                                                   QUANTITY TAKE-OFF
Project Name :        Repair and Maintenance of Day Care Center
Project Location :    Brgy. San Vicente, Culasi, Antique
                       Item Description                                                      Thickness/                Volume
 Item No.                                         Length (m) Width 1  Width 2                           Area (sq.m.)
           Stationing/Location Member/Description                                              Depth                   (cu.m.)
         EXCAVATION
         Location 1
         sta 0+000 sta 0+008          2 SIDES           8.00     0.20                              0.30                    0.96
ITEM 103 Location 2
         sta 0+000 sta 0+022          Left side        22.00     0.30                              0.20                    1.32
                                                            TOTAL                                                       2.28
            GROUTED RIPRAP
            Location 1
            sta 0+000 sta 0+008        2 SIDES                  8.00         0.20                  0.50                    1.60
            Location 2
   511      sta 0+000 sta 0+022        Left side              22.00          0.30                  0.20                    1.32
            Location 3
            Apron Bedding                                       6.00         2.00     5.00         0.30                    6.30
                                                            TOTAL                                                          9.22
Prepared by:                                                           Approved by:
ENGR. RYAN R. MARQUEZ                                                  ENGR. MARLON S. DUBLA
Municipal Technical Facilitator                                        Municipal Engineer
                                                         REPUBLIC OF THE PHILIPPINES
                                                            PROVINCE OF ANTIQUE
                                                           MUNICIPALITY OF CULASI
                                                          DETAILED ESTIMATES
Sub-Project Title:    Repair and Maintenance of Day Care Center
Project Location:     Brgy. San Vicente, Culasi, Antique
Total Project Cost:   PHP 37,000.00
Physical Target:      .10 km.
Project Unit Cost:    370,000.00 per km.
Project Duration:     25 Calendar Days
       ITEM                                Description                    Qty.    Unit       No. of Days Unit Cost         Total Cost
   SPL1               MISCELLANEOUS
                      Unit                                                1.00     lot
                      By direct counting
   A. Materials
                      1 Gang Switch                                       1.00      pc.                           250.00            250.00
                      Flourescent Lamp                                    2.00     pcs.                           500.00          1,000.00
                      Flourescent Lamp starter                            2.00     pcs.                            50.00            100.00
                      7W LED bulb                                         2.00     pcs.                           350.00            700.00
                      Heavy duty Door knob                                2.00     sets                           600.00          1,200.00
                      1/4" Marine plywood                                 5.00     pcs.                           750.00          3,750.00
                      2"x2"x12' good lumber                               10.00    pcs.                           135.00          1,350.00
                      1" CWN                                              1.00     kgs.                            75.00             75.00
                      2" Concrete Nails                                   1.00     kgs                            120.00            120.00
                      Flat Latex white                                    2.00       L                            170.00            340.00
                      1/4L Raw siena                                      1.00      pc.                            80.00             80.00
                      Roof Paint                                          4.00     gall.                          750.00          3,000.00
                      4" paint brush                                      2.00     pcs.                            95.00            190.00
                      2" paint brush                                      2.00     pcs.                            45.00             90.00
                                                                                                      Sub-total                  12,245.00
   B. Labor
                      Carpenter                                           2.00    person           5.00          280.00           2,800.00
                      Laborers                                            2.00    person           5.00          200.00           2,000.00
                                                                                                       Sub-total                  4,800.00
                      Unit Cost                                                            #REF!            per cu.m.
                      Total Cost                                                                                                 17,045.00
         SPL 1        BILLBOARD INSTALLATION
                      KC Billboard                                        1.00     lot
   A. Materials
                      0.40mm x 1.2 x 2.4 GI Sheet                         1.00      sht                       350.00                 350.00
                      50mm Schedule 40 GI Pipe                            1.00    length                     1,600.00              1,600.00
                      3mm x 25mm Angle Bar                                2.00    length                      520.00               1,040.00
                      Welding Rod                                         0.50      kg                        120.00                  60.00
                      1/8 x 1/2 Blind rivets                             100.00     pcs                        2.50                  250.00
                      Portland Cement                                     1.00      bag                       260.00                 260.00
                      Metal Primer                                        1.00       li                       140.00                 140.00
                      Quick dry enamel (white)                            2.00       li                       160.00                 320.00
                      Quick dry enamel (black)                            1.00      qt.                       160.00                 160.00
                      Tinting color(blue)                                 1.00     pint                       108.00                 108.00
                      Tinting color(yellow)                               1.00     pint                       108.00                 108.00
                      Tinting color(red)                                  1.00     pint                       108.00                 108.00
                      1" Paint Brush                                      1.00     pcs.                       18.00                   18.00
                      2" paint brush                                      1.00     pcs.                       34.00                   34.00
   B. Labor
                      Painter                                             2.00    person                     280.00                 560.00
                      Carpenter                                           1.00    person                     280.00                 280.00
                      Laborer                                             4.00    person                     200.00                 800.00
                      Unit Cost                                                          6,196.00           per each
                      Total Cost                                                                                                  6,196.00
   ITEM 602           MONUMENTS AND MARKERS
                      KC Monument                                         1.00     lot
   A. Materials
                      12"x12" S/S Name Plate                               1        pc                        6,500.00            6,500.00
   B. Labor
                      Laborer                                             2.00    person           1.00           200.00            400.00
                      Unit Cost                                                          6,900.00           per each
                      Total Cost                                                                                                  6,900.00
   TOTAL DIRECT COST                                                                 PHP 30,141.00
                                          SUMMARY OF DIRECT COST
Materials                                                                                  23,301.00
Equipment
Labor
   Unskilled                                                                               3,200.00
   Skilled                                                                                 3,640.00
Total                                                                                      30,141.00
                                    TOTAL DIRECT COST                               PHP 30,141.00
Prepared by:                                                       Reviewed by:
ENGR. RYAN R. MARQUEZ                                              ENGR. MARLON S. DUBLA
Municipal Deputy Area Coordinator                                  Municipal Engineer
Concurred by:                                                      Approved by:
LEIZEL CHARICE A. UNTAL                                            HON. JOSE JEFFREY Y. LOMUGDANG
Municipal Area Corrdinator                                         Municipal Mayor
                                                   REPUBLIC OF THE PHILIPPINES
                                                      PROVINCE OF ANTIQUE
                                                     MUNICIPALITY OF CULASI
                                                      PROGRAM OF WORKS
Name of Project:           Repair and Maintenance of Day Care Center                      Net Length:                38.00 m.
Location:                  Brgy. San Vicente, Culasi, Antique                             Thickness:                varies
Appropriation:             PHP 37,000.00
                           KALAHI CIDSS MUNICIPAL TRUST ACCOUNT(LGU
Source of Funds:                                                                          Project Category: Slope Protection
                           UNIT FUND)
Mode of Implementation: By Contract                                                       Classification: Gabion
Duration:         25.00 CD                                                                Total Project Duration:           25 Calendar days
                                                                                          No. Of Working Days:              20 Calendar Days
                                                                                          No. of Pre-Determined
                                                                                          Unworkable Days:                  5 Calendar days
           Minimum Equipment Requirements                                      Minimum Manpower Requirements
                                                  Construction Foreman                                                          1
                                                  Skilled Labor                                                                 2
                                                  Unskilled Labor                                                               4
                                                                                              Unit of
Item                       Scope of Work            % Wt.                Quantity                              Unit Price       Total Amount
                                                                                            Measurement
SPL 1           GROUTED RIPRAP                      56.55           1.00                  lot                  17,045.00                 17,045.00
SPL 1           BILLBOARD INSTALLATION              20.56           1.00                  lot                  6,196.00                   6,196.00
ITEM 602        MONUMENTS AND MARKERS               22.89           1.00                  lot                  6,900.00                   6,900.00
                 Total Direct Cost                  100.00                                                                               30,141.00
                                                                                                Source of Fund
                                Breakdown of Expenditures                                       Municipal LGU
                                                                                                                                    Total Cost
                                                                                               Cash         In-kind
A. DIRECT COST
   A.1 Materials                                                                                  23,301.00                               23,301.00
   A.2 Labor
         A.2.1 Skilled                                                                             3,640.00                                3,640.00
         A.2.2 Unskilled                                                                           3,200.00                                3,200.00
   A.3 Equipment                                                                                        0.00                                     -
                   SUB-TOTAL                                                                                                              30,141.00
B. INDIRECT COST
   B.1 Contractor's Profit (10% of A)                                                              3,014.10                                3,014.10
   B.2 OCM (8% of A)                                                                               1,781.59                                1,781.59
   B.3 Mobilization(1% of A)                                                                        301.41                                  301.41
                   SUB-TOTAL                                                                                                               5,097.10
C. TAXES (5% of A+B)                                                                              1,761.90                                 1,761.90
                   SUB-TOTAL                                                                                                               1,761.90
TOTAL PROJECT COST                                                                                                                   PHP 37,000.00
Prepared by:                                                               Approved by:
ENGR. RYAN R. MARQUEZ                                                      ENGR. MARLON S. DUBLA
Municipal Technical Facilitator                                            Municipal Engineer
LEIZEL CHARICE A. UNTAL                                                    HON. JOSE JEFFREY Y. LOMUGDANG
Municipal Area Corrdinator                                                 Municipal Mayor