0% found this document useful (0 votes)
28 views168 pages

Part B

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views168 pages

Part B

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 168

PART ‘B’ - 59

PART – B
Name of work: Providing repairs to existing plumbing, drainage, tile flooring,
doors and ducts including internal electrical installations etc in Kakatiya Hall of
Residence (1.0K) at NIT Warangal-Reg. Complete Renovation of toilet,
bathrooms, shafts and Approximately 60 damaged hostel rooms-Reg

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 60

Blank

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 61

INDEX- PART-B

Sl. No. Particulars Page No.

1 INDEX 61

2 Special conditions 62-63

3 Additional conditions (Civil component) 64-106

4 Special Conditions for Green Building 107-115

5 Particular Specifications (Civil component) 116-166

6 List of Field Tests and Equipment for Testing of Materials &


167-169
Concrete at Site Laboratory

7 Plant And Equipment Required To Be Owned / Taken On Lease By 170


The Contractor

8 Guarantee Bonds. 171-174

9 Seigniorage Fee 175-180

10 Standard Operating Procedures (SOPs) and Guidelines for 181-191


Construction Sites for COVID-19 Outbreak

11 List of Preferred brand / Manufacturer/ Make (Civil component) 192-226

EE & SM (C)-II
CPWD, Warangal

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 62

SPECIAL CONDITIONS
1.0 General
1.1 Specifications & Order of preference:
1.1.1 Except for the items, for which Particular Specifications are given or where it is
specifically mentioned otherwise in the description of the items in the schedule of
quantities, the work shall generally be carried out in accordance with the “CPWD
Specifications 2019 Vol. I & II” with up to date correction slips, additional / Particular
Specifications, Architectural / structural drawings and as per instructions of Engineer- in-
Charge.
1.1.2 The several documents forming the tender are to be taken as mutually
complementary to one another. Detailed drawings shall be followed in preference to
small scale drawings and figured dimensions in preference to scaled dimensions.
1.1.3 If there is any difference or discrepancy between the description of items as given in
the schedule of quantities, particular specifications for individual items of work
(including special conditions) and I.S. Codes etc., the following order of preference
shall be observed
(i) Description of items as given in Schedule of Quantities.
(ii) Particular Specifications, Special Conditions and Additional conditions, if
any.
(iii) Drawings.
(iv) CPWD Specifications.
(v) General conditions of contract for CPWD works.
(vi) Indian Standard Specifications of B.I.S.
(vii) Manufacturers’ specifications & as decided by Engineer-in-charge.
(viii) Sound Engineering practices.
(ix) Decision of Engineer in charge.
“In the event of any variation/ discrepancy in the drawings, specifications and tender
documents etc. the decision of the Engineer-in-charge shall be final binding and
conclusive on the contractor and in the case the contractor have any doubt and the
same should be got clarified immediately from the Engineer-in-charge and no claim
of the contractor shall be entertained thereafter. Moreover, the agency is not
allowed to take benefit out of any clerical/ grammatical mistake in the standard
clauses/Schedule of Quantities/Specifications etc. being used in the agreement”.
1.1.4 Any reference made to any Indian Standard Specifications, shall imply to the latest
version of that standard, including such revisions / amendments as issued by the
Bureau of Indian Standards up to last date of receipt of tenders. The Contractor shall
keep at his own cost all such publications including relevant Indian Standard Codes
applicable to the work at site.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 63

1.2 Scope:
1.2.1 The works to be governed by this contract shall cover delivery and
transportation up to destination, safe custody at site, insurance, erection, testing
and commissioning of the entire works.
1.2.2.1 The works to be undertaken by the contractor shall inter alia include the following:
i. Preparation of detailed SHOP and detailed civil services drawings and AS
BUILT drawings wherever applicable.
ii. Obtaining of Statutory permissions wherever applicable and required.
iii. Pre-commissioning tests as per relevant standard specifications, code of
practice, Acts and Rules wherever required.
iv. Warranty obligation for the equipment and/or fittings/fixtures supplied by
the contractor.
1.2.3 Contractor shall provide all the Shop drawings or services drawings . These shop
drawings /services drawings shall be got approved from Engineer-in-charge before
implementation and this shall be binding on the contractor. The contractor shall
submit material submittals along with material sample for approval of Engineer-in-
charge prior to delivery of material at site.
1.2.4 All the hidden items such as water supply lines, drainage pipes, conduits, sewers
etc. are to be properly tested as per the design conditions before covering and their
measurements in computerized measurement book duly test checked shall be
deposited with Engineer in charge or his authorized representative, prior to hiding
these items.
1.3 Deployment of Technical staff & skilled labour:
1.3.1 The quality of work is of paramount importance. Contractor shall have to engage
well experienced skilled labour and deploy modern T&P and other equipments to
execute the work to provide the desired quality.
The Contractor shall depute Site Engineer & skilled workers as required for the work.
He shall submit organization chart along with details of Engineers and supervisory
staff. It shall be ensured that all decision making powers shall be available to the
representatives of the contractor at site itself to avoid any likely delays on this
account. The contractor shall also furnish list of persons for specialized works to be
executed for various items of work. The Contractor shall identify and deploy key
persons having qualifications and experience in the similar and other major works, as
per the field of their expertise. If during the course of execution of work, the Engineer-
in-Charge is of the opinion that the deployed staff is not sufficient or not well
experienced; the Contractor shall deploy more staff or better-experienced staff

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 64

at site to complete the work with quality and in stipulated time limit. The Project
Manager of the contractor having minimum twenty years of experience in similar
nature of work along with all technical staff as mentioned in the clause 32 of the
GCC, shall always be available at the site during execution of work.
1.4 Removal of Machinery, Tools & Equipment:
1.4.1 Removal of machinery, tools & equipment shall be allowed to be moved away from
the site only when, in written opinion of Engineer-in-Charge, the same are no longer
required at site of work.
1.5 Soil conditions of site:
1.5.1 Contractor(s) shall study the soil and satisfy himself about complete characteristics
of soil and other parameters at site. No claim whatsoever on account of any
discrepancy between the sub-surface strata conditions that may be actually
encountered at the time of execution of the work and those given in soil report, in-
accuracy or interpretation thereof shall be entertained from the Contractor under
any circumstances. The ground water table is in variable condition and it may vary
from time to time.
1.6 Site condition:
1.6.1 The tenderer shall acquaint himself with the site of work and see the approaches to
the site. In case any approach from main road is required at site or existing approach
is to be improved and maintained for cartage of materials by the contractor, the
same shall be provided, improved and maintained by the contractor at his own cost.
1.7 Precautionary measures:
1.7.1 Temporary barricading shall be provided at Site by the contractor at their own cost.
The barricading physically define the boundaries of the plot for restricted entry to
only those involved in the work and also to prevent any accident and also not
causing any inconvenience to the traffic. The barricading panels shall be painted and
“CPWD” mark should be made in suitable size, shapes and number as directed by
Engineer-in-charge without any extra cost. It shall be dismantled and taken away by
the contractor after completion of the work at his own cost with the permission of
Engineer-in-charge.
1.7.2 Contractor shall take all precautionary measures to avoid any damage to adjoining
property. All necessary arrangement shall be made at his own cost. The contractor
shall take all precautions to prevent his workmen and employees from removing and
damaging any Flora (plant/vegetation) from the campus/site.
1.7.3 The contractor shall take all precautions to avoid accidents by exhibiting necessary
caution boards day and night, speed limit boards, red flags, red lights and providing
barriers. He shall be responsible for all damages and accidents caused to work due to
negligence on his part. No hindrances shall be caused to traffic, during the execution

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 65

of the work. In case of any accident of the labourers/ contractual staff, the entire
responsibility will rest on the contractor and any compensation under such
circumstances, if becomes payable, shall be entirely borne by the contractor.
1.7.4 The contractor, his authorized representative, workmen etc. shall strictly observe
orders pertaining to fire precautions prevailing in the area.
1.7.5 The Contractor shall take all necessary precautions to prevent any nuisance or
inconvenience to the owners, tenants or occupants of the adjacent properties and to
the public in general .The Contractor shall take all care, as not to damage any other
adjacent property or other services running adjacent to the plot. If any damage is
done, the same shall be made good by the Contractor at his own cost and to the
entire satisfaction of the Engineer-in-Charge. The Contractor shall use such
methodology and equipments for execution of the work, so as to cause minimum
environmental pollution of any kind during construction, to have minimum
construction time and minimum inconvenience to road users and to the occupants of
the buildings on the adjacent plot and public in general, etc. He shall make good at
his own cost and to the entire satisfaction of the Engineer in Charge any damage to
roads, paths, cross drainage works or public or private property whatsoever caused,
due to the execution of the work or by traffic brought thereon, by the Contractor.
Further, the Contractor shall take all precautions to prevent any pollution of streams
and waterways. All waste or superfluous materials shall be carted away by the
Contractor, entirely to the satisfaction of the Engineer-in-Charge. Utmost care shall
be taken to keep the noise level to the barest minimum so that no disturbance as far
as possible is caused to the occupants / users of adjoining buildings. No claim what
so ever on account of site constraints mentioned above or any other site constraints
not specifically stated here, shall be entertained from the Contractor. Therefore, the
Contractors are advised to visit site and get first hand information of site constraints.
Accordingly, they should quote their tenders. Nothing extra shall be payable on this
account.
1.8 General cleanliness of the site and Stacking & Storage of Materials:
1.8.1 The site of work shall be always kept clean in general strictly adhering to approved
job layout and green building parameters. The Contractor shall take all care to
prevent any water- logging at site. The waste water shall not be allowed to be
collected at site. It may be directly pumped into the public drainage system with
prior approval of the concerned authorities. For discharge into public drainage
system, necessary permission shall be obtained from concerned authorities after
paying the necessary charges, if any, directly to the authorities. The work shall be
carried out in such a way that the area is kept clean and tidy. All the fees/charges in
this regard shall be borne by the Contractor. Nothing extra shall be payable on this
account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 66

1.8.2 The contractor shall take instructions from the Engineer-in-Charge regarding
collection and stacking of materials at any place. No excavated earth or building
rubbish shall be stacked on areas where other buildings, roads, compound wall,
services etc are to be constructed.
1.8.3 For construction works which are likely to generate malba / rubbish, contractor shall
dispose of malba, rubbish & other unserviceable materials and wastes at his own
cost to the notified/specified dumping ground and under no circumstances these
shall be stacked / dumped even temporarily, outside the construction premises.
1.8.4 The contractor shall construct suitable godowns, yard at the site of work for storing
all other materials so as to be safe against damage by sun, rain, damages, fire, theft
etc. at his own cost and also employ necessary watch and ward establishment for
the purpose at his cost.
1.9 Lab Equipment:
The contractor shall provide at his own cost suitable weighing, surveying and
levelling and measuring arrangements as may be necessary at site for checking. All
such equipments shall be got calibrated in advance from laboratory, approved by the
Engineer-in-Charge. Nothing extra shall be payable on this account. A site laboratory
with the minimum equipments as specified in NIT shall be established, made
functional and maintained within 21 days from the award of the work without any
extra cost to the department.
1.10 Setting Out
1.10.1 The contractor shall establish, maintain and assume responsibility for grades, lines,
levels and bench marks. He shall report any errors or inconsistencies regarding
grades, lines, levels, dimensions to the Engineer-in-Charge before commencing
work. Commencement of work shall be regarded as the contractor’s acceptance of
such grades, lines, levels and dimensions and no claim shall be entertained at a later
date for any errors found.
1.10.2 In order to set the alignment of buildings / foundations and to mark the same on
the ground, the agency is to adopt “total station” surveying method. The agency is
to engage a well versed and well experienced surveyor in “total station” survey.
Nothing extra for this total station survey is payable
If at any time, any error in the respect of setting out appears during the progress of
the work, the contractor shall, at his own expense rectify such error if so required,
to the satisfaction of the Engineer-in-Charge.
a) Though the site levels are indicated in the drawings, the contractor shall
ascertain himself and confirm the site levels with respect to GTS bench mark
from the concerned authorities. The contractor shall protect and maintain
temporary/ permanent benchmarks at the site of work throughout the

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 67

execution of the work. These bench marks shall be got checked by the Engineer-
in-Charge or his authorized representatives. The work at different stages shall
be checked with reference to bench marks maintained for the said
purpose. Nothing extra shall be payable on this account.
b) The approval by the Engineer-in-Charge, of the setting out by the contractor,
shall not relieve the contractor of any of his responsibilities and obligation to
rectify the errors/defects, if any, which may be found at any stage during the
progress of the work or after the completion of the work.
1.10.3 The contractor shall be entirely and exclusively responsible for the horizontal, vertical
and other alignments, the level and correctness of every part of the work and shall
rectify effectively any errors or imperfections therein. Such rectifications shall be
carried out by the contractor at his own cost to the instructions and satisfaction of
the Engineer-in-Charge.

1.10.4 The Contractor shall carry out survey of the work area, at his own cost, setting
out the layout of building in consultation with the Engineer-in-Charge & proceed
further. Any discrepancy between the architectural drawings and actual layout at
site shall be brought to the notice of the Engineer-in-charge. It shall be
responsibility of the Contractor to ensure correct setting out of alignment. Total
station survey instruments only shall be used for layout, fixing boundaries, and
centre lines, etc., along with the odolites. Nothing extra shall be payable on this
account.
1.10.5 Contractor shall provide permanent bench marks, flag tops and other reference
points for the proper execution of work and these shall be preserved till the end of
work. All such reference points shall be in relation to the levels and locations, given
in the Architectural and plumbing drawings.
1.11 Temporary Water, Electricity & Telephone Connections:
1.11.1 The contractor shall make his own arrangements for water including boring of tube
wells etc. if necessary and for Electricity by obtaining electric connections and by
providing diesel generators of adequate capacity if required and make necessary
payments directly to the State Govt. departments concerned. Necessary approval
shall be taken by the contractor from the ground water department for boring of
tube wells. Nothing extra shall be paid on these accounts. Contractor shall get the
water tested from laboratory approved by the Engineer-in-charge at regular
interval as per the CPWD Specifications 2019 as amended up to date. All expenses
towards collection of samples, packing, transportation except testing charges etc.
shall be borne by the contractor. The contractor shall obtain environmental and
pollution clearance for the diesel generators. Nothing extra shall be paid on this
account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 68

1.11.2 The Contractor shall arrange electricity at his own cost for testing of the various
electrical installations as directed by Engineer-in-Charge and for the consumption
by the contractor for executing the work. Also all the water required for testing
various electrical installations, fire pumps, wet riser / fire fighting equipments, fire
sprinklers etc. and also testing water supply, sanitary and drainage lines, water
proofing of underground sump, overhead tanks, water proofing treatment etc. shall
be arranged by the contractor at his own cost. Nothing extra shall be payable on
this account.
1.11.3 Arrangement of temporary telephone connection, water and electricity required by
Contractor, shall be made by him at his own cost and also necessary permissions
shall be obtained by him directly from concerned authorities, under intimation to
the Department. Also, all initial cost and running charges, and security deposit, if
any, in this regard shall be borne by him. The Contractor shall abide by all the rules/
bye laws applicable in this regard and he shall be solely responsible for any penalty
on account of violation of any of the rules / byelaws in this regard. Nothing extra
shall be payable on this account.
1.11.4 The Contractor shall be responsible for maintenance and watch and ward of the
complete installation and water / electricity meter and shall also be responsible for
any pilferage, theft, damage, penalty etc. in this regard. The Contractor shall
indemnify the Department against any claim arising out of pilferage, theft, damage,
penalty etc. whatsoever on this account. Security deposit for the work shall be
released only after No Dues Certificates are obtained from the local Authorities from
whom temporary electric/ water / telephone connection have been obtained by the
Contractor. Nothing extra shall be payable on this account.
1.11.5 The Department shall in no way be responsible for either any delay in getting electric
and/or water and/or telephone connections for carrying out the work or not getting
connections at all. No claim of delay or any other kind, whatsoever, on this account
shall be entertained from the Contractor. Also contingency arrangement of stand-by
water & electrical supply shall be made by the Contractor commencement and
smooth progress of the work so that work does not suffer on account of power
failure or disconnection or not getting connection at all. No claim of any kind
whatsoever shall be entertained on this account from the Contractor. Nothing extra
shall be payable on this account.
1.12 Architectural and structural Drawings:
1.12.1 Indicative Architectural drawings are attached in Part- F of NIT. However during
execution, if any drawings are required, then the same shall be prepared, submitted
by the agency well in advance and get them approved by the Engineer in Charge
for which no extra cost is payable and no extra time is allowed.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 69

1.12.2 The information and site data shown in the drawings and mentioned herein and
also elsewhere in the tender documents are being furnished for general
information and guidance only. The department shall not bear responsibility for
lack of such knowledge and also the consequences thereof. The Engineer-in-
charge in no case shall be held responsible for the accuracy thereof or any
interpretation/ or conclusions drawn there from by the contractor.
1.13 Scaffolding &Staging:
1.13.1 Wherever required for the execution of work, all the scaffolding shall be provided
and suitably fixed, by the contractor. The scaffolding shall be provided strictly
with steel double scaffolding system, suitably braced for stability, with all the
accessories, gangways, etc with adjustable suitable working platforms to access
the areas with ease for working and inspection. Single scaffolding system is strictly
prohibited and shall invite necessary action. It shall be designed to take all
incidental loads. It should cater to the safety features for workmen. Nothing extra
shall be payable on this account. It shall be ensured that no damage is caused to
any structure due to the scaffolding.
1.13.2 The contractor should submit the shop drawings of staging and shuttering for
approval of Engineer-in-Charge before actually commencing the execution of
work under the item. Nothing extra shall be payable on this account.
1.14 Co-ordination with other agencies:
1.14.1 The Contractor shall conduct his work so as not to interfere with or hinder the
progress of the work being performed by other Contractors or by the Engineer-in-
Charge. As far as possible, he shall arrange his work and place, so as not to
interfere with the operations of other Contractors or shall arrange his work with
that of the others, in an acceptable and coordinated manner and shall perform it
in proper sequence.
1.14.2 Other agencies may also simultaneously execute and install the works and the
contractor shall afford necessary facilities for the same. The contractor shall leave
such recesses, holes, openings, trenches etc. as may be required for such related
works (for which inserts, sleeves, brackets, conduits, base plates, clamps etc. shall
be available as specified elsewhere in the contract) and the contractor shall fix the
same at the time of casting of concrete, stone work and brick work, if required,
and nothing extra shall be payable on this account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 70

1.14.3 The Contractor shall cooperate with and provide the facilities to the associate-
Contractors and other agencies working at site for smooth execution of the work.
The Contractor shall –
(i) Allow use of scaffolding already erected, toilets, sheds etc.
(ii) Properly co-ordinate their work with the work of other Contractors.
(iii) Provide control lines and benchmarks to his associate-Contractors and the
other Contractors.
(iv) Provide electricity and water at mutually agreed rates.
(v) Provide hoist and crane facilities for lifting material at mutually agreed
rates.
(vi) Co-ordinate with other Contractors for leaving inserts, making chases,
alignment of services etc. at site.
(vii) Adjust work schedule and site activities in consultation with the Engineer-
in-Charge and other Contractors to suit the overall schedule completion.
Resolve the disputes with other Contractor amicably and the Engineer-in-
Charge shall not be made intermediary or arbitrator. The contractor shall
indemnify the Department against any claim(s) arising out of such
disputes.
1.15 Procurement of materials:
1.15.1 All materials shall only be brought at site as per program as finalised with E-
in-C /as per Milestones included in Part-A of NIT. Materials should be brought
to site as per Phase wise requirement . Any pre-delivery of materials not
required for immediate consumption shall not be accepted and thus not paid
for.
For any material brought prematurely at site without approval of Engineer-In-
Charge, no payment shall be made for such material and Department shall not be
responsible for its damage / deterioration.
Materials shall be brought to site only after taking correct measurements as per
actual requirement of work strictly in accordance with conditions/Clauses of the
tender document. Excess quantities shall not be accepted and paid. i.e., Quantity of
items brought to site and used in work as per actual requirement shall only be
measured and paid irrespective of quantities of BOQ / work schedule.
The agency shall bring the various items & materials as per actual requirement at
site at the time of execution of work strictly in accordance with conditions/clauses
of the tender document The contractor should ensure from the Engineer-in-
charge and from the site condition the actual quantity required / to be used / to be
supplied before bringing the materials at site.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 71

1.15.2 The contractor shall procure the required materials in advance so that there is
sufficient time for testing of the materials and approval of the same before use in
the work.
1.16 Protection of Existing Services & buildings and Materials:
1.16.1 Existing drains, pipes, cables, over-head wires, sewer lines, water lines and similar
services encountered in the course of the execution of work shall be protected
against the damage by the contractor at his own expense. The contractor shall not
store materials or otherwise occupy any part of the site in a manner likely to
hinder the operation of such services. In case temporary supporting of such
services is required to facilitate the work, the same shall be done by the
contractor at no extra cost.
1.16.2 In case the existing services are to be shifted permanently, then before
dismantling the existing services, alternate/diversion of service lines has to be laid
by the contractor so that there is no interruption in use of existing services. The

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 72

contractor has to plan the alternate suitable route for diversion/shifting of service
lines and get the same approved from the Engineer-in-Charge before starting
shifting of services. Nothing extra shall be paid except the payment of dismantling
and laying of new service lines as per conditions of contract.
1.16.3 All fossils, coins, articles of value of antiquity, structures and other remains or
things of geological or archaeological interest discovered on project location
during excavation/construction shall be the property of the Government, and
shall be dealt with as per provisions of the relevant legislation. The contractor will
take reasonable precaution to prevent his workmen or any other persons from
removing and damaging any such article or thing. He will, immediately upon
discovery thereof and before removal acquaint the Engineer-in-charge of such
discovery and carry out the official instructions of Engineer-in-charge for dealing
with the same, till then all work shall be carried out in a way so as not to disturb/
damage such article or thing.
1.16.4 The contractor shall be responsible for the watch and ward / guard of the
buildings, safety of all fittings and fixtures including sanitary and water supply
fittings and fixtures provided by him against pilferage and breakage during the
period of installations and thereafter till the building is physically handed over to
the client department. No extra payment shall be made on this account.
1.16.5 The contractor shall be fully responsible for the safe custody of materials brought
by him/ issued to him even though the materials may be under double lock key
system.
1.17 Rates and other conditions for payment:
The rates quoted by the Contractor are deemed to be inclusive of the following--
1.17.1 Site clearance, setting out work, profile, establishment of reference bench
mark(s), taking spot levels, construction of all safety and protection devices,
barriers, barricading, signage, labour safety, welfare & training measures,
preparatory works, working during monsoon, working at all depths, height, lead,
lift and location etc until / unless specified otherwise, implementation of green
building norms to achieve desired GRIHA ( 3 star) Rating etc. and any other
incidental works required to complete this work. Nothing extra shall be payable
on this account. Payment for centring & shuttering, however, if required to be
done for floor heights greater than 3.50m shall be admissible at rates arrived in
accordance with clause 12 of the agreement if not already specified.
1.17.2 For works below ground level the contractor shall keep that area free from water.
If dewatering or bailing out of water is required the contractor shall do it and
nothing extra shall be paid except otherwise provided in the items of schedule of
quantities.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 73

1.17.3 Any legal or financial implications resulting out of disposal of earth shall be sole
responsibility of the contractor. Nothing extra over the schedule shall be paid on
this account.
1.17.4 All labour, material, tools and plants and other inputs involved in the execution of
the item.
1.17.5 Providing sunk flooring in bath-rooms etc.
1.17.6 Performance test of the entire installation(s) before the work is finally accepted.
1.17.7 Any cement slurry added over base surface (or) for continuation of concreting for
better bond is deemed to have been built in the items.
1.17.8 The percentage quoted by the tenderer, shall be inclusive of all taxes including
GST and levies applicable in respect of this contract shall be payable by the
contractor and Government will not entertain any claim whatsoever in respect of
the same.
1.17.9 For completing the work in time, the Contractor might be required to work in two
or more shifts (including night shifts). No claim whatsoever shall be entertained
on this account, not with-standing the fact that the Contractor may have to pay
extra amounts for any reason, to the labourers and other staff engaged directly or
indirectly on the work according to the provisions of the labour and other
statutory bodies regulations and the agreement entered upon by the Contractor
with them.
1.17.10 The Contractor shall keep himself fully informed of all acts and laws of the Central
& State Governments, all orders, decrees of statutory bodies, tribunals having any
jurisdiction or authority, which in any manner may affect those engaged or
employed and anything related to carrying out the work. All the rules &
regulations and bye-laws laid down by Collector / MC etc. and any other statutory
bodies shall be adhered to, by the contractor, during the execution of work. The
Contractor shall also adhere to all traffic restrictions notified by the local
authorities. It is clarified that the extra sewerage charges (one time charges for
commencement of work) required to be paid to the Municipal Corporation / other
statutory bodies shall be paid by the department and need not be considered by
the contractor. The water charges (for municipal water connection as well as
tanker water) shall be borne by the contractor. Also, if the contractor obtains
water connection for the drinking purposes from the municipal authorities or any
other statutory body, the consequent sewerage charges shall be borne by the
contractor. All statutory taxes, levies, charges (including GST, water and sewerage
charges, charges for temporary service connections and / or any other charges)
payable to such authorities for carrying out the work, shall be borne by the
Contractor. The Contractor shall arrange to give all notices as required by any
statutory / regulatory authority and obtain all requisite licenses wherever

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 74

required and shall pay to such authority all the fees that are required to be paid
for the execution of work. He shall protect and indemnify the Department and its
officials & employees against any claim and /or liability arising out of violations of
any such laws, ordinances, orders, decrees, by himself or by his employees or his
authorized representatives. Nothing extra shall be payable on these accounts. The
fee payable to statutory authorities for obtaining the various permanent service
connections and Occupancy Certificate for the building shall be borne by the
Department.
1.17.11 Royalty at the prevalent rates including contribution towards Mineral Exploration
Research and Innovation Trust (MERIT) @ 2% on Seigniorage fee and District
Mineral Foundation (DMF) @ 30% of Royality / Seigniorage fee shall have to be
paid by the contractor (Rates of Seigniorage fee enclosed in the document is for
guidance only and no claims shall be entertained on account of this) on all the
boulders, stone aggregate, brick aggregate, shingle, coarse or fine sand, earth,
gravel, bajri etc. collected by him for the execution of the work, directly to the
Revenue Authority or authorized agent of the State Government concerned or
Central Government.
Royalty at the prevalent rates including contribution towards Mineral Exploration
Research and Innovation Trust (MERIT) @ 2% on Seigniorage fee and District
Mineral Foundation (DMF) @ 30% of Royality / Seigniorage fee shall be paid by
the contractor or the RMC supplier as per the terms of supply between them, on
all materials such as stone aggregate, coarse or fine sand etc. collected by him for
the execution of the work, directly to the revenue authority of the State
Government concerned. Further, contractor needs to submit proof of submission
of full royalty to the State Government or local authority. Nothing extra shall be
payable on this account.
1.17.12 All ancillary and incidental facilities required for execution of work like labour
camp, stores, fabrication yard, offices for Contractor, watch and ward, temporary
ramp required to be made for working at the basement level, temporary structure
for plants and machineries, water storage tanks, installation and consumption
charges of temporary electricity, telephone, water etc. required for execution of
the work, liaison and pursuing for obtaining various No Objection Certificates,
completion certificates from local bodies etc., protection works, barricading,
testing facilities / laboratory at site of work, facilities for all field tests and for
taking samples etc. during execution or any other activity which is necessary (for
execution of work and as directed by Engineer-in-Charge), shall be deemed to be
included in rates quoted by the Contractor, for various items in the schedule of
quantities. Nothing extra shall be payable on these accounts. Before start of the
work, the Contractor shall submit to the Engineer-in-Charge, a site / construction
yard layout, specifying areas for construction, site office, positioning of

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 75

machinery, material yard, cement and other storage, steel fabrication yard, site
laboratory, water tank, etc.
1.17.13 The Contractor shall assume all liability, financial or otherwise in connection with
this contract and shall protect and indemnify the Department from any and all
damages and claims that may arise on any account. The Contractor shall
indemnify the Department against all claims in respect of patent rights, royalties,
design, trademarks of name or other protected rights, damages to adjacent
buildings, roads or members of public, in course of execution of work or any other
reasons whatsoever, and shall himself defend all actions arising from such claims
and shall indemnify the Department in all respect from such actions, costs and
expenses. Nothing extra shall be payable on this account.
1.17.14 The Contractor shall make all necessary arrangements for protecting from rain or
likewise extreme weather conditions, the work already executed and for carrying
out the further work, during monsoon including providing and fixing temporary
shelters, protections etc. Nothing extra shall be payable on this account. Also, no
claims for hindrance shall be entertained on this account.
1.17.15 In case of flooding of site on account of rain or any other cause and any
consequent damage, whatsoever, no claim financially or otherwise shall be
entertained not withstanding any other provisions elsewhere in the contract
agreement. Also, the Contractor shall make good, at his own cost, the damages
caused, if any. Further, no claims for hindrance shall be entertained on this
account.
1.17.16 No payment shall be made for any damage caused by fire, rain, snowfall, flood or
any other natural calamity, whatsoever during the execution of the work. The
contractor shall be fully responsible for any damage to the govt. property and the
work for which payment has been advanced to him under the contract and he
shall make good the same at his risk and cost. The contractor shall be fully
responsible for safety and security of his material, T&P/Machinery brought to the
site by him. The contractor shall maintain all the work in good condition at his
own cost till the completion of the entire work.
1.17.17 In case the same item appears more than once in the schedule of work under the
same sub head or among the different sub heads of works, the lowest rate quoted
for that item shall be taken for other items also and tender will be evaluated
accordingly.
1.17.18 The ESI and EPF contribution on the part of employer in respect of this contract
shall be paid by the contractor. These contributions on the part of employer paid
by the contractor shall be reimbursed by the Engineer in charge to the contractor
on actual basis. The applicable and eligible amount of EPF& ESI shall be

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 76

reimbursed preferably within 7 days but not later than 30 days of submission of
documentary proof of payment which are in order.
1.18 Foreign Exchange:
1.18.1 No foreign exchange shall be made available by the Department for importing
(purchase) of equipment, plants, machinery, materials of any kind or any other
items if required to be carried out during execution of the work. No delay and no
claim of any kind shall be entertained from the Contractor, on account of
variation in the foreign exchange rate.
1.181.2 The contractors have to quote the corresponding imported items in “Indian
Rupees” in the Schedule of Quantities which shall include all incidental charges
including freight, taxes including GST, import duties, fluctuations in currency
rates. No extra payment will be made over and above the quoted rates.
1.19 Tools & Plant:
1.19.1 No tools and plants including any special T&P etc. shall be supplied by the
Department and the Contractor shall have to make his own arrangements at his
own cost. No claim of hindrance (or any other claim) shall be entertained on this
account.
1.20 As Built & Service Drawings:
1.20.1 The contractor shall submit completion plan (4 sets) as required vide General
Specifications for Electrical works (Part-I internal) 2005 and (Part-ll External) 1994
as applicable within thirty days of the completion of the work.
In case, the contractor fails to submit the completion plan as aforesaid, he shall be
liable to pay a sum of 0.1 % of Tendered Value as may be fixed by the SE cum PD,
CPWD, Hindupur concerned and in this respect the decision of the Superintending
Engineer shall be final and binding on the contractor.
The contractor shall submit completion plans for all the Internal and External Civil,
Electrical and Mechanical Services within thirty days of the completion of the
work.
1.21 Computerized MBs & SMBs:
1.21.1 The contractor shall make available four (04) sets of computerized Standard
Measurement Books (SMBs) having measurement of all the permanent standing
in a building.
1.21.2 The contractor will submit computerized measurement sheet for the work carried
out by him for making payment as per Clause – ‘6’ of the CPWD General

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 77

Conditions of Contract 2023 (with correction slips up to the last date of


submission of tender). For casting of RCC members and other hidden items the
corrected and duly test checked measurement sheets of reinforcement or that of
other hidden items shall be deposited with Engineer in charge or his authorized
representative, before casting of RCC or other hidden items. The delay in
submission of corrected and duly checked measurement sheet may, therefore,
delay casting of RCC or execution of hidden item for which no hindrance shall be
recorded.
1.21.3 Electronic measurement book is introduced. The contractor shall comply with the
same as per the direction of Engineer-in-charge.
1.22 Water Supply & Sanitary Installations & Testing:
1.22.1 Water tanks, taps, sanitary, water supply and drainage pipes, fittings and
accessories should conform to approved manufacturers specifications where
CPWD Specifications are not applicable. The contractor should get the
materials (fixtures/fittings) tested from approved labs wherever required at his
own cost.
1.22.2 The contractor shall give performance test of the entire installation(s) as per the
standing specifications before the work is finally accepted and nothing extra
whatsoever shall be payable to the contractor for the test.
2.0 RECORDING OF HINDRANCES:-
2.1 No Hindrance register will be maintained at site. All the hindrances shall be entered
by contractor in the “online delay control system” of CPWD by following the
procedure explained in CPWD office memorandum no. DG/MAN/394 dated
25.01.2020. Whenever any hindrance comes to the notice of the contractor he
should at once bring it to the notice of Engineer-in-charge who will resolves the
same at the earliest.
2.2 The Contractor shall apply for EOT if the date of completion is to be extended
because of such hindrance.
3.0 SECRECY
3.1 The contractor shall take all steps necessary that all persons employed on any work
in connection with the contract have noticed that the Indian Official Secrets Act 1923
applies to them & will continue so to apply even after the execution of such works
under the contract.
3.2 The contract is confidential and must be strictly confined to the contractor’s own use
(except so far as confidential disclosure to sub-contractors or suppliers as necessary)
and to the purpose of the contract.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 78

3.3 All documents, copies thereof & extracts there from furnished to the contractor shall
be returned to the Engineer-in-Charge on the completion of the work / works or the
earlier determination of the contract.
4.0 LABOUR AND SECURITY
4.1 In the event of the contractor(s) committing a default or breach of any of the
provisions of the Central Public Works Department, Contractor’s Labour Regulations
and Model Rules for the protection of health and sanitary arrangements for the
workers as amended from time to time or furnishing any information or submitting
or filing any statement under the provisions of the above Regulations and’ Rules
which is materially incorrect, he/they shall, without prejudice to any other liability,
pay to the Government a sum not exceeding Rs.500/- for every default, breach or
furnishing, making, submitting, filing such materially incorrect statements and in the
event of the contractor(s) defaulting continuously in this respect, the penalty may be
enhanced to Rs.500/- per day for each day of default subject to a maximum of 5 per
cent of the estimated cost of the work put to tender. The decision of the Engineer-in-
Charge shall be final and binding on the parties.
No payment shall be made for construction of labour housing.
4.2 The Contractor shall display all permissions, licenses, registration certificates, bar
charts, other statements etc under various labour laws and other regulations
applicable to the works, at his site office.
4.3 contractor has to make his own arrangements at his own cost for labor
accommodation outside the campus . since it is working campus no provision will
be made for labor huts accommodation . The contractor shall make his own
arrangement for housing remaining labor at his own premises at his own cost.
4.4 The contractors are required to provide such accommodation as is acceptable to
local bodies and nothing extra shall be paid on this account.
4.5 Contractor has to follow the security requirement of the campus and obtain
necessary entry passes for the labour and vehicles and follow security checks at
entry / exit gates, restriction on movement of vehicle, restricted timings of working
etc. The Department however shall assist the contractor in obtaining such passes for
movement of vehicles and labour. No claim whatsoever shall be entertained on
account of delay in entry of vehicles and labour including restrictions in working
hours, if there is any.
4.6 The contractor shall employ only Indian Nationals after verifying their antecedents
and loyalty. The contractor shall, on demand submit list of his agents, employees and
work people concerned & shall satisfy as to the bonafides of such people.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 79

4.7 The contractor & his work people shall observe all relevant rules regarding security
promulgated in which work is to be carried out by the Controlling Administrative
Authority of the campus/area (hereinafter referred to as “Administrator”).
4.8 The contractor, his representative, workman shall be allowed to enter through
specified gates & timing as laid down by the controlling authority. They shall be
issued an identity card or an individual pass in accordance with the standing rules &
regulations & they should possess the same while working. The contractor shall be
responsible for the conduct & actions of his workmen, agents/ representatives.
4.9 Normally contractor shall be allowed to carry out work between 7 AM to 6 PM.
However, he may also be allowed to carry out the work beyond 6 PM & up to 7 AM,
if the site conditions / circumstances so demand with prior written permission from
the “Administrator”. However, if the work is carried out in more than one shift or at
night, no claim on this account shall be entertained.
4.10 Normally contractor’s material / vehicles etc shall be allowed to move in / go-out
between 7 AM to 7 PM only & no movement of material / vehicles out of site of
work shall be allowed during night hours unless specific permission is obtained from
the “Administrator”.
4.11 In case if a separate entry has been allowed, the contractor has to make all
arrangement for making a separate entry gate and barricading of the working area to
segregate/separate the same from other areas. All these have to be done by the
contractor at his own cost including safeguarding any untoward incident in the
restricted area due to separate entry gate and barricading arranged by the
contractor. No extra amount on this account shall be payable by the department.
4.12 In the event of any restrictions being imposed by the Security agency, CPWD, Traffic
or any other authority having jurisdiction in the area on the working or movement
of labour /material, the contractor shall strictly follow such restrictions and nothing
extra shall be payable to the contractor on such accounts. The loss of time on these
accounts, if any, shall have to be made up by augmenting additional resources
whatever required. Nothing extra shall be payable on this account.

5.0 OFFICE INFRASTRUCTURE:


5.1 For Quality Control Measures, Preparation of Bills and Monitoring the Quality, the
contractor shall provide one Computer having Intel core i3 processor, MS-Windows-
7, A-3 Coloured Inkjet & A-4 Laserjet Printers, Scanners, UPS etc. in the site office of
Engineer-in-Charge and no extra payment shall be done in this regard .
5.2 The contractor shall make arrangement for Helmets and leather shoes (meant of
construction work at sites) for all field staff of the department during the entire

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 80

period of construction for safety reasons. One helmet and two pairs of shoes per
staff member (maximum twelve members) of the departments per year shall be
arranged by the contractor.
6.0 DOCUMENTATION
The Contractor shall render all help and assistance in documenting the total
sequences of this project by way of photography, slides, audio / video recording &
other records etc. Nothing extra shall be payable to Contractor on this account.
However, cost of photographs, slides, audio / video graph etc. shall be borne by the
Department. The original films shall be the property of the Department. No copy
shall be prepared without the prior approval of the Engineer- in – Charge.
7.0 PROGRESS CHART: -
The Contractor shall prepare an integrated program chart before start of work including civil as
well as E & M activities for the execution of work, Showing clearly all activities from the start of
work to completion, with details of manpower, equipment and machinery required for the
fulfilment of the program within the stipulated period and submit the same for approval of the
Engineer-In-Charge within 15 days of the award of the work. These shall be submitted by the
contractor through electronic media besides forwarding hard copies of the same. The integrated
program chart so submitted should not have any discrepancy with the physical milestones
attached in the contract agreement. The program chart should include the following:

(i) Descriptive note explaining sequence of various activities.


(ii) Construction Program shall be prepared on MS PROJECT/PRIMAVERA Software, which will
indicate resources in financial terms, manpower and specialized equipment for every
important stage.
(iii) Program for procurement of materials by the contractor.
(iv) Program for arranging and deployment of manpower both skilled and unskilled so as to
achieve targeted progress.
(v) Program of procurement of machinery/equipment having adequate capacity,
commensurate with the quantum of work to be done within the stipulated period, by the
contractor.
(vi) Program for achieving fortnightly micro milestones and periodic milestones.
(vii) In case of non-compliance/delay in compliance in this, a penalty @ Rs. 1000/- (Rupees
thousand only) per day will be imposed subjected to maximum Rs 1,00,000/- which will
be recovered from the immediate next R/A Bill of the Contractor.
(viii) If at any time, it appears to the Engineer-In-Charge that the actual progress of work does
not conform to the approved program referred above, the contractor shall produce a
revised program showing the modifications to the approved program by additional inputs
to ensure completion of the work within the stipulated time.
(ix) The submission for approval by the Engineer-In-Charge of such program or the furnishing
of such particulars shall not relieve the contractor of any of his duties or responsibilities
under the contract. This is without prejudice to the right of Engineer-In-Charge to take
action against the contractor as per terms and conditions of the agreement.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 81

SUBMISSION OF MONTHLY PROGRESS REPORTS :

Apart from the above integrated program chart, the contractor shall be required to submit
Monthly progress report of the work in a computerized form on 7th of every month. The
progress report shall contain the following, apart from whatever else may be required as
specified above:

(a) Construction schedule of the various components of the work through a bar chart for the next
month (or as may be specified), showing the micro- milestone/milestones, targeted tasks
(including material and labour requirement) and up to date progress. At least 10(ten) digital
photographs showing all the parts of construction site along with at least 5(five) minutes
video of executions of different items in soft copy has to be submitted in every progress
report.
(b) Progress chart of the various components of the work that are planned and achieved, for the
fortnight as well as cumulative up to the fortnight under reckoning, with reason for
deviations, if any in a tabular format.
(c) Plant and machinery statement, indicating those deployed in the work.
(d) Man-power statement indicating :
 Individually the names of all the staff deployed on the work, along with their
designations.
 No. of skilled workers (trade wise) and total no. of unskilled workers deployed on the
work and their location of deployment i.e. blocks.
(e) Financial statement, indicating the broad details of all the running account payment received
up to date, such as gross value of work done, advances taken, recoveries effected, amount
withheld, net payments details of cheque payment received, extra/substituted/deviation
items if any, etc.
In case of noncompliance / delay in compliance in submission of Monthly , a penalty as
mentioned in schedule F will be imposed which will be recovered from the immediate next
R/A Bill of the Contractor.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 82

8.0 PROGRESS AND MONITORING OF WORK:


8.1 The progress report shall contain the following, apart from whatever else may be
required as specified:-
(i) Construction schedule of the various components of the work through a bar
chart for the next three months (or as may be specified), showing the micro
milestones, targeted tasks and up to date progress. At least 10 digital
photographs showing all the parts of construction site along with at least 5
minutes video of executions of different items in soft copy has to be
submitted in every monthly progress report.
(ii) Progress chart of the various components of the work that are planned and
achieved, for the month as well as cumulative up to the month, with reason
for deviations, if any in a tabular format.
(iii) Plant and machinery statement, indicating those deployed in the work.
(iv) Man-power statement, indicating individually the names of all the staff
deployed on the work, along with their designations. Number of skilled
workers and unskilled workers deployed on the work and their location of
deployment.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 83

(v) Financial statement, indicating the broad details of all the running account
payment received up to date, such as gross value of work done, advances
taken, recoveries effected, amount withheld, net payments details of Cheque
payment received, extra /substituted /deviations items if any, etc.
8.2 For completing the work in time, the Contractor might be required to work in two or
more shifts (including night shifts). No claim whatsoever shall be entertained on this
account, not with-standing the fact that the Contractor may have to pay extra
amounts for any reason, to the labourers and other staff engaged directly or
indirectly on the work according to the provisions of the labour and other statutory
bodies regulations and the agreement entered upon by the Contractor with them.
8.3 The work should be planned in a systematic manner so that chase cuttings in the
walls, ceilings and floors is minimized. Wherever absolutely essential, the chase shall
be cut using chase cutting machines. Chases will not be allowed to be cut using
hammer / chisel. The electrical boxes should be fixed in walls simultaneously while
raising the brick work. The contractor shall ensure proper co-ordination of various
disciplines viz. building works, sanitary & water supply & electrical installations etc.
8.4 The contractor shall conduct his work, so as not to interfere with or hinder the
progress or completion of the work being performed by other contractor(s) or by the
Engineer-in-Charge and shall as far as possible arrange his work and shall place and
dispose of the materials being used or removed so as not to interfere with the
operations of other contractor or he shall arrange his work with that of the others in
an acceptable and coordinated manner and shall perform it in proper sequence to
the complete satisfaction of Engineer-in-charge.
8.5 The Contractor shall do proper sequencing of the various activities by suitably
staggering the activities within various pockets in the plot so as to achieve early
completion. The agency may deploy adequate equipment, machinery and labour as
required for the completion of the entire work within the stipulated period specified.
Also ancillary facilities shall be provided commensurate with requirement to
complete the entire work within the stipulated period. Nothing extra shall be
payable on this account. Adequate number/sets of equipment in working condition,
along with adequate stand-by arrangements, shall be deployed during entire
construction period. It shall be ensured by the Contractor that all the equipment,
Tools & Plants, machineries etc. provided by him are maintained in proper working
conditions at all times during the progress of the work and till the completion of the
work. Further, all the constructional tools, plants, equipment and machineries
provided by the Contractor, on site of work or his work shop for this work, shall be
exclusively intended for use in the construction of this work and they shall not be
shifted / removed from site without the permission of the Engineer-in-Charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 84

8.6 All material shall only be brought at site as per program finalized with the Engineer- in-
Charge. Any pre-delivery of the material not required for immediate consumption shall
not be accepted and thus not paid for.
9.0 PROJECT REVIEW MEETINGS:
The contractor, immediately on award of work shall submit details of his key
personnel to be engaged for the work at site. In addition, he shall furnish the Engineer-
in-charge detailed organization involved with the work.
The contractor shall present the programme and status at various review meetings
as required.
Monthly Review Meetings: Shall be attended by Project - in - charge and the
Management Representative who can take independent decisions along with CPWD,
client’s representatives.
Agenda
a) Progress Status/Statistics.
b) Completion Outlook.
c) Major hold ups/slippages.
d) Assistance required.
e) Critical issues.
f) Any decision on queries raised either by Contractor/PMC.
g) Anticipated cash flow requirement for next two months.
10.0 ENGAGING SPECIALISED AGENCIES FOR WORKS: -
10.1 The Contractor shall engage specialized agencies having adequate technical
capability and experience of having executed at least one work of similar items for
executing the following items of the work and/or any other items of work where
specialized firm is required to be engaged as per contract conditions.

10.2 The Specialized agency for the work shall be got approved from the Engineer-in-
Charge well before actual commencement of the item of work. The contractor shall
submit the list of specialized agencies proposed to be engaged by him along with
their technical capability and necessary performance certificates, within 15 days of
the stipulated date of start to substantiate technical capability and experience of the
agency for prior approval of the Engineer-in-Charge.
10.3 It shall be the responsibility of main contractor to sort out any dispute / litigation
with the Specialized Agencies without any time & cost overrun to the Department.
The main contractor shall be solely responsible for settling any dispute / litigation

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 85

arising out of his agreement with the Specialized Agencies. The contractor shall
ensure that the work shall not suffer on account of litigation/ dispute between him
and the specialized agencies / sub-contractor(s). No claim of hindrance in the work
shall be entertained from the Contractor on this account. No extension of time shall
be granted and no claim what so ever, of any kind, shall be entertained from the
Contractor on account of delay attributable to the selection/rejection of the
Specialized Agencies.
11.0 REFUND OF SECURITY DEPOSIT:
11.1 The Security Deposit shall be released 12 months after completion of entire scope of
work of agreement and for this, the contractor shall have to produce a certificate
stating that no defects are pending for rectification from the Engineer-in-charge, but
subject to other provisions specified elsewhere in the contract agreement.
12.0 SAFETY MEASURES

Safety:
1. The Contractor will comply of the provisions contained in “safety, Health and
Environment health book 2019” available CPWD web site www.cpwd.gov.in
failing which he / they will be liable for the penalties on each violation subject to
compounding of the same to maximum of such default as mention in the various
unsafe act / unsafe conditions in this manual. This apart from the other
fines/levies/penalties mentioned in the documents elsewhere. It is incumbent
upon the contractor to ensure in undertaking all health and safety compliance
for safety of all concern to generate safety conscious and safety regulatory as his
primary statutory duties or responsibilities in the contract.

2. The Contractor shall comply with the safety procedures, norms and guidelines
(as applicable) as outlined in the document Part 7 Constructional practices and
safety- 2016, National Building code of India, Bureau of Indian Standards. A copy
of all pertinent regulations and notices concerning accidents, injury and first-aid
shall be prominently exhibited at the work site. Depending upon the scope &
nature of work, a person qualified in first-aid shall be available at work site to
render and direct first-aid to casualties. A telephone may be provided to first-aid
assistant with telephone numbers of the hospitals displayed. Complete reports of
all accidents and action taken thereon shall be forwarded to the competent
authorities.

3. The Contractor shall ensure the following activities for construction workers
safety, among other measures:

a) Guarding all parts of dangerous machinery.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 86

b) Precautionary signs for working on machinery

c) Maintaining hoists and lifts, lifting machines, chains, ropes, and other lifting
tackles in good condition.

d) Durable and reusable formwork systems to replace timber formwork and


ensure that formwork where used is properly maintained.

e) Ensuring that walking surfaces or boards at height are of sound construction


and are provided with safety rails or belts.

f) Provide protective equipment; helmets etc.

g) Provide measures to prevent fires. Fire extinguishers and buckets of sand to


be provided in the fire-prone area and elsewhere.

h) Provide sufficient and suitable light for working during night time.

4. Contractor shall within two weeks of award of work, submit to the Engineer-in-
Charge for his approval, list of measures for maintaining safety of manpower
deployed for construction and avoidance of accidents.

The Contractor(s) shall take all precautions to avoid accidents by exhibiting necessary
caution boards day and night, speed limit board, red flags, red lights and providing
barriers. He shall be responsible for all damages and accidents caused to existing/new
work due to negligence on his part. No hindrances shall be caused to traffic during the
execution of the work. In case of any accident of labours / contractual staff’s, the entire
responsibility will rest on the part of the contractor and any compensation under such
circumstances, if becomes payable, the same shall be entirely borne by the contractor and
department shall have no role on this account.
12.1 The issue of construction safety & standards has gained utmost importance in recent
times. This subject is to be dealt with in an integrated manner with an approach to
developing and establishing a safety culture at work sites. Broadly, its components
are:
(i) Creating awareness.
(ii) Education.
(iii) Training.
(iv) Implementation.
(v) Enforcement measures.
All workers of contractor and associate agencies, invariably and at all the times, must
follow all safety norms, adopt safe construction practices and use all required safety
gadgets in their working throughout the project duration.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 87

12.2 The contractor shall issue Photo Identity Cards with unique numbers containing
salient information of workers for the labour & his staff.
12.3 The Contractor shall monitor and achieve the objectives of construction safety
continuously, progressively and through affirmative action, and shall oversee
implementation of safety program over the entire construction period.
12.4 Warning / Caution Boards
All temporary warning / caution boards / glow signage display such as “Construction
Work in Progress”, “Keep Away”, “No Parking”, Diversions & protective Barricades
etc. shall be provided and displayed during day time by the Contractor, wherever
required and as directed by the Engineer-in-Charge. These glow signage and red lights
shall be suitably illuminated during night also. The Contractor shall be solely
responsible for damage and accident caused, if any, due to negligence on his part.
Also he shall ensure that no hindrance, as far as possible, is caused to general traffic
during execution of the work. This signage shall be dismantled & taken away by the
Contractor after the completion of work, only after approval of the Engineer – in –
Charge. Nothing extra shall be payable on this account.
12.5 Sign Boards
12.5.1 The Contractor shall provide and erect a display board of size and shape as required and
paint over it, in a legible and workman like manner, the details about the salient
features of the project, as required by the Engineer-in-Charge. The Contractor shall
fabricate and put up a sign board in an approved location and to an approved design
indicating name of the project, client / owner, architects, structural consultants,
Department etc. besides providing space for names of other Contractors, Associate
contractors and specialized agencies. Nothing extra shall be payable on this account.
12.5.2 A display board shall be kept at site which would list the names of workers, teamsand
agencies following safety program in the best manner. This would be updated weekly.
12.5.3 Necessary protective and safety equipments shall be provided to the Site Engineer,
Supervisory staff, labour and technical staff of the contractor by the Contractor at his
own cost and used at site.
12.5.4 No inflammable materials including P.O.L shall be allowed to be stored in huge
quantity at site. Only limited quantity of P.O.L may be allowed to be stored at site
subject to the compliance of all rules / instructions issued by the relevant authorities
and as per the direction of Engineer -in- Charge in this regard. Also all precautions
and safety measures shall be taken by the Contractor for safe handling of the P.O.L
products stored at site. All consequences on account of unsafe handling of P.O.L shall
be borne by the Contractor.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 88

13.0 SPECIAL CONDITION FOR HARDWARE AND SANITARY WARES:


13.1 Engineer-in-Charge will take a decision regarding model numbers of equivalent
Door/window hard ware/ sanitary ware at the time of execution, in case the
material, from the manufacturer whose model number is mentioned, is not
available. However, in case, the equivalent model so approved, is cheaper than the
model already mentioned in item/approved makes list, the price adjustment will be
made based on the difference in market rate. In case, the rate of subsequently
approved model is more, no extra payment will be made on this account.”
13.2 The following procedure should be followed in case of removal of rejected/sub-
standard materials from the site of work.
i) Whenever any material brought by the contractor to the site of work is
rejected, entry thereof should invariably be made in the site order book
under the signature of the AE/AEE giving approximate quantity of such
materials.
ii) As soon as the material is removed, a certificate to that effect may be
recorded by the AE/AEE against the original entry, giving the date of removal,
mode of removal i.e. whether by truck, carts or by manual labour. If removal
is by truck, the registration number of the truck should be recorded.
14.0 INSPECTION OF WORKS:
14.1 In addition to the provisions of relevant clauses of the contract, the work shall also
be open to inspection by the SE cum PD, CPWD, Hindupur and other senior officers
of CPWD in addition of the Engineer-in-charge, his authorized representatives,
Authorities and Team of Third Party Quality Assurance engaged for the work. The
contractor shall at times during the usual working hours and at all times at which
reasonable notices of the intention of the Engineer-in-charge or other officers as
stated above to visit the works shall have been given to the contractor, either
himself be present to receive the orders and instructions or have a responsible
representative duly accredited in writing, to be present for that purpose.
14.2 The committee/consultant/Third party quality assurance appointed by CPWD, shall
be inspecting the works including workshops and fabrication factory to ensure that
the works in general being executed according to the design, drawings and
specifications laid down in the contract. Their observations shall be communicated
by CPWD engineering staff and compliance is to be reported to CPWD. The
committee/consultant appointed by CPWD shall certify on completion of particular
building that it has been constructed according to the approved drawings design and
specifications.
14.3 Senior Officers of CPWD, Dignitaries from Central Ministry / Department, State
Government and Client Department Authorities shall be inspecting the on-going

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 89

work at site at any time with or without prior intimation. The contractor shall,
therefore, keep updated the following requirements and detailing:-
(i) Display Board showing detail of work, weekly progress achieved with respect
to targets, reason of shortfall, status of manpower, wages being paid for
different categories of workers.
(ii) Entrance and area surrounding to be kept cleaned.
(iii) Display layout plan key plan, Building drawings including plans, elevations and
sections.
(iv) Upto date displays of programme chart (Bar charts).
(v) Keep details of quantities executed, balance quantities, deviations, possible
Extra item, substituted Item etc.
(vi) Keep plastic / cloth mounted one sets of building drawings.
(vii) Set of Helmets and safety shoes for safety.
15.0 INSURANCE POLICIES:
Before commencing the execution of work, the Contractor shall, without in any way
limiting his obligations and liabilities, insure at his own cost and expense against any
damage or loss or injury, which may be caused to any person or property, at site of
work. The Contractor shall obtain and submit to the Engineer-in-Charge proper
Contractor All Risk Insurance Policy for an amount equivalent to the contract amount for
this work, with Engineer-in-Charge as the first beneficiary. The insurance shall be
obtained in joint names of Engineer-in-Charge and the Contractor (who shall be second
beneficiary). Also, he shall indemnify the Department from any liability during the
execution of the work. Further, he shall obtain and submit to the Engineer-in- Charge, a
third party insurance policy for maximum Rs. 10 lakh for each accident, with the
Engineer-in-Charge as the first beneficiary. The insurance shall be obtained in joint
names of Engineer-in-Charge and the Contractor (who shall be second beneficiary). The
Contractor shall, from time to time, provide documentary evidence as regards payment
of premium for all the Insurance Policies for keeping them valid till the completion of
the work. The Contractor shall ensure that Insurance Policies are also taken for the
workers of his Sub-Contractors / specialized agencies also. The contractor including
subcontractors shall provide comprehensive group insurance cover for all the workers
and their supervisory staff deployed at site. The details of insurance cover to be
provided shall be submitted by the contractor / associate agencies within 20 days of
date of start. In case of a default, appropriate policy shall be got done by the safety
monitoring committee and double the fee of the policy shall be recovered from the next
bill of the contractor. Without prejudice to any of its obligations and responsibilities
specified above, the Contractor shall within 15 days from the date of letter of
acceptance of the tender and thereafter at the end of each quarter submit a report to

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 90

the Department giving details of the Insurance Policies along with Certificate of these
insurance policies being valid, along with documentary evidences as required by the
Engineer-in-Charge. No work shall be commenced by the Contractor unless he obtains
the Insurance Policies as mentioned above. Also, no payment shall be made to the
Contractor on expiry of insurance policies unless renewed by the Contractor. Nothing
extra shall be payable on this account. No claim of hindrance (or any other claim) shall
be entertained from the contractor on these accounts.

16.0 APPLICABLE PERMITS:


16.1 The contractor(s) shall give to the Municipality, police and other authorities all
necessary notices etc. that may be required by law and obtain all requisite licenses
for temporary obstructions, enclosures etc. and pay all fee, taxes including GST and
charges which may be levied on account of these operations in executing the
contract. He shall make good any damage to the adjoining property whether public
or private and shall supply and maintain lights either for illumination or for
cautioning the public at night.
16.2 The contractor shall ensure that applicable permits mandated by the local bodies
and in case warranted for this work are obtained as required under the Applicable
Laws.
17.0 LOCAL BYE-LAWS:
17.1 The building work shall be carried out in the manner complying in all respects with
the requirements of relevant bye-laws of the local body under the jurisdiction of
which the work is to be executed or as directed by the Engineer-in-Charge and
nothing extra shall be paid on this account.
17.2 Some restrictions may be imposed by the local police etc. on the working time and
for movement of labour, materials etc. the contractor shall be bound to follow all
such restrictions/instructions and nothing extra shall be payable on this account.
17.3 The contractor shall not stack building material/ malba on the road or on the land
owned by any other authority, as the case may be. In case, the Contractor is found
stacking the building material/ malba as stated above, he shall be liable to pay the
stacking charges as may be levied by local body or authority and also to face penal
action as per the rules, regulations and bye-laws of the said body or authority. The
Engineer-in-Charge shall be at liberty to recover the sums due but not paid to the
concerned authorities on the above counts from any sums due to the contractor
including amount of the Security Deposit or Retention Money in respect of this
contract or any other contract.
18.0 FINAL TESTING OF THE INSTALLATION:

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 91

The Contractor shall demonstrate trouble free functioning of all the Civil and E & M
installations and services. The Engineer-in-Charge or his authorized representatives
shall carry out final inspection of the various Civil and E & M services and
installations. Any defect(s) noticed during demonstration shall be rectified by the
Contractor at his own cost to the entire satisfaction of the Engineer-in-Charge.
Nothing extra shall be payable on this account.
19.0 De-watering
(i) De-watering required, if any, shall be done conforming to BIS Code IS: 9759
(guide lines for de-watering during construction) and / or as per the
specifications approved by the Engineer-in-Charge. Design of an appropriate
and suitable dewatering system shall be the Contractor’s responsibility. Such
scheme shall be modified / augmented as the work proceeds based on fresh
information discovered during the progress of work, at no extra cost. At all
times during the construction work, efficient drainage of the site shall be
carried out by the Contractor and especially during the laying of plain cement
concrete, taking levels etc. The Contractor shall also ensure that there is no
danger to the nearby properties and installations on account of such lowering
of water table. If needed, suitable precautionary measures shall be taken by
the Contractor. Also the scheme of dewatering adopted shall have adequate
built in arrangement to serve as stand-by to attend to repair of pumps etc. and
disruption of power / fuel supply. Nothing extra shall be payable for all the
operations described in this para.
(ii) In trenches where surface water is likely to get into cut / trench during
monsoons, a ring bund of puddle clay or by any other means shall be formed
outside, to the required height, and maintained by the Contractor. Also,
suitable steps shall be taken by the Contractor to prevent back flow of pumped
water into the trench. Nothing extra shall be payable on this account.
a. For works below ground level the contractor shall keep that area free from
water. If dewatering or bailing out of water is required the contractor shall
do the same at his own cost and nothing extra shall be paid except
otherwise provided in the items of Schedule of Quantities.
b. The Contractor shall make all necessary arrangements for protecting from
rains, fog or likewise extreme weather conditions, the work already
executed and for carrying out further work, during monsoon including
providing and fixing temporary shelters, protections etc. Nothing extra
shall be payable on this account and also no claims for hindrance shall be
entertained on this account.
c. In case of flooding of site on account of rain or any other cause and any
consequent damage, whatsoever, no claim financially or otherwise shall be

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 92

entertained notwithstanding any other provisions elsewhere in the


contract agreement. Also, the Contractor shall make good, at his own cost,
the damages caused, if any. Further, no claims for hindrance shall be
entertained on this account.
d. The contractor will take reasonable precautions to prevent his workman
and employees from removing and damaging any flora (plant/vegetation)
from the project area.

20.0 Site condition:


a. The contractor shall at his own expense and risk arrange land for accommodation of
labour outside the NIT campus. The contractor shall setting up of office, the storage
of materials, erection of temporary workshops, construction of approach roads to
the site of the work including land required for carrying out of all jobs connected
with the execution in the campus & completion of the work. If during construction, it
becomes necessary to remove or shift the stored materials shed workshop, access
roads, etc, to facilitate execution of any other work by any other agency, the
contractor shall carry out the removal of shifting as directed by the Officer – in –
charge and no claim whatsoever, shall be entertained on this account.
b. The site shall be handed over on as is where is basis and it shall be deemed that the
contractor has satisfied himself as to the nature and location of the work, transport
facilities, availability of land for setting up of camp, etc. the department will bear no
responsibility for lack of such knowledge & the consequences thereof.
c. No surplus land is available with the Department and hence, no labour campus is
permitted at site. Only limited number of Labour hutments for Security, Watch and
Ward and essential personnel amounting to not more than 20 will be permitted at site.
Contractor should hire suitable land in the vicinity of site and maintain his labour
campus at site as per the CPWD Contract conditions and specifications.
d. The site for execution of work is located inside existing campus of NIT Warangal and is
very congested and there is no space for labour hutments, batching plant or stacking of
construction materials. Therefore, the agency shall have to arrange space outside the
campus at its own risk and cost for labour huts, batching plant and stacking of
materials required for construction, cost of which may be factored in, while quoting for
the work. No claim, whatsoever, shall be admissible on account of hindrance or
additional cost being incurred for these activities

e. In case any shoring/protection is required to protect the adjacent area shall be taken
care at free of cost for construction of basement below the ground level as it is only
temporary arrangement. Nothing extra shall be paid on this account. The bidder shall
take all precautions to avoid nuisance and also for protecting their properties by taking

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 93

all protection measures before taking up any of the excavation, piling, basement
concreting work etc. The excavation shall be carried out by taking all the technical
protective measures into consideration to safe guard the adjacent properties from land
sliding, falling, cracking, or any other damage through any of the operations involved in
erecting this building. He shall also follow all municipal guidelines of the local bodies to
take up the construction. Nothing extra shall be paid on this account for any of the
operations involved including obtaining statutory approval from the local bodies.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 94

ADDITIONAL CONDITIONS (Civil Component)


1.1 QUALITY ASSURANCE/TESTING OF MATERIALS: -
1.1.1 Water tanks, taps, sanitary, water supply & drainage pipes, fittings & accessories
should conform to bye-laws of local body/corporation, where CPWD specifications
are not available. The Contractor (s) should engage approved, licensed plumbers for
the work and get the materials (fixtures/fittings) tested, by the municipal
Body/Corporation authorities wherever required at his own cost.
1.1.2 With each Running Bill, the details of test carried out shall be submitted by the
contractor as per Performa given in the tender document.
1.1.3 Samples of materials required for testing shall be provided free of charge by the
contractor. The contractor shall provide at his own cost suitable weighing and
measuring arrangements at site for checking the weight / dimension as may be
necessary. The sealed samples are to be handed over to the testing lab by the
contractor in the presence of representative of Engineering in charge. The cost of
relevant tests, to be carried out in approved labs shall be borne by the contractor
himself.
All other expenditure required to be incurred for taking samples; conveyance,
packing etc. shall be borne by the contractor himself.
1.1.4 The Contractor shall at his own risk and cost make all arrangements and shall provide
all such facilities including material and labour, the Engineer-in-Charge may require
for collecting, preparing, forwarding the required number of samples for testing as
per the frequency of test stipulated in the contract specifications, TPQA or as
considered necessary by the Engineer-in-Charge, at such time and to such places, as
directed by the Engineer-in-Charge. Nothing extra shall be payable for the above.
1.1.5 The Contractor or his authorized representative shall associate in collection,
preparation, forwarding and testing of such samples. In case he or his authorized
representative is not present or does not associate him, the result of such tests and
consequences thereon shall be binding on the Contractor .The Contractor or his
authorized representative shall remain in contact with the Engineer-in–Charge or his
authorized representative associated for all such operations. No claim of payment or
claim of any other kind, whatsoever, shall be entertained from the Contractor.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 95

1.1.6 Maintenance of Register of Tests:-


(i) All the registers of tests carried out at Construction Site or in outside
laboratories shall be maintained by the contractor which shall be issued to the
contractor by Engineer-in-Charge.
(ii) All Samples of materials including Cement Concrete Cubes shall be taken jointly
with Contractor by representative of the Engineer in Charge. All the assistance
shall be provided by the contractor. Cost of sample materials is to be borne by
the contractor and he shall be responsible for safe custody of samples to be
tested at site.
(iii) All the test in field lab setup at Construction Site shall be carried out by the
Engineering Staff deployed by the contractor which shall be 100% witnessed
by representative of the Engineer in Charge.
(iv) All the entries in the registers will be made by the designated Engineering
Staff of the contractor and same should be regularly reviewed by Engineer in
Charge or his representative.
(v) Contractor shall be responsible for safe custody of all the test registers.
1.1.7 Extensive testing of the materials used for construction is a pre-requisite for
attaining high quality of the work. This shall also require specialized tests, physical,
chemical, ultrasonic, x-ray and various other types of tests which cannot possibly be
carried out in a site laboratory. These tests also require specialized personnel who
regularly deal in such testing. Therefore the need arises for carrying out the tests in
outside laboratories. These laboratories may be in the Govt. sector, Semi Govt. or
Private sector. All Govt. Institutes, Indian Institute of Technology, National Institute
of Technology, Central and State funded laboratories stands approved. No approval
is required for testing in these laboratories/institutes. Testing from only those private
laboratories are allowed as approved by office of ADG,hyd from time to time.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 96

However, testing of material in any Govt., Lab / Public Undertaking Lab / IIT or NIT
Lab / Govt. Engineering College may be allowed by Executive Engineer without prior
approval of SE cum PD, CPWD, Hindupur or higher officers provided these labs have
all necessary facility to carry out the required tests.
1.1.8 Ultrasonic pulse velocity test shall be conducted on all RCC columns and at least 5%
of the total number of other RCC members in each category i.e. beam, slab and
footing for ensuring quality of concrete as per directions of Engineer- in charge. The
cost of the same shall be borne by the contractor.
1.1.9 In case there is any discrepancy in frequency of testing as given in list of mandatory
tests and that in individual sub-heads of work as per CPWD Specifications higher of
the two frequencies of testing shall be followed and nothing extra shall be payable
on this account.
1.1.10 The contractor shall ensure quality construction in a planned and time bound
manner. Any sub-standard material / work beyond set out tolerance limit shall be
summarily rejected by the Engineer-in-charge & contractor shall be bound to replace
/ remove such sub-standard / defective work immediately. If any material, even
though approved by Engineer-In-Charge is found defective or not conforming to
specifications shall be replaced / removed by the contractor at his own risk & cost.
1.1.11 In addition to the supervision of work by CPWD Engineers, the Architects deployed
by the Client/CPWD, CPWD Quality Control/ Assurance Team and Third party Quality
Control/ Assurance Team shall also be carrying out regular and periodic inspection of
the ongoing activities in the work and deficiencies, shortcomings, inferior
workmanship pointed out by them shall be communicated by CPWD engineers to
the contractor. Upon receipt of instructions from Engineer in Charge these are also
to be made good by necessary improvement, rectification, replacement up to his
complete satisfaction. Special attention shall be paid towards line and level of
internal and external plastering, exposed smooth surface of RCC members by
providing fresh shuttering plates, rubberized linings to all the shuttering joints,
accurate joinery work in wooden doors and windows, thinnest joints in stone/ tiling /
cladding work, non-hollowness in floor and dado tiles work, protection of scratches
over flooring by impounding layer of plaster of Paris, water tight pipe linings,
absence of hollow vertical joints in brick masonry, proper compaction of filled up
earth etc to achieve an Institution of International standards and up keeping of
quality assurance shall be of paramount importance, as such.
1.1.12 The Contractor shall submit, within 15 days after the date of award of work, a
detailed and complete method statement for the execution, testing and Quality
Assurance, of such items of works, as directed by the Engineer-in-Charge. All the
materials to be used in the work, to give the finished work complete in all respects,
shall comply with the requirements of the specifications and shall pass all the tests

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 97

required as per specifications as applicable or such specifications / standards as


directed by the Engineer-in-Charge. However, keeping the Quality Assurance in
mind, the Contractor shall submit, on request from the Engineer-in-Charge, his own
Quality Assurance procedures for basic materials and such items, to be followed
during the execution of the work, for approval of the Engineer-in-Charge.
1.2 FIELD LABORATORY
The contractor has to establish within 30 days from the award of work a field
laboratory at site including all necessary equipments and skilled manpower for the
Field Tests as indicated in the tender document at his own cost to have proper
quality control. Rs.5,000/-per day shall be recovered from the contractor for any
delay beyond the specified period. If contractor fails to establish lab within
additional period of 15 days, the Engineer in charge shall initiate action as deemed fit
under relevant clauses of the agreement.
For performing the above tests, the Field Testing Equipments and Instruments as
indicated in the tender document are to be arranged and maintained by the
contractor at his own cost.
1.2.1 The contractor shall ensure quality construction in a planned and time bound
manner. Any sub-standard material / work beyond set-out tolerance limit shall be
summarily rejected by the Engineer-in-Charge & contractor shall be bound to replace
/ remove such sub-standard / defective work immediately.
1.2.2 The list of Laboratory/ Field equipment referred above is to be arranged and
maintained by the contractor at the site of work. In case the equipment required for
any test is not available at site, the department shall get the test conducted from the
third party. However in that event, besides providing free materials of sample, the
cost of taking of sample, packing, transportation, testing charges etc. shall be borne
by the contractor irrespective of the results.
1.3 SAMPLE OF MATERIALS:-
1.3.1 All materials and fittings brought by the contractor to the site for use shall conform
to the samples approved by the Engineer-in-Charge which shall be preserved till the
completion of the work. If a particular brand of material is specified in the item of
work in Schedule of Quantity, the same shall be used after getting the same
approved from Engineer-in-Charge. Wherever brand / quality of material are not
specified in the item of work, the contractor shall submit the samples as per List of
Approved Makes given in the tender document for approval of Engineer-in-Charge.
For all other items, ISI Marked materials and fittings shall be used with the approval
of Engineer-in-Charge. Wherever ISI Marked material / fittings are not available, the
contractor shall submit samples of materials / fittings manufactured by firms of
repute conforming to relevant Specifications or IS codes for the approval of Engineer-
in-Charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 98

1.3.2 The Contractor shall procure and provide all the materials from the manufacturers /
suppliers as per the list attached with the tender documents, as per the item
description and particular specifications for the work. Nothing extra shall be payable on
this account. Also, the material shall be procured only after written approval of the
Engineer-in-Charge.
1.3.3 To avoid delay, contractor should submit samples / as stated above well in advance
so as to give timely orders for procurement. If any material, even though approved
by Engineer-in-Charge is found defective or not conforming to specifications shall be
replaced / removed by the contractor at his own risk & cost. Samples including brand
/ quality of materials and fittings to be used in the work shall be got approved from
the Engineer-in-Charge, well in advance of actual execution and shall be preserved
till the completion of the work.
1.3.4 BIS marked materials except otherwise specified shall also be subjected to quality
test besides testing of other materials as per the specifications described for the
item/material. Wherever BIS marked materials are brought to the site of work, the
contractor shall, furnish manufacturer’s test certificate or test certificate from
approved testing laboratory to establish that the material procured by the
contractor for incorporation in the work satisfies the provisions of specifications
relevant to the material and / or the work done.
BIS marked items (except cement & steel for which separate provisions have been
made) required on the work shall be got tested, for only important tests, which
govern the quality of the product, as decided by the Engineer-in-Charge. The
frequency of such tests (except the mandatory test) shall be 5% of the frequency as
specified in BIS. For mandatory test, frequency shall be as specified in the CPWD
Specifications.
1.3.5 For certain items, if frequency of tests is neither mentioned in the CPWD
Specifications nor BIS, then tests shall be carried out as per directions of Engineer-in-
Charge.
2.0 CEMENT & STEEL REINFORCEMENT
2.1 Contractor has to procure Cement and Steel and has to produce manufacturers test
certificate and challan for each lot of Cement & Steel Reinforcement procured at
site.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 99

2.2 CEMENT:-
2.2.1 The contractor shall procure 43 grade ordinary Portland Cement (OPC) conforming
to IS: 8112 / Portland Pozzolona Cement (PPC) conforming to IS: 1489 (Part-1) as
stipulated in the items of work, from reputed manufacturers of cement as
mentioned in “List showing preferred brands / Manufacturers / Makes”. The cement
of approved make as aforesaid in 50 kg bags bearing manufacturer’s name and ISI
marking, along with manufacturers test certificate for each lot shall be procured by
the contractor. Portland Pozzolona Cement is to be used for RCC works only subject
to fulfillment of conditions of circular No. CDO/SE (RR)/Fly ash (MAN) 02 dated
09.04.09. However, if the contractor uses higher grade of cement or uses OPC only
nothing extra shall be paid. The use of PPC shall be regulated as per the following
conditions stipulated in the circular dated 09.04.2009:-
a. IS:456-2000 Code of Practice for Plain and Reinforced Concrete (as amended upto
date) shall be followed in regard to Concrete Mix Portion and its production as
under:
i) The concrete mix design shall be done as “Design Mix Concrete” as prescribed
in clause-9 of IS 456 mentioned above.
ii Concrete shall be manufactured in accordance with clause 10 of above
mentioned IS:456 covering quality assurance measures both technical and
organizational, which shall also necessarily require a qualified Concrete
Technologist to be available during manufacture of concrete for certification
of quality of concrete.
b. Minimum M30 grade of concrete shall be used in all structural elements of RCC,
both in load bearing and framed structure.
c. The mechanical properties such as modulus of elasticity, tensile strength, creep
and shrinkage of fly ash mixed concrete or concrete using fly ash blended
cements (PPCs) are not likely to be significantly different and their values are to
be taken same as those used for concrete made with OPC.
d. To control higher rate of carbonation in early ages of concrete both in fly ash
admixed as well as PPC based concrete, water/binder ratio shall be kept as low as
possible, which shall be closely monitored during concrete manufacture.
If necessitated due to low water/binder ratio, required workability shall be
achieved by use of chloride free chemical admixtures conforming to IS: 9103. The
compatibility of chemical admixtures and super plasticizers with each set OPC, fly
ash and /or PPC received from different sources shall be ensured by trails.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 100

e. In environment subjected to aggressive chloride or sulphate attack in particular,


use of fly ash admixed or PPC based concrete is recommended. In case, where
structural concrete is exposed to excessive magnesium sulphate, fly ash
substitution/content shall be limited to 18% by weight. Special type of cement
with low C3A content may also be alternatively used. Durability criteria like
minimum binder content and maximum water/binder ratio also need to be given
due consideration in such environment.
f. Wet curing period shall be enhanced to a minimum of 10 days or its equivalent. In
hot & arid regions, the minimum curing period shall be 14 days or its equivalent.
g. Subject to General Guidelines detailed out as above, PPC manufactured
conforming to IS: 1489 (Part-I) shall be treated at par with OPC for manufacture
of Design Mix Concrete for structural use in RCC.
h. Till the time, BIS makes it mandatory to print the %age of fly ash on each bag of
cement, the certificate from the PPC manufacturer indicating the same shall be
insisted upon before allowing use of such cements in works.
i. While using PPC for structural concrete work, no further admixing of fly ash shall
be permitted.
2.2.2 Samples of cement arranged by the contractor shall be taken by the Engineer-in-
Charge and got tested in accordance with provisions of relevant BIS Codes. The
cement for such testing purpose shall be supplied by the contractor free of charge. In
case test results indicate that the cement arranged by the contractor does not
conform to the relevant BIS Codes, the same shall stand rejected and shall be
removed from the site by the contractor at his own cost within a week’s time of
written order from the Engineer-in-Charge to do so. The cost of tests shall be borne
by the contractor himself .

2.2.4 OPC &PPC bags shall be stored in separate godowns. Separate godowns for tested
cement and fresh cement (under testing) to be constructed by the contractor at his
own cost as per sketches given in C.P.W.D Specifications having weather-proof roofs
and walls. The size of the cement godown is indicated in the sketches for guidance.
The actual size of godown shall be as per site requirements and nothing extra shall be
paid for the same. Each godown shall be provided with a single door with two locks.
The keys of one lock shall remain with Engineer-in-Charge or his authorized

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 101

representative of the work and that of other lock with the authorized agent of the
contractor at the site of work so that the cement is issued from godown according to
the daily requirement with the knowledge of both parties. The account of daily
receipt and issue of cement shall be maintained in a register in the prescribed
proforma and signed daily by the contractor or his authorized agent and Engineer-in-
Charge or his authorized representative in token of its correctness. The day to day
receipt and issue accounts of different grade/brand of cement shall be maintained
separately in the standard proforma by the contractor or his authorized
representative who shall be duly signed by the authorized representative of the
Engineer-in-Charge before issue to the work on day to day basis.
Required number of cement godowns each having capacity as decided by the Engineer-
in-Charge shall be constructed by the contractor at site of work for which no extra
payment shall be made. The contractor shall be responsible for the watch and ward and
safety of the cement go-downs. The contractor shall facilitate the inspection of the
cement go-downs by the Engineer-in-Charge at any time.
The pages of the register should be machine numbered and each page initialed by the
EE. The cement godown and the register are required to be checked by the AE/EE in-
charge of the work as mentioned below:-
a) At least weekly or fortnightly, respectively in case of works at the he
headquarters of AE/EE and.
b) Whenever they visit the site of work in case of works located outside the Sub-
Divisional/Divisional Head Quarters.
c) In the case of large concentrated projects like major bridges etc., the EE
should check the cement register at least fortnightly.
2.2.5 The actual issue and consumption of cement on work shall be regulated and proper
accounts maintained as provided in the contract. The theoretical consumption of
cement shall be worked out as per procedure prescribed in Clause-42 of the contract
and shall be governed by the conditions laid therein.
2.2.6 If the quantity of cement actually used in the work is found to be more than the
theoretical quantity of cement including authorized variation, nothing extra shall be
payable to the contractor on this account. In the event of it being discovered that
after the completion of the work, the quantity of cement used is less than the
quantity ascertained as herein before provided (allowing variation on the minus side
as stipulated in Clause - 42), the cost of quantity of cement not so used shall be
recovered from the contractor as specified in schedule. Decision of the Engineer-in-
Charge in regard to theoretical quantity of cement which should have been actually
used as per the schedule and recovered at the rate specified, shall be final and
binding on the contractor.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 102

For non-scheduled items, the decision of the SE cum PD, CPWD, Hindupur regarding
theoretical quantity of the cement, which should have been actually used, shall be
final and binding on the contractor.
2.2.7 Cement brought to site and cement remaining unused after completion of work shall
not be removed from site without written permission of the Engineer-in-Charge.
2.2.8 Damaged cement shall be removed from site immediately by the contractor on
receipt of notice in writing from the Engineer-in-charge. If he does not do so within
three days of receipt of such notice, the Engineer-in-charge shall get it removed at
the cost of the contractor.
2.2.9 In case the contractor brings surplus quantity of cement the same shall be removed
from the site after completion of work by the contractor at his own cost after
approval of the Engineer-in-Charge.
2.2.10 Cement, which is not used within 90 days from its date of manufacture, shall be
retested at approved laboratory. Until the results of such tests are found
satisfactory, it shall not be used on the work.
2.2.11 Compressive Strength of Cement
The average compressive strength of at least three mortar cubes (area of face 50
cm2) composed of one part of cement, three parts of standard sand (conforming to
IS 650:1996) by mass and P/4+3.0 percent (of combined mass of cement plus sand)
water, and prepared, stored and tested in the manner described in IS 4031 (Part 6):
1988, shall be as follows:
a) 72±1 hour not less than 23 MPa
b) 162±2 hour not less than 33 MPa
c) 672±4 hour not less than 43 MPa
NOTE: - P is the percentage of water required to produce a paste of standard
consistency (see as below)
Consistency of Standard Paste:-
The quantity of water required to produce a paste of standard consistency, to be
used for the determination of the water content mortar for the compressive
strength tests and for the determination of soundness and setting time, shall be
obtained by the method described in IS 4031 (part 4) : 1988.
2.3 STEEL REINFORCEMENT: -
2.3.1 (a) The Contractor shall procure IS marked TMT bars of various grades from the
Approved steel manufacturers (as per the list of approved makes furnishing part of
this document) or their authorized dealers having valid BIS license for IS: 1786-2008
and further confirming to the OM No.DG/MAN/382, dated 06.02.2019.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 103

The procured steel should have following qualities:


i. Excellent ductility, bend ability and elongation of finished product due to
possible refining technology.
ii. Consumption of steel should be accurate as per design
iii. Steel should have no brittleness problem in finished product.
iv. Steel should carry the quality of corrosion and earthquake resistance.
v. Quality steel with achievement of proper level of sulphur and phosphorus as
per IS: 1786-2008.
2.3.2 The contractor shall have to obtain and furnish test certificates to the Engineer-in-
charge in respect of all supplies of steel brought by him to the site of work.
2.3.3 Samples shall also be taken and got tested by the Engineer-in-charge as per the
provisions in this regard in relevant BIS codes. In case the test results indicate that
the steel arranged by the contractor does not conform to the specifications, the
same shall stand rejected, and it shall be removed from the site of work by the
contractor at his cost within a week time on written orders from the Engineer-in-
charge to do so. Else the department shall remove it and recover double the cost of
removal from the contractor.
2.3.4 The steel reinforcement bars shall be stored by the contractor at site of work in such
a way as to prevent their distortion and corrosion, and nothing extra shall be paid on
this account. Bars of different sizes and lengths shall be stored separately to
facilitate easy counting and checking.
2.3.5 For checking nominal mass, tensile strength, bend test, re-bend test etc. specimens
of sufficient length shall be cut from each size of the bar at random, and at
frequency not less than that specified below:
Size of bar For consignment below 100 For consignment above 100
tonnes tonnes
Under 10mm dia One sample for each 25 One sample for each 40 tonnes or
bars tonnes or par thereof. part thereof.
10mm to 16mm dia One sample for each 35 One sample for each 45 tonnes or
bars tonnes or part thereof. part thereof.
Over 16mm dia One sample for each 45 One sample for each 50tonnes or
bars tonnes or part thereof. part thereof.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 104

2.3.6 The contractor shall supply free of charge the steel required for testing including its
transportation to testing laboratories. The cost of tests shall be borne by the
contractor.
2.3.7 The actual issue and consumption of steel on work shall be regulated and proper
accounts shall be maintained as provided in clause 10 of the contract. The
theoretical consumption of steel shall be worked out as per procedure prescribed in
clause 42 of the contract and shall be governed by conditions laid therein. In case the
consumption is less than theoretical consumption including permissible variations
leading to under designing of the structure, the work shall be summarily rejected,
otherwise recovery at the rate so prescribed shall be made after ensuring structural
soundness and stability.. In case of excess consumption, no adjustment needs to be
made.
2.3.8 The steel brought to site and the steel remaining unused shall not be removed from
site without the written permission of the Engineer-in-charge.
2.3.9 The contractor shall submit original vouchers from the manufacturer for the total
quantity of steel supplied under each consignment to be incorporated in the work.
All consignment received at the work site shall be inspected by the Site staff along
with the relevant documents before acceptance. The contractor shall obtain Original
Vouchers and Test Certificates and furnish the same to the Engineer-in-Charge in
respect of all the lots of steel brought by him from approved supplier to the site of
work. The original vouchers and test certificates shall be deposited by the Site staff
and kept on record in the site office.
2.3.10 Reinforcement including authorized spacer bars and laps shall be measured in length
of different diameters as actually (not more than as specified in the drawings) used
in the work nearest to a centimeter. Wastage and unauthorized overlaps shall not be
measured.
2.3.11 The standard sectional weights referred to as in Table 5.4 in para 5.3.4 in CPWD
Specifications will be considered for conversion of length of various sizes of M.S.
Bars, Steel Bars and T.M.T. bars into Standard Weight.
2.3.12 Records of actual Sectional weights shall also be kept dia-wise and lot-wise. The
average sectional weight for each diameter shall be arrived at from samples from
each lot of steel received at site. The decision of the Engineer-in-Charge shall be final
for the procedure to be followed for determining the average sectional weight of
each lot. Quantity of each diameter of steel received at site of work each day will
constitute one single lot for the purpose. The weight of steel by conversion of length
of various sizes of bars based on the actual weighted average sectional weight shall
be termed as Derived Actual Weight. However for the stipulated issue of steel
reinforcement up to and including 10mm diameter bars, the actual weight of steel
issued shall be modified to take into account the variation between the actual and

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 105

the standard coefficients and the contractors’ accounts will be debited by the cost of
modified quantity.
2.3.13 (a) If the Derived Weight as in sub-para (2.3.12) above is less than the Standard
Weight as in Sub-para (2.3.11) above then the Derived Actual Weight shall be taken
for payment provided, if it is within the following tolerances specified in IS1786-
2008, otherwise whole lot will be rejected.
2.4
Tolerances on Nominal Mass

Nominal Size in mm Tolerance on Nominal mass Percent

Batch Individual Individual


Sample* sample for coil**

a) Upto and including 10 +7 -8 +8


b) Over 10 upto and
Including 16 +5 -6 +6
c) Over 16 +3 -4 +4

* For individual sample plus tolerance is not specified.


**For coils batch tolerance is not specified.

b) If the Derived Actual Weight is found more than the Standard Weight, the Standard
Weight as per in sub-para (2.3.11) above shall be taken for payment. In such case
nothing extra shall be paid for the difference between the Derived Actual Weight and
the Standard Weight.
2.4 SAFETY IN CONSTRUCTION
2.4.1 The contractor shall employ only such methods of construction, tools and plants as
are appropriate.
2.4.2 The contractor shall take all precautions and measures to ensure safety of works and
work man and shall be fully responsible for the same.
2.4.3 Safety pertaining to construction such as centering & shuttering, scaffolds, ladders,
working platforms, gangway etc. shall be governed by CPWD safety code, relevant
safety codes and the directions of Engineer in charge.
2.4.4 All the staging to be either of tubular steel structure with adequate bracings as
approved or made of built up structural sections made from rolled structural steel
sections.
2.4.5 Form work shall be properly designed for self weight, weight of reinforcement,
weights of fresh concrete and in addition the various live loads likely to be
imposed during construction process.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 106

2.4.6 The form work shall be designed & constructed so as to remain sufficiently rigid
during placing & compaction of concrete & shall be such as to prevent loss of
slurry from the concrete.
2.4.7 The vertical supports shall be adequately braced or otherwise secured in position
that these do not fall when the load gets released or the supports are accidentally
hit.
2.4.8 A thorough inspection of tubular steel centering is necessary before its erection and
members showing evidence of excessive rusting, kinks, dents or damaged welds
shall be discarded. Buckled or broken members shall be replaced. Care shall also be
taken that locking devices are in good working order and that coupling pins are
effectively aligned to frames. Tubes should have end to end joints in adjacent tubes
staggered. Sleeve couplers should be used in preference to joint pins for axial
connections.
2.4.9 Inclined forms which give rise to very high horizontal forces should be taken care of
by trussing and diagonal bracing
2.4.10 Vertical members should be placed centrally under the members to be supported
and over the member supporting them with no eccentricity exceeding 25mm
2.4.11 The centering frames shall be tied together with sufficient braces to make a rigid and
solid unit. It shall be ensured that struts and diagonal braces are in proper position
and are secured so that frames develop full load carrying capacity. As erection
progresses, all connecting devices shall be in place and shall be fastened for full
stability of joints and units.
2.4.12 Wedges under the supports shall be set on firm soil / PCC which assures adequate
stability for all props. Care shall be taken not to disturb the soil under the supports.
Adequate drainage shall be provided to drain away the water coming due to rains,
easing of forms or during the curing of the concrete to avoid softening of the
supporting soil strata.
2.4.13 During pouring of the concrete the centering shall be constantly inspected and
strengthened, if required wedges below the vertical supports tightened and
adjustment screws properly adjusted as necessary.
2.4.14 Only workmen actually engaged in the form work shall be allowed in the area during
operations. Those engaged in removing the form work shall wear helmets, gloves
and heavy soled shoes and approved safety belts etc.
2.4.15 The safety code as lay down in respective clauses of Agreement shall be strictly
followed.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 107

SPECIAL CONDITIONS FOR GREEN BUILDING

The building is proposed to be designed for as 3 Star Rated Green Building confirming to
GRIHA (Green Rating for Integrated Habitat Assessment) green building rating system. The
contractor is required to execute the work in a befitting manner.
Special conditions for GRIHA rating
The contractor shall plan and execute the work in a manner to preserve and protect the
landscape during construction and shall arrange the materials/equipment and follow the
procedure as per latest version of GRIHA rating as applicable.
All the mandatory criteria of GRIHA and additional conditions for Green Building
practices are to be necessarily followed.
The contractor shall comply with NBC norms on construction safety, health and
sanitation as per GRIHA rating system.
The construction activity shall be done in a befitting manner and the contractor shall adopt
measures to prevent air pollution at site in compliance with criterion 9 of GRIHA rating as
applicable.
The contractor shall comply with all the instructions and schemes for execution of
Green building.
Nothing shall be paid extra for all these conditions except for the items existing in the
schedule of quantities. For such items work done shall be paid on the basis of the
agreement rates.
Pre-construction Stage
1. Construction Vehicles, Equipment and Machinery
(i) All vehicles, equipment and machinery to be procured for construction shall
conform to the relevant Bureau of India Standard (BIS) norms.
(ii) Emission from the vehicles must conform to environmental norms.
(iii) Dust produced from the vehicular movement and other site activities is to be
mitigated by sprinkling of water.
(iv) Noise limits for construction equipments shall not exceed 75 dB(A), measured at
one meter from the edge of the equipment in free area, as specified in the
Environment Protection Act,1986, schedule VI part E, as amended on 9th
May,1993. The maximum noise levels near the construction site should be
limited to 65 dB (A) Leq (5 min) in project area.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 108

Construction Stage
Construction Wastes Disposal
(i) The pre-identified dump locations will be a part of solid waste management plan
to be prepared by the Contractor in consultation with Engineer -in-charge.
(ii) Contractor shall get approved the location of disposal site prior to
commencement of the excavation on any section of the project location.
(iii) Contractor shall ensure that any spoils of material / construction waste will not
be disposed off in any municipality solid waste collection bins.
Procurement of Construction Materials
(i) All vehicles delivering construction materials to the site shall be covered to avoid
spillage of materials and maintain cleanliness of the roads.
(ii) Wheel Tyres of all vehicles used by of the contractor, or any of his sub contractor
or materials suppliers shall be cleaned and washed clear of all dust/mud before
leaving the project premises. This shall be done by routing the vehicles through
tyre washing tracks.
(iii) Contractor shall arrange for regular water sprinkling at least twice a day (i.e.
morning and evening) for dust suppression of the construction sites and unpaved
roads used by his construction vehicles.
Water Pollution
(i) The Contractor shall take all precautionary measures to prevent the wastewater
during construction to accumulate anywhere.
(ii) The wastewater arising from the project is to be disposed off in the manner that
is acceptable to the CPCB.
Air and Noise Pollution
Contractor shall use dust screens and sprinkle water around the construction site to arrest
spreading of dust in the air and surrounding areas.
(i) Contractor shall ensure that all vehicles, equipment and machinery used for
construction are regularly maintained and confirm that emission levels comply
with environmental emission standards/norms.
(ii) For controlling the noise from Vehicles, Plants and Equipments, the Contractor
shall confirm the following:
(a) All vehicles and equipment used in construction will be fitted with exhaust
silencers.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 109

(b) Servicing of all construction vehicles and machinery will be done regularly
and during routine servicing operations, the effectiveness of exhaust
silencers will be checked and if found defective will be replaced.
(c) Noise emission from compactors(rollers) front loaders, concrete mixers,
cranes(movable), vibrators and saws should be less than 75 dB(A).
(d) As per the standards/guidelines for control of Noise Pollution from
Stationary Diesel Generator (DG) sets, noise emission in dB(A) from DG Sets
(2-1010 KVA) should be less than 94+10 log 10 (KVA). The standards also
suggest construction of acoustic enclosure around the DG Set and provision
of proper exhaust muffler with insertion loss of minimum 25 dB (A) each as
mandatory.
Personal Safety Measures for Labour
Contractor shall provide the following items for safety of workers employed by contractor
and associate agencies:
(i) Protective footwear/ helmet and gloves to all workers employed for the work on
mixing, cement, lime mortars, concrete etc. and openings in water
pipeline/sewer line.
(ii) Welder’s protective eye-shields to workers who are engaged in welding works.
(iii) Safety helmet and Safety harness/ belt Provide adequate sanitation/safety
facilities for construction workers to ensure the health and safety of the workers
during construction, with effective provisions for the basic facilities such as
sanitation, drinking water and safety equipments or machinery.
(iv) All the workers should be wearing helmet and shoes all the time on site.
(v) Masks and gloves should be worn whenever and wherever required.
(vi) Adequate drinking water facility should be provided at site, adequate number of
decentralized latrines and urinals to be provided for construction workers.
(vii) Full time workers (if any with the approval of Engineer-in-Charge) residing on site
should be provided with clean and adequate temporary hutment.
(viii) First aid facility should also be provided.
(ix) Overhead lifting of heavy materials should be avoided. Barrow wheel and hand-
lift boxes should be used to transport materials onsite.
(x) Tobacco and cigarette smoking should be prohibited onsite.
(xi) All dangerous parts of machinery are well guarded and all precautions for
working on machinery are taken.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 110

(xii) Maintain hoists and lifts, lifting machines, chains, ropes and other lifting
tackles in good condition. Provide safety net of adequate strength to arrest
falling material down below.
(xiii) Use of durable and reusable formwork systems to replace timber formwork and
ensure that formwork where used is properly maintained.
(xiv) Ensure that walking surfaces or boards at height are of sound construction and
are provided with safety rails and belts. Provide protective equipments such as
helmets.
(xv) Provide measure to prevent fire. Fire extinguisher and buckets of sand to be
provided in fire-prone area and elsewhere.
(xvi) Provide sufficient and suitable light for working during night.
(xvii) Ensure that measures to protect workers from materials of construction,
transportation, storage and other dangers and health hazards are taken.
(xviii) Ensure that the construction firm/division/company have sound safety policies.
(xix) Comply with the safety procedure, norms and guidelines (as applicable) as
outlined in NBC 2016.
(xx) Adopt additional best practices and prescribed norms as in NBC 2016.
Identify roads on-site that would be used for vehicular traffic. Update vehicular roads (if
these are unpaved) by increasing the surface strength by improving particle size, shape and
mineral type that make up the surface base. Add surface gravel to reduce source of dust
emission. Limit amount of fine particles (smaller than 0.075mm) to 10 -20%. Limit vehicular
speed on site 10km/h. Nothing extra will be payable for this.
All material storages should be adequately covered and contained so that they are not
exposed to situations where winds on site could lead to dust/particulate emissions.
Spills of dirt or dusty materials shall be cleaned up promptly so the spilled material does not
become a source of fugitive dust and also to prevent of seepage of pollutant laden water
into the ground aquifers. When cleaning up the spill, ensure that the clean - up process does
not generate additional dust. Similarly, spilled concrete slurries or liquid wastes should be
contained/cleaned up immediately before they can infiltrate into the soil/ground or runoff
in nearby areas.
Ensure that water spraying is carried out by wetting the surface by spraying water on:
(i) Any dusty material.
(ii) Areas where demolition work is carried out.
(iii) Any unpaved main-haul road and.
(iv) Areas where excavation or earth moving activities are to be carried out.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 111

The contractor shall ensure the following:


(i) Cover and enclose the site by providing dust screen, sheeting or netting to scaffold
along the perimeter of a building.
(ii) Covering stockpiles of dusty material with impervious sheeting.
(iii) Covering dusty load on vehicles by impervious sheeting before they leave the site.
(iv) Transferring, handling/storing dry loose materials like bulk cement and dry
pulverized fly ash inside a totally enclosed system.
(v) Spills of dirt or dusty materials shall be cleaned up promptly so that the spilled
material does not become a source of fugitive dust and also to prevent
seepage of pollutant laden water into the ground aquifers. When cleaning up the
spill, ensure that the clean-up process does not generate additional dust. Similarly,
spilled concrete slurries or liquid wastes should be contained / cleaned up
immediately before they can infiltrate into the soil/ground or runoff in nearby areas.
(vi) Clear vegetation only from areas where work will start right away.

Adopt measures to prevent air pollution in the vicinity of the site due to construction
activities. There is no standard reference for this. The best practices should be followed (as
adopted from international best practice documents and codes).

Provide safety barricading of site by drawing ribbon band along the site boundary, next to a
road or other public area.
The contractor shall provide experienced personnel with suitable training to ensure that
these methods are implemented. Prior to the commencement of any work, the method of
working, plant equipment and air pollution control system to be used on -site should be
made available for the inspection and approval of the Engineer -in-Charge to ensure that
these are suitable for the project.
Employ measures to segregate the waste on-site into inert, chemical or hazardous wastes.
Recycle the unused chemical/hazardous wastes such as oil, paint, batteries and asbestos. As
per GRIHA 5 rating (inert and Hazardous waste must be collected and storied separately
from site. Proper training must be given to all construction workers in order to train them to
be able to handle different kind of waste on site. In addition to segregating the inert and
hazardous waste, it is also important to either reuse the construction waste on site or safety
disposes it off to designated agencies for recycling.
To preserve the existing landscape and protect it from degradation during the process of
construction. Select proper timing for construction activity to minimize the disturbance such
as soil pollution due to spilling of the construction material and its mixing with rainwater.
The construction management plan including soil erosion control management plan shall be
prepared accordingly for each month. The application of erosion control measures includes

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 112

construction of gravel pits and tyre washing bays of approved size and specification for all
vehicular site entry/exits, protection of slopes greater than 10%. Sedimentation Collection
System and run-off diversion systems shall be in place before the commencement of
construction activity. Preserve and protect the existing vegetation by not-disturbing or
damaging to specified site areas during construction.
The Contractor should follow the construction plan as proposed by the Engineer-in-charge /
landscape consultant to minimize the site disturbance such as soil pollution due to spilling.
Use staging and spill prevention and control plan to restrict the spilling of the contaminating
material on site.
Spill prevention and control plans should clearly state measures to stop the source of the
spill. Measures to contain the spill and measures to dispose the contaminated material
and hazardous wastes. It should also state the designation of personnel trained to prevent
and control spills. Hazardous wastes include pesticides, paints, cleaners and petroleum
products.
A Soil Erosion and Sedimentation Control Plan (ESCP) should be prepared prior to
construction and should be applied effectively.
The contractor shall prepare and submit ‘Spill prevention and control plans’ before the
start of construction, clearly stating measures to stop the source of the spill, to contain the
spill, to dispose the contaminated material and hazardous wastes, and stating
designation of personnel trained to prevent and control spills. Hazardous wastes
include pesticides, paints, cleaners, and petroleum products.
The contractor shall ensure that no construction leaches (Ex: cement slurry) is allowed to
percolate into the ground. Adequate precautions are to be taken to safeguard against this
including reduction of wasteful curing processes, collection, basic filtering and reuse. The
contractor shall follow requisite measures for collecting drainage water run-off from
construction areas and material storage sites and diverting water flow away from such
polluted areas. Temporary drainage channels, perimeter dike/swale, etc. shall be
constructed to carry the pollutant -laden water directly to the treatment device or facility
(municipal sewer line).
All lighting installed by the contractor around the site and at the labour quarters during
construction shall be energy efficient fixtures of the appropriate illumination levels.
All paints, adhesives and sealants should comply with the VOC limits prescribed as Green
initiatives as follows:
The VOC (volatile organic compound) content of adhesives and sealants used on the interior
of the building must be less than VOC content limits mentioned below. A list of all the
adhesives and sealants used for the project is to be submitted along with the
manufacturer’s certificate supporting the VOC content.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 113

Architectural Applications VOC Limit(g/l minus water)


Indoor Carpet Adhesives 50
Carpet Pad Adhesives 50
Wood Flooring Adhesives 100
Rubber Floor Adhesives 60
Sub floor Adhesives 50

Ceramic Tile Adhesives 65

VCT and Asphalt Tile Adhesives 50


Dry Wall and Panel Adhesives 50
Cove base adhesives 50
Structural Glazing Adhesives 100

Multipurpose Construction Adhesives 70

Substrate Specific Application VOC Limit(g/l minus water)

Metal to Metal 30
Porous Material(except wood) 50
Plastic Foams 50
Wood 30
Fibreglass 80

Specialty Application VOC Limit(g/l minus water)


PVC Welding 510
CPVC Welding 490

ABS Welding 325

Plastic cement welding 250


Adhesive primer for plastic 550

Top and Trim Adhesive 250


Contact Adhesive 80
Special purpose Contact Adhesive 250
Structural wood member adhesive 140
Sheet applied rubber lining operations 850

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 114

Sealants VOC Limit(g/l minus water)


Architectural 250
Non Membrane Roof 300
Roadway 250
Single-ply roof membrane 450
Other 420
Sealant Primers
Architectural, nonporous 250
Architectural, porous 775
Other 750
Aerosol Adhesives
General purpose mist spray 65% VOC’s by weight
General purpose web spray 55% VOC’s by weight
Special purpose aerosol adhesives (all types) 70% VOC’s by weight

All the building materials and systems used on site must be as per the specifications and
approved makes by the Engineer-In-Charge.
All required certificates explaining the properties of the building material/system needs to
be obtained from the manufacturer/vendor as required by the green building rating
authority. The final certificates would be produced after the approval of green building
consultant with necessary due diligence. The purchase orders of all the materials made with
the manufacturers / authorized vendors should be maintained and shall be provided for the
process with due diligence upon request.
Water saving measures as suggested by the consultants need to be followed on site.
The contractor / subcontractor shall prepare and submit a Site Management Plan
(SMP) within 10 days of start, for approval by the Engineer -in-charge. This SMP shall
indicate the locations of godown, stockpiles, barricading, waste storage, offices, vehicular
movement routes etc. In short this SMP would comprehensively represent how the site
activities shall be managed conforming to GRIHA 3 Star guidelines.
Any other site management measures suggested by the Engineer-in-charge / Green building
consultant shall be followed on site.
The contractor shall submit to the Engineer -in-Charge after construction of the
buildings, a detailed as built quantification of the following within 10 days of recording of
completion.”

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 115

(i) Total materials used


(ii) Total waste generated,
(iii) Total waste reused,
(iv) Total water used,
(v) Total electricity consumed, and
(vi) Total diesel consumed.
Evidence for the implementation of the all the above required measures shall be provided
to the Engineer-in-Charge in the form of photographs and templates as required which is
required for the submission to the green building rating authority.
Nothing extra shall be payable for above provisions unless otherwise specified in Schedule
of Quantity.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 116

PARTICULAR SPECIFICATIONS
(Civil Component)
1. GENERAL
1.1 The work shall be carried out as per CPWD Specifications 2019 Vol. I & II with up to
date correction slips.
1.2 The work shall be executed and measured as per metric dimensions given in the
Schedule of quantities, drawings etc. (F.P.S. units wherever indicated are for
guidance only).
1.3 Wherever any reference to any Indian Standard Specification occurs in the
documents relating to this contract, the same shall be inclusive of all amendments
issued thereto or revisions thereof, if any.
1.4 Unless otherwise specified in the schedule of quantities the rates for all items of
the work shall be considered as inclusive of pumping out or bailing out water if
required for which no extra payment will be made. This will include water
encountered from any source, such as rains, floods, and sub-soil water table being
high due to any other cause whatsoever.
1.5 Unless otherwise specified in the schedule of quantities, particular specifications or
CPWD specifications (subject to the order or preference) the rates tendered by the
tenderer shall be all inclusive and shall apply to all lifts, all heights and all floor
including terrace, leads and depths and nothing extra over and above the schedule
of quantity shall be payable on this account.
1.6 The work shall be carried out in accordance with the Architectural drawings,
structural drawings and approved shop drawings. The structural shop and
architectural drawings shall have to be properly correlated before executing the
work. In case of any difference noticed between architectural and structural
drawings, the contractor shall obtain final decision of the Engineer-in-charge. In
case of any discrepancy in the item given in the schedule of quantities appended
with the tender and architectural drawings related to the relevant items, the
former shall prevail unless and otherwise given in writing by the Engineer in charge.
Nothing extra shall be payable on this account.
1.7 Wherever any reference to any Indian Standards occurs in the documents relating
to this contract, the same shall be inclusive of all amendments issued thereto or
revisions thereof, if any, up to the date of receipt of tenders.
1.8 The following additional specifications shall apply:
1.8.1 All stone aggregate and stone ballast shall be of hard stone variety and to be
obtained from quarries near& around to site of work, approved by the Department
of Mines, Govt. of Telangana. and as per direction of the Engineer in charge

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 117

1.8.2 Coarse sand should be obtained from sand quarries of nearby rivers, approved by
the Department of Mines, Govt. of Telangana. and as per direction of the Engineer
in charge. Sand to be used for cement concrete work including RCC, mortar for
masonry and plaster work shall be of standard quality and screened as required. It
shall be clean sand.
In case of non availability of sand, the agency may be permitted at the discretion of
Engineer-in Charge to use crushed stone sand on their request on production of
adequate proof of non availability of the same, provided it confirms to grading and
other requirements given in CPWD specifications. The change in sand type or
source would require revision of Mix Design of Concrete from the any Gov /semi
government laboratories. Only those private sector labs which were approved by
O/o ADG (H) from time to time are allowed . Can we write like this. , for which
nothing extra shall be paid. In case of use of crushed stone sand, all necessary
precautions for CC work, RCC work, masonry work, plaster work and all other related
works shall be taken by the agency as per relevant CPWD specifications and BIS
codes without any extra cost.
1.9 The rates for all items of work shall unless clearly specified otherwise include for all
floor levels of building and cost of all operations and all inputs of labour, material,
T&P, scaffolding, wastages, watch and ward, other inputs, all incidental charges, all
taxes, GST, duties, levies etc. required for execution of the work.
1.10 All crossings, embedment etc. in walls and floors for water supply, drainage and
sanitary pipes, fittings etc. shall be provided for individual walls and floors so as to
avoid cuttings of masonry work and floors. All such areas shall be made good
during finishing and nothing extra shall be payable on these accounts.
1.11 Product delivery, storage and handling of chemicals.
1.11.1 The contractor shall construct storage space for Chemicals to ensure that the
storage conditions are as recommended by the manufactures.
1.11.2 All the materials shall be procured and delivered in sealed containers with labels
legible and intact.
1.11.3 All the chemicals (polymers, epoxy, water proofing compound, plasticizer,
Polysulphide, all exterior and interior paints, polish etc.) shall be procured in
convenient packs say 20 litres/Kgs.} capacity packing only or as approved by the
Engineer-in-Charge, and not in bigger capacity containers, say 200 litre (Kgs.) drums
unless otherwise specifically permitted by the Engineer-in-Charge. One sample
from each lot of the chemical procured by the contractor shall be tested in a
laboratory. These laboratories may be in the Govt. sector, Semi Govt. or Private
sector. All Govt. Institutes, Indian Institute of Technology, National Institute of
Technology, Central and State funded laboratories stands approved. No approval is
required for testing in these laboratories/institutes. Testing from only those private

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 118

laboratories are allowed as approved by office of ADG,hyd from time to time.

1.11.4 All material required for the execution of the work shall be got approved, procured
and deposited with the Departmental supervisory staff. The materials shall be kept
in joint custody of the contractor and the Department. The watch and ward of
suchmaterial shall, however, remain to be the responsibility of the contractor and no
claim, whatsoever, on this account shall be entertained. Different containers of
each chemical shall be serially numbered on packing and also consumed in that
order.
Day-to-Day account of receipt, issue and balance shall be regulated by the
Department and proper account shall be maintained at site of work in the
prescribed form as per the standard practice.
1.11.5 All the chemicals shall be procured by the contractor directly from the
manufacturer..
1.11.6 The original copies of challan / cash memos towards the quantity of various
chemicals procured shall be made available by the contractor at the request from
the Engineer-in-Charge and a copy of the same shall be kept in record.
1.11.7 The Name of manufacturers, manufacturer’s product identification, and
manufacturer’s mixing instructions, warning for handling and toxicity and date of
manufacturing and shelf life shall be clearly and legibly mentioned on the labels of
the each container.
1.11.8 The contractor shall submit for the chemicals procured, manufacturer’s and / or
authorized dealer’s certificate regarding supplying and verifying conformance to
the material specifications, as specified.
1.11.9 All filled containers shall be handled in safe manner and in a way to avoid breaking
container seals.
1.11.10 Empty containers of the chemicals should not be removed from site till the
completion of work and shall be removed only with the written approval of the
Engineer-in-Charge.
1.11.11 All arrangements for measuring, dosing and mixing of material / chemicals at site
have to be made by the contractor.
1.11.12 Contractor shall suitably advise his site Engineer and all the workers as regards safe
handling of chemicals. Necessary protective and safety equipments in form of hand
gloves, goggles etc. shall be provided by the contractor and be also used at site.
1.11.13 All incidental charges of any kind including cartage, storage and wastage and safe
custody of material etc. shall be borne by the contractor and no claim, whatsoever,
shall be entertained on this account.

1.11.14 The chemicals shall be tested in an independent laboratory from the any Gov /semi

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 119

government laboratories. Only those private sector labs which were approved by
O/o ADG (H) from time to time are allowed or successor at the frequency as
specified. If required, more samples may have to be tested as per the directions of
the Engineer-in-Charge. Nothing extra shall be payable on this account. However,
testing charges shall be borne by the department for the samples satisfying the
requirements specified in the tender.
2. EARTH WORK:-
2.1 Earth work shall be executed as per CPWD specifications.
2.2 Excavation shall be undertaken to the width of footing including necessary margins
for construction operation as per drawing or directed otherwise. Where the nature
of soil or the depth of the trench and season of the year, do not permit vertical sides,
the contractor at his own expense shall put up the necessary shoring, strutting and
planking or cut slopes with or without steps, to a safer angle or both with due regard
to the safety of personnel and works and to the satisfaction of the Engineer.
Measurement of plan area of excavation for payment shall only be permitted.
2.3 All the major excavation shall be carried out by mechanical excavator. No extra
payment shall be made for that.
2.4 The contractor shall make at his own cost all necessary arrangements for maintaining
water level, in the area where works are under execution low enough so as not to
cause any harm to the works or problems in carrying out with the execution and
the rates for all items of work shall be considered as inclusive of pumping out or
bailing out water, if required and for which no extra payment shall be made. This
will include water coming from any source, such as rains, accumulated rain water,
floods, leakages from sewer and water mains subsoil water table being high or due
to any other cause whatsoever. The contractor shall make necessary provision of
pumping, dredging, bailing out water coming from all above sources and excavation
and other works shall be kept free of water by providing suitable system approved
by the Engineer-in-Charge.
2.5 De-watering required, if any, shall be done conforming to BIS Code IS: 9759 (guide
lines for de-watering during construction) and / or as per the specifications approved
by the Engineer-in-Charge. Design of an appropriate and suitable dewatering system
shall be the Contractor’s responsibility. Such scheme shall be modified / augmented
as the work proceeds based on fresh information discovered during the progress of
work, at no extra cost. At all times during the construction work, efficient drainage of
the site shall be carried out by the Contractor and especially during the laying of
plain cement concrete, taking levels, etc. The Contractor shall also ensure that there
is no danger to the nearby properties and installations on account of such lowering
of water table. If needed, suitable precautionary measures shall be taken by the
Contractor. Also the scheme of dewatering adopted shall have adequate built in
arrangement to serve as stand-bye to attend to repair of pumps etc. and disruption

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 120

of power / fuel supply. Nothing extra shall be payable on this account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 121

2.6 In trenches where surface water is likely to get into cut / trench during monsoons, a
ring bund of puddle clay or by any other means shall be formed outside, to the
required height, and maintained by the Contractor. Also, suitable steps shall be
taken by the Contractor to prevent back flow of pumped water into the trench.
Nothing extra shall be payable on this account.
AGGREGATE:

The aggregate (both fine and coarse aggregates) to be used in the work shall confirm to
CPWD specifications. The coarse aggregate and fine aggregate from natural source & other
than natural natural sources, are permitted to be used in the work. IS: 383-2016 permits use
of recycled aggregates (RA) and use of Recycled Concrete Aggregate (RCA) produced from
other than natural sources, for using in plain and reinforced cement concrete. The use of
aggregate from other than natural source is subjected to their confirmation of quality
standards & their extent of utilization shall be as specified in IS: 383-2016.

Use of recycled aggregate specified above shall supercede the specifications of aggregate
from natural sources mentioned else where in the tender document.

The manufactured aggregates shall be permitted with their extent of utilization as


percentage of total mass of fine or coarse aggregate as the case may be, as indicated in IS: 383-
2016, for use in plain and reinforced concrete and lean concrete.

Products manufactured from C&D recycled waste can be used in the work subjected to their
availability, quality control and meeting relevant standard and specifications, in the following
indicative list of works:

a. Screened soil for filling applications in road work and under floors
b. Recycled aggregates of size upto 150mm for subbase applications in road work
c. Manufactured sand in plaster
d. Concrete blocks, kerb stone, paver blocks in open areas and footpath etc.

Use of recycled aggregates shall be limited to the utilization extent specified in IS: 383-2016
for concrete work and maximum upto 25% in road work.

With a view to ensure maximum utilization of Construction & Demolition (C&D) waste,
Ministry of Environment, Forest and climate change has notified C&D waste management
Rule 2016 vide notification dated 29.03.2016 and a copy of the same is at the end of the part
B.
3.0 R.C.C. WORK:-
3.1 Ready Mix Concrete:
3.2.1 The contractor shall bring Ready Mix Concrete from approved RMC plants as
mentioned in the list showing preferred Brands/ Manufacturers/Makes enclosed in
this NIT. The contractor has to produce text of MOU proposed to be entered
between purchaser (the contractor) and supplier (R.M.C. plant) to the Engineer-in-

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 122

charge. The Engineer-in-charge shall give approval in writing. The contractor shall
draw the MOU with approved RMC plant owner / company and submit to Engineer- in-
charge within a week of such approval. The contractor will not be allowed to purchase
ready mixed concrete without completion of above stated formalities for use in this
project.
3.2.2 Notwithstanding the approval granted by Engineer-in-charge in aforesaid manner,
the contractor shall be fully responsible for quality of concrete including input
control, transportation and placement etc.
3.2.3 The Engineer-in-charge will reserve right to inspect at any such stage and reject the
concrete if he is not satisfied about quality of product. The contractor should
therefore draw MOU / agreement with RMC owner / company very carefully keeping
all terms and conditions / specifications forming a part of this tender document.
(i) The Engineer-in-charge reserves the right to exercise control over the
ingredients, water and admixtures purchased, stored and to be used in the
concrete including conducting of tests for checking quality of materials,
recordings of test results and declaring the materials fit or unfit for use in
production of mix.
(ii) Calibration check of the RMC.
(iii) Weight and quantity check on the ingredients, water and admixtures added for
batch mixing.
(iv) Time of mixing of concrete.
(v) Testing of fresh concrete, recordings of results and declaring the mix fit or unfit
for use. This will include continuous control on the workability during production
and taking corrective action.
3.2.4 For exercising such control, the Engineer-in-charge shall periodically depute his
authorized representative at the RMC plant. It shall be responsibility of the
contractor to ensure that all necessary equipment manpower & facilities are made
available to E-in-C and/ or his authorized representative at RMC plant.
3.2.5 Ingredients, admixtures & water declared unfit for use in production of mix shall not
be used. A batch mix found unfit for use shall not be loaded into the truck for
transportation.
3.2.6 All required relevant records of RMC shall be made available to the Engineer-in-
charge or his authorized representative. The E-in-C shall, as required, specify
guidelines & additional procedures for quality control & other parameters in
respect of materials and production & transportation of concrete mix, which shall
be binding on the contractor & the RMC plant.
3.3 Ingredients:

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 123

3.3.1 The sources of coarse aggregate, fine aggregate, water, admixture & cement to be
used in concrete work shall be identified by the contractor & he will satisfy himself
regarding their conforming to the relevant specifications & their availability before
getting the same approved from the Engineer-In-Charge.
(a) Coarse Aggregate: - As per CPWD Specifications.
(b) Fine Aggregate: - River sand or manufactured sand As per CPWD
Specifications.
(c) Water: - It shall conform to requirements laid down in IS: 456-
2000 / Para 3.1.1 of CPWD Specifications (Vol. I 2019)
(d) Cement: - Portland Pozzolona Cement (Fly Ash based) conforming
to IS: 1489/ OPC of grade 43 shall confirm to IS: 8112,
required in the work from reputed manufacturers of
cement as per the approved make in 50 kg. Bags
bearing manufacturer’s name and ISI marking, along
with manufacturers test certificate for each lot.
Portland Pozzolona Cement is to be used for RCC works
only subject to fulfillment of conditions of circular
number CDO / SE (RR) / fly ash (MAN) 02 dated
09.04.09 shall be used for design mix concrete and
shall conform to IS-1489 (Part I). However, if the
contractor uses higher grade of cement nothing extra
shall be paid.
e) Mineral additives: GGBS shall confirm to IS: 12089-1987 and that of fly
ash shall confirm to IS: 3812-2003. Uniform blending
with cement to be ensured in accordance with clause
5.2 & 5.2.1 of IS: 456-2000.

(f) Admixture/ Plasticizer: - The admixture shall conform to IS: 9103. The chloride
content in admixture shall satisfy the requirement of
BS: 5075. The total amount of chlorides in admixture
mixed concrete shall also satisfy the requirements of
IS: 456:2000. Admixtures shall not be used without
approval of Engineer-in-Charge. Whenever required,
the admixture of approved quality & approved make
only shall be used to attain the required workability.
Nothing extra on account of use of Admixture /
Plasticizer shall be payable.
3.4. WATER CEMENT RATIO AND SLUMP

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 124

3.4.1 In proportioning a particular mix, the manufacturer/producer/contractor shall give


due consideration to the moisture content in the aggregates, and the mix shall be so
designed as to restrict the maximum free water cement ratio to less than the 0.45.
3.4.2 Due consideration shall be given to the workability of the concrete thus produced.
Slump shall be controlled on the basis of placement in different situations.
Degree of
Placing Conditions Slump (mm)
Workability
(1) (2) (3)

Lightly reinforced sections in slabs, beams, walls, Low 25-75


columns
Heavily reinforced section in slabs, beams, walls, Medium 50-100
columns.

Pumped concrete Medium 75-100

Design mix parameters:


Grade of Concrete M25 M30

(i) Nominal Max size of 20 mm angular as per CPWD 20 mm angular as per CPWD
aggregate specification specification

ii) Degree of workability


(Slump) mm
25 to 75mm 25 to 75mm
a) Without Pump
b) With Pump
75 to 125mm 75 to 125mm
(iii) Degree of quality Good. Good.
control
(iv) Type of exposure Moderate. Moderate.

(v) Max free water 0.5 0.45


cement/ ratio
(vi) Type of cement used i) Portland Pozzolana cement i) Portland Pozzolana cement
with min 30% fly ash content with min 30% flyash content
or or
ii) OPC- 43 in combination ii) OPC- 43 in combination with
with GGBS. GGBS.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 125

(vii) Minimum 360 kg/cum 380 kg/cum


Cementitious Content
(250 kg cement + 110 kg (265 kg cement + 115 kg
(cement + mineral
GGBS) GGBS)
additive)

(Viii) Fine Aggregate Coarse sand as per CPWD Coarse sand as per CPWD
specifications. specifications.

Note: Any excess cement required as per mix design shall be met from GGBS and nothing
extra shall be paid for such addition of GGBS. The dosage of super plasticizer / High
Range water reducers (HRWR) shall be adjusted to achieve the required strength
and workability

Sl. No. Grade of Concrete M10 M15


1 Nominal Max size of 20 mm angular as per 20 mm angular as
aggregate CPWD specification per CPWD
specification
2 Degree of workability
(Slump) mm
50-100 mm 50-100 mm
c) Without Pump 75 to 125mm 75 to 125mm
d) With Pump

3 Degree of quality control Good. Good.


4 Type of exposure Moderate. Moderate.

5 Max free water cement/ 0.5 0.5


ratio

6 Type of cement used i) Portland Pozzolana i) Portland Pozzolana


cement with min 30% cement with min
fly ash content 30% fly ash content
or or
ii) OPC- 43 in ii) OPC- 43 in
combination with combination with
GGBS. GGBS.

7 Minimum Cementitious 260Kg/cum. 300Kg/cum.


Content (cement + mineral
(182 kg cement + 78 kg (210 kg cement + 90
admixture)
GGBS) kg GGBS)

8 Fine Aggregate Coarse sand as per Coarse sand as per

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 126

CPWD specifications.. CPWD


specifications..

9 Mix applicable Plain cement concrete Plain cement


concrete
10 Method application Pumping Pumping
11 Max Cement content - -
12 (A) Characteristic Greater than or Greater than or
compressive strength equivalent to equivalent to
compliance fck+0.825xEstablished fck+0.825xEstablishe
requirement. (Mean of standard deviation d standard deviation
group of 4 non-
Or Or
overlapping tests and
consecutive test) Fck+3whichever is more Fck+3whichever is
(N/Sqmm) more

(B) Individual test Fck-3 Fck-3


(N/Sqmm)

Sl.no.12 above is added for the purpose of operation of Clause 16 of IS 456 2000.

Note: Any excess cement required as per mix design shall be met from GGBS and nothing
extra shall be paid for such addition of GGBS. The dosage of super plasticizer / High Range
water reducers (HRWR) shall be adjusted to achieve the required strength and
workability.

3.5 CHARACTERISTIC COMPRESSIVE STRENGTH COMPLIANCE REQUIREMENT


In the designation of concrete mix letter M refers to the mix and the number to the
specified characteristic compressive strength of 15 cm – Cube at 28 days expressed
in N/mm2.

Specified Mean of the Group of 4 Non-overlapping Individual Test Results in


Grade consecutive test results in N/mm2 N/mm2

(1) (2) (3)


M25 ≥ Fck + 0.825 x established standard ≥ Fck – 4 N/mm2
deviation (rounded off to nearest 0.5
Or
N/mm2)
Above
Or
Fck + 4 N/mm2, whichever is greater where
fck is characteristic compressive strength of
CC cube at 28 days.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 127

Note: (i) In the absence of established value of standard deviation, the values
given in Table as mentioned below may be assumed, and attempt
should be made to obtain results of 30 samples as early as possible to
establish the value of standard deviation.
(ii) The acceptance criteria for compressive strength as mentioned in
IS:456- 2000 as amended up to date shall prevail over the above
criteria in case of any difference.

3.6 The Contractor shall engage one of the following approved laboratories / test house for
designing the concrete mix in accordance with relevant IS Code and to conduct
laboratory tests to ensure the target strength & workability criteria for a given grade of
concrete: -
The contractor shall submit at his own cost, the mix design report from approved
laboratories such as AU, Visakhapatnam / IIT Chennai/IIT Hyderabad /National
Institute of Technology, Warangal/JNTU Hyderabad/NCCBM Hyderabad / any other
government institute /college or any laboratory as approved by ADG Hyderabad,
CPWD from time to time for approval of Engineer-in-charge within 30 days from the
date of issue of letter of acceptance of the tender. No concreting shall be done until
the mix design is approved. Every time sources of materials/cement is changed mix
design report shall be got re- done and has to be got approved from Engineer In charge.
The various ingredients for mix design / laboratory tests shall be sent to the lab/ test
houses through the Engineer-in-charge and the samples of such aggregates sent shall
be preserved at site by the department. Nothing extra shall be paid on this account.
In the event if all the above laboratories are unable to carry out the requisite design/
testing, the contractor may have it done from any other NABL accredited laboratory
with prior approval of the SE cum PD, CPWD, Hindupur.

3.7 The contractor shall submit the report on design mix from any of above approved
laboratories for approval of Engineer in Charge within 30 days from the date of
issue of letter of acceptance of the tender. No concreting shall be done until the
design mix is approved. In case of the likely use of admixtures in concrete, the
contractor shall design and test the concrete mix by using trial mixes with
admixtures also, for which nothing extra shall be payable.
3.8 In case of change of source or characteristic properties of the ingredients used in the
concrete mix design during the work, the contractor as per the directions of the
Engineer-in-charge shall submit a revised concrete mix design report. Nothing extra
shall be paid on this account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 128

3.9 All cost of mix designing and testing, connected therewith, including charges payable
to the laboratory shall be borne by the Contractor including redesigning of the
concrete mix whenever required & as directed by Engineer-In-Charge.
3.10 The mix design for a specified grade of concrete shall be done for a target mean
compressive strength Tck = Fck + 1.65s
Where Fck = Characteristic compressive strength at 28 days.
s = Standard deviation which depends on degree of quality
control.

The degree of Quality Control for this work is “good” for which the standard
deviation obtained for different grades of concrete shall be as follows: -
GRADE OF CONCRETE STANDARD DEVIATION
M-25 4.0
M-30 5.0

M-35 5.0
M-40 5.0
However, actual standard deviation based on test strength of samples for each grade
of concrete shall be calculated separately as per procedure laid down in clause 9.2.4
of Code of Practice IS 456:2000.
3.10.1 TRIAL BATCHES
(a) The designed mix proportions shall be checked for target mean compressive
strength by means of trial batches.
(b) Minimum three sets of separate preliminary tests shall be carried out for
each trial batch of concrete mix. Each test shall comprise of six specimens
and only one test-set of six specimens shall be made on any particular day.
(c) The quantities of materials for each trial mix shall be sufficient for at least six
specimens (cubes) and the concrete required for carrying out workability
tests.
(d) The workability of trial mix No.1 shall be measured and mix shall be carefully
observed for freedom from segregation, bleeding and its finishing
characteristics. The water content, if required, shall be adjusted
corresponding to the required changes in the workability.
(e) With the modified Water Content, the mix proportions shall be recalculated
by keeping with water cement ratio unchanged. The mix proportion, as
modified, shall form the Trial Mix No.2 and tested for the specified strength
and workability.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 129

(f) In addition, trial mix No.3 and 4 shall be designed by keeping water contents
same as that determined for trial mix 2 but varying the water cement ratio by
+ 10 percent of the specified value and tested for their design characteristics.
(g) Out of the six specimen of each set, three shall be tested at seven days and
remaining three at 28 days. The preliminary tests at seven days are intended
only to indicate the strength to be attained at 28 days, while the design mix
shall be approved only on the basis of test strength at 28 days.

3.10.2 APPROVAL OF DESIGN MIX


The design mix shall be considered satisfactory and approved if at least three
preliminary test-sets individually satisfy the following strength and workability
criteria:
(a) The average strength of each test-set is not less than the specified target
mean compressive strength (Tck).
(b) The strength of any specimen cube is not less than 0.85 fck.
(c) The concrete mix is of required degree of workability and acceptable
concrete finish.

3.11 DESIGN MIX CONCRETE FROM FULLY AUTOMATIC COMPUTERISED CONCRETE


BATCHING AND MIXING PLANT
3.11.1 Proportioning Concrete
In proportioning cement concrete, the quantity of both cement and aggregates
shall be determined by weight. The cement shall be weighed separately from the
aggregates. Water shall either be measured by volume in calibrated tanks or
weighed. All measuring equipment shall be maintained in a clean and serviceable
condition. The amount of mixing water shall be adjusted to compensate for
moisture content in both coarse and fine aggregates. The moisture content of
aggregates shall be determined in accordance with IS : 2386 (Part III). Suitable
adjustments shall also be made in the weights of aggregates to allow for the
variation in weight of aggregates due to variation in moisture content.
3.11.2 Production of Concrete
3.11.2.1 The concrete shall be produced in a central batching and mixing plant with,
computerized printing for contents and admixture dosage. The batching plant
shall be fully automatic. Automatic batcher shall be charged by devices which,
when actuated by a Single starter switch will automatically start the weighing
operation of each material and stop automatically, when the designated weight of
each material has been reached. The batching plant shall have automatic

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 130

arrangement for dispensing the admixture and shall also be capable of discharging
water in more than one stage. A print out from the batching plant for every lot
shall be submitted. A batching plant essentially shall consist of the following
components: Separate storage bins for different sizes of aggregates, silo for
cement; and water storage tank.

 Batching equipment
 Mixers
 Control panels
 Mechanical material feeding and elevating arrangements
3.11.2.2 The compartments of storage bins for aggregates shall be approximately of equal size.
The cement compartment shall be centrally located in the batching plant. It shall be
watertight and provided with necessary air vent, aeration fittings for proper flow of
cement & emergency cement cut off gate. The aggregate and sand shall be charged by
power operated centrally revolving chute. The entire plant from mixer floor upward shall
be enclosed and insulated. The batch bins shall be constructed so as to by self-cleansing
during drawdown. The batch bins shall in general conform to the requirements of IS :
4925.
3.11.2.3 WATER:
1. Water to be used in manufacturing and curing of Concrete shall be tested before
use. All such tests shall be submitted to the Engineer in charge for his approval
before water is used in work.
2. Contractor shall identify the location of source of water intended to be used. Each
such source of water shall be separately tested. In the event of a change in source
of water all tests specified herein shall have to be repeated.
3. In the event of water is drawn from tube wells or open wells, water samples shall
be for seasonal fluctuations in water table or at intervals to be directed by the
Engineer in charge.
4. Water samples from each source shall be tested as under:
Test Number of tests for each source
a. Acidity 3
b. Alkalinity 3
c. Presence of Solids 3

Mean values of the above tests shall be taken as the representative value and the
acceptance criteria shall be based on these test results. All testing procedure and
computation of test results shall conform to IS: 3025
5. Approved quality water shall be collected and stored in the Under Ground
sumps/elevated tanks for the day to day requirement of work and same shall be
used for all cement works and also for curing. Due care shall be taken in this
regard.
3.11.2.4 The batching equipment shall be capable of determining and controlling the
prescribed amounts of various constituent materials for concrete accurately i.e.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 131

water, cement, sand, individual size of coarse aggregates etc. The accuracy of the
measuring devices shall fall within the following limits.

Measurement of Cement ±2% of the quantity of cement in each batch

Measurement of Water ±3% of the quantity of water in each batch


±3% of the quantity of aggregate in each
Measurement of Aggregate
batch
±3% of the quantity of admixture in each
Measurement of Admixture
batch

3.11.2.5 Mixing Concrete


3.11.2.5.1 The mixer in the batching plant shall be so arranged that mixing action in the
mixers can be observed from the operator's station. The mixer shall be equipped
with a mechanically or electrically operated timing, signaling and metering
device which will indicate and assure completion of the required mixing period.
The mixer shall have all other components as specified in IS: 4925.
3.11.2.6 Transportation, Placing and Compaction of Concrete
3.11.2.6.1 Mixed concrete from the batching plant shall be transported to the point of
placement by transit mixers or through concrete pumps or steel closed bottom
buckets capable of carrying 0.6 cum concrete. In case the concrete is proposed
to be transported by transit mixer, the mixer speed shall not be less than 4 rev/
min. of the drum nor greater than a speed resulting in a peripheral velocity of
the drum as 70 m / minute at its largest diameter. The agitating speed of the
agitator shall be not less than 2 rev / min. nor more than 6 rev / min. of the
drum. The number of revolutions of the mixing drum or blades at mixing speed
shall be between 70 to 100 revolutions for a uniform mix, after all ingredients,
have been charged into the drum. Unless tempering water is added, all rotation
after 100 revolutions shall be at agitating speed of 2 to 6 rev / min. and the
number of such rotations shall not exceed 250. The general construction of
transit mixer and other requirements shall conform to IS: 5892.
3.11.2.6.2 In case concrete is to be transported by pumping, the conduit shall be primed by
pumping a batch of mortar / thick cement slurry through the line to lubricate it.
Once the pumping is started, it shall not be interrupted (if at all possible) as
concrete standing idle in the line is liable to cause a plug. The operator shall
ensure that some concrete is always there in the pump-receiving hopper during
operation. The lines shall always be maintained clean and shall be free of dents.
3.11.2.6.3 Materials for pumped concrete shall be batched consistently and uniformly.
Maximum size of aggregate shall not exceed one-third of the internal diameter

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 132

of the pipe. Grading of aggregate shall be continuous and shall have sufficient
ultra fine materials (materials finer than 0.25mm). Proportion of fine aggregates
passing through 0.25mm shall be between 15 & 30% and that passing through
0.125 mm sieve shall not be less than 5% of the total volume of aggregate.
When pumping long distances and through hot weather, set-retarding
admixtures may be used. Admixtures to improve workability can be added.
Suitability of concrete shall be through pumping shall be verified by trial mixes
and by performing pumping tests.
3.12 PREPARATION OF MIXES AS PER APPROVED DESIGN MIX AND CONDUCTING
CONFIRMATORY TEST AT FIELD LAB.
3.12.1 The contractor shall make the cubes of trial mixes as per approved Mix design at
site laboratory for all grades, in presence of Engineer in charge using sample of
approved materials proposed to be used in the work prior to commencement of
concreting and get them tested in his presence to his entire satisfaction for 7
days and 28 days . Test cubes shall be taken from trial mixes as follows.
3.12.2 For each mix, a set of six cubes shall be made from each of the three consecutive
batches. Three cubes from each set of six shall be tested at age of 7 days and
remaining three cubes at age of 28 days. The cubes shall be made, cured,
transported and tested strictly in accordance with specifications. The average
strength of nine cubes at age of 28 days shall exceed the specified target mean
strength for which design mix has been approved, the evaluation of test results
will be done as per IS : 456-2000.
3.12.3 Frequency of Sampling
3.12.3.1 Sampling Procedure engaged for
A random sampling procedure shall be adopted to ensure that each concrete
batch shall have a reasonable chance of being tested that is the sampling should
be spread over the entire period of concreting and cover all mixing units.
3.12.3.2 Frequency
The minimum frequency of sampling of concrete of each grade shall be in
accordance with the following:
_
_
Quantity of Concrete in the Number of Samples
Work, m3
I-5 1
6 - 15 2
16 - 30 3
31- 50 4
51 and above 4 plus one additional sample

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 133

for each additional 50 m3 or part


thereof
NOTE- At least one sample shall be taken from each Shift. Where concrete is produced at
continuous production unit, such as batch-mixed concrete plant, frequency of’ sampling may
be decided by Engineer-in-charge in such a manner so as to ensure that each concrete batch
shall have a reasonable chance of being tested.

3.12.4 Test Specimen


Three test specimens shall be made for each sample for testing at 28 days.
Additional samples may be required for various purposes such as to determine
the strength of concrete at 7 days or at the time of striking the formwork, or to
determine the duration of curing, or to check the testing error. Additional
samples may also be required for testing samples cured by accelerated methods
as described in IS 9103. The specimen shall be tested as described in IS 516.
3.12.5 Test Results of Sample
The test results of the sample shall be the average of the strength of three
specimens. The individual variation shall not be more than +/- 15 percent of the
average. If more, the test results of the sample are invalid. 90% of the total tests
shall be done at the laboratory established at site by the contractor and
remaining 10% in the laboratory as mentioned in para 3.1.5, or in any other
NABL accredited laboratory as directed by the SE cum PD, CPWD, Hindupur
3.12.6 ACCEPTANCE CRITERIA
3.12.6.1 Compressive Strength
The concrete shall be deemed to comply with the strength requirements when
both the following condition is met:
a) The mean strength determined from any group of four consecutive test
results complies with the appropriate limits in col 2 of Table given under
para 3.1.4 above.
b) Any individual test result complies with the appropriate limits in col 3 of
Table given under para 4.1.4 above.
3.12.6.2 Quantity of Concrete Represented by Strength Test Results
The quantity of concrete represented by a group of four consecutive test-results
shall include the batches from which the first and last samples were taken
together with all intervening batches.
Where the mean rate of sampling is not specified the maximum quantity of
concrete that four consecutive test results represent shall be limited to 60 m 3.
3.12.6.3 Concrete of each grade shall be assessed separately.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 134

3.12.6.4 Concrete is liable to be rejected if it is porous or honey-combed, its placing has


been interrupted without providing a proper construction joint, the
reinforcement has been displaced beyond the tolerances specified, or
construction tolerances have not been met. However, the hardened concrete
may be accepted after carrying out suitable remedial measures to the
satisfaction of the Engineer-in-Charge.
3.12.7 Ultrasonic Pulse Velocity Method of Test for RCC
3.12.7.1 The underlying principle of assessing the quality of concrete is that
comparatively higher velocities are obtained when the quality of concrete in
terms of density, homogeneity and uniformly is good. The consistency of the
concrete as regards its general quality gets established. In case of poorer quality
lower velocities are obtained. If there are cracks, voids or flaws inside the
concrete which come in the way of transmission of pulse, lower velocities are
obtained.
3.12.7.2 The quality of concrete in terms of uniformity, incidence or absence of internal
flaws, cracks and segregation etc. indicative of the level of workmanship
employed, can thus be assessed using the guidance given in table below, which
have been evolved for characterizing the quality concrete in structure in term of
the ultrasonic pulse velocity.
Velocity criterion for Concrete Quality Grading.
Sl. Pulse velocity by Cross Concrete Quality Grading
No. Probing (km/sec)
1 Above 4.5 Excellent
2 4.5 to 3.5 Good
3 3.5 to 3.0 Medium
4 Below 3.0 Doubtful
Note: In Case of “doubtful” quality it may be necessary to carry further tests.

3.12.7.3 Pulse velocity method of test of concrete is to be conducted for CPWD works as
a routine test. The acceptance criteria as per the above table will be applicable
which is as per IS 13311 (part-1): 1992. From the above “Good” and “Excellent”
grading are acceptable and below these grading the concrete will not be
acceptable. The cost of testing shall be borne by the contractor.
3.12.7.4 All RCC Columns and 5% of the other of RCC members in each category i.e.
beam, column, slab and footing may be tested by UPV test method for
establishing quality of concrete. It is suggested that test be conducted on RCC
beam near joint with column, on RCC column near joint with beam, on RCC
footings and rafts. On RCC rafts a suitable grid can be worked out for
determining number of tests. In addition doubtful areas such as honeycombed

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 135

locations, locations, where continuous seepage is observed, construction joints


and visible loose pockets will also be tested.
3.12.7.5 The test results are to be examined in view of the above acceptance criteria “Good”
and “Excellent” and wherever concrete is found with less than required quality
as per acceptance criteria, repairs to concrete will be made. Honeycombed areas
and loose pockets will be repaired by grouting using Portland Cement
Mortar/Polymer Modifies Cement Mortar /Epoxy Mortar ,etc. after chipping
loose concrete in appropriate manner. In areas where concrete is found below
acceptance criteria and defects are not apparently visible on surface ,injecting
approved grout in appropriate proportion using epoxy grout /acrylic Polymer
modified cements slurry made with shrinkage compensating cement / plain
cement slurry etc will be resorted to for repairs.(refer relevant chapters from
CPWD Hand Book on Repairs and Rehabilitation of RCC Buildings).Repair to
concrete will be done till satisfactory results are obtained as per the acceptance
criteria by retesting of the repaired area. If satisfactory results are not obtained
dismantling and relaying of concrete will be done.
3.13 SPECIAL CONDITIONS FOR DESIGN MIX CONCRETE
1 The term machine batched, machine mixed and machine vibrated design mix
cement concrete used in the document shall mean the concrete produced at site
in fully automatic concrete batching & mixing plant (IS 4925), placed in position
by the concrete pump and vibrated by surface vibrator/ needle vibrator/ plate
vibrator, as the case may be to achieve required strength and durability.
(However for small elements like lintels, chajjas, shelves etc, the requirement of
pumping would be dispensed with as per direction of Engineer – in – charge and
placement would be done through alternative means).
2. Design mix concrete shall be used in the work for all structural members. For
design mix concrete revised CPWD specifications 2019 along with relevant IS
codes shall be followed in general along with the specific provisions made
herein.
3. Design parameters for M 10 Design mix concrete
Following parameters shall be adopted for mix design.

S.No Grade of Concrete M10

1 Nominal Max size of aggregate 20 mm angular as per CPWD


specification
2 Degree of workability (Slump) mm
e) Without Pump 50-100 mm

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 136

f) With Pump 75 to 125mm

3 Degree of quality control Good.

4 Type of exposure Severe.


5 Max free water cement/ ratio 0.65
6 Minimum Cement Content 220Kg/cum.

7 Fine Aggregate Coarse sand as per CPWD specifications..


8 Mix applicable Plain cement concrete
9 Method application Pumping
10 Max Cement content 500 kg/Cum

11 C) Characteristic compressive strength Greater than or equivalent to


compliance requirement. (Mean of fck+0.825xEstablished standard deviation
group of 4 non-overlapping tests
Or
and consecutive test) (N/Sqmm)
Fck+3whichever is more
(D) Individual test (N/Sqmm) Fck-3

Sl.no.12 above is added for the purpose of operation of Clause 16 of IS 456 2000.
(4) Approved admixtures conforming to IS-9103 shall be permitted to be used. The
chloride content in the admixture shall satisfy the requirement of BIS 5075. The
total amount of chloride content in the admixture mixed concrete shall satisfy
the requirement of IS 456-2000.
(5) The concrete mix design with and without admixture will be carried out by the
contractor through the laboratory to be approved by the Engineer-in- Charge.
(6) The various ingredients for mix design/ laboratory tests shall be sent to the
lab/test houses through the Engineer-in-Charge and the samples of such
ingredients sent shall be preserved at site till completion of work or change in
Design Mix whichever is earlier. The sample shall be taken from the approved
materials, which are proposed to be used in the work.
(7) The contractor shall submit the mix design report from approved laboratories
such as AU, Visakhapatnam / IIT Chennai/IIT Hyderabad /JNTU
Hyderabad/NCCBM Hyderabad or any Govt Engineering college / Institute OR
any other laboratory as approved by ADG ,Hyderbad CPWD from time to time
for approval of Engineer-in-charge within 30 days from the date of issue of letter
of acceptance of the tender. No concreting shall be done until the mix design is

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 137

approved.

(8) The contractor shall make cubes of trial mixes as per approved mix design at site
laboratory for all grades of concrete in presence of the Engineer-in-charge using
same ingredients as adopted for design mix, prior to commencement of
concreting and get them tested in presence of Engineer- in – Charge for 7 days
and 28 days. For each design mix, a set of six cubes shall be prepared from each
of the three consecutive batches. Three cubes from each set shall be tested at
the age of 7 days and three cubes at the age of 28 days. The cubes shall be
made, cured, transported and tested strictly in accordance with CPWD
specification. The average strength of nine cubes at the age of 28 days shall
exceed the specified target mean strength for which design mix has been
approved.
(9) Tests shall be done at the laboratory as approved by the Engineer-in-charge.
(10) For each change of source or quality / characteristic properties of the
ingredients during the work, from that approved & used in the concrete mix a
fresh mix design shall be got done by the contractor. Revised trial mix test shall
be conducted and shall be submitted by the contractor as per the direction of
the Engineer-in-charge.
(11) The cost of packaging, scaling, transportation, loading, unloading cost of samples
and the testing charges for mix design in all cases shall be borne by the
contractor.
(12) The mix design shall be done considering the degree of quality control as ‘good’
in all cases.
13) The Item of design mix cement concrete shall be inclusive of all the ingredients
including admixtures it required labour, machinery, T&P etc. (Expect shuttering
which will be measured & paid for separately) required for a design mix concrete
of required strength and workability. The rate quoted by the agency for the mix
design items shall be net & nothing extra shall be payable on account of change
in quantities of concrete ingredients like sand, aggregates and admixtures etc.
as per the approved mix design until unless specified elsewhere in the Notice
Inviting Tender Documents.
14) No fly ash shall be allowed to be added in the Design Mix at site
3.14 COVER BLOCKS: Contractor shall use factory made cover blocks of approved shape
and strength for all RCC works to avoid displacement of bars in any direction and to
ensure proper cover. Alternatively, the contractor may manufacture the cover blocks

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 138

as per approved methodology by Engineer-In-charge. The grade of concrete shall be


same grade as of concrete in which they will be used. The concrete shall be fibre
reinforced concrete with 6mm downgraded aggregate. Shape & size shall be as
decided by Engineer-In-charge.

3.15 CURING:
i) The contractor shall ensure moist curing to all structural members in
general. Curing shall be done with 2 or 3 layers of wet hessian cloth covered
by PVC sheets in order not to allow the moisture to evaporate.
ii) Since the design mix is having controlled water content, the contractor shall
protect the concrete from drying shrinkage by resorting to early age curing.
Covering of wet hessian cloth shall be done after the onset of the final
setting time.
iii) The contractor shall submit methodology of proposed curing which ensures
continuous maintenance of required temperature regime.
iv) Membrane curing by chemical compounds may be allowed at places which
are normally inaccessible and repair works and nothing extra is payable on
this account. If curing compounds are proposed for any particular use, the
contractor shall obtain permission for use of any particular brand of
compounds from Engineer-In-Charge.

3.16 RATES: -
(i) The rate includes the cost of materials, labour and T&P, including mixing, placing,
pumping of concrete and transportation involved in all the operations described
above except for the cost of centring, shuttering & reinforcement which will be paid
for separately.

(ii) In case of rejection of concrete on account of unacceptable compressive strength,


governed by para “Standard of Acceptance” as above, the work for which samples
have failed shall be redone at the cost of contractor. However, the Engineer-in-
charge may order for additional tests (like cutting cores, ultrasonic pulse velocity
test, load test on structure or part of structure, etc) to be carried out at the cost of
contractor to ascertain if the portion of structure wherein concrete represented by
the sample has been used, can be retained on the basis of results of individual or
combination of these tests. The Contractor shall take remedial measures necessary
to retain the structure as approved by the Engineer-in-charge without any extra
cost. However, for payment, the basis of rate payable to contractor shall be
governed by the 28 days cube test results and reduced rates shall be regulated in
accordance with CPWD Specifications.
3.17 RCC WORK (ORDINARY)

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 139

3.17.1 The work shall be done in accordance with CPWD Specifications with upto date
correction slips.
3.17.2 Water Cement ratio for Ordinary RCC work shall not be more than 0.45. Contractor
shall use concrete mixture of proper design having arrangement for measuring water
for mixing of concrete.
3.18 FORM WORK
3.18.1 The work shall be done in general as per CPWD Specifications.
3.18.2 Only M.S. centering / shuttering and scaffolding material unless & otherwise
specified shall be used for all R.C.C. work to give an even finish of concrete surface.
However, marine-ply shuttering in exceptional cases as per site requirement may be
used on specific request from contractor to be approved by the Engineer-in-Charge.
3.18.3 Nothing extra shall be paid for the centering and shuttering, circular in shape
whenever the formwork is having a mean radius exceeding 6m in plan.
3.18.4 Nothing extra shall be paid for grid beams and the corresponding slabs having clear
span more than 1.20 meters.
3.18.5 In order to keep the floor finish as per architectural drawings and to provide
required thickness of the flooring as per specifications, the level of top surface of
R.C.C. shall be accordingly adjusted at the time of its centering, shuttering and
casting for which nothing extra shall be paid to the Contractor except the places
where different type of flooring is provided in the same room.
As per general engineering practice, level of floors in toilet / bath, balconies, shall be
kept 12 to 20mm or as required, lower than general floors shuttering should be
adjusted accordingly. Nothing extra is payable on this account.
3.18.6 Steel shuttering as approved by the Engineer-in-Charge shall be used by the
contractor. Minimum size of shuttering plates shall be 600mm x 900mm except for
the case when closing pieces are required to complete the shuttering panels.
Dented, broken, cracked, twisted or rusted shuttering plates shall not be allowed to
be used on the work.
The shuttering plates shall be cleaned properly with electrically driven sanders to
remove any cement slurry or cement mortar or rust. Proper shuttering oil or de-
bonding compound such as “Reebole” of FOSROC or equivalent shall be applied on
the surface of the shuttering plates in the requisite quantity before assembly of steel
reinforcement. Nothing extra shall be paid on this account.
3.18.7 Concreting of upper floor shall not be done until concrete of lower floor has set at
least for 14 days but form work and reinforcement can be taken up after the
concrete has set atleast for three days.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 140

3.18.8 Double steel scaffolding having two sets of vertical supports shall be provided for
external wall finish, cladding etc. The supports shall be sound and strong, tied
together with horizontal pieces over which scaffolding platform shall be fixed.
Scaffolding shall have steel staircase for inspection of works at upper levels. Nothing
extra shall be paid on this account.
3.19 REINFORCEMENT:-
3.19.1 The reinforcement shall be done as per CPWD Specifications.
3.19.2 The rate of item of reinforcement of RCC work includes all operations including
Straightening, cutting, bending, welding, binding with annealed steel or welding and
placing in position at all the floors with all leads and lift complete as per CPWD
Specifications.
3.19.3 The contractor shall provide approved type of support for maintaining the bars in
position and ensuring required spacing and correct cover of concrete to
reinforcement as called for in the drawings, spacer blocks of required shape and size.
Chairs and spacer bars shall be used in order to ensure accurate positioning of
reinforcement. Spacer blocks shall be cast well in advance with approved
proprietary pre-packed free flowing mortars (Conbextra as manufactured by M/S
Fosroc Chemicals India Ltd. or approved equivalent) of high early strength and same
colour as surrounding concrete. However, Cover Guard Bars shall also be used to
maintain proper cover of RCC Columns in addition to spacer blocks as mentioned
above. Pre-cast cement mortar/concrete blocks/blocks of polymer shall not be used
as spacer blocks unless specially approved by the Engineer-in-charge. The rate of RCC
items is inclusive of cost of such cover blocks & Cover Guard Bars. Nothing extra shall
be paid on this account.

4.0 MASONRY WORK:-


4.1.1 The Fly ash brick masonry shall be carried out with good quality as per CPWD
Specifications.
4.1.2 The rate shall also include for leaving chases / notches for dowels / cramps for all
kinds of cladding to come over brick work.
4.1.3 Brick work provided around shaft or lift walls or around slab cutouts shall be
measured in the brick for corresponding floor level. Nothing extra shall be paid on
this account.
4.1.4 M.S. Strip/ Bar provided at every third course of half brick masonry shall be in single
piece. If required, welding joint can be used without overlaps. Nothing extra shall be
paid for welding and overlaps.
5.0 EXPANSION JOINT

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 141

5.1 General
5.1.1 Seismic / separation/ expansion joints shall be provided where shown in the
drawings and as per CPWD specifications and as directed by Engineer-in-Charge.
They shall be constructed with in gap between the adjoining parts of the works of
the width specified.
5.1.2 The contractor shall ensure that no debris is allowed to enter and be lodged in
seismic/ separation/ expansion joints.
5.1.3 The expansion joint shall be cleaned and made dry completely. All loose materials
shall also be removed. The joints gap shall be made uniform in width and depth after
cleaning the joints. The backup materials of best quality shall be provided in position
in order to produce thoroughly together in required proportion as prescribed by
manufacture specification, so that a uniform mixture obtained. The mixed solution
shall be applied to two sides of the joint that it covers the sides complete. Disturbed
edges of RCC members near expansion joints shall be finished with rich mortar
without any extra work includes providing required width of expansion board in the
joints and measurement of expansion board only shall be taken.
6.0 GRANITE/ MARBLE OR LIKE WORKS
6.1 The granite/ marble or like stonework shall, in general, be carried out as per the
CPWD Specifications. The specifications for dressing, laying, curing, finishing,
measurements, rate etc. for the granite/ marble or like stone flooring shall be same
as that of works for the Marble flooring, skirting and risers of steps under Flooring
Sub Head of the CPWD Specifications. The wall lining / veneer work with granite/
marble or like stone shall be as per the CPWD Specifications for Marble work Sub
Head.
6.2 The decision of the Engineer-in-Charge as regards the approval of the samples for
the various types of the granite/ marble or like stones shall be final and binding on
the Contractor. No claim of any kind whatsoever shall be entertained from the
Contractor on this account. The Contractor shall then procure and get the mock up
prepared at site of work for approval of quality of workmanship and the granite/
marble or like stone as specified. The mock up shall be prepared in lift lobby, toilet
etc. on one of the floors. The size of the stones shall be as per the architectural
drawings. If the quality of the workmanship and the material is as per the required
standards, the mock up shall be allowed as part of the work and measured for
payment and shall not be dismantled. Otherwise, it shall be dismantled by the
contractor as directed by the Engineer-in-Charge and taken away from the site of the
work at his own cost. Nothing extra shall be payable on this account.
6.3 The granite/ marble or like stone slabs shall be cut to required sizes and shapes, as
per the architectural drawings, to negotiate the curved steps in segmented manner.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 142

The risers shall also be cut to required sizes and shapes and the edges chamfered at
the joints, all as per the architectural drawings. However, the Contractor shall
prepare the detailed shop drawings for the same and commence work only after the
approval by the Engineer-in-Charge. The rate shall also include any consequent
wastage, incidental charges involved in this work. Nothing extra shall be payable on
this account. For the purpose of payment, the actual area of each type of granite/
marble or like stone as laid shall be measured.
6.4 For the steps (risers and treads) in the linear profile, the granite/ marble or like stone
shall be provided in single pieces as per the architectural drawings, unless otherwise
specifically permitted by the Engineer-in-Charge. Wherever grooves are required to
be provided the same is to be done as per architectural drawings and as directed by
the Engineer-in-charge. Wherever required, the joints shall be provided as per the
architectural drawings. Nothing extra shall be payable on these accounts.
6.5 The granite/ marble or like stone slabs used for providing and fixing in the sills, soffits
and jambs of doors, windows, ventilators and similar locations shall be in single piece
unless otherwise directed by the Engineer-in-Charge. Wherever stone slab other
than in single piece is allowed to be fixed, the joints shall be provided as per the
architectural drawings and as per the directions of the Engineer-in-Charge.
Depending on the number of joints, as far as possible, the stone slabs shall be
procured and fixed in slabs of equal lengths as per the architectural drawings and as
directed by Engineer-in-Charge.
6.6 While fixing the granite/ marble or like stone slabs in sills, soffits and jambs of doors,
windows, ventilators etc., rebates shall be made by overlapping the stones at the
required places for fixing shutters for doors, windows and ventilators etc. as shown
in the architectural drawings and as per the directions of the Engineer-in-Charge.
Epoxy based adhesives shall be used for fixing the granite/ marble or like stones to
each other, or wherever required. The authorized overlap as per the architectural
drawings or as directed by the Engineer-in-Charge shall be measured for payment
under the same item. However, any extra mortar thickness required due to the
overlap arrangement shall be deemed to have been included in the rate of this item.
Nothing extra shall be payable on this account. The stone shall have uniform
thickness and shall be provided in sizes as per the architectural drawings. The stone
slab shall have uniformly leveled surface after fixing. All the joints shall be finished
smoothly in a workmanlike manner.
6.7 The granite/ marble or like stone work shall be adequately protected by a layer of
Plaster of Paris, which shall be maintained throughout and removed just before
handing over of the works for which nothing extra shall be payable.
6.8 VACUUM DEWATERED CONCRETE ON ROAD (VDF):

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 143

i. Flooring shall be laid in the Mechanical Workshop and other areas as shown in the
drawing with required thickness as per design requirement to sustain load of
vehicle movement and other impact load.
ii. Concreting shall of RMC M30 grade. Flooring shall have hard top on the concrete
base. Flooring shall be laid in panels as per the direction of Engineer in charge,
expansion joint shall be provided as per requirement. Specification for RMC and
cement will remain same as mentioned technical specifications in contract/RCC
sub head.
iii. De-vacuumization shall be done for removing the voids. The whole concrete
surface shall be leveled, compacted by ramming and troweling. Prepared surface
shall be allowed to set.
iv. Hard top to be prepared as per the specifications with Nito hardener and one part
of dry cement, the heard top shall be provided over concrete base immediately
after it is set, compacted and leveled with a steel trowel. The surface shall be
troweled to bring the hardener coat to a leveled Surface. Excessive troweling shall
be avoided. After the initial set, further compaction shall be done by steel
troweling. Final brushing where required (to achieve desired surface finish) shall
be made before the floor top becomes too hard. Curing shall be done as per CPWD
Specifications.
v. Filling the joints with bitumen material as approved by Engineer in charge.
7.0 WOOD WORK
7.1 The wood work in general shall be carried out as per CPWD Specifications (Volume-I)
2019, with up-to-date correction slips
7.2 The sample of timber to be used shall be deposited by the contractor with Engineer-
in-charge before commencement of work.
7.3 The shape and size of beading shall be as per drawings. The joints of beading shall be
mitred.
7.4 Timber shall be of specified species, good quality and well seasoned. It shall have
uniform colour, reasonably straight grains and shall be free from knots, cracks,
shakes and sapwood. It shall be close grained. The contractor shall deposit the
samples of species of timber to be used with the Engineer-in-Charge for testing
before commencement of the work.
7.5 Wood work shall not be painted, oiled or otherwise treated before it has been
approved by the Engineer-in-charge. All portion of timber including architrave
abutting against masonry, concrete, stone or embedded in ground shall be painted
with approved wood preservative or with boiling coaltar.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 144

7.6 The contractor(s) shall produce cash voucher and certificates from approved Kiln
Seasoning Plants about the timber used on the work having been kiln seasoned and
chemically treated by them, falling which it would not be accepted as kiln seasoned
and/or chemically treated.
7.7 Transparent sheet glass conforming to IS: 2835 shall be used. Thickness being
governed as under unless otherwise specified in the item in wood work/steel work:
Area of Glazing Thickness
(a) For glazing area up to 0.50 sqm 4.0 mm
(b) For glazing area more than 0.50 sqm 6.0 mm
to 0.90 sqm
7.8 Factory made wooden flush door and panelled and wire gauge shutters shall be
manufactured and carried out as per CPWD specifications (Volume-I, 2019 with upto
date correction slips).
7.9 The work shall be executed through specialized agencies to be approved by the
Engineer –in- Charge.
7.10 The contractor shall propose well in advance to Engineer-in-Charge, the names and
address of the factory where from the contractor intends to get the shutters
manufactured along with the credential of the firm. The contractor shall place the
order for manufacturing of shutters only after obtaining approval of the Engineer in
Charge whose decision in this case shall be final & binding. In case the firm is not
found suitable he shall propose another factory. The factory may also be inspected
by a group of officers before granting approval; shutters shall however he accepted
only if these meet the specified test.
7.11 Contractor will arrange stage wise inspection of the shutters at factory by the
Engineer-in-Charge or his authorized representative. The contractor will have no
claim if the shutters brought at site in part or full lot are rejected by the Engineer-in-
Charge due to bad workmanship / quality. Such defective shutters will not be
measured and paid. The contractor shall remove the same from the site of work
within 7 days after the written instruction in this regard are issued by the Engineer- in-
Charge.
7.12 The shutters should be brought at site without primer / painting.
7.13 (a) Inspection of shutters shall be carried out for dimensions & tolerances, size & type
general construction & workmanship, finish & glazing at the following frequency: -

Permissible number of
Lot Size Sample Size
defectiveness
Upto 25 2 0

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 145

26 to 50 5 0
51 to 100 8 0
101 to 150 13 1

151 to 300 20 2
301 to 500 32 3
501 to 1000 50 5
1001 & above 80 7

(b) Criteria for conformity


Any sample shutter failing in any one or more of the requirements inspected for as
above shall be considered as defective. A lot shall be considered as having satisfied
the requirements of the standard if the number of defective shutters in the sample
does not exceed the corresponding permissible number of defectiveness given
above.
(c) Testing – The shutters shall be tested for species seasoning & treatment, defects in
the timber, panel material, construction & workmanship in the approved Laboratory
at the frequency mentioned in CPWD specification.
If shutters are found defective in any one of the criterion double the shutter shall be
tested & if found permissible can be accepted. If shutter is found defective in more
than one criterion, the whole lot shall be rejected.
(d) Finish
i) All components of door shutter shall have smooth finish.
ii) Panels of the door shutters shall be flat and well sanded to a smooth and level
Surface.
iii) All the surfaces of door shutters which are required to be painted or polished or
varnished shall be got approved from the Engineer In Charge before applying
protective coat of primer, polish or varnish.

8.0 Flush Doors


8.1 General
The door shall be of flush type solid core marine grade with single or double shutter
as the case may be.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 146

8.2 Shutters
Flush door shutters shall have a solid core and may be of the decorative or non-
decorative (Paintable type as per IS 2202 (Part I). Nominal thickness of shutters may
be 30mm as mentioned in the BOQ. Thickness and type of shutters shall be as
specified.
Width and height of the shutters shall be as shown in the drawings or as indicated by
the Engineer-in-Charge. All four edges of the shutters shall be square. The shutter
shall be free from twist or warp in its plane. The moisture content in timbers used in
the manufacture of flush door shutters shall be not more than 12 per cent when
tested according to IS 1708.
8.3 Core
The core of the flush door shutters shall be a marine grade block board having
wooden strips held in a frame constructed of stiles and rails. Each stile and rail shall
be a single piece without any joint. The width of the stiles and rails including lipping,
where provided shall not be less than 45mm and not more than 75mm. The width of
each wooden strip shall not exceed 30mm. Stiles, rails and wooden strips forming
the core of a shutter shall be of equal and uniform thickness. Wooden strips shall be
parallel to the stiles.
8.4 End joints of the pieces of wooden strips of small lengths shall be staggered. In a
shutter, stiles and rails shall be of one species of timber. Wooden strips shall also be
of one species only but it may or may not be of the same species as that of the stiles
and rails. Any species of timber may be used for core of flush door. However, any non-
coniferous (Hard wood) timber shall be used for stiles, rails and lipping.
8.5 Face Panel
The face panel shall be formed by gluing, by the hot-press process on both faces of
the core, either plywood or cross-bands and face veneers. The thickness of the cross
bands as such or in the plywood shall be between 1.0mm and 3.0mm. The thickness
of the face veneers as such or in the plywood shall be between 0.5mm and 1.5mm
for commercial veneers and between 0.4mm and 1.0mm for decorative veneers,
provided that the combined thickness of both is not less than 2.2mm. The direction
of the veneers adjacent to the core shall be at right angles to the direction of the
wooden strips. Finished faces shall be sanded to smooth even texture. Commercial
face veneers shall conform to marine grade plywood and decorative face veneers
shall conform to type I decorative plywood in IS 1328.
8.6 Lipping
Lipping, where specified, shall be provided internally on all edges of the shutters.
Lipping shall be done with battens of first class hardwood or as specified of depth

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 147

not less than 25mm. For double leaved shutters, depth of the lipping at meeting of
stiles shall be not less than 35 mm. Joints shall not be permitted in the lipping.
8.7 Rebating
In the case of double leaves shutters the meeting of stiles shall be rebated by 8 mm
to 10 mm. The rebating shall be either splayed or square type as shown in drawing
where lipping is provided. The depth of lipping at the meeting of stiles shall not be
less than 30 mm.
8.8 Opening for Glazing
When required by the purchaser opening for glazing shall be provided and unless
otherwise specified the opening for glazing shall be as per drawings. The bottom of
the opening shall be at a height as shown in the drawings. Opening for glazing shall
be lipped internally with wooden batten of width not less than 25 mm.
8.9 Tolerance
Tolerance on width and height shall be + 3 mm and tolerance on nominal thickness
shall be ± 1.2 mm. The thickness of the door shutter shall be uniform throughout
with a permissible variation of not more than 0.8 mm when measured at any two
points.
Adhesive:- Adhesive used for bonding various components of flush door shutters
namely, core, core frame, lipping, cross-bands, face veneers, plywood etc. and for
bonding plywood shall conform to BWP type, phenol formaldehyde synthetic resin
adhesive conforming to IS 848.
8.10 Tests
As per CPWD Specifications.
8.11 Fixing
As per CPWD Specifications.
8.12 Measurements
As per CPWD Specifications.
9.0 STEEL WORK
9.1 All steel work shall be carried out as per CPWD Specifications. (Volume 1) 2019 with
up-to-date correction slips.
9.2 All welded steel work shall be tested for quality of weld as laid down in IS 822: 1970
before actual execution.
10.0 FLOORING
10.1 All work in general shall be carried out as per CPWD Specifications (Volume 1) 2019
with up-to-date correction slips.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 148

10.2 Whenever flooring is to be done in patterns of tiles and stones, the contractor shall
get samples of each pattern laid and approved by the Engineer-in-charge before final
laying of such flooring. Nothing extra shall be payable on this account.
10.3 Different stones / tiles used in pattern flooring shall be measured separately as
defined in the nomenclature of the item and nothing extra for laying pattern flooring
shall be paid over and above the quoted rate. No additional wastage, if any, shall be
accounted for any extra payment.
10.4 Samples of flooring stones/ Tile (Kota/ Marble/ Granite/ Ceramic tiles/ Vitrified tiles
etc.) shall be deposited well in advance with the Engineer-in-Charge for approval.
The sizes of stones for flooring shall be of a size not less than 600mmx600mm or as
approved by Engineer-in-Charge. Approved samples should be kept at site with the
Engineer-in-Charge and the same shall not be removed except with the written
permission of Engineer-in-Charge. No payment whatsoever shall be made for these
samples.
10.5 The Marble/ Kota/ Granite or any other stone shall be fully supported by the details
establishing the quarry and its location or source.
10.6 Full width Marble/ Kota/ Granite stone over kitchen platform shall be provided
except to adjust for closing pieces. The marble / stone flooring in treads and risers of
staircase is to be laid in single piece.
10.7 The rate of items of flooring is inclusive of Providing Sunken Flooring in Bathrooms,
Kitchen, W.C., etc. and nothing extra on this account is admissible.
10.8 Chasing of required width and thickness shall be made in brick work at skirting
location so as to flush the external surface of skirting with internal plastering. No
extra payment towards making chases in brick work at skirting shall be made and the
same is presumed to be inclusive of rate quoted for the item of providing and fixing
skirting.
10.9 Proper gradient shall be given to flooring for toilets, verandah, kitchen, courtyard
etc. so that the wash water flows towards the direction of floor trap. Any reverse
slope if found, shall be made good by the contractor by ripping open the
floor/grading concrete and nothing shall be paid for such rectifications.
10.10 The flooring and skirting will be executed as per pattern shown in the Architectural
drawings and as per approval of Engineer-in-Charge and nothing extra shall be
payable on this account.
10.11 The rate shall include the cost of all materials and labour involved in all the
operations. Nothing extra shall be paid for use of cut/sawn stone/ tiles in the work.
11.0 VITRIFIED TILES FLOORING

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 149

11.1 The tiles shall be of approved make and shall generally conform to Table 12
ofIS15622. The Vitrified tiles of specified sizes shall be used & sample of tiles shall be
got approved from the Engineer – in – charge. The Mandatory tests for vitrified tiles
shall be got done as per CPWD Specifications (volume – 1) / relevant BIS Code.
11.2 The vitrified shall be as specified in the item. The tiles shall be of specified colours as
shown in the drawings or as approved by Engineer – in – Charge and will be laid in
pattern as per architectural drawings. Nothing extra shall be paid for laying tiles in
specific pattern. The tiles shall be first quality of approved make.
13.0 FINISHING:-

13.1 The work shall be done in accordance with CPWD Specifications -2019 Vol. I to Vol. II
with upto date correction slips and the manufacturer’s specifications where CPWD
specifications are not available.

13.2 The quantity of paint required as per the theoretical consumption including
wastages, if any, shall be procured from the approved manufacturer or his
authorized dealers and deposited with the representative of the Engineer-in-Charge
at site.

13.3 The paint shall be obtained in smaller packing (around 20 litre).

13.4 The paint shall be kept in the joint custody of the Department and the Contractor
and day-to-day account of receipt and issue shall be maintained. However, the safe
custody and watch and ward shall remain to be the responsibility of the Contractor.

Nothing extra shall be payable on this account.

13.5 The name of the manufacturer, manufacturer’s product identification, and


manufacturer’s mixing instructions, warnings and instructions for handling and
application, toxicity and date of manufacturing and shelf life shall be clearly and
legibly mentioned on the labels of each container. These details shall be kept in
record. The material shall be consumed in the order of material brought to site, first
come first consume basis. The Contractor shall obtain and submit to the Department
the manufacturer’s certificate for compliance of the various characteristics of the
materials as per the manufacturer’s specifications and also copy of the
manufacturer’s test report for the record.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 150

13.6 Empty containers of the paints shall not be removed from site till the completion of
the work unless otherwise permitted and shall be removed only with the permission
of the Engineer-in-Charge or his authorized representative at site of work.

13.7All arrangements for measuring, dosing etc. at site shall be made by the Contractor.
Nothing extra shall be payable on this account.

13.8The Contractor shall apply samples of each kind of paint for the approval of shade and
colour as per the directions of the Engineer-in-Charge before procuring the paint in
mass.

13.9All incidental charges of cartage, storage, wastage, safe custody, scaffolding, cost of
samples and mock ups etc. shall be borne by the Contractor and no claim, whatsoever,
shall be entertained on this account.

14.0 SANITARY INSTALLATIONS /WATER SUPPLY / DRAINAGE:-

14.1 The contractor shall be responsible for the protection of the sanitary and water
supply fittings and other fittings and fixtures against pilferage and breakage during
the period of installation and thereafter until the building is handed over.

14.2 The contractor shall furnish all labour, materials and equipment, transportation and
incidental necessary for supply, installation, testing and commissioning of the
complete Plumbing / Sanitary system as described in the Specifications and as shown
on the drawings. This also includes any material, equipment, appliances and
incidental work not specifically mentioned herein or noted on the
Drawings/Documents as being furnished or installed, but which are necessary and
customary to be performed under this contract. The Plumbing / Sanitary System
shall comprise of following:

a. Sanitary Fixtures and Fittings.

b. Internal and External Water Supply.

c. Internal and External Drainage.

d. Balancing, testing & commissioning.

e. Test reports and completion drawings.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 151

14.3 For the work of water supply and sanitary installations, the contractor shall engage
the approved licensed plumbers and submit the name of proposed plumbing
agencies with their credentials for approval of the Engineer-in-Charge. For quality
control & monitoring of workmanship, contractor shall assign at least one engineer
who would be exclusively responsible for ensuring strict quality control, adherence
to specifications and ensuring top class workmanship for the installation.

14.4 The work in general shall be carried out as per CPWD Specifications (Volume II) 2019
with up-to-date correction slips.

14.5 The tendered rates shall include the cost of cutting holes in walls, floors, RCC slabs
etc. wherever required and making good the same for which nothing extra shall be
paid.

14.6 Nothing extra for providing & fixing CP Brass caps /extension pieces wherever
required for CP Brass fittings shall be paid beyond the rates payable for corresponding
CP Brass fittings.

14.7 The contractor shall examine all architectural, structural, plumbing, electrical and
other services drawings and check the as-built works before starting the work, report
to the Engineer In-Charge any discrepancies and obtain clarification. Any changes
found essential to coordinate installation of his work with other services and trades,
shall be made with prior approval of the Engineer In-Charge without additional cost
to the department.

14.8 All the shop drawings shall be prepared on computer through AutoCAD System
based on Architectural Drawings and site measurements within 15 Days of the
stipulated date of start of the contract, contractor shall furnish, for the approval of
Engineer In-Charge, the two sets of detailed shop drawings of complete work and
materials including Typical toilets drawings showing exact location of supports, flanges,
bends, tee connections, reducers, detailed piping drawings showing exact location
and type of supports, valves, fittings etc;

14.9 These shop drawings shall contain all information required to complete the work.
These Drawings shall contain details of construction, size, arrangement, operating

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 152

clearances, performance characteristics and capacity of all items of equipment. Each


shop drawing shall contain tabulation of all measurable items of
equipment/materials/works and progressive cumulative totals from other related
drawings to arrive at a variation-in- quantity statement at the completion of all shop
drawings. Minimum 4 sets of drawings shall be submitted after final approval along
with CD. When he makes any amendments in the above drawings, the contractor shall
supply two fresh sets of drawings with the amendments duly incorporated along with
check prints, for approval. The contractor shall submit further four sets of shop
drawings to the Engineer In-Charge for the exclusive use by the Engineer In-Charge
and all other agencies. No material or equipment may be delivered or installed at the
job site until the contractor has in his possession, the approved shop drawing for the
particular material/equipment / installation.

14.10 Shop drawings shall be submitted for approval four weeks in advance of planned
delivery and installation of any material to allow the Engineer In-Charge ample time
for scrutiny. No claims for extension of time shall be entertained because of any
delay in the work due to his failure to produce shop drawings at the right time, in
accordance with the approved programme.

14.11 Samples of all materials like valves, pipes and fittings etc. shall be submitted to the
Engineer In-Charge prior to procurement for approval and retention by Engineer In-
Charge and shall be kept in their site office for reference and verification till the
completion of the Project. Wherever directed a mockup or sample installation shall
be carried out for approval before proceeding for further installation without any
extra cost.

14.12 Approval of shop drawings shall not be considered as a guarantee of measurements


or of building dimensions. Where drawings are approved, said approval does not
mean that the drawings supersede the contract requirements, nor does it in any way
relieve the contractor of the responsibility or requirement to furnish material and
perform work as required by the contract.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 153

14.13 All materials and equipment shall conform to the relevant Indian Standards and shall
be of the approved make and design. Makes shall be in conformity with list of
approved manufacturers as per the tender document.

14.14 Balancing of all water systems and all tests as called for the CPWD Specifications
shall be carried out by the contractor through a specialist group, in accordance with
the Specifications and Standards. The installation shall be tested and shall be
commissioned only after approval by the Engineer In-Charge. All tests shall be
carried out in the presence of the representatives of the Engineer In-Charge and
nothing extra shall be payable on this account.

14.15 The contractor shall submit completion plans for water supply, internal sanitary
installations and building drainage work within 30 days of the date of completion.
These drawings shall be submitted in the form of two sets of CD’s and four
portfolios (300 x 450 mm) each containing complete set of drawings on approved
scale indicating the work as installed. These drawings shall clearly indicate complete,
piping layouts and sequencing of automatic controls, location of all concealed piping,
valves, controls and other services. In case the contractor fails to submit the
completion plans as aforesaid, security deposit shall not be released and these shall
be got prepared at his risk and cost.

14.16 The CCI/CI/PVC/CPVC/SWR pipe and GI pipe etc. wherever necessary shall be fixed to
RCC columns, beams etc. with rawl plugs and nothing extra shall be paid for this.

14.17 The variation in consumption of material shall be governed as per CPWD


specification and clauses of the contract to the extent applicable.

14.18 The pig lead to be used in joints of 150mm,100mm, 75mm, 50mm dia of sand cast
iron, centrifugally cast (Spun) iron pipes shall be as per relevant CPWD Specifications.

14.19 The contractor shall bear all incidental charges for cartage, storage and safe custody
of materials and shall construct suitable godowns, yards at the site of work for
storing materials so as to be safe against damage by sun, rain, fire or theft etc., at his
own cost and also employ necessary watch and ward establishment for the purpose
at his own cost.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 154

14.20 All fixtures and fittings shall be provided with all such accessories as are required to
complete the item in working condition whether specifically mentioned or not in the
Schedule of Quantities, specifications, elsewhere in this tender document &
drawings. The quoted rates shall be deemed to be all inclusive for a complete item fit
for use including all materials, labour, T&P, specials, equipment, testing &
commissioning etc. Accessories shall include proper fixing arrangement, brackets,
nuts, bolts, screws and required connection pieces. Nothing extra whatsoever shall
be payable on this account.

14.21 Fixing screws shall be half round head chromium plated brass screws with C.P.
washers where necessary or otherwise as provided in the item.

14.22 Porcelain sanitary ware shall be glazed vitreous china of first quality free from warps,
cracks and glazing defects and shall conform to relevant BIS codes. Colour of sanitary
ware, shall be specified or as selected by the Engineer-in-Charge. Nothing extra shall
be payable on this account.

14.23 Horizontal pipes running along ceiling shall be fixed on structural adjustable clamps
of approved design. Horizontal pipes shall be laid to uniform slope and the clamps
adjusted to the proper levels so that the pipes fully rest on them and are properly
secured.

14.24 Contractor shall provide all nuts, bolts, welding material and paint the Clamps with
one coat of red oxide and two or more coats of black enamel paint.

14.25 Slotted angle/channel supports on walls shall be provided wherever shown on


drawings. Angles/channels shall be of sizes shown on drawings or specified in
schedule of quantities. Angles/channels shall be fixed to brick walls with bolts
embedded in cement concrete blocks and to RCC walls with suitable anchor
fasteners. The spacing of support bolts horizontally shall not exceed 1 m.

14.26 Wherever M.S. clamps are required to be anchored directly to brick walls, concrete
slabs, beams or columns, nothing extra shall be payable for clamping arrangement
and making good with cement concrete 1:2:4 mix (1 cement: 2 coarse sand: 4 stone
aggregate 20 mm nominal size) or as directed by the Engineer-in-Charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 155

14.27 The ground colour shall be applied throughout the entire length of pipe. Colour
bands shall be superimposed on the ground colour and shall be applied near valves,
junctions, joints, service appliances, bulkheads, valves, etc. for clear identification of
fluid being carried and to avoid confusion. The relative proportional widths of the
first colour band to the subsequent bands shall be 4:1.The minimum width of the
narrowest colour band shall be 25 mm.

14.28 Rates for all items quoted shall be inclusive of all work and items given in the above
mentioned specifications and Schedule of Quantities and applicable for the work
under floors, in shafts or at ceiling level at all heights and depths. All rates are
inclusive of cutting holes and chases in RCC and masonry work and making good the
same. All rates are inclusive of pre testing and on site testing of the installations,
materials and commissioning.

14.29 Cleaning and Disinfection of Pipelines:-

On completion of hydraulic tests and before a pipe is disinfected, it shall be proved


to be free from obstruction, debris and sediment by scouring or by any other process
which the Engineer-in-charge may prescribe. Upon satisfactory completion of testing
and cleaning, the pipelines shall be disinfected as ordered. Chlorine solution shall be
applied at the charging point as the pipeline is being filled and dosing shall be
continued until the pipeline is full and at least 50 parts of chlorine per million parts
of water have been made available and distributed evenly. If ordinary bleaching
power is used, proportions will 150 gms of power to 1000 litre of water. If a
proprietary brand is used, the proportion shall be as specified by the manufacturer.
The treated water shall be left in pipeline for a period as directed but not exceeding
24 hours chlorine residual tests shall be taken at various points along the pipeline.
The disinfection process shall be repeated until the sample of water taken from the
pipeline is declared fit for human consumption by a recognized laboratory.

14.30 Opening, cut out in slabs, beams as required shall be left out by inserting PVC spouts
of required size before casting of RCC members. Nothing extra shall be paid on this
account.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 156

14.31 The entire responsibility for the quality of work will however rest with the building
contractor only.

15.0 STAINLESS STEEL RAILINGS:

15.1 Providing, fabricating and fixing in position welded built-up section using stainless
pipes and connecting plates, of Grade S.S. 304 and of required diameter & thickness
as per the directions of the Engineer-in-Charge, at the junctions of doors, on walls,
other locations as directed etc. including cutting, welding, grinding, bending to
required profile and shape, hoisting, buffing and polishing, cutting chase/embedding
in RCC / Masonry, fixing using stainless steel screws, nuts, bolts and washers or
stainless steel fasteners as required to make it rigidly fixed & stable and making good
the plaster/flooring etc. all complete, at all floors and all levels as directed by the
Engineer-in-Charge.

15.2 Rate includes cost of all inputs of materials, labour, T&P, etc. involved in the work
and all incidental charges to execute this item. However, for the purpose of
payment only the actual weight of the stainless pipes and stainless steel plates
provided and fixed shall be measured in kg.

16.0 Alluminium work

16.1.1 The work shall be carried out as per specified CPWD specifications in general and as
per direction of Engineer-in-Charge.

17.0 UPVC WINDOWS:

All openable and fixed window system shall have minimum 3 hollow chambers from
front to back. The sliding system frames shall have minimum 3 chambers from front
to back.

All sections of the frame and sash shall be reinforced in accordance with the system
supplier’s recommendations using galvanized mild steel in a single continuous
length.

GENERAL REQUIREMENTS- Profile

The profile is to be extruded from a compound that has been blended to ensure
quality and consistency. The material shall be white or of approved shade, high

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 157

impact modified window grade UPVC and shall be colorfast and conform to BS EN
12608:2003 as below:

Description of Material Required Value


Flexural modulus of Elasticity Shall not be less than 2200 N/mm2

Resistance to impact by falling mass at – 10 not more than 1 test specimen


°C for Class II ( falling mass 1000g ; shall show rupture in wall
falling height 1500mm - as per BS EN
12608:2003)

Mean Breaking Stress for welded corners Shall not be less than 35N/mm2 for
compression bending test or 25N/
mm2 for tensile bending test
The profile shall be a hollow 3-chamber (across depth) profile with an outer wall
thickness not less than 2.4 mm. The profile shall be of first grade/quality uniform and
free from foreign bodies, cracks or marks.

Fabrication of window

a) The window units shall be designed with all corner joints, transom joints and
mullion joints being mitered and fusion welded.

i) All excess material is to be neatly trimmed and neatly feature grooved/raised


nib finish at corners, transom joints and mullion joints.

ii) There will be no mechanical joining of the profile.

iii) No polishing flush of any joints will be permitted.

iv) The window units shall be designed so that the route of drainage is
prevented from passing through the reinforcement chamber.

v) The finished product shall be free from all sharp edges, burrs and the like that
may be hazardous to the user.

vi) The dimensional tolerances on the finished outer frame height and width
shall be + 3mm. Frame assemblies shall be such that they can be installed
square within a maximum difference in the diagonals of 4mm. Minimum
overlap of sash on frame shall be 8mm

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 158

vii) In all window units, adequate drainage should be provided to permit the
escape of water from platforms or horizontal members beneath each sealed
unit. The drainage slots shall not penetrate into the reinforcement chambers.
Rain water Stop to be provided wherever necessary to provide barrier to
excess rain water.

Reinforcement

a. Reinforcement shall be made from galvanized mild steel of not less than
2.2mm thickness as per strength requirement unless otherwise approved
by Engineer in Charge

b. Steel reinforcement shall conform to IS 277:2003 or equivalent -Base


material of steel shall conform to IS 513:2008 – Drawing Grade

c. The reinforcement shall be installed in accordance with the


recommended actions. The reinforcement shall conform to the wind load
requirements of IS 875: Part 3. The reinforcement shall be in one
continuous length and should be installed minimum 5mm and maximum
10mm from the face of the profile to be welded.

d. The reinforcement shall be secured to the profile so that it does not move
or rattle and it maintains the structural integrity of the frame and
satisfactory thermal separation. Reinforcement is to be fixed at a
maximum of 100mm from the ends and then at a maximum of 300mm
centers.

Glazing and Weather seals- GLAZING

Window shall be such that glazing or re-glazing on site is possible without the need
to remove the outer frames from the structure of the building.

All glazing is to be packed in accordance with the system supplier’s


recommendations to prevent any kind of damage during handling.

All beads will be cut at the correct degree recommended by the manufacturer. Glass
retention clips shall be fitted in accordance with the Systems supplier’s
recommendations.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 159

WEATHER SEALS

The weather seals shall be EPDM/ Silicone seals. ASTM- D412 and ASTM- D2240 are
standard specifying test methods for Tensile strength and Hardness of the gasket
whereas the required value shall be specified

Ultimate tensile strength min >7.5 N/mm2

The weather seals are to be fitted in continuous lengths and grooves. The joints in
the vent weather seal are to be positioned at the bottom and in the outer frames at
the top.

Security and Safety

Fasteners shall be designed so that they cannot be released from the outside by the
insertion of a thin blade. No opening light shall be openable or removable from the
outside, when it is fastened in the closed position, except by use of special tools or
breaking part of the window.

QUALITY CONTROL AND TESTING OF MATERIALS


Raw Material

The material from which the profiles are made shall consist substantially from white
polyvinyl chloride as per BS EN 12608:20003. Only those additives and pigments
may be used that are needed for the manufacture of the compound and its
subsequent conversion into sound, durable extrusions of good surface finish and
mechanical strength, as assessed by the requirements of this specification.

Profile Properties- Appearance and Finish

The color of the profile shall be uniform and the color of all profiles in a system shall
be uniform. The profile shall be free from foreign bodies, cracks or sink marks when
viewed by normal corrected vision at 90o to the surface and at a distance of 1 meter
in normal diffused north light.

Dimensions and Weights

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 160

The profiles shall be straight such that the longitudinal axis of the profile, as
measured on the face surfaces, may deviate from the straight line by no more than
1mm per meter.

The cross section of the profile shall conform in shape and dimensions and may
deviate by no more than + 0.5mm; glazing channels and seal grooves may deviate by
not more than + 0.3mm. The weight of the profile per meter shall not be more than
5% below the nominal value.

Window properties: All load bearing members shall be adequately reinforced so as to


resist the wind load requirements of IS 875: Part 3. Calculations shall be submitted
for all window designs.

Air Tightness: The air infiltration for windows shall not exceed 1 litres/ second m2 @
75 Pa for both positive and negative pressures (certified for use in air conditioned
buildings)

Water Tightness: The water penetration for windows shall be minimum 15 minutes
@ 150 Pa as per AS 4420.5

Installation of Frame

i. Before installation the Installation Team is to make sure that the opening has
been prepared and finished. Allow a 5mm gap between the frame and the
opening. The new window shall be set in the prepared opening. Allow for
suitable packing blocks.

ii. The window shall be fixed into the aperture, by drilling and fixing through the
outer frame, to the existing structure using ‘Fischer’ fixings, F8S type bolts.

iii. The fixings shall be no less than 150mm from corners or transoms/mullions and
at no more than 600mm centers.

iv. When the frame is securely fixed in position then fit glass and glazing beads.
Allow for any necessary glazing blocks and glass lock devices.

v. Check windows for correct operation before proceeding with making good.

vi. No fixings are to penetrate the drainage channels.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 161

vii. The windows shall be first treated with Polyurethane Foam (PU Foam) to
enhance insulation against heat and Noise. The gap between masonry and the
frame is to be filled with Neutral Cure Silicon (exposed to sun surface) and/or
Acrylic Sealant (only for the internal surface).

viii. The silicone joints should be covered with Architraves/trims as per direction of
Engineer-in-charge.

Making Good

i. Making good to the external surface of the window frame and finish with a
compatible approved low modular silicone sealant to BS5889. All trims and
quadrants are to be approved by the Engineer- in- Charge prior to fixing.

ii. Allow for making good any disturbed plaster, brickwork and decorations
internally and externally including color wash to brickwork.

iii. Clean off excess material and check fittings and gearing.

iv. Leave installation clean and in good working order.

GENERAL ITEMS

i. This specification is to be read in conjunction with any other relevant documents


and drawings.

ii. Sizes are not to be scaled from any drawings or sketches but should be
measured on site prior to manufacture.

Window Accessories

i. Window should be designed and reinforced such that it can withstand the wind
load requirements by providing suitable strengthening accessories.

ii. The window shall meet the requirements of water tightness.

iii. Trims: - Shall be used to cover the window to masonry joints.

Window Hardware

i. All slider door/windows are to be provided with multi point locking arrangement
with/without key locking facility as per the requirement. The hardware to be of

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 162

G-U or ROTO or equivalent make. The slider locking mechanism handles are of
projected/flush type.

ii. Casement window friction stays are to be of G-U or Securitize or equivalent make
of appropriate size and weight bearing capacity, made of SS304. The stack height
of friction stay is to be 16 + 0.5mm.

iii. The casement windows are to be provided with multi point locking mechanism of
G-U/Avocet / ROTO or equivalent make and handle to suite the same.

iv. Measurement- Area of window shall be measured for payment correct to a


centimeter from outer edge of the window frames.

Rate includes all the materials, glazing, stainless steel wire gauge, window hardware,
labour and fixing etc. all complete.

SPECIAL CONDITIONS:

i. The contractor shall submit the profiles of the proposed vendors and facilitate the
inspection of the factories by the Engineer-In-Charge for assessing the capability of
the vendors for delivering quality product within specified time schedule.

ii. The contractor shall facilitate visits by Engineer-In-Charge or his authorized


representatives to the approved factory while fabrication of each lot of doors &
windows and obtain the permission of the Engineer-In-Charge for its transportation
to the site. This, however, does not absolve the contractor from his responsibility
regarding the quality of the product.

iii. Though finished product is taken from the vendor, any damage to the unit either
during transportation / installation, is liable for rejection.

iv. The contractor shall submit the methodology of installation of door & window units in
the finished openings of RCC or masonry. The spacing of anchoring system shall not
be more than 600mm between successive anchors. The anchoring system shall be on
two sides for doors and on all sides for windows. The contractor shall provide
necessary bed blocks of specified Cement Concrete of required size in AAC block
masonry as per the requirement. The CC will be paid for separately.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 163

List of specialized work & specifications


1. Water proofing work
2. Structural glazing work under façade work

12.0 WATER PROOFING:-


12.1 The work shall be got executed as per manufactures’ specifications and the
application of water proofing treatment shall be done by authorized applicators
of the approved Manufacture of water proofing material.
12.2 Contractor shall also submit the names of manufacturer of water proofing material
along with information about their technical capabilities for the approval of Engineer-
in-charge within 15 days from the date of award of work.
12.3 Total quantity of the water proofing compound required shall be arranged only after
obtaining the prior approval of the make by Engineer-in-charge in writing. Materials
shall be kept under double lock and key and proper account of the water proofing
compound used in the work shall be maintained. It shall be ensured that the
consumption of the compound is as per specified requirements.
12.4 The finished surface after water proofing treatment shall have adequate smooth
slope as per the direction of the Engineer-in-charge.
12.5 Before commencement of treatment on any surface, it shall be ensured that the
outlet drain pipes / spouts have been fixed and the spout openings have been
chased and rounded off properly for easy flow of water.

WATER PROOFING TREATMENT


Work shall be executed as per CPWD Specifications, 2019 Vol I & II with upto date
correction slips.

Water Proofing on terrace, in Sunken portion of toilet and lift well, in water storage
tanks on terrace, Inside the Under Ground sumps, inside the Swimming pool & inside the
Over Head Tanks.

A. On Terrace :

Providing and laying water proofing membrance on terrace roof slabs of the building
using two component, liquid applied, elastomeric Polyurea Polyurethane hybrid
membrane applied by brush, roller or spray, material conforming to Dr. Fixit superseal-
600 or equivalent from other approved makes.
1) Providing and laying, M-15 grade angular fillet at the roof level parapet wall
junction of size 75mm x 75mm and curing the same.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 164

2) Before application the surface including fillet shall be well prepared to


achieve a smooth and even surface by using a scratch coat made of Dr. Fixit
superseal P-110 mixed with Dr. Fixit superseal P-100 aggregate mixed in a
ratio of 1:1 and applying by using a spatula or Trowel.

3) This scratch coat shall be followed by application of primer coat with Dr.
Fixit superseal P-100 WB primer.

4) After the surface is air cured for 6 hours the water proofing membrance with
superseal-600 be applied in two coats to achieve a Dry Film thickness of 1.5
mm (Theoritical consumption of superseal-600 not less than 2.2Kg/sqm).
The tensile strength of membrance shall not be less than 6 N / mm2 and
elongation shall not be less than 600%.

5) The cured membrance shall be covered with a Geotextile of minimum 150


GSM to protect the membrance from filling materials.

6) Laying protective and slope making float finished concrete screed of M-20
grade plain cement concrete as per approved design on roof slab membrane
/ Geotextile to an average of 75 mm thick with slope as per design, mixed
with CONPLAST X4211C of M/s Fosroc or equivalent integral based water
proofing admixture, with minimum thickness of 50mm at the rain water
outlet, in proper slope of 1.5%, including making golas at the junctions of
horizontal and vertical surfaces, finished with 12mm thick cement plastering
in CM 1:3 mixed with CONPLAST X4211C of M/s Fosroc or equivalent
integral based water proofing admixture including finishing the surface by
machine trowelling.

7) Cutting grooves of 3mm width x 30 mm depth within 24 hours to 48 hours


after laying the concrete to form grid of 1.2m x 1.2m and filling the grooves
after 28 days with gungrade polysulphide sealant.

8) High Albeito paint (Dr. Fixit or equivalent) as top surface coating.

B. In Sunken portion of toilet and lift well:

Providing and laying water proofing treatment to the mother slab at sunken floors at all levels.
The operation shall be carried out after scrapping and properly cleaning the surface to remove
loose particles with wire brushes and thoroughly washing with water and allowing it to dry all
complete in all respects as per the direction of Engineer in charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 165

Any surface undulations, cracks and crevices must be duly filled and repaired with cement mortar
1:3 (1 cement : 3 fine sand) mixed with latex polymers such as Dr. Fixit pidicrate URD Fosroc SBR
latex or equivalent

(i) First coat of brush bond Ultra flex of Fosroc or Fast flex ultra of Dr. Fixit or equivalent @ DFT
1mm thick as per manufacturers specifications. This coat to be air cured for 6 to 8 hours.

(ii) Second coat of brush bond ultra flex of Fosroc or Fast flex ultra of Dr. Fixit or equivalent as
per manufacturers specifications. This coat is to be air cured for 3 to 5 days. First coat and
second coat together should have minimum DFT 1.50mm thick. (

(iii) Third coat of bond coat with Dr. Fixit spatter dash bond coat or SBR latex of fosroc @ 3 liter
per bag of cement applied as per manufacture specification to get good bonding with next
layer or equivalent.

(iv) Fourth coat of 12mm thick cement plaster in cement mortar 1:3 (1cement : 3 fine sand) with
floating coat of neat cement punning both admixed with complast X421 IC of Fosroc or Pidi
proof 101 LW of pidilite or equivalent. The rate includes preparation of surface by scarifying
the surface of the existing roof slab by manual or Mechanical means, removal of loose
materials from surface using compressed air and sealing of all joints, corners, junctions of
pipes and R.C.C. with polymer modified cement, all complete as per direction of Engineer in
charge. Over it M10 concrete to be filled over water proofing treatment in sunken floor

C. In water storage tank on terrace, Inside the Under Ground sumps, inside the
Swimming pool & inside the Over Head Tanks etc :

1) Providing and laying water proofing treatment to the mother slab and inner
surfaces of walls of over head water storage tank on terrace and inside the
Under Ground Sump etc. by applying : (i) First coat of Brush bond RFX @ DFT
1mm thick of M/S Fosroc chemicals or equivalent as per manufacturer's
specification. This coat is to be air cured for 6 hours. (ii) Second coat of Brush
bond RFX @ DFT 1mm thick of Fosroc chemicals or equivalent as per
manufacturer's specification. This coat is to be air cured for 6 hours.Both First
& Second coat together should have minimum DFT 1.5 mm thick (iii) Third
coat of bond coat with Cemet slurry mixed with SBR latex @ 3 liters per bag
of cement applied as per manufacturers specification to get good bonding
with next layer. (iv) Fourth coat of 12 mm Thick Cement Plaster in Cement
mortar 1:3 (1 Cement : 3 coarse sand) with floating coat of neat cement
punning both admixed with conplast X421 IC of Fosroc or Pidi Proof 101 LW of
pidilite or equivalent appled before the air curing of third layer. The work
includes preparation of surface treatment, removal of loose materials from
surface using compressed air and sealing of all joints, corners, junctions of
pipes and R.C.C with polymer mixed slurry etc. grouting the voids with
polymer modified cement, all complete as per direction of Engineer-in-
charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 166

2) Providing and applying solvent free Food grade Epoxy coating for internal
surfaces of potable water retaining structures using two pack solvent- free
epoxy resin material such as NITOCOTE – EP 405 of M/s Fosroc Chemicals or
equivalent, applying in two coats, each coat of dry filling thickness not less
than 100 micron. The total thickness of two coats shall not be less than 200
micron dry filling thickness. The material shall be applied at the rate of 0.1 Kg
per Sq-m per coat. The colour of the material for each coat shall be different
such as white or blue and vice versa, as per the direction of Engineer-in-
Charge. The finished surface shall be smooth, glassy and easy to clean. The
cured epoxy film shall comply with the requirement IS 9833-1981. The work
includes preparation of concrete surface to fill up the blow holes and voids
including removal of foreign matter and if required grit blasting shall be done
to prepare the surface.

The air blow holes and imperfections if any shall be filled up with NITOCOTE- EP /
NITOMOTAR- FC as per the direction of Engineer-in-Charge. The prepared surface shall be
applied with a coat of suitable primer as per the manufactures specification before
application of first coat of epoxy coating. The work is inclusive of all the above operations,
such as surface preparation, primer coat and epoxy coating with approved materials of
approved make and nothing extra shall be paid
12.6 GUARANTEE BOND FOR ALL WATER PROOFING ITEMS:-

Ten years Guarantee bond in prescribed proforma given in the tender document
shall be submitted by the contractor which shall also be signed by both the
specialized agency and the contractor to meet their liability / liabilities under the
guarantee bond. However, the sole responsibility about efficiency of water proofing
treatment shall rest with the building contractor.10%(Ten per cent) of the cost of
water-proofing work shall be retained as Security Deposit and the amount so
deducted would be released after 10 (Ten) years from the date of completion of
the entire work under the agreement, if the performance of the treatment is found
satisfactory. If any defect is noticed during the guarantee period, the contractor shall
rectify it within 15 days of receipt of intimation of defects in the work. If the defects
pointed out are not attended to within the specified period, the same will be got
done from another agency at the risk and cost of contractor. However this security
deposit can be released in full, if bank Guarantee or FDR of equivalent amount for
Full 10 (Ten) years is produced and deposited with the department.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 167

12.7 The entire water proofing work on sunken slabs of all toilets, roof slabs shall be
video recorded covering all the operations / activities such as surface preparation
to the final layer of water proofing coating. The video clippings shall be submitted
to Engineer-in-charge along with monthly progress report during each month.
Nothing extra shall be paid towards to cost of video recording and submission of
DVD disk / pen drive consisting the video clippings.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 168

LIST OF FIELD TESTS AND EQUIPMENTS FOR TESTING OF MATERIALS &


CONCRETE AT SITE LABORATORY
LIST OF FIELD TESTS
i) Particle size and shape.
ii) Slump test.
iii) Flakiness & Elongation Index tests.
iv) Compressive strength (concrete or bricks) test.
v) Rebound Hammer test.
vi) Bulking of sand.
vii) Silt content of sand.
viii) Temperature measuring with thermometer with brass protected end 0-200 C.
ix) Proctor density of compacted earth.
x) Mix grading of DBM & BC.
xi) Thickness & density of compacted layer of DBM & BC.
xii) Pressure test of water supply lines.
xiii) Leakage test of water supply lines & sanitary stacks.
xiv) Any other tests as per CPWD specifications.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 169

(TABLE-1)
Equipments for Testing of Materials & Concrete at Site Laboratory
All necessary equipment for conducting all necessary tests shall be provided at the site in
the well furnished site laboratory of minimum 25 sqm area by the contractor at his own
cost The following minimum laboratory equipments shall be set up at site office laboratory:-
Numbers
Sl. No. Equipment
(Minimum)
1 Slump cone 1

2 Graduated glass measuring cylinder As per requirement


3 Sets of sieves for coarse aggregate 1
4 Sets of sieves for fine aggregate 1
5 Electronic balance 100kg 1
6 Physical balance weight upto 5kg 1
7 Measuring jars 100ml, 200ml, 500ml 3 Nos. each

8 Gauging trowels 100mm & 200 mm with wooden handle 1 Nos. each
9 Spatula 100mm & 200mm with long blade wooden handle 1 Nos. each
10 Vernier calipers 12” & 6” size 1 No. each

11 Digital PH meter least count 0.01 mm 1

12 Digital Micrometer least count 0.01mm 1


13 Digital paint thickness meter for steel 500 micron range 1 No.
14 GI tray 600x450x50mm, 450x300x40mm 24 Nos. each

15 Screw gauge 0.1mm -10mm, least count 0.05 1 No


16 Thickness gauge for measuring flakiness index 1 No
17 Elongation gauge 1 No

18 Measuring cylinder 3,5,10 & 15 liter cylinder 1 No

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 170

19 Motorized sieve shaker 1 No.

20 Extra Bottom plates for 15 cm cube mould 6 nos.


21 Mortar Cube vibrator 1 No.
22 Iron Weight of 5 kg, 2 kg, 1 kg, 500 gm, 200 gm, 100 gm 1 No.
23 Brass Weight of 50 gm, 20 gm, 10 gm, 5 gm, 2 gm, 1 gm 1 No.
24 Hammer 1lb& 2lb 2 Nos. each
25 Any other equipment for site tests as outlined in BIS and as As per requirement
directed by the Engineer-in-charge.

Note:
1. A site laboratory with temporary structure of minimum 25 sqm area may be fabricated
at site by the contractor for accommodating above instruments and for conducting of
various tests for which no extra payment shall be made to the contractor.
2. One sample keeping room of minimum area of 20 sqm should also be fabricated at site
for keeping various materials brought by the contractor at site and approved by the
Engineer-in-charge. No extra payment on account of this shall be made to the
contractor.
3. All the above structures should be decent looking and shall be fabricated as per
direction of Engineer-in-charge.
4. All the above structure shall be demolished after completion of work and the dismantled
material shall be the property of the contractor.
5. Contractor should comply with observations raised by the NITW client/CPWD in
connection with quality aspects of work.
6. Contractor has to establish at least two floors centering and shuttering material at site.
7. For small quantities of RCC works Batch Mix Plant has to be establish at site.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 171

(TABLE-2)
PLANT AND EQUIPMENT REQUIRED TO BE OWNED / TAKEN ON LEASE
BY THE CONTRACTOR at his own cost

Numbers
Sl. No. Equipment
(Minimum)
1. Hopper Mixers for mixing of mortar 1 No
Water pump, Water sump 1 No
Welding machine. 1 No
Paver Finisher / Machine Trowels / Screed Vibrators. 1 No
DG Set 100 KVA 1 No
Air Compressor 1 No
Any other machinery required for completion of the As per requirement
work as per decision of Engineer-in-charge.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 172

GUARANTEE BOND TO BE EXECUTED BY THE CONTRACTOR


FOR REMOVAL OF DEFECTS AFTER COMPLETION IN RESPECT OF
WATER-PROOFING WORKS (All Water - Proofing Items).

The agreement made this.................... Day of................. (Two Thousand _ _


only).............. Between ....................................S/o............................................... (Herein after called
the GUARANTOR of the one part) and the PRESIDENT OF INDIA (hereinafter called the Government
of the other part)

WHEREAS THIS agreement is supplementary to a contract (Hereinafter called the Contract)


dated ....................... and made between the GUARANTOR OF THE ONE PART AND the Government of
the other part whereby the contractor inter alia undertook to render the building and structures in
the said contract recited completely water and leak-proof.

AND WHEREAS THE GUARANTOR agreed to give a guarantee to the effect that the said
structures will remain water/leak proof for (10) Ten years from the date of completion of work.
NOW THE GUARANTOR hereby guarantees that work executed by him will render the
structures completely leak proof and the minimum life of such water proofing treatment shall be
(10) Ten years to be reckoned from the date after the expiry of maintenance period prescribed in
the contract.

The decision of the Engineer-in-charge with regard to nature and cause of defect shall be
final and binding on Guarantor.
During this period of guarantee, the guarantor shall make good all defects and in case of any
defect being found render the building water proof to the satisfaction of the Engineer-In-Charge
calling upon him to rectify the defects failing which the work shall be got done by the Department by
some other contractor at the Guarantor’s cost and risk. The decision of the Engineer-in-charge as to
the cost payable by the Guarantor shall be final and binding.
That if the guarantor fails to execute the water proofing or commits breach there under,
then the guarantor will indemnify the principal and his successor against all loss, damage, cost
expense or otherwise which may be incurred by him by reason of any default on the part of the
GUARANTOR in performance and observance of this supplementary agreement. As to the amount of
loss and/or damage and / or cost incurred by the Government, the decision of the Engineer-in-
charge will be final and binding on both the parties.
IN WITNESS WHEREOF these presents have been executed by the obligator.......................
And ........................................ by ..................................for and on behalf of the PRESIDENT OF INDIA
on the day, month and year first above written.

SIGNED, sealed and delivered by OBLIGATOR in the presence of:-

1. ................................................ 2. ...........................................

SIGNED FOR AND BEHALF OF THE PRESIDENT OF INDIA BY................................... in the


presence of :-

1. ............................................... 2. ..........................................

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 173

(On Non-judicial stamp paper of minimum Rs. 100/-)


Modified form for Bank Guarantee for Earnest Money Deposit / Performance
Guarantee/Security Deposit/Mobilization Advance
(This form supersedes the form given in GCC – 2020)

1. Whereas the Executive Engineer ……………………………………… (Name of Division)


…………………………………………, CPWD on behalf of the President of India (hereinafter called “The
Government”) has invited bids under ………………………… (NIT Number) ............................dated
…………………….. For …………………………….. (Name of work
………………………………………………………………………………………………………………………………………………………
………………………………………………… The Government has further agreed to accept irrevocable Bank
Guarantee for Rs. (Rupees ………………………………………………………………… Only) valid upto (date) *
…………………………. As Earnest Money Deposit from …………………………………………….. (Name and
Address of Contractor) ........................................................ (Hereinafter called “the contractor”)
for compliance of his obligations in accordance with the terms and conditions of the said NIT.

** or **

Whereas the Executive Engineer …………………….. (name of Division) .................... , CPWD on behalf
of the President of India (hereinafter called “The Government”) as entered into an agreement
bearing number …………………………. With .......................... (Name and address of the contractor)
……………………….. (Hereinafter called “the Contractor”) for execution of work
………………………………. (Name of work)
..........................................................…………………………………………. The Government has further
agreed to accept an irrevocable Bank Guarantee for Rs. (Rupees ………………………………………………..
only) valid up to ………………. (Date) ..................... As Performance Guarantee / Security Deposit /
Mobilization Advance from the said Contractor for compliance of his obligations in accordance
with the terms and conditions of the agreement.

2. We, (indicate the name of the bank).....................(Hereinafter referred to as “the Bank”), hereby
undertake to pay to the Government an amount not exceeding Rs. (Rupees …………………………….
Only) on demand by the Government within 10 days of the demand.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 174

3. We, (indicate the name of the Bank) ........................... , do here by undertake to pay the amount
due and payable under this guarantee without any demur, merely on a demand from the
Government stating that the amount claimed is required to meet the recoveries due or likely to
be due from the said amount due from the said Contractor. Any such demand made on the Bank
shall be conclusive as regards the amount due and payable by the Bank under this Guarantee.
However, our liability under this guarantee shall be restricted to an amount not exceeding Rs.
(Rupees ................................................ only).

4. We, (indicate the name of the Bank) ........................... , further undertake to pay the Government
any money so demanded notwithstanding any dispute or dispute raised by the contractor in any
suit or proceeding pending before any Court or Tribunal, our liability under this Bank Guarantee
being absolute and unequivocal. The payment so made by us under this Bank Guarantee shall be
valid discharge of our liability for payment there under and the Contractor shall have no claim
against us for making such payment.

5. We, (indicate the name of the Bank) ..................... , further agree that the Government shall have
the fullest liberty without our consent and without affecting any manner our obligation here
under to vary any of the terms and conditions of the said agreement or to extend time of
performance by the said Contractor from time to time or to postpone for any time or from time
to time any of the powers exercisable by the Government against the said contractor and to
forbear or enforce any of the terms and conditions relating to the said agreement and we shall
not be relieved from our liability by reason of any such variation or extension being granted to
the said Contractor or for any forbearance, act of omission on the part of the Government or any
indulgence by the Government to the said Contractor or by any such matter or thing whatsoever
which under the law relating to sureties would, but for this provision, have effect of so relieving
us.

6. We, (indicate the name of the Bank)...................... , further agree that the Government at its
option shall be entitled to enforce this Guarantee against the Bank as a principal debater at the
first instance without proceeding against the Contractor and notwithstanding any security or
other guarantee the Government may have in relation to the Contractor’s liabilities.

7. This guarantee will not be discharged due to the change in the constitution of the Bank or the
Contractor.

8. We, (indicate the name of the Bank) ......................... , undertake not to revoke this guarantee
except with the consent of the Government in writing.

9. This Bank Guarantee shall be valid up to ................................... Unless extended on demand by


the Government. Notwithstanding anything mentioned above, our liability against this guarantee
is restricted to Rs. (Rupees....................................................... only) and unless a claim in writing is

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 175

lodged with us within the date of expiry or extended date of expiry of this guarantee, all our
liabilities under this guarantee shall stand discharged.

Date ……………………….

Witness:

1. Signature ……………………………….. Authorized signatory


Name and address Name
Designation
Staff Code no.

2. Signature ……………………………….. Bank Seal


Name and Address

Note:
1. *Date to be worked out on the basis of validity period of 90 days where only financial bids are
invited and 180 days for two / three bid system from the date of submission of tender.
2. ** in paragraph 1, strike out the portion not applicable. Bank Guarantee will be made either for
earnest money or for performance guarantee / security deposit / mobilization advance, as the case
may be.
3. The Bank Guarantee shall be drawn on non-judicial stamp paper of minimum Rs.100.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 176

Seigniorage Rates

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 177

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 178

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 179

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 180

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 181

--Blank--

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 182

Standard Operating Procedures (SOPs) and


Guidelines for Construction Sites for COVID-19
Outbreak

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 183

Standard Operating Procedures (SOPs) and Guidelines for Construction Sites for COVID-19
Outbreak
The agency shall follow the below mentioned standard operating procedures and
guidelines scrupulously at the construction site to contain the outbreak of COVID-19,
failure to adhere to the SoPs issued by CPWD and other orders & Guidelines issued by
Various Governments(Govt of India and/or Govt of AP and/or Dist. Administration or
Local Govt.) from Time to Time will result in levy of nonrefundable penalty of Rs.5000/-
per day on the agency by Engineer-in-charge which shall be final and binding on the
contractor. The quoted rates shall inclusive of all such required measures and materials
like Soaps, Detergents, Sanitizers, Disinfectants, Masks, Gloves and other personal
protection equipment’s to contain COVID-19 and nothing extra shall be paid. All such
penalties shall be recovered from the respective Running account bills of the contractor.
ln response to COVID-19 outbreak, the following Standard Operating Procedures (SOPs) and
guidelines to ensure safety of construction site workers are issued for field units. Ln addition
to trained Supervisor (s), a Site Safety Representative (SSR) will be deployed at every site, to
ensure the safety guideline is followed. Necessary trainings will be given in advance to
Supervisors and SSRs, so that they can train the workers further.
a. General guidelines – Applicable to All
1. The workers coming from outside will be required to self-declare their health
profile as per Annexure 1 and shall be quarantined for a period of at least 15 days.
Mandatory
2. Thermal Scanning of everyone entering and exiting a construction site will be done
for fever with thermal scanners. lf anyone leaves and re-enters the site during the
shift, re-screening of the individual will be done prior to re-entry into the work site.
3. PPE and Other material requirement shall be documented as per Annexure 2.
4. Provision for hand wash & sanitizer (touch free recommended) will be made at all
entry and exit points and common areas (including at distant locations like higher
floors). Everyone will be required to wash & sanitize his/her hands before entering
the site and using PPEs. Same procedure to be followed after removing PPEs and
exiting the premise. Sufficient quantities of all the items should be available at the
site.
5. All Protocol including Emergency Response will be laid out. Periodic tailgate
sessions will be arranged to review site protocols in view of highly dynamic scenario
ensuring social distancing norms. During these sessions, everyone including
workers will be informed about the safety guidelines and important updates.
Necessary arrangements for announcements shall be made at every site.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 184

6. Mandatory use of PPEs (face mask, hand gloves and other as applicable) by
everyone entering the premise. Re-usable PPEs should be thoroughly cleaned and
should not be shared with others.

7. Entire construction site including site office, labour camp, canteens, pathways,
toilets, and entry / exit gates will be disinfected on daily basis. Housekeeping team
should be provided with necessary PPEs.
8. There will be total Ban on non-essential visitors at sites (including from Head office
staff, consultants etc.).
9. There will be strict ban on Gutka, Tambaku, Paan etc. on site and spitting shall be
strictly prohibited.
10. Food should be consumed at designated areas only ensuring social distancing.
11. Common sitting arrangements should be removed.
12. Post lunch, waste should be disposed by individual in designated bins and area
should remain clean.
13. Areas with a probability of bigger gathering, for eg. Cleaning area, toilets etc.
should be identified and all arrangements should be made to ensure social
distancing.
14. A doctor will be present periodically (at least once a week) at site on allotted time
for any medical assistance.
15. Appropriate signage at construction site spelling out safety practices in the
language which is understood by all.
16. Hospital/clin ics in the nearby area, which are authorized to treat COVID-'19
patients, should be identified and list should be available at Site all the time.
17. For any confusion, clarification and update, everyone should approach designated
authority or rely on authentic source.
18. Rumors shall be discouraged and offenders be warned.
19. An isolation room shall be created at site.
b. Guidelines for workers:
1. On day 0, before resuming the work on site post lockdown period, mandatory
medical check-up will be arranged for all workers. The workers coming from
outside will be quarantined for a period of at least 15 days. Only medically fit
workers will be deployed at site and medical assistance will be arranged for unfit
workers. Medical checkup camp should be arranged every month.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 185

2. The labours staying at site will not be allowed to go outside. All the essential items
will be made available to labours at site only. lf necessary, the workers can go out
wearing PPEs, after informing supervisor. Similarly, no outside labour will be
allowed at site without following proper procedure and instructions.
3. Start time on site will be staggered to avoid congestion at the entry gates. Number
of workers working at a particular time / place will be reduced by making
arrangements for different shifts / areas. Accordingly, additional staff such as
security guards, supervisors etc. will be deployed.
4. As in most cases, workers reside at the Sites; hence there is no need for any travel.
For Workers staying outside, (which are always nearby) special transportation
facility will be arranged without any dependency on the public transport system.
5. During attendance, training and other sessions, social distancing guidelines will be
followed along with provision of no {ouch attendance.
6. Workers should not shake hands when greeting others and while working on the
site.
7. Workers shall avoid contact with sick people and avoid going to site if they are
feeling sick, have fever, cough or shortness of breath. ln such case, supervisor
should be informed immediately.
8. Workers with such symptoms should not come to site and should be placed in
isolation and medical assistance will be provided on immediate basis.
9. Mandatorily wear face masks while working on site. While not wearing masks,
worker shall cover his mouth and nose with tissues.
10. Cough/sneeze should be done in the crook of one's arm and your elbow.
11. Avoid large gatherings or meetings of 10 people or more. Stay at least 6 feel away
from others on job sites and in gatherings, meetings, and training sessions.
12. Not more than 214 persons (depending on size) will be allowed to travel in lifts or
hoists. Use of staircase for climbing should be encouraged.
13. Workers should clean hands frequently by washing them with soap and water for at
least 20 seconds. When hand washing isn't possible, alcohol based hand sanitizer
with greater than 60% ethanol or 70% isopropanol should be used.
14. Workers should not share their belongings like food, water bottles, utensils, mobile
phones etc. with others.
15. The utensils should be washed properly post use at designated place.
16. Post work, workers should change their clothes before leaving the site and clothing
should not be shook out.
17. Avoid touching eyes, nose, or mouth with unwashed hands.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 186

c. Guidelines for Material, Tools. Machinery, Vehicles etc.


1. Wipe down interiors and door handle of machines or construction vehicles, the
handles of equipment and tools that are shared, with disinfectant prior to using.
2. Non-ouch waste bin with disposable garbage bag should be installed for waste
collection at all common access areas.
3. Proper disposal of garbage should be ensured.
4. At all point of time, easy access to parking should be ensured since public transit is
limited.
5. All construction material arriving at site should be left idle for 3 days before use to
ensure safe usage.
6. All vehicles and machinery entering the premise should be disinfected by spray
mandatorily.
d. Emergency protocol in case of detection of symptoms of COVID 19 to be observed by
Project Manager of Contractor
1. Immediate shift worker to isolation room. Inform the Engineer-in charge CPWD or his
Nodal officer.
2. Call for a doctor.
3. Keep worker under observation for a few days in isolation room. ln case of doubt act
per advice of local doctor.
4. Covid testing shall be arranges as per instruction of Doctor and if so advised by Doctor
move worker to Hospital.
5. Prevent rumors and take strict action against those who spread it.
e. Responsibility of various stakeholder
Responsibility of various stakeholders shall be as below
Sl No Designation Responsibility
2 CPWD Nodal officer as To coordinate efforts on behalf of Engineer in Charge
Designated by and ensure compliance of these SOPs. He shall send a
Engineer in Charge daily confirmation of compliance of SOPs.

1 Project Overall responsibility of ensuring compliance of


procedure and precautions in SOP.
Manager of
Contractor To submit daily compliance report to CPWD Nodal
officer
To designate a senior person as COVID Marshal and

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 187

form a team under him


2 COVID To exclusively look after the implementation of all the
precautions and procedure at work site and labour
Marshal
camps
(Nodal
To intimate daily requirement of PPEs, sanitizers,
Officer) disinfectants etc in their respective sections
Regular attendance of workers to ensure no one leaves
the site
Permission from local authorities
Ensuring Timely payment to workers/ staff

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 188

Annexure 1

COVID-l9 (Coronavirus) Exposure Questionnaire for New workmen

Name: Native (State, District/City, Village)


Age :
Gender :

Please answer the following questions with as much detail as possible:


2. Location/Travel Declaration
a. Please provide your locations/travel patterns over the past 14 days in Table below:

Country City/Village Date Arrived/Since Date departed


when you have been
in the location

3. Any cases of COVID-'19 in your in the locations where you have been for last 14 days?

YES NO
4. Are you, or have you been in close contact with anyone who has been quarantined or
who has been diagnosed with novel coronavirus (SARS-CoV-2/COVID-19)? lf yes, please
provide details.

YES NO

5. Have you ever been quarantined due to a possible exposure to novel coronavirus (SARS-
CoV-2/COVID-19)? lf yes, please provide dates and locations.

YES NO

6. Have you experienced any of the following symptoms within the last 14 days?
. Any fever
. Cough
. Shortness of breath
. Malaise (flu-like tiredness)
. Rhinorrhea (mucus discharge from the nose)
. Sore throat
. Gastro-intestinal symptoms such as nausea, vomiting and/or diarrhea

lf yes, to any of these, please indicate which and provide full information.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 189

7. Are you currently in good health?

YES NO

Declaration

I confirm that the answers I have given are, to the best of my knowledge, true, and that I
have not withheld any material information that may influence the assessment or
acceptance of this application.

I agree that this form will constitute part of my application for insurance(s) and that failure
to disclose any material fact known to me may invalidate my insurance(s).

Signature

Date

Time

Witness

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 190

Annexure 2
PPE and Other material requirement
Sl List of items
At Stores At workmen
No (Personal At office
camp
Sanitization)
1 Hand Sanitizer 1 bottle (500m1) 1 bottle 2 bottle (500m1) at all
(min 60% at all entrances (500m1) at all entrances and to be refilled
alcohol) and to be refilled entrances and on regular basis
on regular basis to be refilled
on regular
basis
2 Alcohol based To be made To be made 2 bottles (500m1) at the
Soap Solution available on available on front side of each camp
demand demand visible & easy to access
along with water availability
for washing.
Need to be refilled on
regular basis

Soap (100 gm) 1 No in each 1 No. to be distributed to


toilets and each Contractor workman
wash basins once in a week.

Sl List of Personal Protective


Scope
No Equipment (PPEs)
1 Nose Mask & Paper Tissues For all workmen (daily one for at least one
month

2 Face mask/Face shield/Goggles For workmen involved in disinfection/


sanitization activity (new one to be issued for
each day activity and COVID Marshal
3 Gloves (Nitrile) For workmen involved in disinfection/
sanitization activity (new one to be issued for
each day activity)
4 Coverall/Gowns (Nitrile) For COVID Marshals and workmen involved in
disinfection/ sanitization activity (new one to
be issued for each day activity)

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 191

LIST OF PREFERRED BRANDS /


MANUFACTURERS / MAKES

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 192

LIST SHOWING PREFERRED BRANDS/ MANUFACTURERS/MAKES

NOTE: -
1) A List of Preferred Brand Names of Various Materials / Products are shown below

for usage in execution of Work. However, Approved equivalent material of any

other Specialized Companies / Firms may also be used , in case it is established that

the Brands Specified below are not available in the market and subject to Approval

of the alternate Brand by the Engineer In charge.

2) It must be ensured, in general, that all materials to be used in the works shall bear

BIS Certification mark. In cases where for a particular material/product, BIS

Certification Mark is not available, then the material proposed to be procured can

be used subject to the condition that it should conform to CPWD Specifications and

relevant BIS codes. In such cases written approval of the Engineer-in -Charge shall

be obtained before use of such material in their works.

3) The list given below does not absolve the Executing Agency from their

responsibility for using these products. It is only after, they are satisfied about the

quality and performance, and the products shall be used. To achieve this, proper

check on the quality of the product, actually to be used, should be exercised.

4) The above list is provisional and subject to product conformity of standards of

relevant codes.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 193

List of Approved materials for (Civil)


Sl. Material
Brand Makes
No Description
A B Dinesh A B Dinesh
Areocon HIL
Bilt Bilt
Ecorex Ecorex
Fastbuilt Fastbuilt
Kncrete Koncrete
1 AAC Blocks NCL NCL VEKA Ltd.

Nucon Green Way building materials India Pvt. Ltd.

Renacon Renaatus Procon Pvt. Ltd.


Siporex SIPOREX
Ultra Tech Cement Ltd
Xtralite

Anutone Anutone Acoustics Ltd.


Himalyan Accoustics Himalyan Accoustics
Kanuf Knauf Gypsum India Pvt. Ltd.
2 Acoustic Insulation
Lloyd Insulation Lloyd Insulation (India) Ltd.
Saint Gobain Gyproc Saint Gobain Gyproc India
Twingerinsul U.P. Twiga fiber glass ltd.
Ardex endure Ardex endure
Actativ
Bitumat Co Ltd Bitumat Co Ltd
polypropylene
Ferrous crete Ferrous Crete ( India ) Pvt Ltd
3 (APP) Modified
Hydrotech ltd Hydrotech ltd
water proof
Pidilite Pidilite industries
membrane
STP Shalimar tar products
Asian Tractor Premium
Asian paint
emulsion
4 Acrylic emulsion Berger (BISM) Berger Paints
Dulux (Super Cover) ICI Dulux
Nerolac (Beauty Gold) Nerolac

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 194

Sl. Material
Brand Makes
No Description

Apex (ACE) Asian Paints


Berger Berger
Acrylic smooth
5 Dulux ICI duLux
exterior paint
Nerolac Nerolac
Nippon Nippon
Apex Duracast Asian Paints
Asian paints Asian Paints
Acrylic textured
6 Heritage Heritage Rajkamal Group
plaster
Nerolac Nerolac
Spectrum paints Spectrum paints Ltd.
Akzonobel Akzonobel
Asian paints Asian paints
Acrylic exterior
7 Berger Berger paints India ltd
Texture
Ebco Ebco
Nerolac Nerolac paints Ltd.
Asian Paints Asian Paints
CICO CICO Industries
Dunlop India Tyre & Rubber Co (India) Ltd.
8 Adhesive Finical Pidilite Industries
Proofex of Adhesive FOSROC India
Sika Sika India Pvt. Ltd
Vamorganic Vamorqanic Ltd.
Ardex Endura/Gold star Ardex Endura
Adhesive for AAC Ferrous Crete Ferrous Crete ( India ) Pvt Ltd
9
Block/Tiles Tile Adhesive Plus Berger Paints
Ultra tech Ultra tech cement ltd
Cool grills Cool grills, Pune
10 Air transfer grills
Systemair India Systemair India Pvt Ltd.
Kartar Kartar valves private Ltd.
11 Air release valve Kirloskar Kirloskar brothers Ltd.,
RBM AFS Ltd

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 195

Sl. Material
Brand Makes
No Description

Bhoruka Bhoruka Aluminium Ltd.,


Hindalco Hindalco Industries Ltd...
Aluminium Hydro Hydro Extrusion
12 doors/windows INDAL Indian Aluminium Ltd.,
sections Jindal Jindal Aluminium Ltd ,
Omalco Extrusion Omalco Extrusion Pvt Ltd.
Padmavati Exrusion Padmavath Extrusion Private Ltd.
Bhoruka Bhoruka Aluminium Ltd.,
Define Define Overseas Pvt. Ltd.

Aluminium system/ Everite Everite Agencies


Anodised Hardima Hardima sales corporation
13
Aluninium fittings Jyothi Jyothi industries
for doors/windows Kawneer Kawnear India
Schueco Schueco India Pvt. Ltd.,
Sigma Sigma Corporation
Alpolic Alpolic
Alstone Alstone
Alstrong Alstrong
Alex panel M/s Alex Panels
Aluminium Alucobond 3A composites India Pvt Ltd.
14
composite panels Aludecor M/S Aludecor lamination Pvt ltd.
Eurobond M/S Euro panel products Pvt ltd.
Eurobond Eurobond pvt Ltd.
Hynadecor Hynadecor
Reynobond Reynobond
MFE (MIVAN) (MIVAN)
Aluminium
15 MFS MFS
framework
S-form S-form
Anchor/ SS Stone Anchor Anchor Ltd.
16 Cladding Clamps/ BOSCH BOSCH Ltd.
Dash fasteners Canon Canon

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 196

Sl. Material
Brand Makes
No Description

Fischer Fischer India


Helfen Helfen Gmbh
Hilti Hilti India Pvt. Ltd.
Nutech Nutech Concrete Products Pvt. Ltd.
Trixel Axel India Pvt. Ltd.
Wurth Wuerth India Pvt. Ltd.
Bergar Berger paints India Ltd
Anti corrosive bit
17 Bituminous black Asian Paints
mastic paint
Shalimar Shalimar paints India Ltd.
Alu Alpha Alu Alpha India
Dorma Dorma India Pvt. Ltd.
Butt Hinges
Dorset Dorset Industries Pvt. Ltd.
18 openable window
Earit Bihari Earit Bihari India Pvt. Ltd.
shutters
Hafela Hafele India Pvt. Ltd.
Helix Helix India
AMITEX AMITEX Enterprises, Delhi.
Eco green Flooring Jupiter Traders Bangalore.

Bamboo Wood Epitome Bamboo wood


Mutha Industries Pvt.,Ltd., Mumbai.
19 Flooring and wall Products
paneling. Floor India Flooring India Company, Panipat, Haryana.
FLOSTO Tanks Devi Polymer Pvt.,Ltd., Chennai.
VIVANTA VIVANTA Enterprises, Mumbai.
Ambuja Cement Ambuja Cements Ltd.
ACC ACC Cements Ltd
Bharathi Bharathi Cement Corporation Ltd.
Birla Birla Corporation Ltd
Cement
20 Century Cement Birla Gold Cement
OPC / PPC
Chettinad Chettinad Cements Corporation Ltd
Coromandal India Cements Ltd.
Dalmia Dalmia Cement Bharat Ltd.
Jaypee Cement Jaypee Cement Ltd

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 197

Sl. Material
Brand Makes
No Description

J.K. Cement J.K. Cement Pvt. Ltd.


Konark Cement Konark Cement
Maha Cement Myhome Industries Pvt. Ltd.
Penna Cement Penna Cement Industries Ltd.
Ramco Ramco
Shree Cement Shree Cement
Ultra Tech Ultra Tech Cement Ltd
Zuari Zuari Cement Limited
Dazzle Dazzle Designer tiles Pvt Ltd
Eurocon Eurocon tiles india
Hindustan tiles Hindustan tiles, Ranchi Pune
Cement Concrete
21 NTC NTC Parking tiles
Parking Tiles
NITCO NITCO Ltd
Poddar Poddar Udyog
Ultra Ultra tile private Ltd
Altek NCL Alltek & seccold Ltd.
Ardex Endura Ardex Endura India Pvt. Ltd.
Asian paints Asian paints Ltd
Cement based wall
22 Berger Berger
putty
Birla Wall Care Birla Cements Ltd.,
Ferrous Crete Ferrous Crete (India) Pvt. Ltd
J.K wall putty J.K. Cement Ltd
Bison Bison Group
23 Cement Board
Everest Everest Techno polis
Asian paints Asian Paints
24 Cement Primer Berger Berger paints India Ltd.
JK Primaxx JK Cement Ltd
Kapilansh Kapilansh Dhattu Udyog (P) Ltd.
Centrifugal Hubless
NECO Jayaswal NECO Ltd.
25 Cast Iron Pipe &
Raj (RPMF) Raj Pattern Makers and Founders Pvt.,Ltd.
Fittings
SKF Singhaliorn Foundary Pvt.,Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 198

Sl. Material
Brand Makes
No Description

Electrosteel Electrosteel castings Ltd.


Centrifugally (Spun) Jindal Jindal saw Ltd.
26
cast Iran Kesoram Kesoram Industries ltd.
Lanco / Sripipes Electrosteel castings Ltd.
Bengal Iron Corporation Bengal Iron Corporation
HEPCO HEPCO
Centrifugally Caste
Kapilash Kapilash Dhatu Udyog (P) Ltd.
27 (Spun) Iron Soil
Neco Jayaswal Neco Ltd
Pipe
RPMF Raj Pattern Makers and Founders Pvt. Ltd

SKF SKF industries


BASF BASF India Ltd.
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Fosroc India
Latex shield 2K/Tank shield
Chemical water Berger Paints Ltd.
28 PW
proofing system
MC- Bauchemie MC- Bauchemie India Ltd.
Perma construction Aid Perma construction Aid Pvt Ltd
Sika Sika India
Smart Care Asian Paints Ltd.
Sunanda speciality coating Sunanda speciality coating Pvt Ltd.
DURSBANTCT DE-NOCIL Ltd.
HILBAN Hindustan Insecticides Ltd.
NOBAN Chemtts Wets & Flows Pvt. Ltd
29 Chloropyriphos
PIRAMID AMVAC AGRI RASAYAN Pvt. Ltd.
Premise Agenda Bayer Ltd.
Sarups Pest Control Sarups Pest Control Ltd.
BURN BURN
CI double flange IVS Indian Valves Private Ltd.
30
sluice valve Kartar Kartar valves private Ltd. ,
Kirloskar Kirtoskar brothers Ltd. ,

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 199

Sl. Material
Brand Makes
No Description

Leader leader valves Ltd ,


RBM AF-S LL,
Zoloto Zoloto Industries
Fluidtech Fluidtech
CI double flangad
31 Kirloskar Kirloskar Brothers Ltd.
non raturn valve
Zoloto Zoloto Industries
BIC Bengal iron corporation
HEPCO HEPCO India
32 CI Manhole cover Neco Jayaswal Neco Ltd..
RPMF M/s Raj Pattern Makers & Founders Pvt. Ltd.
SKF SKF Industries
Fischer Fischer India
Clamp, Rebar,
33 Hilti Hilti India Pvt.Ltd.
Chemical fastener
Wurth Wuerth
CERA M/s Cera Sanitaryware Ltd.
ESS Bathsense & Royal Asian Paints Ltd.
Hindware HSIL Ltd.
Jaquar Jaquar Group
34 C.P.Brass Fittings Johnson Prism Johnson Ltd.
KEROVIT M/s Kajaria Ceramic Limited
Kingston Kingston Brass India Pvt., Ltd.
MARC MARC Sanitation Pvt.Ltd.
Parryware Parryware Sanitaryware
Ashirwad Ashirwad PVC Pipes
Astral Astral Polytechnik Ltd..
Birla Aerocon HIL Ltd.

CPVC pipe and Finolex Finolex Industries Ltd.


35
fittings Flowgard Flowgard
Prince Prince Pipes and finttings Ltd,.
Supreme Supreme Industries Ltd.
Truflo HIS Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 200

Sl. Material
Brand Makes
No Description

Alu Alpha Alu Alpha India


Concealed tower Dorma Dorma India Pvt. Ltd.
36
bolt Dorset Dorset Industries Pvt. Ltd.
Ingersolrand Ingersolrand (India) Ltd.
ACCO Proof ACC Cements Ltd
Asian Paints smart care damp
Asian Paints Ltd.
proof
BASF BASF India Ltd.
CICO CICO Industries
Dr. Fixit Pidilite Industries
Duraseal Apurva India Pvt. Ltd.
Damp Proof
37 Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
material
Fosroc Fosroc Chemicals India Pvt. Ltd.
Impermo Snowcem Paints
MAPEI MAPEI Construction Products India P Ltd
MYK MYK LATICRETE India Pvt. Ltd.
PIDILITE Pidilite Industries
SIKA Sika India Pvt. Ltd.
Weather Coat Roof Guard Berger Paints India Ltd.
Electro steel Electro steel
Jindal Jindal
38 DI Fittings Kapilansh Kapilansh
Keshoram Keshoram
Tata Ductura Tata Ductura
Electrosteel Electrosteel
Jindal Jindal
39 DI Pipes
Keshoram Keshoram
Tata Ductura Tata Ductura
Amstrong Amstrong flooring
Engineered wood
40 Mikasa Real wood floors Grean Lam Industries
floor
New wood Naw Wood India ltd

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 201

Sl. Material
Brand Makes
No Description

Pergo Red floor India


Werner Dura floor wemer GmbH
Amee Rubber Amee Rubber industries Pvt Ltd
Anand Anand NVI-I products (P) Ltd.,
41 EPDM Gaskets Bohra Bohra rubber Pvt Ltd..
Hanu Hanu Industries
Roop Roop Polimers Ltd.,
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd
EPDM water Fosroc Fosroc India
42 proofing Pidilite Pidilite Industries
Membrane Smart care Asian paints
STP Shalimar tar products
Ardex Ardex Endura Ltd.
Asian paints Asian paints
CICO Poxy CICO Technologies Ltd.
43 Epoxy
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Fosroc India
Shalibons Shalimar tar products
Ardex Endura Ardex Endura India Pvt. Ltd.
Asian epoxy Asian Paints
Berger Berger paints India Ltd.
44 Epoxy Paint
Nerolac Nerolac
Shalimar Shalimar paints India Ltd.
STP Ltd. Shalimar Tar Products
Ardex Endura Ardex Endura India Pvt. Ltd
BASF BASF India Ltd.
Epoxy tile joint
45 Ferrous Crete Ferrous Grete (India) Pvt. Ltd
cements
Fosroc Fosroc indd
Laticrete MYK Laticrete India
Expansion Joint Dura Board HD100 Supreme Industries
46
Bitumen board DURAFILL Supreme Industries

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 202

Sl. Material
Brand Makes
No Description

STP Shalimar Tar Products


Andhra Polymers Pvt. Ltd./Aarolite
Aerolite
lndustnas Pvt. Ltd.
Armstrong Armstrong Wond Indusvies
Diamond (GRG Tiles) Diamond International Inex Pvt. Ltd.
47 False Ceiling Griddsquare Gridsquare Ceilings
Gypframe steel British Gypsum
Knauf Knauf Gypsum India Pvt. Ltd.
Lloyd Lloyd Insulation (India } Ltd
Saint Gobain Saint Gobain Gyproc
Andhra Polymers Pvt. Ltd./Aarolite
Aerolite
Industries Pvt. Ltd
False ceilings
Anutone Anutone Accoustics Ltd.
Members
Armstrong Amstrong World lndustries
(Perimeter, Ceiling
48 Gridsquare Gridsquare Ceilings
section,
Hunter Dougals Hunter Dougals
intermediates,
Knauf Knauf Gypsum India Pvt. Ltd.
angles etc.,)
Saint Gobain Gyproc Saint Gobain Gyproc India
USG Boral USG Boral
Access floor sytem Access Floor system
Hewetson Hewetson India
Kebao Inner Space (Distributors)
49 False Floor
PINNACLE PINNACLE
Unifloor Unifloor India Ltd.
Unitile Unitile office systems Pvt. Ltd.
Backers FS Backers FS
Dorma Dorma India Pvt. Ltd.
Fire Rated
50 Dorset Dorset Industries Pvt. Ltd.
hardware
Geze Geze GMBH
Ingersolrand Ingersolrand (India) Ltd.
51 Fire rated glass Contra Flam / Pyroswiss of Saint Gobain India Pvt. Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 203

Sl. Material
Brand Makes
No Description

Saint Gobain
Pilkinton Pilkinton India
Promat Promat Fire & Insulation (P) Ltd.
Pyran of Schott Schott glass India Pvt. Ltd.
Akzonobel Dulex Akzonobel Paints
Asian paints Asian Paints
52 Fire retardant paint Htlti Hilti India Pvt. Ltd.
Jotun Jotun paints
STPL Ltd. STPL Ltd.
Atroflame Atroflame ltd.
Hilti Hilti India Pvt. Ltd.
53 Fire Smoke Seal
Promat Promat Fire & Insulation (P) Ltd.
Raven Raven Global
Saint Gobain Saint Gobain India Pvt. Ltd.
Asahi Asahi India Glass ltd.
54 Float Glass
Pilkinton Pilkinton India
Modiguard Gujarat Guardian Ltd.
Arco Arco valve Pvt ltd
IBP IBP industries
Float Valve (Ball
55 Leader Leader valve Ltd
valve)
Prayag Prayag Polymers Pvt Ltd.
Zoloto Zoloto industries
Dorma Donna lndia Pvt Ltd.
Floor spring (For GEZE GEZE GmbH
56
non DSR Items) Ingersolrand lngersolrand India Pvt Ltd
OZONE Ozone Hardware.
Bath sense Asian Paints
CERA CERA Sanitary ware Ltd.,
Hindware HSIL Ltd,
57 Flushing Cistern
Jaquar Jaquar Group
Kohler Kohler
Parryware ROCA Bath Pvt. Ltd.,

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 204

Sl. Material
Brand Makes
No Description

Somany Somany
Fly ash cement
58 Concerned CE/SE’s will approve based on local availability.
bricks
Ambieance Ambieance
Cactus Cactus
Duroplast Duroplast Extrusion pvt ltd.
FRP Door Frames
59 Jain doors Pvt. Ltd. Jain doors Pvt. Ltd.
shutter
Jayna Jain wood industries
Meena fibre glass Meena fibre glass
Polyline Polyline
Earl Bihari Earl Bihari Pvt. Ltd.
60 Friction stay hinges
KINLONG Kinlong lndustriss
Everlast Composites Everlast Composites Pvt.,Ltd.
61 FRP covers Fibrocast Fibrocast FRP cover manufacturer
Thermodrain Poly products (I) Pvt.,Ltd.
Bhushan Bhushan steel
Galvolume sheet
Essar Essar Group
for roofing,
62 JSW JSW
cladding, sandwitch
Llyod metal craft Llyod Insulation
panel
Tata Blue Scope Tata Blue Scope
Jenco Jenco Group
63 Galvanising Karamtara Karamtara Engineering Pvt.,Ltd.
Steel lite Galvanized Steel Ltd.
HB HB Industries
ICS Sgree samarth Englnears
Surya Surya Roshni Ltd.
64 G I Pipe fittings
TATA TATA Steel Ltd.,
Unik Unik malleable
Zoloto Zoloto Industfiea
HISSAR HISSAR
65 G.I. Pipes
Jindal Jindal Pipes Ltd.,

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 205

Sl. Material
Brand Makes
No Description

Surya Surya Roshni Ltd.


TATA TATA Steel Ltd.,
Zenith Zenith Birla (India) Ltd.
Classic Classic Hardware
Dorma Dorma India Pvt. Ltd.
Dorset Dorset Industries Pvt. Ltd.
Geze Geze GMBH
Glass door
66 Godrej Godrej
hardware
Hafele Hafele India Pvt. Ltd.
Kich Kich Architectural Products Ltd.
Ozone Ozone Hardware
Squash Squash glass doors
Birla White Birla Corportion Ltd.
Bisazza Bisazza Italy
Coral Coral tiles
Italia Tie italia mosaic Pvt Ltd
67 Glass mosaic tiles
JK White JK Cement ltd.
Mridul Mridut tiles
Paljadto Palladto Mosaics
PAVIT (Eco Tile) PAVIT Ceramics Pvt Ltd.
Aparna Vitero Tiles
AGL Asian Granite India Ltd.
CERA CERA Sanitaryware Ltd
Jonson Prism Jonson Ltd.
Kajaria Kajaria Ceramic Ltd.
Glazed Ceramic NITCO NITCO Ltd.
68
tiles (Also wall tiles) Oasis M/s Oasis Vitrified Pvt.Ltd.
Orient Bell Orient Bell Ltd.
RAK RAK Ceramic India Pvt. Ltd.
Somany Somany Ceramic Ltd.
Varmora Granito Varmora Granite Granite Pvt. Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 206

Sl. Material
Brand Makes
No Description

Vitero Tiles Floor and Wall Tile


Vitero
Manufactures India
Ultra Ultra Ltd.
Ecovision Ecovision Industries Pvt ltd.
Mahesh GRC Mahesh Prefab Pvt Ltd.
69 GRC Jali & Tile
Terrafirma Terrafirma GRC Industries
Unistone Unistone Interiors Pvt.,Ltd.
GRP/SMC Panel AMITEX AMITEX Enterprises, Delhi.
Tank (New product FLOSTO Tanks Devi Polymer Pvt., Ltd., Chennai.
70 in the market PIPECO Tanks PIPECO Tanks
performance is yet
VIVANTA VIVANTA Enterprises, Mumbai.
to be established)
Asian Paints - Smart casre Asian Paints Pvt. Ltd.
Ardex Ardex Endura Adhesive India Pvt. Ltd.
BASF BASF India Ltd.
CICO CICO Industries
Dr. Fixit Pidilite Industries
Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
71 Grout Fosroc GP2 FOSROC India
Fugabella, Porcelana Kerakoll India Pvt. Ltd.
Home shield super grout Berger Paints India Limited.
LATA POXY MYK LATICRETE India Pvt. LTd.
MYK Schomburg MYK Arments Range of products
SIKA Sika India Pvt.Ltd.
Weber Saint Gobain India Pvt. Ltd.
Audco L&T Valves
Leader leader valves Ltd ,
72 Gun metal Valves
Sant Sant Valaves Pvt. Ltd.
Zoloto Zolota Industries
Armstrong Armstrong world Industries
73 Gypsum Board
Gyproc Saint Gobain Saint Gobain Gyprock India Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 207

Sl. Material
Brand Makes
No Description

Lafarge Lafarge Gypsum India Pvt. Ltd.


USG Boral board USG Board India (P) Ltd.
Ferrous crete (Ferro-500,
Ferrous crete manufacturers
Gypsum) Plaster)
74 Gypsum plaster Gyproc Saint Gobain (Elite 90) The Saint-Gobain group
Ultra Tech Cement Ltd.
Ultra tech

ABC Ceramics ABC Ceramics


Endura Johnson India
Heat resistant tiles Johnson Johnson India
75
on terrace Somany Somany Ceramic Tiles
Swastik Swastik Tiles
Thermatek Thermatek
Armstrong Armstrong world industries Ltd.
High Desity (HDF)
76 Green ply Green Ply Industries Ltd.
Prelaminated board
Pergo Red Floor India
Allura/ Graniza range Asian paints
High end exterior
77 Berger Berger paints India ltd
Texture
SKK Brand SKK Ltd
Dorma Dorma India Pvt. Ltd.
Dorset Dorset Industries Pvt. Ltd.
Hydraulic door
Everite Everite agencies
78 closers/ Floor
Godrej Godrej locking solutioin & systems
springs
Hardwyn Hardwyn hardware
MAGNUM KIT Mukund Overseas
Basant Betons Basant Betons
BHARAT (NILSON) Bharat
Interlocking Dazzie Dazzle Designer tiles Pvt Ltd

79 Concrete Paver Hindustan tiles Hindustan tiles, Ranchi Pune

Blocks NITCO (ROCKARD) NITCO


REGENCY Regency
Shree Shree Bharat Paver blocks

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 208

Sl. Material
Brand Makes
No Description

Ultra Ultra tile private Ltd


Vyara Tiles VYARA Tiles Pvt. Ltd. / Surat
Any alternative tiles as approved by CE/SE based on local availability.
Archid ply Archid ply industries ltd.
A1 Teak A1 Teak Products Pvt.,Ltd.
Century Centuray laminates
Decolam Decolam India Pvt. Ltd.
Formica Formica Laminates (India) Pvt. Ltd.
Green Lam Green lam Industries Ltd.
80 Laminate
KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Kitmica Kitply Industries Ltd.
Merino Merino laminates
Royal touche Royal touche laminates
Sonear Sonear Laminates
Sunmica Sunmica Industries
Armstrong Armstrong flooring India Pvt. Ltd.
Linoleum sorts Forbo Forbo Flooring India Pvt. Ltd.
81
flooring Gerflor Gerflor flooring
Dorset Dorset Industries Pvt. Ltd.
Godrej Godrej locking solution & systems
Hafele Hafele India Pvt. Ltd.
Harrison Harrison locks
82 Locks & Latches Hitech Globe Locks India
Helix Helix India
Link Link Locks
Plaza Bharat lock House
Yale ASSA ABOLOY India (P) Ltd.
3M 3M
Roop Roop Polymer Ltd.
83 Masking Tapes
Sun Sun
Wonder polymer Wonder Tape Industries

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 209

Sl. Material
Brand Makes
No Description

Asian paints Asian paints


84 Melamine Polish Melamine Gold Wudfin Pidilite industries
Polycure Polycure Malaysia
Mechanical coupler Dextra Dextra India Pvt Ltd.
85
for reinforcement Sanfield Sanfield India Ltd.
Alchemica Alchemica Ltd.
Ardex Endura Ardex Endura Ltd.
Asian paints Smart care water proofing products
BASF BASF India Ltd.
Membarane water Dr. Fixit Pidilite industries
86
proofing system Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Hydro tech Hydro tech Ltd.
MYK Schomburg MYK Arments range of products
STP Ltd Shalimar tar products
Texsa Texsa India Ltd.
Godrej Godrej Security Solutions
Kenwood Kenwood Ply & Board
MPP Schodders MPP Technology Pvt. Ltd.
Metalic / Steel Fire NAVAIR NAVAIR International Pvt. Ltd.
87
Door Promot Promot fire & Insulation (P) Ltd.
Shakthi Hormann Shakthi Hormann Pvt. Ltd.
Signumfire Protection Signumfire Protection pvt. Ltd.
Sukri Sukri Fire Doors Pvt. Ltd.
Essar Essar Steel Ltd.
JSW JSW Structural Metal Decking Ltd
88 Metal Deck Sheet
SAIL SAIL
TATA TATA steel
Amit Lovely metal Industries Pvt. Ltd.
Mild Steel Butt
Deepak Deepak
89 Hinges/ Piano
Garg D.P. Garg & Company
hinges
Jolly Jolly Engineering works

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 210

Sl. Material
Brand Makes
No Description

Jyoti Jyoti Architectural Pvt. Ltd.


Saswat Saswat
Supreme Supreme Industries
Swift Swift screws
AIS Mirror Asahi India Glass Ltd.
Atul Autl Glass Industries Ltd.
90 Mirror
Modi Guard Gujarat Guardian Ltd
Saint Gobain Saint Gobain Glass India Ltd.,
Evoke Evoke
Modular kitchen/
Godrej Godrej & Boyce co
91 wardrobes/Hardwa
Sleek Asian Paints
re and Accessories
Spacewood Spacewood
Apollo Appolo Tubes Ltd.
JINDAL JSW
Kalinga Kalinga Tubes Ltd.
92 M.S. Pipe, Tubes
SAIL SAIL
Surya Surya Roshi Ltd.
TISCO TATA STEEL
Multy walled Danapalon Danapal Light architecture
93 polycarbonate
Lexan GE GE lexan
roofing sheets
Everest Everest Industries
Non Asbestos
94 HIL HIL Ltd.
Sheets
RAMCO RAMCO Industries Ltd.
Godrej Godrej Security Solutions
Non Metalic Fire Kenwood Kenwood Ply & Board
95
door NAVAIR NAVAIR International Pvt. Ltd.
Promot Promat Fire & Insulation (P) Ltd.
BASF BASF India Ltd
Non Metallic floor
96 CICo CICO Technologies ltd
surface hardness
Fosroc Fosroc India

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 211

Sl. Material
Brand Makes
No Description

Hardonite Hardonite
Ironite Ironite
Pidilite Pidilite Industries ltd
Sika Sika India
Berger (BISOM) Berger Paints
Oil Bound Dulux (Maxilite) Dulux
97
Distemper MG Polyplast Nerolac
Tractor Aqalock Asian Paint
Overdeck insulation Dowcorning Dowcorning
with extruded Owen scorning Owen scorning
98
polystyrene board
Supreme Petrochemical Ltd. Supreme Petrochemical Ltd.
(XPS board)
Panel Doors/Wire Jain doors Jain Door Pvt. Ltd.
99 mesh Door shutters
NCL Nagarjuna
/Fire proof doors
PE-AL-PE
100 Kitec Kitec Industries (Índia) Pvt. Ltd.
Composite Pipes
Berger Berger Paints
Dulex ICI dutax
Nerolac Nerolac Kansia Nerolac Pains Ltd.
101 Pink primer
Nippon Nippon
Asian paint
Wood primer

BASF BASF India Ltd.


Chryso-HP/ Delta / Optima Chryso India Pvt. Ltd.
CICO CICO Industries

Plasticiser & Super Contrament, Power flow MC Bauchemie (India) Pvt. Ltd.
102
Plasticiser Conplast SP 430 FOSROC India
MYK Schomburg MYK Arments Range of products
Plastiment, Sikament Sika India Pvt. Ltd.
Smart Care Techno Asian Paints Limited

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 212

Sl. Material
Brand Makes
No Description

Plast/Smart care maximo


plast.
Sunanda Chemicals Sunanda Chemicals Ltd.
Plastic Accurate Buildcon Accurate Buildcon company
103 Encapsulated Foot KGM KGM Exports
Rest KK India KK Manhole and gratings Co Pvt Ltd.
Koochie Play Koochie Play systems Pvt ltd.
104 Play Equipments
Play world systems Play world systems India.
BBR BBR (India) Pvt. Ltd.
Post tensioning CRUX Crux Processing systems Pvt. Ltd.
105
System Ultracon Ultracon Structural Systems Pvt. Ltd.
VSL VSL India pvt. Ltd.
Alcox Hindeggan Alcox Ltd.
Danapalan Danapal Light architecture
Poly carbonate
106 GE Lexon GE Silicones
Sheet
MG Polyplast
MG Polyplast

Polycarbonate
Convex mirrors,
107 Unique safety solutions Unique safety solutions
Rubbarised road
hump
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Smart care sealant
Poly sulphide MYK Schomburg MYK Arments range of products
108
sealant Pidilite Pidilite Industries
STP Ltd Shalimar tar products
Techseal Choksey chemical Pvt ltd.
Tuff seal Bondit construction chemical
Polyethylene
109 Supreme Supreme Industries
backer rod

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 213

Sl. Material
Brand Makes
No Description

BASF BASF
Ferrous Ferrous Crete ( India ) Pvt Ltd
110 Polyurea Ultra Pidilite Pidilite Industries
SIKA SIKA India
Smart care Asian paints
Akzonoble Akzonoble Coating Ltd.
111 Powder coating Berger Berger Paints India Ltd.
Jotun Jotun Group
Powder & PVDF Aura International Aura International Pvt.,Ltd.
112 Processer MJ coaters MJ Coaters Pvt.,Ltd.
SP Coating SP Architectural Coating Pvt.,Ltd.
Archid ply Archid Ply Industries Ltd.
Associate Associate Décor Limited
Centuary Centuary MDF

Prelaminated Ecoboard Ecoboard Industries Ltd.


113 particle board Green Lam Green lam Industries Ltd.
Exterior Grade Kitlam Kit Ply Industries Ltd.
Merino Marino laminates
Novapan GVK Novapan Industries Pvt. Ltd.
TESA Action Co. TESA Action Co.

Premium Acrylic Berger Berger


smooth exterior Dulux ICI dulux
114
Paint with silicon Nerolac Nerolac
additives ULTIMA Asian paint
PTMT/PVC water PEARL Precision Products
supply sanitary Prayag Prayag Polymers (P) Ltd
115 fittings, bibcocks,
pillar cock Angle Supreme Supreme industries
valve,
DP Wires DP Wires Ltd.
116 PT Strands
TATA wiron TATA STEEL LTD.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 214

Sl. Material
Brand Makes
No Description

Usha Martin Usha Martin Ltd.


Ambieance Ambieance
Accucel Accura Polytech Pvt. Ltd.
Duroplast Duroplast extrusion Pvt. Ltd.
Encraft Encraft India Pvt. Ltd.
PVC Doors and
117 Plastic Wood Plastic Wood
Frames
Polyline Polyline extrusion Pvt. Ltd.
Rajshri Rajshri Productions Pvt. Ltd.
Sintex Sintex Plastic technology Ltd.
VEKA M/s NCL Veka Ltd.
Sintex Sintex Plastic technology Ltd.
PVC / HDPE water
118 Supreme Supreme Industries Ltd.
storage tanks
Vectus Vectus Industries Ltd.
Akash Enterprises Akash Enterprises
PVC Perforated Rex Polyextrusion Rex Polyextrusion ltd.
119
Pipes Supreme Supreme industries.
Zenplas Pipes Zenplas Pipes Pvt ltd.
Armstrong Armstrong world Industries
120 PVC flooring Ger flor Ger flor flooring
LG Hausys LG Hausys
Akzonoble Akzonoble Coating Ltd.
121 PVDC coating
Valspar Valspar India Coating Corporation Ltd.
BASF BASF
Fosroc Fosroc India
PU Coating (UV
Pidilite Pidilite industries
122 resistant Liquid
PU Roof Koat Berger Paints Ltd
Applied coating)
SIKA SIKA India
Smart care Asian paints
PU Enamel Metalic Akzonobel Akzonobel
123 Paints on MS Asian paints Asian paints
Structure & Epoxy Berger Berger paints India Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 215

Sl. Material
Brand Makes
No Description

paints ( Premium MRF MRF paints


Quality) SKK SKK ltd
Access Floor systems Access Floor Systems
Tate Tate
Raised / Cavity
124 Uni floor Uni floor India
flooring
Unitile Unitile India
Zt floor Zt floor Pvt.,Ltd
Indian Hume Pipes Indian Hume Pipe Ltd.,
Jain & Co Jain spun pipes Co.,
125 RCC Pipes Lakahmi Sood & Sood Lakshmi Sood & Sood Pipa Co.
Madurai spun pipe Madura spun pipe company
Vishnu Vishnu Spun Pipes.
Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
Gyproc plasters Saint Gobain Gyproc India
Ready mix cement Ramco super plaster
Ramco super plaster melamine
126 plaster melamine
Read Plast Ultratech cements Ltd
Ultra tech Ultra tech Cement Ltd
Berger Berger Paints
Dulex ICI dulex
Red Oxide Zinc High performance yellow
127 Asian Paint
Chromate primer metal primer
Nerolac Nerolac
Nippon Nippon
Asahi Asahi India Glass ltd.
Glaverbel Glaverbel India
128 Reflective glass Modifloat Gujarat Guardian Ltd.
Pilkinton Pilkinton India
Saint Gobain Saint Gobain India Pvt. Ltd.
RMC plants ACC ACC Cements Ltd
129
( Ready Mix A B Dinesh A B Dinesh Concrete India Pvt., Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 216

Sl. Material
Brand Makes
No Description

Concrete) Aparna Aparna Ready Mix concrete


Lafarge Lafarge India Pvt. Ltd.
NUVOCO Nuvoco Vistas Corporation Ltd.
RB Ready Mix RB Ready Mix
RDC RDC Concrete (India) Pvt.Ltd.
RMC (India) RMC (India) Pvt. Ltd.
Ultra Tech Ultra Tech Cement Ltd
Liyod Insulation Liyod Insulation ltd.
Rockwool/Glass
130 Supreme Supreme Industries ltd.
wool insulation
Twiga fiber Twiga fiber glass ltd
Advent Advent concrete vision
BASF BASF
Danapalan Danapal Light architecture
Essar Essar Group.
Fosroc Fosroc
GE Plastic GE Silicones
Sandwich PUF
GE Plastic GE Silicones
131 panelled roofing
JINDAL MECTEC/ JINDAL Mectec Pvt Ltd
sheets
LEXAN LEXAN Ltd
Liyod Insulation Liyod Insulation (India) ltd
Lloyd Insulation Lloyd insulation (India ) Ltd
Pidilite Pidilite Industries ltd
Smart care Asian paints
Supreme Supreme ltd
AOS System AOS System
Grohe Grohe
Hindware HSIL Ltd
Sensor based Auto
132 Jaquar Jaquar Group
flush systems
Kochier Kochier
Parryware Parryware Sanitary ware
TOTO TOTO ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 217

Sl. Material
Brand Makes
No Description

Nu-TEC Nu-Tech concrete products (P) Lld,.


SFRC Cover and
133 KK KK Manhole and gratings Co Pvt Ltd.,
grating
Kutty Kutty Industries
Shear Stud/
134 KOCO KOSTER & CO
Connector
BASF BASF India Ltd.
Dow Corning Dow corning Indd
135 Silicon coating
GE GE Silicones
Wacker Wacker silicones
136 Silicon Gaskets Sree Geurev Sree Gaurav Rubber products
3M 3M Science
Solar studs/
Avery Dennison Avery Donnison India Pvt Ltd.
137 Median markers
Nikkalite Nippon carbide Industires (USA)
Dorma Dormakaba
hafele Hafele Ltd.
Spider patch Kich Kich india
138 fittings for Ozone Ozone Ltd.
structural glazing Saint Gobain Glass India ltd
Sevax

Spray applied Buildon Buildon


Readymade Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
139
plaster/ Gysum Gyproc cute 100 Gyproc India.
plaster Ultratech Ultratech cement ltd.
Neco JayaSwal Neco Ltd
Kartar Kartar valves private Ltd. ,
Spun cast iron
140 Electrosteel Electrosteel
fittings
Kapilansh Centrifugal Kapilansh Dhatu Udyoo (P)Ltd.
SKF brand SINGHALIRON FOUNOARY Pvt. Ltd.
Spun cast iron Jagannath Sri Jaqannath iron Foundry Pvt. Ltd
141
covers & gratings Kapilansh Centrifugal Kapilansh Dhatu Udyoo{P)Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 218

Sl. Material
Brand Makes
No Description

Neco Jayaswal Neco Ltd


SKF brand SINGHALIRON FOUNOARY Pvt. Ltd„
Ark Product Pvt. Ltd. Ark Product Pvt. Ltd.
Connect Connect Ltd.
Jindal JSW
142 Stainless Steel
KINGSTON KINGSTON
Salem SAIL
SAIL SAIL
Alloy Alloy Ltd.
Atul Atul fasteners Ltd.
GKW GKW Limited
Stainless Steel
143 Helix Helix India
screws
Kundan Kundan Industries Ltd.
Nettlefold Nettlefold Screws
Pooja Pooja Steel Corporation
Dorma Dorma India Pvt. Ltd.
Stainless steel Butt Helix Helix India
144
hinges Prayag Prayag Polymers (P) Ltd.
Ozone Ozone Hardware
Earl Bihari Earl Bihari India Pvt. Ltd.
EBCO EBCO
Stainless steel Hetich Hetich India
145
friction hinges Haffle Haffle India Pvt. Ltd.
ROTO ROTO Frank Asia
Securistyle Securityle India Pvt. Ltd.
Atul Atul fasterners Ltd.
Stainless steel
Hilti Hilti India Pvt. Ltd.
146 Bolts, washers,
Kundan Kundan Industries Ltd.
nuts
Pooja Pooja Steel Corporation
Stainless steel Atul Atul fasterners Ltd.
147
pressure plate Dorset Dorset Industries Pvt.Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 219

Sl. Material
Brand Makes
No Description

screws Kundan Kundan Industries Ltd.


Pooja Pooja Steel Corporation
CERA M/s Cera Sanitaryware Ltd.
Diamond Pheonix Appliances Pvt. Ltd.
Franke Franke India Ltd.
Futura Futura Kichen Sinks India Pvt. Ltd.
Hindware HSIL Ltd
Stainless Steel Jhonson Prision Jhonson Ltd.,
148
Kitchen sink Jindal Centuary polytech
Joyna Joyna
Navkar Shri Navkar Metals Ltd
Nilkanth Nilkant
Nirali Jyoti (India) Matel Industries Pvt Ltd
Silver Shine Blue stone sanitary Industries Pvt. Ltd.
Accucel Accura polytech Pvt ltd.
Steel Windows/
Madhu industries Madhu industries, San Harvic, NCL
149 Pressed steel
NCL NCL Industries
frames
San Harvic San Harvic
APL Apollo Tubes Ltd
JSPL JSPL
JSW JSW
150 Structural Steel
SAIL SAIL
TISCO TATA STEEL
VIZAG RINL
Asian paints Smart care sealant
BASF BASF India Ltd.
Dow corning Dow corning india

151 Structural sealant Fosroc Fosroc India


GE GE silicones
STP Ltd. Shalimar tar products
Wacker Wacker silicones

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 220

Sl. Material
Brand Makes
No Description

Berger Berger Paints


Dulex ICI dulex Ltd
Synthetic enamel
152 Premium gloss enamel Asian paint Ltd
Paint
Nerolac Nerolac Paints Ltd
Nippon Nippon Paint India Ltd.
Hollitex Hoilitex carper tilas
Synthetic Carpet
153 Standard Carpets Standard Carpets
tiles
TOLI TOLI Corporation
Armstrong Armstrong flooring
Synthetic Sports
155 Gerflor RMG Polyvinyl India Ltd.
Flooring
LG Wondorfloor LG Hausys India
Astral Astral poiytechnik Ltd.
Finolex Finolex Industries Ltd .
Flowgard Ashirwad PVC Pipes
SWR PVC Pipes & Nandi Nandi pipes Pvt., Ltd.
156
fittings
Prince Prince Pipes and fittings
Sudhakar Sudhakar PVC Pipes
Supreme Supreme Industries Ltd
Asahi Asahi India Glass ltd.
FUSO FUSO Glass India Pvt. Ltd.
Tempered Gurind Gurind India
157 reflective/ clear Imapct Safety Impact Safety glass works Pvt. Ltd.
glass Modiguard Gujarat Guardian Ltd.
Pilkington Pilkington India Pvt. Ltd.
Saint Gobain Saint Gobain India Pvt. Ltd.
Asian Asian Paints Ltd.
Elastospray BASF
Thermal Insulation
158 Pidilite Pidilite Industries
treatment
Rock India Pvt. Ltd Rock India Pvt. Ltd
Weather Kool & Seal Berger Paints India Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 221

Sl. Material
Brand Makes
No Description

JSW JSW Steel Ltd.


TMT Bars SAIL Steel Authority of India Ltd.
159
TISCO TATA STEEL LTD.
VIZAG Rastriya Inspat Nigam Ltd.
AKG AKG
Astral Astral polytechnik Ltd.
Ashirwad Aahirwad PVC Pipes
UPVC Pipes and
Finolex Finales Industries Ltd.
160 fittings (Rain water
KSR KSR
pipes)
Prepoly Premier PVC Industry
Prince Pnnce pipes and fittings Ltd.
Supreme Supeme industries Ltd.
Aluplast Alu Alpha India
Duroplast Duro Plast Extrusion Pvt. Ltd.
Encraft Encraft India Pvt. Ltd.
Fenesta Fenesta DCM Shriman

Komarling Profile India Window Technology Pvt. Ltd.


UPVC doors, door
161 frames and LG LG India Pvt. Ltd.

windows MARCOLINI M/s Mathura Poly pack Pvt, Ltd.


Prominance M/s Prominance Window Systems
Rehau Rehau Unlimited Polymer Solutions
Sintex Sintex Plastic technology Ltd.
Venster/ OKOTECH Aparna Enterprises limited
VEKA M/s NCL Veka Ltd.
COAR COAR
DNV DNV Global Pvt.,ltd.
162 UPVC Hardware
HOPPE HOPPE
PULSE LGF SYSMAC (India) Pvt.,Ltd.
Vitreous BATHSENSE Asian paints( Bath division)
163 Commodes/ CERA CERA Sanitaryware Ltd.,
Washbasin Hindware HSIL Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 222

Sl. Material
Brand Makes
No Description

Jaquar Jaquar Group


Kerovit M/s Kajaria Ceramic limited
Kohler Kohler world Wide
Parryware ROCA Bath Pvt. Ltd.,
Roca ROCA Bath room products
RAK Sanitaryware RAK Sanitaryware
Somany Somany Ceramic Ltd.
Durostone Ever stone International
Vitrified paving Johnson Johnson India
164
tiles Kajaria Kajaria Ceramics
PAVIT PAVIT Ceramics Pvt. Ltd.
AGL Asian Granite India Ltd.
CERA M/s CERA sanitary ware Ltd.
Johnson Prism Johnson Ltd.
Kajaria Kajaria Ceramic Ltd.
Marbito Marito tiles
NITCO NITCO Ltd.
165 Vitrified Tiles
Oasis M/s Oasis Vitrified Pvt.Ltd.
RAK RAK Ceramic India Pvt. Ltd.
Restile Restile Ceramic Ltd.
Somany Somany Ceramic Ltd.
Varmora Granito Varmora Granite Pvt. Ltd.
Vitero Aparna Enterprises limited
Archidply Archid Ply Industries Ltd.

Water Proof A1 Teak A1 teak Industries Pvt. Ltd.

Plywood, Century ply Century Flush Doors

Commercial ply, Duroply Duro Ply Industries Ltd.


166
Fire retardant ply Duroplast Duroplast

and Block boards / Dura sleek Dura sleek

Shuttering ply Grassim ply Shree Ram Industries


Green panel Green panel Industries Lid.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 223

Sl. Material
Brand Makes
No Description

Green Ply Green Ply Industries Ltd.


Jayna ply Jain Wood Industries
KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Kitply Kitply Industries Ltd.
Polyline Polyline
Asian exterior wall primer Asisn paint
Berger Bergar Paints
Water Proof
167 Cem Colour Snowcem Paints
cement paint
ICI DULUX ICI DULUX
Surfa Surfacoats (India) Pvt. Ltd.
ARCO Arco valves Pvt. Ltd ,
Water supply leader leader valves Ltd ,
168
Valves Nanda Nanda Miller company
Zoloto Zoloto Industries
Advani Advani oerlikon Ltd.
ESAB ESAB India Pvt. Ltd.
ESS, BATHSENSE & Premium
169 Welding rods Asian Paints (Bath Division)
Range : Royale
HlNDWare HSIL Ltd.
Jaquar Jaquar Group
Johnson Prism Jhonson Ltd
Kerovit M/s Kajaria Ceramic limited
Kingston Kingston brass India
Water supply
MARC MARK Showers
fixtures like
170 Metro Metro sanitations Pvt. Ltd.,
bibcock, Shower
Parryware ROCO bath roam products Pvt. Ltd,
panels
Prayag Prayag polymers Pvt Ltd ,
Seiko Seiko Sanitations
Watarman Kewal brothers
Water proofing Accoproof ACC cement Ltd.
171
Compound Alchemica Alchemica Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 224

Sl. Material
Brand Makes
No Description

Ardex Endura Ardex Endura ( India ) Ltd.


Asian Paints Asian Paints
CICO CICO Technologies Ltd.
Cement Mix Plus/Advanced
Berger Paints India Ltd.
Latex Plus
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Fosroc India
Impermo Snoweem paints
MYK Schomburg MYK Schomburg range of products
Penetron Penetron India Pvt Ltd.
Shaliplast LW+ STP Ltd
Sika Sika India
Ardex Endura Ardex Endura Ltd.
BASF BASF India Ltd.
Dr. Fixit Pidilite industries
172 Water stops
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Hydroswell Sika India
Hydrotite Sika India
Asian paints Smart care SC GP grout grey
BASF BASF
Water proofing Care Care
173 materials/ GP Ferrous crete Ferrous Crete ( India ) Pvt Ltd
Grouts Home shield Super grout Berger Paints Ltd.
Pidilite Pidilite Industries ( Dr.fixit)
SIKA SIKA India
Fosroc Fosroc India
Weather silicon Down corning Down corning india
174
make and grade Momentive (GE) GE silicones
Birla Birla Corporation Ltd.
175 White Cement J.K. JK Cement Ltd.
Travancore Travancore Cements Ltd.

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 225

Sl. Material
Brand Makes
No Description

Alstone Alstone Industries Pvt., Ltd., Jaipur, Rajastan.


Wood Polymer
Century M/s Century Ply Boards (I) Limited
composite material
Ecoste Ecoste wood polymer composite, Delhi.
for door frames and
Echon Kumar Arch Tech, Pvt.Ltd., Rajastan.
176 shutters, plain/pre
Green ply Greenply Industries Limited
laminated boards
Qute Qute Extractions Pvt.Ltd., Chennai.
for wall linings
Rajeswari Products Pvt.,Ltd., Madya
etc. Rajasree
Pradesh.
Archiply Archiply
A1 Teak A1 Teak Products Ltd.
Century Century Flush Doors
Duro Flushdoors Dura Ply industries Ltd.
Greenlam Greenlam Ply Industries Ltd.
Indian Timber Products Indian Timber Products
Jain doors Pvt.Ltd. Jain doors Pvt.Ltd.
Jayna Flush Doors Jain Wood Industries
Kailash Hi Tech Timber Industries India pvt.
Kailash
Wooden Flush door Ltd.
177
shutters KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Kenwood Kenwood Ply & Board
Kitply Kitply Industries Ltd.
Mayur Mayur Ply industries
MP Ply wood products MP Wood products
National plywood National plywood
Raavella door Raavella Industries (P) Ltd.
Shakthi Shree Shakthi Modern Flush doors
Swatic ply Swatic ply
Vidya ply Vidya ply
TP Grout
(Non-Shrink,
178 Flowable, Teemax Grout TP-1 M/s Teemage Builders (P) Ltd
Cementitious Grout
conforming to

Corrections/Omissions/Insertions – NIL AE EE
PART ‘B’ - 226

Sl. Material
Brand Makes
No Description
relevant “IS and
ASTM” Standards
with up to date
amendments)
Johnson Endura cool roof tile
Heat Resistant tiles
179 Thermatek Heat resistant terrace tiles
on terrace
Igloo tiles Igloo tiles
HPL (High pressure
180 Century , Merino, GreenLam
laminate )

Note:
1. Any other brand as approved by the ADG (RH), CPWD, and Hyderabad till last date of
submission of bid will also become part of the above list.
2. The above list is provisional and subject to product conformity with standards of
relavant codes.
3. Items which are not mentioned in above list but required at site shall be supplied
with prior approval of Engineer-in-Charge. Items not required at site as per scope of
work, but mentioned in the above list may not be considered.
4. The Contractor shall obtain prior approval from the Engineer-in-charge before
placing order for any specific material. The Contractor shall make a detailed
submittal with catalogues and highlighted proposed specifications, as well as full
details of the works executed by the specialized agency, as specified.

EE & SM (c)-II,
CPWD, Warangal.

Corrections/Omissions/Insertions – NIL AE EE

You might also like