0% found this document useful (0 votes)
75 views4 pages

Erection Checklist

Uploaded by

rmcincharge
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views4 pages

Erection Checklist

Uploaded by

rmcincharge
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

COHERENT ENGINEERING SERVICES

Documet CHECKLIST FOR ERECTION OF PRECAST CONCRETE ELEMENTS


Project
Element ID Checklist No:
Block&Floo
Date:
r:
Note : Please appropriate box as per requirements
Sl No DESCRIPTION YES NA
1 Identification of element available [ ] [ ]
ELEMENT INSPECTION/ RECEIVE CHECKS
1 Critical dimensions
i Length [ ] [ ]
ii Width [ ] [ ]
iii Height or thickness [ ] [ ]
iv Straightness [ ] [ ]
v Squareness [ ] [ ]
2 Surface condition
i No honeycomb [ ] [ ]
ii No crack [ ] [ ]
iii No chipping [ ] [ ]
iv Edge straight [ ] [ ]
v No excessive pinholes [ ] [ ]
vi Flatness or evenness [ ] [ ]
3 Lifting points/ inserts
i Location [ ] [ ]
ii Physical condition [ ] [ ]
4 Sleeve system / Connections
i Starter bar (length, size and spacing) [ ] [ ]
ii Loop and lapping bars (length, size) [ ] [ ]
5 MEP services
i Location [ ] [ ]
ii Physical condition [ ] [ ]
6 Storage and loading points
i Condition [ ] [ ]
ii Stacking method [ ] [ ]
PRE-ERECTION (INSTALLATION AREA)
1 Tools, equipment (drills, auto-level, theodolite, brackets, bolts) [ ] [ ]
and temporary props and bracings
2 Survey reference lines and level marks [ ] [ ]
3 Construction joint treatment [ ] [ ]
4 Location and conditions of corrugated steel sleeves [ ] [ ]
INSTALLATION
1 Setting out and position of elements
i Verticality [ ] [ ]
ii Alignment [ ] [ ]
iii Level [ ] [ ]
2 Adequacy of temporary supports [ ] [ ]
3 Grouting work (check mix ratio)
i Horizontal joints [ ] [ ]
ii Corrugated pipe sleeve connection [ ] [ ]
4 Joint and connection details - Re bar connection [ ] [ ]
FINAL INSPECTION/ POST INSTALLATION
1 No visible crack or damage [ ] [ ]
2 Water tightness test on,
ii External wall panels [ ] [ ]
iii Joints between external wall and window frame [ ] [ ]
Note: Please record NA where not applicable