San Vicente Day Care

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views4 pages

San Vicente Day Care

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Republic of the Philippines

Province of Antique
Municipality of Culasi

QUANTITY TAKE-OFF

Project Name : Repair and Maintenance of Day Care Center


Project Location : Brgy. San Vicente, Culasi, Antique

Item Description Thickness/ Volume


Item No. Length (m) Width 1 Width 2 Area (sq.m.)
Stationing/Location Member/Description Depth (cu.m.)
EXCAVATION
Location 1
sta 0+000 sta 0+008 2 SIDES 8.00 0.20 0.30 0.96
ITEM 103 Location 2
sta 0+000 sta 0+022 Left side 22.00 0.30 0.20 1.32

TOTAL 2.28

GROUTED RIPRAP
Location 1
sta 0+000 sta 0+008 2 SIDES 8.00 0.20 0.50 1.60
Location 2
511 sta 0+000 sta 0+022 Left side 22.00 0.30 0.20 1.32
Location 3
Apron Bedding 6.00 2.00 5.00 0.30 6.30

TOTAL 9.22

Prepared by: Approved by:

ENGR. RYAN R. MARQUEZ ENGR. MARLON S. DUBLA


Municipal Technical Facilitator Municipal Engineer
REPUBLIC OF THE PHILIPPINES
PROVINCE OF ANTIQUE
MUNICIPALITY OF CULASI

DETAILED ESTIMATES

Sub-Project Title: Repair and Maintenance of Day Care Center


Project Location: Brgy. San Vicente, Culasi, Antique
Total Project Cost: PHP 37,000.00
Physical Target: .10 km.
Project Unit Cost: 370,000.00 per km.
Project Duration: 25 Calendar Days

ITEM Description Qty. Unit No. of Days Unit Cost Total Cost

SPL1 MISCELLANEOUS
Unit 1.00 lot
By direct counting
A. Materials
1 Gang Switch 1.00 pc. 250.00 250.00
Flourescent Lamp 2.00 pcs. 500.00 1,000.00
Flourescent Lamp starter 2.00 pcs. 50.00 100.00
7W LED bulb 2.00 pcs. 350.00 700.00
Heavy duty Door knob 2.00 sets 600.00 1,200.00
1/4" Marine plywood 5.00 pcs. 750.00 3,750.00
2"x2"x12' good lumber 10.00 pcs. 135.00 1,350.00
1" CWN 1.00 kgs. 75.00 75.00
2" Concrete Nails 1.00 kgs 120.00 120.00
Flat Latex white 2.00 L 170.00 340.00
1/4L Raw siena 1.00 pc. 80.00 80.00
Roof Paint 4.00 gall. 750.00 3,000.00
4" paint brush 2.00 pcs. 95.00 190.00
2" paint brush 2.00 pcs. 45.00 90.00
Sub-total 12,245.00
B. Labor
Carpenter 2.00 person 5.00 280.00 2,800.00
Laborers 2.00 person 5.00 200.00 2,000.00
Sub-total 4,800.00

Unit Cost #REF! per cu.m.


Total Cost 17,045.00

SPL 1 BILLBOARD INSTALLATION


KC Billboard 1.00 lot
A. Materials
0.40mm x 1.2 x 2.4 GI Sheet 1.00 sht 350.00 350.00
50mm Schedule 40 GI Pipe 1.00 length 1,600.00 1,600.00
3mm x 25mm Angle Bar 2.00 length 520.00 1,040.00
Welding Rod 0.50 kg 120.00 60.00
1/8 x 1/2 Blind rivets 100.00 pcs 2.50 250.00
Portland Cement 1.00 bag 260.00 260.00
Metal Primer 1.00 li 140.00 140.00
Quick dry enamel (white) 2.00 li 160.00 320.00
Quick dry enamel (black) 1.00 qt. 160.00 160.00
Tinting color(blue) 1.00 pint 108.00 108.00
Tinting color(yellow) 1.00 pint 108.00 108.00
Tinting color(red) 1.00 pint 108.00 108.00
1" Paint Brush 1.00 pcs. 18.00 18.00
2" paint brush 1.00 pcs. 34.00 34.00
B. Labor
Painter 2.00 person 280.00 560.00
Carpenter 1.00 person 280.00 280.00
Laborer 4.00 person 200.00 800.00

Unit Cost 6,196.00 per each


Total Cost 6,196.00

ITEM 602 MONUMENTS AND MARKERS


KC Monument 1.00 lot
A. Materials
12"x12" S/S Name Plate 1 pc 6,500.00 6,500.00
B. Labor
Laborer 2.00 person 1.00 200.00 400.00

Unit Cost 6,900.00 per each


Total Cost 6,900.00
TOTAL DIRECT COST PHP 30,141.00

SUMMARY OF DIRECT COST


Materials 23,301.00
Equipment
Labor
Unskilled 3,200.00
Skilled 3,640.00
Total 30,141.00

TOTAL DIRECT COST PHP 30,141.00

Prepared by: Reviewed by:

ENGR. RYAN R. MARQUEZ ENGR. MARLON S. DUBLA


Municipal Deputy Area Coordinator Municipal Engineer

Concurred by: Approved by:

LEIZEL CHARICE A. UNTAL HON. JOSE JEFFREY Y. LOMUGDANG


Municipal Area Corrdinator Municipal Mayor
REPUBLIC OF THE PHILIPPINES
PROVINCE OF ANTIQUE
MUNICIPALITY OF CULASI
PROGRAM OF WORKS

Name of Project: Repair and Maintenance of Day Care Center Net Length: 38.00 m.
Location: Brgy. San Vicente, Culasi, Antique Thickness: varies
Appropriation: PHP 37,000.00
KALAHI CIDSS MUNICIPAL TRUST ACCOUNT(LGU
Source of Funds: Project Category: Slope Protection
UNIT FUND)
Mode of Implementation: By Contract Classification: Gabion
Duration: 25.00 CD Total Project Duration: 25 Calendar days
No. Of Working Days: 20 Calendar Days
No. of Pre-Determined
Unworkable Days: 5 Calendar days

Minimum Equipment Requirements Minimum Manpower Requirements


Construction Foreman 1
Skilled Labor 2
Unskilled Labor 4

Unit of
Item Scope of Work % Wt. Quantity Unit Price Total Amount
Measurement
SPL 1 GROUTED RIPRAP 56.55 1.00 lot 17,045.00 17,045.00
SPL 1 BILLBOARD INSTALLATION 20.56 1.00 lot 6,196.00 6,196.00
ITEM 602 MONUMENTS AND MARKERS 22.89 1.00 lot 6,900.00 6,900.00
Total Direct Cost 100.00 30,141.00

Source of Fund
Breakdown of Expenditures Municipal LGU
Total Cost
Cash In-kind
A. DIRECT COST
A.1 Materials 23,301.00 23,301.00
A.2 Labor
A.2.1 Skilled 3,640.00 3,640.00
A.2.2 Unskilled 3,200.00 3,200.00
A.3 Equipment 0.00 -
SUB-TOTAL 30,141.00
B. INDIRECT COST
B.1 Contractor's Profit (10% of A) 3,014.10 3,014.10
B.2 OCM (8% of A) 1,781.59 1,781.59
B.3 Mobilization(1% of A) 301.41 301.41
SUB-TOTAL 5,097.10
C. TAXES (5% of A+B) 1,761.90 1,761.90
SUB-TOTAL 1,761.90
TOTAL PROJECT COST PHP 37,000.00

Prepared by: Approved by:

ENGR. RYAN R. MARQUEZ ENGR. MARLON S. DUBLA


Municipal Technical Facilitator Municipal Engineer

LEIZEL CHARICE A. UNTAL HON. JOSE JEFFREY Y. LOMUGDANG


Municipal Area Corrdinator Municipal Mayor