Concreting Checklist

Uploaded by

asmaul salleh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views2 pages

Concreting Checklist

Uploaded by

asmaul salleh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT NAME:

CONCRETING WORK INSPECTION CHECKLIST


INSPECTION DATE : 22/1/24
PACKAGE NO : C03&C09(N2&H2)
CONTRACTOR : OCS YES Construction
LOCATION : Ext. Road 1 DRAWING NO : FEK2-LAY-ANC-01-SSTR-170-06
LEVEL/GRIDLINE : Level 1

1st Inspection 2nd Inspection Remark /


Item Description Yes No N/A Yes No N/A Non-Conformance
1 Formwork
a. A 50mm thick lean concrete layer has been in
b. Setting out / control points for alignment,
position
c. Transfer level, drop, step down
d. Dimension (width & depth/height)
e. Top level of concrete marking
f. Tightness of form joints (to prevent grout loss)
g. Construction joints (level, verticality & position)
h. Marking/fixing for opening and sleeve (type,
size
and position)
i. Cleanliness of form
j. Mould oil (if applicable)
2 Reinforcement Bar
a. Size and location of spacer as specified
b. Minimum concrete cover is secured
c. Condition of reinforcement bar (Securely tied,
free
d. Main bar (diameter, number, position, spacing, Lap length for beam and column
top 52 times bar diameter (min
600mm)
hook, lap length, anchorage length)
e. Link (diameter, number, spacing, hook, cover,
welding point, penetration rebar)
f. Starter Bar ( diameter,number,length)

g. BRC (size, number, position, spacing, lap


length,
h. Additional rebars/ trimmer bars / anti crack
bars for
3 Others
a. Position, spacing and rigidity of props /
scaffoldings
b. Treatment of existing construction joints (free
from laitance, exposed aggregate)
c. Application of waterproofing addmixtures /
material
d. Install cast in plate, hook. (If any)
e. M&E services checked
REMARK / NON-CONFORMANCE

Inspected by : Inspected and Checked and Approved by :


Approved by :
Name : Name : Name :
Designation : Designation : Designation :
Date : Date : Date :
* This section is applicable for mock up inspection by consultant only and will be crossed out for daily basis inspection.