0% found this document useful (0 votes)
19 views38 pages

Mercado Chart

Uploaded by

noel.sabilano670
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views38 pages

Mercado Chart

Uploaded by

noel.sabilano670
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 38

Client/Owner Mr. & Mrs.

Albert & Baby Mercado


Project Location #67 Garnnet Street , Northview 1 Quezon City
Project : Proposed Second (2) Storey - Extension project
Subject : Project Schedule
MAY
01-06
Pct. Wt. Start Finish Duration Wk 1

A GENERAL REQUIREMENTS 150,000.00 2.58% Wk 1 Wk 3 3.00 0.86%


SUBSTRUCTURE
a.1 Wall Footings ₱ 11,759.63 0.20% Wk 4 Wk 5 2.00
b.1 Foundation Walls ₱ 6,433.43 0.11% Wk 5 Wk 6 2.00
c.1 Column Footing ₱ 213,868.23 3.68% Wk5 Wk7 3.00
d.1 Column Foundation ₱ 92,272.86 1.59%
e.1 Footing Tie Beams ₱ 199,266.83 3.42%
f.1 Ground Floor slab ₱ 240,655.21 4.14%
SECOND FLOOR
a.2 Column Support ₱ 174,504.03 3.00% Wk 17 Wk 18 2.00
b.2 Second floor girders ₱ 427,734.86 7.35%
b.3 Roof Framing Girders ₱ 306,910.62 5.27%
b.4 2nd Floor Slab ₱ 669,513.32 11.51%
b.5 Cancrete Canopy ₱ 22,019.81 0.38%
b.6 Balcony Railing ₱ 27,263.60 0.47%
b.7 Exterior Enclusure ₱ 537,123.00 9.23%
b.8 Exterior Painting ₱ 113,652.00 1.95%
b.9 Exterior Wall Tiles ₱ 42,480.00 0.73%
b.10 Windows
b.11 Rafter Trusses (RT-1) ₱ 533,123.00 9.16% Wk 19 Wk 20 2.00
b.12 Roofing System ₱ 213,091.00 3.66% Wk 20 Wk 22 3.00
INTERIORS
c.1 Interior Masonry ₱ 212,305.85 3.65%
c.2 Doors ₱ 39,900.00 0.69%
c.3 Stairs ₱ 75,891.62 1.30%
c.4 Wall Finishes ₱ 416,924.26 7.17%
c.5 Floor Finishes ₱ 81,880.00 1.41%
c.6 Ceiling Finishes ₱ 127,664.30 2.19%
c.7 Painting ₱ 76,860.00 1.32%
PLUMBING/SANITARY
d.1 Plumbing Fixture ₱ 20,700.00 0.36% Wk 22 Wk 37 16.00
d.2 Cold Waterlines ₱ 43,963.00 0.76% Wk 22 Wk 41 20.00
d.3 Waste Pipes & Fittings ₱ 73,848.00 1.27% Wk 37 Wk 42 6.00
d.4 Septic Tank ₱ 33,584.00 0.58% Wk 39 Wk 52 14.00
d.5 Rain Water Drainage ₱ 333,976.00 5.74% Wk 22 Wk 53 32.00
d.e Rain water equipment ₱ 48,626.67 0.84%
ELECTRICAL
e.1 Service Entrance & Meter Center ₱ 28,200.00 0.48%
e.2 Panel Boards ₱ 25,200.00 0.43%
e.3 Branch Wiring ₱ 120,338.00 2.07%
e.4 Lighting Controls ₱ 16,347.00 0.28% Wk 39 Wk 50 12.00
e.5 Lighting Fixtures ₱ 28,190.00 0.48% Wk 13 Wk 50 16.00
e.6 Wirings ₱ 32,236.00 0.55% Wk 13 Wk 54 18.00
₱ 5,818,306.13 100.00%

Proposed Work Progress 0.86%


Proposed Cummulative Work Progress 0.86%
Actual Weekly
Actual Cummulative
MAY MAY-JUNE JUNE JUNE-JULY JULY JULY-AUG AUGUST
08-13 15-20 22-27 29-03 05-10 12-17 19-24 26-01 03-8 10-15 17-22 24-29 30-05 06-12 12-17 18-24
Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16 Wk 17
0.86% 0.86%

0.10% 0.10%
0.06% 0.06%
1.23% 1.23% 1.23%

1.50%
0.03% 0.03% 0.03% 0.03% 0.03%
0.03% 0.03% 0.03% 0.03% 0.03%

0.86% 0.96% 0.16% 1.28% 1.23% 1.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.06% 0.06% 1.56%
1.72% 2.58% 2.73% 4.01% 5.24% 6.47% 6.47% 6.47% 6.47% 6.47% 6.47% 6.53% 6.59% 6.65% 6.71% 8.27%
AUG-SEPT SEPTEMBER SEPT-OCT OCTOBER OCT-NOV NOVEMBER DECEMBER
25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-02 03-08 09-15 16-22 23-28 01-07
Wk 18 Wk 19 Wk 20 Wk 21 Wk 22 Wk 23 Wk 24 Wk 25 Wk 26 Wk 27 Wk 28 Wk 29 Wk 30 Wk 31 Wk 32

1.50%
4.58% 4.58%
1.22% 1.22% 1.22%

0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%

0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%

0.03%
0.03% 0.03% 0.03%

1.56% 4.61% 5.83% 1.22% 1.46% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%
9.83% 14.44% 20.28% 21.50% 22.96% 23.20% 23.44% 23.68% 23.91% 24.15% 24.39% 24.63% 24.87% 25.11% 25.35%
DECEMBER MAR-APR APRIL APR-MAY MAY JUNE

02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21
Wk 33 Wk 34 Wk 35 Wk 36 Wk 37 Wk 38 Wk 39 Wk 40 Wk 41 Wk 42 Wk 43 Wk 44 Wk 45 Wk 46 Wk 47 Wk 48
0.02% 0.02% 0.02% 0.02% 0.02%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%

0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
0.03% 0.03% 0.03% 0.03%

0.24% 0.24% 0.24% 0.24% 0.45% 0.43% 0.49% 0.49% 0.52% 0.49% 0.48% 0.27% 0.31% 0.31% 0.31% 0.31%
25.59% 25.83% 26.07% 26.31% 26.55% 26.98% 27.47% 27.96% 28.49% 28.97% 29.46% 29.73% 30.04% 30.34% 30.65% 30.95%
JUNE JUN-JUL JULY

22-28 29-05 06-12 13-19 20-26 27-31


Wk 49 Wk 50 Wk 51 Wk 52 Wk 53 Wk 54
0.04% 0.04% 0.04% 0.04%
0.18% 0.18% 0.18% 0.18% 0.18%

0.02% 0.02%
0.03% 0.03%
0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

0.31% 0.31% 0.25% 0.25% 0.21% 0.03%


31.26% 31.56% 31.81% 32.06% 32.28% 32.31%
Client/Owner Mr. & Mrs. Albert and Baby Mercado
Project Location #67 Garnet Street , Northview 1 Batasan Hills. Quezon City
Project : Proposed Two (2) Storey - Extension with Roof Deck
Subject : Project Schedule / Activity Chart
MAY MAY-JUN JUNE JUNE-JULY
01-06 08-13 15-20 22-27 29-03 05-10 12-17 19-24 26-01
Pct. Wt. Start Finish Duration Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9

1 General Requirements 110,000.00 1.82% Wk 1 Wk 3 4.00 0.45% 0.45% 0.45% 0.45%


2 Concreting Works 2,440,830.43 40.38% Wk 3 Wk 14 13.00 3.11% 3.11% 3.11% 3.11% 3.11% 3.11%
3 Plastering & Finishing (CHB Walls) 750,049.35 12.41% Wk 14 Wk 17 6.00
4 Rafter Trusses (RT-1) 533,123.00 8.82% Wk 15 Wk 17 3.00
5 Roofing Works 213,091.53 3.53% Wk 17 Wk 18 3.00
6 Doors (with Hardwares) & Windows 196,795.55 3.26% Wk 18 Wk 19 3.00
7 Exterior & Interior Partitions & Exterior Finishing 498,804.26 8.25% Wk 19 Wk 23 14.00
8 Woodworks & Ceilings Boards 127,664.30 2.11% Wk 22 Wk 23 5.00
9 Interior Finising (Walls & Ceilings)Painting 190,512.00 3.15% Wk 24 Wk 27 7.00
10 Exterior Tiling 42,480.80 0.70% Wk 26 Wk 27 6.00
11 Ironmongeries & Stairs 119,445.85 1.98% Wk 27 Wk 29 7.00
12 Plumbing/Sanitary Works 554,698.77 9.18% Wk 12 Wk 32 17.00
13 Electrical Works 266,858.33 4.42% Wk 11 Wk 36 19.00
6,044,354.17 100.00%

Proposed Work Progress 0.45% 0.45% 0.45% 3.11% 3.11% 3.11% 3.11% 3.11% 3.11%
Proposed Cummulative Work Progress 0.45% 0.91% 1.36% 4.47% 7.58% 10.68% 13.79% 16.90% 20.00%
Actual Weekly
Actual Cummulative
JULY JULY-AUG AUGUST AUG-SEPT SEPTEMBER OCTOBER OCT-NOV NOVEMBER DEC-TURN OVER
03-8 10-15 17-22 24-29 31-05 07-12 14-19 21-26 28-02 04-09 11-16 18-23 23-30 02-07 09-14 16-21 23-28 30-04 06-11 13-18 20-25 27-02 04-09
Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16 Wk 17 Wk 18 Wk 19 Wk 20 Wk 21 Wk 22 Wk 23 Wk 24 Wk 25 Wk 26 Wk 27 Wk 28 Wk 29 Wk 30 Wk 31 Wk 32

3.11% 3.11% 3.11% 3.11% 3.11% 3.11% 3.11%


2.07% 2.07% 2.07% 2.07% 2.07% 2.07%
2.94% 2.94% 2.94%
1.18% 1.18% 1.18%
1.09% 1.09% 1.09%
0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
0.42% 0.42% 0.42% 0.42% 0.42%
0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45%
0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28%
0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54%
0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23%

3.34% 3.34% 3.88% 5.95% 5.71% 8.65% 8.11% 6.42% 4.02% 3.62% 2.45% 2.45% 1.64% 2.18% 2.63% 2.63% 2.63% 2.63% 1.93% 1.81% 1.55% 1.36% 0.59%
23.34% 26.68% 30.56% 36.51% 42.22% 50.87% 58.99% 65.40% 69.42% 73.04% 75.49% 77.94% 79.58% 81.76% 84.40% 87.03% 89.66% 92.30% 94.23% 96.04% 97.59% 98.96% 100%
DEC-TURN OVER
11-16
Wk 31

T
U
R
N

O
V
E
R

W
E
E
K
Client/Owner
Project Location
Project : Proposed Three (3) Storey - Nine (9) Bedroom Residence with Roof Deck
Subject : Project Schedule / S-Curve / GANTT Chart

Pct. Wt. Start Finish Duration


100%
1 General Requirements 304,920.00 4.03% Wk 1 Wk 3 3.00

2 Concreting Works 1,853,637.76 24.49% Wk 4 Wk 23 90%


20.00
3 Plastering & Finishing (CHB Walls) 29,172.00 0.39% Wk 17 Wk 18 2.0080%
4 Rafter Trusses (RT-1) 28,900.85 0.38% Wk 19 Wk 20 2.00
70%
5 Roofing Works 54,723.83 0.72% Wk 20 Wk 22 3.00
60%
6 Doors & Windows (with Hardwares) 507,540.00 6.71% Wk 22 Wk 37 16.00
7 Exterior & Interior Partitions & Exterior Finishing 1,390,556.42 18.37% Wk 22 Wk 41 50%
20.00
8 Woodworks & Ceilings Boards 93,886.65 1.24% Wk 37 Wk 42 6.0040%
9 Interior Finising (Walls & Ceilings) 925,584.00 12.23% Wk 39 Wk 52 14.00
30%
10 Interior Tiling 1,543,087.92 20.39% Wk 22 Wk 53 32.00
11 Ironmongeries 252,952.92 3.34% Wk 39 Wk 50 20%
12.00
12 Plumbing/Sanitary Works 140,771.32 1.86% Wk 13 Wk 50 16.00
10%
13 Electrical Works 442,200.00 5.84% Wk 13 Wk 54 18.00
0%
7,567,933.67 100.00% 1 2

Proposed Work Progress


Proposed Cummulative Work Progress
Actual Weekly
Actual Cummulative
AUGUST AUG-SEP SEPTEMBER SEP-OCT OCTOBER OCT-NOV NOVEMBER
01-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-02 03-09 10-16 17-23 24-29 30-05 06-12 12-17
Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16
100%
1.34% 1.34% 1.34%
90% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22%
80%

70%

60%

50%

40%

30%

20%

10% 0.12% 0.12% 0.12% 0.12%


0.32% 0.32% 0.32% 0.32%
0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1.34% 1.34% 1.34% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.67% 1.67% 1.67% 1.67%
1.34% 2.69% 4.03% 5.25% 6.48% 7.70% 8.93% 10.15% 11.38% 12.60% 13.83% 15.05% 16.72% 18.38% 20.05% 21.71%
NOVEMBER NOV-DEC DECEMBER DEC-JAN JANUARY JAN-FEB FEBRUARY

18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-02 03-08 09-15 16-22 23-28
Wk 17 Wk 18 Wk 19 Wk 20 Wk 21 Wk 22 Wk 23 Wk 24 Wk 25 Wk 26 Wk 27 Wk 28 Wk 29 Wk 30 Wk 31

S Curve
1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22%
0.19% 0.19%
0.19% 0.19%
0.24% 0.24% 0.24%
0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42%
0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92%

0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%

0.12% 0.12%
0.32% 0.32% 0.32% 0.32%
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

1.86% 1.86% 1.74% 1.98% 1.47% 3.44% 3.20% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98% 1.98%
23.57% 25.43% 27.17% 29.15% 30.62% 34.06% 37.26% 39.23% 41.21% 43.18% 45.16% 47.13% 49.11% 51.08% 53.06%
MARCH MAR-APR APRIL APR-MAY MAY JUNE

01-07 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14
Wk 32 Wk 33 Wk 34 Wk 35 Wk 36 Wk 37 Wk 38 Wk 39 Wk 40 Wk 41 Wk 42 Wk 43 Wk 44 Wk 45 Wk 46 Wk 47

0.42% 0.42% 0.42% 0.42% 0.42% 0.42%


0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92%
0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
0.87% 0.87% 0.87% 0.87% 0.87% 0.87% 0.87% 0.87% 0.87%
0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%
0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28%
0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
0.32% 0.32% 0.32%
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48

1.98% 1.98% 1.98% 1.98% 1.98% 2.18% 1.76% 2.91% 2.91% 3.03% 2.11% 2.12% 1.91% 2.23% 2.23% 2.23%
55.03% 57.01% 58.98% 60.96% 62.93% 64.91% 66.67% 69.59% 72.50% 75.53% 77.64% 79.76% 81.66% 83.90% 86.13% 88.36%
JUNE JUN-JUL JULY

15-21 22-28 29-05 06-12 13-19 20-26 27-31


Wk 48 Wk 49 Wk 50 Wk 51 Wk 52 Wk 53 Wk 54

0.87% 0.87% 0.87% 0.87% 0.87%


0.64% 0.64% 0.64% 0.64% 0.64% 0.64%
0.28% 0.28% 0.28%
0.12% 0.12% 0.12%
0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32%
47 48 49 50 51 52 53 54

2.23% 2.23% 2.23% 1.84% 1.84% 0.96% 0.32%


90.59% 92.82% 95.05% 96.88% 98.72% 99.68% 100.00%
Client/Owner
Project Location
Project : Proposed Five (5) Storey - Nine (9) Bedroom Residence with Roof Deck
Subject : Project Schedule / S-Curve / GANTT Chart

Pct. Wt.
1 General Requirements 304,920.00 3.48%
2 Concreting Works 1,853,919.09 21.17%
3 Plastering & Finishing (CHB Walls) 29,172.00 0.33%
4 Rafter Trusses (RT-1) 28,900.85 0.33%
5 Roofing Works 54,723.83 0.62%
6 Doors & Windows (with Hardwares) 790,416.00 9.02%
7 Exterior & Interior Partitions & Exterior Finishing 1,687,267.01 19.26%
8 Woodworks & Ceilings Boards 107,712.74 1.23%
9 Interior Finising (Walls & Ceilings) 845,064.00 9.65%
10 Interior Tiling 2,115,256.84 24.15%
11 Ironmongeries 252,952.92 2.89%
12 Plumbing/Sanitary Works 160,571.32 1.83%
13 Electrical Works 528,000.00 6.03%
8,758,876.59 100.00%

Proposed Work Progress


Proposed Cummulative Work Prog
Actual Weekly
Actual Cummulative

1,404,484.16
AUGUST AUG-SEP SEPTEMBER
01-07 08-14 15-21 22-28 29-04 05-11 12-18
Start Finish Duration
100% Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7
Wk 1 Wk 3 3.00 1.16% 1.16% 1.16%
90%
Wk 4 Wk 23 20.00 1.06% 1.06% 1.06% 1.06%
Wk 17 Wk 18 80%
2.00
Wk 19 Wk 20 2.00
70%
Wk 20 Wk 22 3.00
60%
Wk 22 Wk 37 16.00
Wk 22 Wk 41 50%
20.00
Wk 37 Wk 42 6.00
40%
Wk 39 Wk 52 14.00
30%
Wk 22 Wk 53 32.00
Wk 39 Wk 50 12.00
20%
Wk 13 Wk 50 16.00
10%
Wk 13 Wk 54 18.00
0%
1 2 3 4 5 6 7 8

oposed Work Progress 1.16% 1.16% 1.16% 1.06% 1.06% 1.06% 1.06%
oposed Cummulative Work Progress 1.16% 2.32% 3.48% 4.54% 5.60% 6.66% 7.71%
ual Weekly
ual Cummulative

0.3 0.02
lc cont tc
421,345.25 28,089.68 1,853,919.09
SEPTEMBER SEP-OCT OCTOBER OCT-NOV NOVEMBER
19-25 26-02 03-09 10-16 17-23 24-29 30-05 06-12 12-17 18-24
Wk 8 Wk 9 Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16 Wk 17

1.06% 1.06% 1.06% 1.06% 1.06% 1.06% 1.06% 1.06% 1.06% 1.06%
0.17%

0.11% 0.11% 0.11% 0.11% 0.11%


0.33% 0.33% 0.33% 0.33% 0.33%

7 8 9 10 11 12 13 14 15 16 17 18 19

1.06% 1.06% 1.06% 1.06% 1.06% 1.51% 1.51% 1.51% 1.51% 1.67%
8.77% 9.83% 10.89% 11.95% 13.01% 14.51% 16.02% 17.53% 19.04% 20.71%
NOV-DEC DECEMBER DEC-JAN JANUARY JAN-FEB
25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-02
Wk 18 Wk 19 Wk 20 Wk 21 Wk 22 Wk 23 Wk 24 Wk 25 Wk 26 Wk 27

S Curve
1.06% 1.06% 1.06% 1.06% 1.06% 1.06%
0.17%
0.16% 0.16%
0.21% 0.21% 0.21%
0.56% 0.56% 0.56% 0.56% 0.56% 0.56%
0.96% 0.96% 0.96% 0.96% 0.96% 0.96%

0.75% 0.75% 0.75% 0.75% 0.75% 0.75%

0.11%
0.33% 0.33% 0.33%

17 18 19 20 21 22 23 24 25 26 27 28 29

1.67% 1.56% 1.77% 1.27% 3.55% 3.34% 2.28% 2.28% 2.28% 2.28%
22.39% 23.94% 25.71% 26.98% 30.53% 33.87% 36.15% 38.43% 40.71% 42.99%
FEBRUARY MARCH MAR-APR

03-08 09-15 16-22 23-28 01-07 02-08 09-15 16-22 23-29 30-05
Wk 28 Wk 29 Wk 30 Wk 31 Wk 32 Wk 33 Wk 34 Wk 35 Wk 36 Wk 37

S Curve

0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56%
0.96% 0.96% 0.96% 0.96% 0.96% 0.96% 0.96% 0.96% 0.96% 0.96%
0.20%

0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%

27 28 29 30 31 32 33 34 35 36 37 38 39

2.28% 2.28% 2.28% 2.28% 2.28% 2.28% 2.28% 2.28% 2.28% 2.49%
45.27% 47.56% 49.84% 52.12% 54.40% 56.68% 58.97% 61.25% 63.53% 65.81%
APRIL APR-MAY MAY JUNE

06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21
Wk 38 Wk 39 Wk 40 Wk 41 Wk 42 Wk 43 Wk 44 Wk 45 Wk 46 Wk 47 Wk 48

0.96% 0.96% 0.96% 0.96%


0.20% 0.20% 0.20% 0.20% 0.20% 0.20%
0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69%
0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%
0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
0.33% 0.33% 0.33% 0.33%
37 38 39 40 41 42 43 44 45 46 47 48 49

1.92% 2.85% 2.85% 2.97% 2.00% 2.00% 1.80% 2.13% 2.13% 2.13% 2.13%
67.73% 70.59% 73.44% 76.41% 78.41% 80.41% 82.21% 84.34% 86.48% 88.61% 90.75%
JUNE JUN-JUL JULY

22-28 29-05 06-12 13-19 20-26 27-31


Wk 49 Wk 50 Wk 51 Wk 52 Wk 53 Wk 54

0.69% 0.69% 0.69% 0.69%


0.75% 0.75% 0.75% 0.75% 0.75%
0.24% 0.24%
0.11% 0.11%
0.33% 0.33% 0.33% 0.33% 0.33% 0.33%
47 48 49 50 51 52 53 54

2.13% 2.13% 1.78% 1.78% 1.09% 0.33%


92.88% 95.01% 96.79% 98.57% 99.66% 100.00%
FEBRUARY FEB/MAR MARCH
09-11 12-18 19-25 26-04 05-11 12-18
Pct. Wt. Start Finish Duration Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6
2.39% Wk 1 Wk 15 15.00 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%
#REF! Wk 3 Wk 0 -2.00 #REF! #REF! #REF! #REF!
#REF! Wk 5 Wk 0 -4.00 #REF! #REF!
#REF! Wk 0 Wk 0 1.00
#REF! Wk 0 Wk 0 1.00
#REF! Wk 0 Wk 0 1.00 231,000.00 2.39% General Requirements
#REF! Wk 0 Wk 0 1.00 4,423,873.19 45.82% Concreting Works
#REF! Wk 0 Wk 0 1.00 22,100.00 0.23% Plastering & Finishing (CHB Walls)
#REF! Wk 0 Wk 0 1.00 21,894.58 0.23% Rafter Trusses (RT-1)
#REF! Wk 17 Wk 0 -16.00 41,457.45 0.43% Roofing Works
#REF! Wk 0 Wk 0 1.00 598,800.00 6.20% Doors & Windows (with Hardwares)
#REF! Wk 0 Wk 0 1.00 81,600.56 0.85% Woodworks & Ceilings Boards
#REF! Wk 17 Wk 0 -16.00 640,200.00 6.63% Interior Finising (Walls & Ceilings)
#REF! Wk 0 Wk 0 1.00 1,278,232.58 13.24% Exterior & Interior Partitions & Exteri
#REF! Wk 0 Wk 0 1.00 1,602,467.30 16.60% Interior Tiling
#REF! Wk 0 Wk 0 1.00 191,631.00 1.98% Ironmongeries
#REF! Wk 0 Wk 0 1.00 121,644.94 1.26% Plumbing/Sanitary Works
#REF! Wk 0 Wk 0 1.00 400,000.00 4.14% Electrical Works
#REF! 9,654,901.60 100.00%

0.16% 0.16% #REF! #REF! #REF! #REF!


0.16% 0.32% #REF! #REF! #REF! #REF!
0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MARCH MAR/APR APRIL APR/MAY MAY
19-25 26-01 02-08 09-15 16-22 23-29 30-06 07-13 14-20 21-27
Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12 Wk 13 Wk 14 Wk 15 Wk 16
0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

equirements

& Finishing (CHB Walls)

Windows (with Hardwares)


ks & Ceilings Boards
nising (Walls & Ceilings)
Interior Partitions & Exterior Finishing

Sanitary Works

#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MAY/JUN
28-03
Wk 17

#REF!
#REF!
#REF!

#REF!

#REF!

#REF!
#REF!
0.00%
0.00%

You might also like