Door single hung 3'3" x 7'0" high overall with frame having 11/4" thick sash and 31/4"
x 21/4" timber frame. (glazing,
ironmongery & painting measured seperately)
Per 22.75 sq.ft (3'3" x 7'0")
MATERIALS
a) Frame -
1.5 cu.ft 4" x 3" timber - = -
2 nos spur stones
6 no Fibre / plastic plugs with 4" long brass screws
2 no 5
/8" mild steel dowels 4" long
b) Sash -
14 sq.ft 11/2" planks - = -
5 sq.ft 1" planks
LABOUR
5 days carpenter
1.5 days un skilled labourer - = -
Rate per 22.75 sq.ft
Rate per 1sq.ft
Door glazed and panelled double hung 4'0" x 7'0" high overall with frame including 11/4" thick sash and 33/4" x 23/4"
frame.(glazing, iron mongery and painting measured seperately)
Per 28.00 sq.ft (4'0" x 7'0")
MATERIALS
a) Frame -
1.67 cu.ft 4" x 3" timber - = -
2 nos spur stones
6 no Fibre / plastic plugs with 4" long brass screws
2 no 5
/8" mild steel dowels 4" long
b) Sash -
16 sq.ft 11/2" planks - = -
7 sq.ft 1" planks
LABOUR
6 days carpenter
2 days un skilled labourer - = -
Rate per 28.00 sq.ft
Rate per 1sq.ft
Plywood door single hung 3'11/2" x 6'11/2" overall with frame having 11/4" thick sash and 33/4" x 23/4" frame. (iron mongery
and painting measured seperately)
Per 21.75 sq.ft (3'11/2" x 6'11/2")
MATERIALS
a) Frame -
1.8 cu.ft 4" x 3" timber - = -
2 nos spur stones
6 no Fibre / plastic plugs with 4" long brass screws
b) Sash -
1 no 6'9" x 2'9" plywood sash - = -
LABOUR
0.75 day carpenter
0.375 day un skilled labourer
0.25 day mason (fixing frame)
0.25 day un skilled labourer (do)
Rate per 21.75 sq.ft
Rate per 1sq.ft
Door ledged, braced and battened single hung 2'6" x 6'6" overall, with frame having 7/8" thick tongued & grooved planks
and 33/4" x 23/4" frame. (ironmongery and painting measured seperately)
Per 16.25 sq.ft (2'6"x 6'6")
MATERIALS
a) Frame -
1.7 cu.ft 4" x 3" timber - = -
2 nos spur stones
6 no Fibre / plastic plugs with 4" long brass screws
2 no /8" mild steel dowels 4" long
5
b) Sash -
21 sq.ft 1" thick planks - = -
3 doz 1 /4" long brass screws
1
LABOUR
2.25 day carpenter
1 day un skilled labourer
0.25 day mason (fixing frame)
0.25 day un skilled labourer (do)
Rate per 16.25 sq.ft
Rate per 1sq.ft