0% found this document useful (0 votes)
36 views5 pages

74 343 Exam

Uploaded by

plastic2020
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views5 pages

74 343 Exam

Uploaded by

plastic2020
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Vendor : Microsoft

Exam Code : 74-343

Version: Demo

Cheat-Test.net, help you pass any IT exam!


Cheat-Test.net - The Worldwide Renowned IT Certification Material Provider!
The safer, easier way to help you pass any IT Certification exams.

We provide high quality IT Certification exams practice questions and answers


(Q&A). Especially Cisco, Microsoft, HP, IBM, Oracle, CompTIA, Adobe, Apple,
Citrix, EMC, Isaca, Avaya, SAP and so on.
And help you pass an IT Certification exams at the first try.

Cheat-Test product Features:

• Verified Answers Researched by Industry Experts


• Questions updated on regular basis
• Like actual certification exams our product is in multiple-choice questions (MCQs).
• Our questions and answers are backed by our GUARANTEE.

7x24 online customer service: support@cheat-test.net

Click Here to get more Free Cheat-Test Certification exams!


http://www.Cheat-Test.net
Q: 1
You are a project manager, and your company uses Project Professional 2013. You are setting up a
preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks
and link them in a Finish to Start relationship. The project team member asks you to increase the
duration of the predecessor task. You notice that the successor task start date is now before the finish
date of the predecessor task. You want the successor task to start after the predecessor finishes.
What should you do?
A. Select both tasks and click Unlink.
B. Select the successor task and click Mark on Track.
C. Select the predecessor task and click Respect Links.
D. Select the successor task and click Respect Links.
Answer: D

Q: 2
You are using Project Standard 2013. Management wants to see an overview of your project that
shows the overall start and finish dates, total duration, and the name of the project. They want to see
this information in a simple layout that does not include task details. You need to show one line item
that displays all the requested information in the Gantt view. What should you do?
A. Apply the Top Level Tasks filter.
B. On the format ribbon, check the box next to Project Summary Task.
C. Apply the default Summary Tasks filter.
D. On the format ribbon, check the box next to Summary Tasks.
Answer: D

Q: 3
Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well
as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the
projects so that Project 1 is the highest priority project and gets all the required resource availability
first. Project 2 then gets resources as they become available from Project 1. You need to maintain
this priority throughout the execution of the project. What should you do?
A. Set resource leveling to prioritize by project, priority, and standard.
B. Make sure the resource pool is configured to list Project 1 first.
C. Level Project 1 first, and then level Project 2.
D. Set Project Priority higher for Project 1, and then set resource leveling to level by priority, standard.
Answer: D

Q: 4
Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. As you build the task breakdown, you notice a potential scheduling problem
indicated by a wavy red line under the finish date of a detail task. You need to determine the cause
of the wavy red line. What should you do?
A. Evaluate the task to determine if there is a deadline.
B. Insert the Constraint Type field and view the task constraints.
C. Evaluate the task by using the Task Inspector.
D. View the Resource Sheet to see if you have overallocated resources.
Answer: C

Q: 5
You are a project manager who uses Project Professional 2013. You have worked on a project for four
years and have created a very detailed project plan in Project Professional 2013. You use milestones
as key deliverables, and you use summary tasks as phases. Your company requests a presentation
of the key deliverables for each phase of your project plan in a simple and consolidated view that fits
in one Microsoft PowerPoint slide. You need to ensure that phases and key deliverables are clearly
shown in the timeline and are not confusing to the audience. What should you do?
A. Create a new Timeline view from existing tasks in your project plan. Drag the timeline into a blank
PowerPoint slide.
B. Create a new Timeline view that automatically shows milestones for each stage of your project.
Copy the full-size timeline and paste to your PowerPoint slide.
C. Add all summary tasks to your timeline. Project Professional 2013 will automatically recognize and
add all milestones on each stage to your Timeline view. Copy the full-size timeline and paste to the
PowerPoint slide.
D. Add all summary tasks to your timeline. Add all milestones to your timeline. Copy the full-size
timeline and paste to your PowerPoint slide.
Answer: D

Q: 6
You are a project manager who uses Project Standard 2013. You work on a project that requires you
to generate many documents. Each task in your project plan must have a document associated and
stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in
size.
You need to share this project plan by email with your team and ensure that they can easily access
the documents.
What should you do?
A. In the Task Information notes, insert an object from a file. Uncheck the Link option and make sure
that it is a document, not a link. Select your document and click on it. Project will automatically create
the reference to this document.
B. Create a task custom field named Link to Document, and select the field type as Text Hyperlink.
Copy the SharePoint URL of each document and paste it as a text into the Link to Document task
custom field. Project Standard 2013 will convert this text to a clickable hyperlink.
C. Copy and paste the document into your Gantt chart, and create a link between your task and the
document.
D. Go to backstage and use the feature Add and Link a SharePoint Document to My Tasks to select
your document in your SharePoint Library. Select your task. Project will automatically create a clickable
hyperlink.
E. Copy the SharePoint URL of each document and paste in the Hyperlink task standard field as a
text. Project will convert this text to a clickable hyperlink.
Answer: E

Q: 7
You are a project manager for an organization that uses Project Professional 2013. You manage a
critical project across multiple regions. All information regarding the project must be shared through
email directly to the stakeholders. You have already added all of the tasks and milestones to Timeline,
aiming to present the most important information of the project through graphs. You are not allowed
to send the .mpp file to your stakeholders since they will not be able to open it. You need to share the
Timeline view through email. What should you do?
A. Select Visual Reports, select a Built-in template for Timeline views, and click Generate. When the
report has been generated, copy and paste the output in the body of your email.
B. Activate the Timeline view. Click the View tab, select Other Views, and choose Save View. Name
this view and save it, before going to the body of your email and attaching the view you just saved.
C. Activate the Timeline view. Then go to the Format tab and click Copy Timeline For Email. Paste
where necessary in the body of your email.
D. Choose File, Share. In the Share page, select Email. Then select Send as Attachment.
Answer: C

Q: 8
You are a project manager for a company that uses Project Professional 2013. You are responsible for
communicating the progress of your projects every month. Your company provides you with a Gantt
Chart view that uses the standard Entry table. You need to communicate the progress of tasks that
have a finish date of either October 2 or October 22. What should you do?
A. Go to the Task tab, open the Find window, and set the parameters to find the required dates, setting
the Look in Field to Finish. Then click Find Next.
B. Go to the View tab, open the More Views window, and create a new view.
C. Go to the View tab and use the Date Range filter.
D. Go to the View tab and select Display AutoFilter. Click on the arrow next to the Finish column and
check only the required dates.
Answer: D

Q: 9
You are a project manager who uses Project Professional 2013. You have created a project which
involves three other colleagues who are also using Project Professional 2013. You and your colleagues
are over budget and cannot spend any more money on this project. To ensure that the latest version
of the project file is always the one being used, you need to save, share, and sync this project plan
File among your colleagues without using email. What should you do?
A. Save and sync your project by using SkyDrive.
B. Save and sync selected tasks in the project by using SkyDrive.
C. Save and sync your project to a shared Microsoft Excel file.
D. Save and sync selected tasks in your Microsoft SharePoint Tasks List.
Answer: A

Q: 10
You are a project manager who uses Project Professional 2013. You work in a software development
project, which is in progress and has reached 60% of actual progress. Your company decides to use
the new Project Reports views to communicate all the project progress across the key users. They
also decide to report information about a specific period only, normally one month behind the current
day. You need to access the report view that your company previously created; however, you must
only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?
A. Access your report and change the scale by zooming in and out.
B. Access your report and create a new Date Range group.
C. Access your report and use the default Date Range filter.
D. Access your report view and edit the time category under the field list pane.
Answer: D