -‐ The unit shall be provided with ____ drums (45 kg) of
calcium hypochlorite powder with 70% available chlorine.
vi. Chlorine Test Kit -‐ The test kit shall be of colorimetric type and the residual
chlorine shall be determined by a simple visual comparison between
permanent color standard of known value and sample color. The test kit
3. Flowmeter/Totalizer
ii. A test run will be conducted in the presence of the Engineer, Owner and
the Contractor. In the event of the failure of the flowmeter / totalizer to
operate to meet specifications. The supplier shall replace the unitand
shall receive no additional compensation thereof. For the purpose of
payment, the work will not be accepted until the test has been made to
the satisfaction of the Owner and the Engineer.
iii. The flowmeter shall be magnetic drive, propeller type and shal be
furnished with integral cast body grained high tensile cast iron faced and
drilled with ANSI flanged ends, and shall be designed and manufactured
according to ISO 4064/1-‐ 1977, with a nominal working pressure of 150
psi and shall be furnished with non- ‐ corrosive, non-‐toxic liners which
shall have straightening vanes. The flowmeter shall be suitable for
nominal flows for the required capacity and shall register within two
percent (2%) of true flows at all flows within 1he rated range. The
register drive shall be completely isolated from the water pressure by an
O ring sealed bronze housing. The propeller drive shall be magnetically
coupled to the register drive by use of permanent type ceramic magnet.
The propeller shall be fabricated of thermoplastic material resistant to
normal water corrosion. The meter shall be furnished with a six- ‐digit
straight reading type of totalizer indicating flows in cubic metre and a dial
or flow rate indicator in cubic metre per hour (m 3/hr) with graduations
from 0 to 360 m3/hr.
° Name of Manufacturer
° Nominal Flow (Qn) in m3/hr
° Year of Manufacture and Serial Number
° Indicator of Flow Direction
° Working Pressure in bar
The water meter shall conform to the requirements of ISO 4064 Part 1: Measurement of
Water Flow in Closed conduits- ‐Meters for Cold Potable Water, subject to the following
additional requirements.
The meter body (or casing) shall be brand new, manufactured from copper alloy
containing not less than 75% copper; or a copper alloy containing not less than 57%
copper, with an anti-‐ corrosion treatment. Meter bodies shall be smoothly finished and
free from defects. Bodies which have been repaired are not acceptable. All coatings
shall be free from defects of any kind. Meter bodies shall have a common inlet- ‐outlet
axis and shall be suitable for horizontal installation.
All external fasteners and seals shall be designed for easy disassembly, after a lengthy
in-‐service use, without the need for special tools or equipment.
The measuring chamber of the meter shall be a self- ‐contained unit manufactured
either in copper alloy containing not less than 85% copper with suitable amounts of tin,
lead and zinc, or in a suitable synthetic polymer, that will withstand all normal
conditions of operation without change in form or dimension. It shall be firmly seated
and easily removed, and be secured so that the meter's accuracy will not be adversely
affected by any distortion of the meter body.
The movement of the measuring element (rotor) shall be transmitted to the register
magnet by means of a permanent driver magnet on the upper end of theelement's
spindle. The magnet shall be of suitable non- ‐corrosive, magnetic material. The
magnetic coupling shall be protected from external magnetic fields of 1,500 gauss by
suitable shielding.
13.4 REGISTER
The lens covering register dial shall be securely fastened to achieve hemetical sealing
and shall be of clear tempered glass of 5 mm minimum thickness (or of suitable
synthetic polymer which shall of be of high impact ultra violet stabilized polycarbonate
resin film of clear transparency. Dial lenses shall be resistant to impact and abrasion.
Impact resistance shall be taken as the capability to resist the impact of a 12mm
diameter steel dropped from a height of one (1) meter without sustaining any evident
damage. Abrasion resistance shall be taken as the capability to resist permanent scratch
marks using a material not harder than a Philippine one peso coin. Meter dial lenses
shall be held in place by a hinged lid or similar holding device of suitable synthetic
polymer.
Register box ring and lid shall be of the same material composition as the meter body
or of suitable synthetic polymer.
Each meter shall be provided with a pair of tailpieces. Tailpieces shall be of the same
material composition as the meter body.
The end of the tailpiece joining the meter spud shall have a shoulder and shall be
provided with gasket. The opposite end of the tailpiece shall have external tapered right
hand pipe threads in accordance with ISO recommendation R7.
The length of the tailpieces shall be such that the overalllength of the assembly (meter
length-‐ face to face of spuds-‐plus length of two (2) tailpieces) shall be as follows:
13.9 SEALING
Each meter shall be supplied with 2.5 mm diameter copper wire and other suitable type
of seal system to discourage unauthorized opening or removal of the meter and also lo
indicate if such unauthorized act has been made. All elements of the sealing system
including length of wire. location of wire holes, etc., shall be suitable for covering all
possible means of tempering in particular, disturbance of the coupling nuts of the
accuracy adjustment device, if there is any; and of the register assembly. The seal shall
be blank and suitable for sealing by a compression tool. The sealing elements shall be
provided in such a way that after sealing, both before and after the water meter has
been correctly installed, there is no possibility of altering or dismantling the meter
without damaging the sealing elements.
The maximum pressure loss shall be 1bar over the entire flow range.
13.12 WARRANTY
All meters shall be guaranteed against defects in workmanship and materials for a
period of one (1) year from the date of acceptance. Defective meters or parts discovered
within this period shall be replaced without charge upon their return tothe
manufacturer/supplier. This warranty shall not apply if the meter has been modified by
using replacement parts not made by the manufacturer of the meter or if it has been
exposed to service conditions exceeding those of normal operating conditions.
The manufacturer also guarantees that replacements (whole meter), replacement parts
and service shall be made available within thirty (30) calendar days from notice during a
period of at least five (5) years from date of acceptance.
13.13 ACCREDITATION
c. If it does, the following tests may be conducted on five (5) new sealed samples: