0% found this document useful (0 votes)
35 views1 page

Assignment 6 FINAL

Uploaded by

Pratham Nainani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

Assignment 6 FINAL

Uploaded by

Pratham Nainani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ASSIGNMENT - 6

RCC FRAMED BUILDING ESTIMATION CALCULATION


NAME - PRATHAM NAINANI SEM - IX

Item no. Particulars of items No. Length Breadth Height/ Depth Quantity Explanatory Notes Rate

1 EARTHWORK IN EXCAVATION
Columns 6 1.2 1.5 1.6 17.28 CU. M Rs 150
In between columns per CU.M
Front and back walls 2 5.06 0.23 0.15 0.35 CU.M L= 7.46 - 2.4 = 5.06
Side and internal walls 3 3.73 0.23 0.15 0.38 CU.M L= 5.23 - 1.5 = 3.73
Steps including 10 cm projection
I. 1 2.9 1.3 0.17 0.64 CU.M L= 2.7+0.1+0.1= 2.9
B= 1.2+0.1= 1.3
TOTAL 18.65 CU.M

Deduct for column on left side 1 0.815 0.6 0.17 0.083 CU.M L= 0.6+0.115+ 0.1= 0.815
B= 0.75- 0.15= 0.6
NET TOTAL 18.567 CU.M TOTAL COST
Rs 2785
2 RCC WORK 1:2:4 IN FOOTING AND COLUMN
Footing of columns Rs. 4500
Rectangular bottom 6 1.2 1.5 0.2 2.16 CU.M per CU.M
Trapezoidal portion 6
0.25/3(1.8+0.25+√0.45)= 0.22 1.32 CU.M A1= 1.2X1.5= 1.8, A2= 0.47X0.54= 0.25
h/3(A1+A2+√A1A2)
TOTAL 3.48 CU.M

Column 6 0.23 0.3 4.69 1.94 CU.M H= 3.04+ 0.6+ 1.5+ 0.45= 4.69
NET TOTAL 5.42 CU.M TOTAL COST
Rs.24390
3 12mm Thk INTERNAL PLASTER
Room 1 Rs. 650
Front and back walls 2 4 NA 3.04 24.32 SQ.M per sq m
left and right walls 2 5 NA 3.04 30.4 SQ.M
Room 2
Front and back walls 2 3 NA 3.04 18.24 SQ.M
left and right walls 2 5 NA 3.04 30.4 SQ.M
TOTAL 103.36 SQ.M
DEDUCTION
Door 1 0.9 NA 2.1 1.89 SQ.M
Opening 1 1.2 NA 2.1 2.52 SQ.M
Window 2 1.2 NA 1.8 4.32 SQ.M
TOTAL 8.73 SQ.M
NET TOTAL 94.63 SQ.M TOTAL COST
Rs.61510
4 BRICKWORK 230mm Thk IN SUPERSTRUCTURE
Room 1 Rs. 5000
Front and back walls 2 4 0.23 3.04 5.59 CU.M per CU.M
left and right walls 2 5 0.23 3.04 6.99 CU.M
Room 2
Front and back walls 2 3 0.23 3.04 4.19 CU.M
Right wall 1 5 0.23 3.04 3.49 CU.M
Steps
i 1 1.5 0.6 0.15 0.13 CU.M
ii 1 2.1 0.9 0.15 0.28 CU.M
iii 1 2.7 1.2 0.25 0.81 CU.M
TOTAL 21.48 CU.M
Deduction
Door 1 0.9 0.23 2.1 0.43 CU.M
Opening 1 1.2 0.23 2.1 0.57 CU.M
Window 2 1.2 0.23 1.8 0.99 CU.M
Lintel (L=0.9) 1 1.26 0.23 0.23 0.066 CU.M L/5= 0.9/5= 0.18 Lintel projection
Lintel (L=1.2) 3 1.68 0.23 0.23 0.26 CU.M L/5= 1.2/5=0.24 Lintel projection
TOTAL 2.31 CU.M TOTAL COST
NET TOTAL 19.17 CU.M Rs. 95850
GRAND TOTAL
Rates reffered from maharashtra jeevan pradhikaran, schedule of rates 2018- 2019
Rs. 184535