CMT Cof
CMT Cof
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
1. CEMENT MORTAR
2. CONCRETE WORK
1 CEMENT CONC.1:1:2 CUM 1 12.20 15.25 30.50 3050 610 1220 4880
2 CEMENT CONC.1:1.5:3 CUM 1 8.00 15.00 30.00 2000 600 1200 3800
3 CEMENT CONC.1:2:4 CUM 1 6.40 16.00 32.00 1600 640 1280 3520
4 CEMENT CONC.1:3:6 CUM 1 4.40 16.50 33.00 1100 660 1320 3080
5 CEMENT CONC.1:4:8 CUM 1 3.40 17.00 34.00 850 680 1360 2890
6 CEMENT CONC.1:5:10 CUM 1 2.60 16.25 32.50 650 650 1300 2600
3. D.P.C
4. BRICK WORK
1 RR IN FOUNDN. 1:6 WITH C.C 1:6:12 CUM 1 1.65 12.375 412.5 495 0 908
2 CR IN FOUNDN. 1:6 CUM 1 1.50 11.25 0 375 450 0 825
3 PLAIN ASHLAR IN S/S 1:6 WITH PTNG.1:2 CUM 1 1.08 8.1 0 270 324 0 594
7. MARBLE WORK
1 20MM TH.WALL LINING OVER C.M.12MM SQM 1 0.2088 0.783 0 52.2 18.7 31.32 0 102
1:3 WITH CMT.SLRY.& PTNG.WHT.CMT 0.034
2 20MM TH.COUNTER OVER 20MM C.M.1:4 SQM 1 0.1064 0.532 0 26.6 21.28 0 48
(0.2 -1.0 SQM. AREA OF EACH SLAB)
8. WOOD WORK
1 HOLD FAST IN CC 1:2:4 NO. 1 0.022 0.055 0.11 5.5 2.2 4.4 12
9. STEEL WORK
10. FLOORING
BRICK FLOORING
1 C.M. 1:4 SQM 1 0.37 1.85 0 92.5 74 0 167
2 C.M. 1:6 SQM 1 0.257 1.9275 0 64.25 77.1 0 141
C.C.FLOORING
1 25MM TH.1:2:4 WITH FLOATING COAT SQM 1 0.244 0.5 1 61 20 40 121
2 40MM TH.1:2:4 WITH FLOATING COAT SQM 1 0.34 0.74 1.48 85 29.6 59.2 174
Page 1
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
3 50MM TH.1:2:4 WITH FLOATING COAT SQM 1 0.404 0.9 1.8 101 36 72 209
4 75MM TH.1:2:4 WITH FLOATING COAT SQM 1 0.564 1.3 2.6 141 52 104 297
5 C.C.HARDNER FLOORING
i) 52MM TH. WITH 40MM UNDER LAYER SQM 1 0.462 1.045 2.09 115.5 41.8 83.6 241
ii) 62MM TH. WITH 50MM UNDER LAYER SQM 1 0.526 1.205 2.41 131.5 48.2 96.4 276
18MM TH. SKIRTING WITH C.M 1:3 &
6 SQM 1 0.28 0.885 0 70 35.4 0 105
FLT.COAT
21MM TH. SKIRTING WITH C.M 1:3 &
7 SQM 1 0.3102 0.99825 0 77.55 39.93 0 117
FLT.COAT
TERRAZO FLOORING
1 40MM TH. (34 + 6)MM
i) GREY CEMENT SQM 1 0.339 0.645 1.29 84.75 25.8 51.6 162
ii) WHITE CEMENT SQM 1 0.258 0.645 1.29 64.5 44.55 25.8 51.6 186
0.081
iii) WITH 50% WHITE CEMENT SQM 1 0.2984 0.645 1.29 74.6 22.22 25.8 51.6 174
0.0404
2 40MM TH. (31 + 9)MM
i) GREY CEMENT SQM 1 0.3566 0.6025 1.205 89.15 24.1 48.2 161
ii) WHITE CEMENT SQM 1 0.241 0.6025 1.205 60.25 63.58 24.1 48.2 196
0.1156
iii) WITH 50% WHITE CEMENT SQM 1 0.2988 0.6025 1.205 74.7 31.79 24.1 48.2 179
0.0578
3 40MM TH. (28 + 12)MM
i) GREY CEMENT SQM 1 0.3814 0.5485 1.097 95.35 21.94 43.88 161
ii) WHITE CEMENT SQM 1 0.2194 0.5485 1.097 54.85 89.1 21.94 43.88 210
0.162
iii) WITH 50% WHITE CEMENT SQM 1 0.3004 0.5485 1.097 75.1 44.55 21.94 43.88 185
0.081
Page 2
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
5,6 OR 7 MM TH. TILES IN
1 SQM 1 0.1884 0.7065 0 47.1 27.5 28.26 0 103
FLRNG/SKG./DADO
12MM TH C.M. 1:3 & JNTNG WHT. CEMENT 0.05
10mm Th.CERAMIC TILES OVER 20MM
2 SQM 1 0.2484 1.242 0 62.1 27.5 49.68 0 139
C.M.
1:4 GROUTING WITH WHITE CEMENT 0.05
TILE WORK IN SKIRTING,RISERS,DADO
3 SQM 1 0.2088 0.783 0 52.2 27.5 31.32 0 111
ON
12MM TH. BED C.M.1:3 WITH CEMENT
0.05
SLURRY
POINTING WITH WHITE CEMENT
Page 3
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
MARBLE STONE FLOORING
20MM TH. OVER 20MM C.M. 1:4 WITH
1 SQM 1 0.27024 1.35 0 67.56 54.048 0 122
GREY
30MM TH. OVER 20MM C.M. 1:4 WITH
2 SQM 1 0.2726 1.36 0 68.15 54.52 0 123
GREY
40MM TH. OVER 20MM C.M. 1:4 WITH
3 SQM 1 0.2774 1.39 0 69.35 55.48 0 125
GREY
4 EXTRA IF WHITE CEMENT FOR JOINTING SQM 1 0.0152 0 0 8.36 0 0 8
DADO 30MM TH. OVER 12MM C.M. 1:3
5 SQM 1 0.2468 0.93 0 61.7 37.02 0 99
GREY
KOTA STONE FLOORING
25MM TH. OVER 20MM C.M. 1:4 WITH
1 SQM 1 0.2982 1.49 0 74.55 59.64 0 134
GREY
30MM TH. OVER 20MM C.M. 1:4 WITH
2 SQM 1 0.3062 1.53 0 76.55 61.24 0 138
GREY
40MM TH. OVER 20MM C.M. 1:4 WITH
3 SQM 1 0.3222 1.61 0 80.55 64.44 0 145
GREY
DADO 25MM TH. OVER 12MM C.M. 1:3
4 SQM 1 0.2748 1.03 0 68.7 41.22 0 110
GREY
SAND STONE FLOORING
40MM TH. OVER 20MM C.M. 1:5 WITH
1 SQM 1 0.155 0.97 0 38.75 38.75 0 78
GREY
WITH JOINTS FINISH FLUSH
40MM TH. OVER 20MM C.M. 1:5 WITH
2 SQM 1 0.1862 1.16 0 46.55 46.55 0 93
GREY
POINTING WITH C.M.1:2
40MM TH. OVER 20MM C.M. 1:5 WITH
3 SQM 1 0.1656 1.04 0 41.4 41.4 0 83
GREY
WITH JOINTS 5MM TH.FINISH FLUSH
40MM TH. OVER 20MM C.M. 1:5 WITH
4 SQM 1 0.1968 1.23 0 49.2 49.2 0 98
GREY
WITH JOINTS 5MM &POINTING WITH
C.M.1:2
11. ROOFING
12. FINISHING
CEMENT PLASTER
1 12 mm 1:2 SQM 1 0.1958 0.49 0 48.95 19.58 0 69
2 12 mm 1:4 SQM 1 0.1094 0.55 0 27.35 21.88 0 49
3 12 mm 1:6 SQM 1 0.072 0.54 0 18 21.6 0 40
4 15 mm 1:2 SQM 1 0.234 0.59 0 58.5 23.4 0 82
5 15 mm 1:4 SQM 1 0.1308 0.65 0 32.7 26.16 0 59
6 15 mm 1:6 SQM 1 0.086 0.65 0 21.5 25.8 0 47
7 20 mm 1:2 SQM 1 0.3046 0.76 0 76.15 30.46 0 107
8 20 mm 1:4 SQM 1 0.1702 0.85 0 42.55 34.04 0 77
9 20 mm 1:6 SQM 1 0.112 0.84 0 28 33.6 0 62
CEMENT PLASTER WITH FLOATING COAT
1 12 mm 1:3 SQM 1 0.1908 0.55 0 47.7 22.02 0 70
2 12 mm 1:4 SQM 1 0.1534 0.55 0 38.35 21.88 0 60
3 15 mm 1:3 SQM 1 0.2194 0.66 0 54.85 26.31 0 81
4 15 mm 1:4 SQM 1 0.1748 0.65 0 43.7 26.16 0 70
Page 4
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
5 20 mm 1:3 SQM 1 0.2724 0.86 0 68.1 34.26 0 102
6 20 mm 1:4 SQM 1 0.2142 0.85 0 53.55 34.04 0 88
Page 5
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
CEMENT PLASTER IN TWO COATS
1 18MM TH. U/L 12mm 1:5 & T/L 6mm 1:6 SQM 1 0.1252 0.78 0 31.3 31.3 0 63
2 18MM TH. U/L 12mm 1:5 & T/L 6mm 1:3 SQM 1 0.1626 1.02 0 40.65 40.65 0 81
ROUGH CAST U/L 12mm 1:4 & T/L 10mm
3 SQM 1 0.2318 1.16 0 57.95 46.36 0 104
1:3
ROUGH CAST U/L 12mm 1:5 & T/L 10mm
4 SQM 1 0.2116 1.32 0 52.9 52.9 0 106
1:3
ROUGH CAST U/L 12mm 1:6 & T/L 10mm
5 SQM 1 0.1944 1.46 0 48.6 58.32 0 107
1:3
6 MM CEMENT PLASTER
1 6 mm 1:4 SQM 1 0.0548 0.274 0 13.7 10.96 0 25
2 6 mm 1:3 WITH FLOATING COAT SQM 1 0.1174 0.275 0 29.35 11.01 0 40
3 NEAT CEMENT PUNNING SQM 1 0.044 0 0 11 0 0 11
TERRAZO PLASTER
1 18MM TH. U/L 12mm 1:3 & T/L 6mm - GREY SQM 1 0.2328 0.873 0 58.2 34.92 0 93
18MM TH. U/L 12mm 1:3 & T/L 6mm -
2 SQM 1 0.1468 0.551 0 36.7 47.3 22.02 0 106
WHITE
0.086
WASHED STONE GRIT PLASTER
U/L 12mm 1:4 & T/L 15mm 1:0.5:2 I/C
1 SQM 1 0.3534 0.55 0 88.35 21.88 0 110
SLURRY
13. MISCELLANEOUS
1 PLINTH PROTECTION (50mm TH. 1:3:6) SQM 1 0.22 0.825 1.65 55 33 66 154
14. SANITARY
Page 6
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
S.W/RCC PIPES
1 JOINTING S.W.PIPE WITH 1:1
i) 100 mm dia. RMT 1 0.0434 0.054 0 10.85 2.17 0 13
ii) 150 mm dia. RMT 1 0.0646 0.081 0 16.15 3.23 0 19
iii) 200 mm dia. RMT 1 0.0866 0.108 0 21.65 4.33 0 26
iv) 230 mm dia. RMT 1 0.0974 0.122 0 24.35 4.87 0 29
v) 250 mm dia. RMT 1 0.108 0.135 0 27 5.4 0 32
2 JOINTING S.W.PIPE WITH 1:3
i) 100 mm dia. RMT 1 0.0214 0.080 0 5.35 3.21 0 9
ii) 150 mm dia. RMT 1 0.032 0.120 0 8 4.8 0 13
iii) 200 mm dia. RMT 1 0.0426 0.160 0 10.65 6.39 0 17
iv) 230 mm dia. RMT 1 0.048 0.180 0 12 7.2 0 19
v) 250 mm dia. RMT 1 0.0534 0.200 0 13.35 8.01 0 21
3 C.C.1:5:10 ALROUND S.W.PIPES
i) 100 mm dia. RMT 1 0.3848 2.405 4.81 96.2 96.2 192.4 385
ii) 150 mm dia. RMT 1 0.4706 2.941 5.883 117.65 117.65 235.3 471
iii) 200 mm dia. RMT 1 0.5486 3.429 6.858 137.15 137.15 274.3 549
iv) 230 mm dia. RMT 1 0.6006 3.754 7.508 150.15 150.15 300.3 601
v) 250 mm dia. RMT 1 0.6344 3.965 7.930 158.6 158.6 317.2 634
C.C.1:5:10 UPTO HAUNCHES OF
4
S.W.PIPES
i) 100 mm dia. RMT 1 0.1828 1.143 2.285 45.7 45.7 91.4 183
ii) 150 mm dia. RMT 1 0.2964 1.853 3.705 74.1 74.1 148.2 296
iii) 200 mm dia. RMT 1 0.3484 2.178 4.355 87.1 87.1 174.2 348
iv) 230 mm dia. RMT 1 0.3822 2.389 4.778 95.55 95.55 191.1 382
v) 250 mm dia. RMT 1 0.4056 2.535 5.070 101.4 101.4 202.8 406
5 GULLY TRAP NO. 1 0.54 135 0 0 135
6 JOINTING R.C.C PIPE WITH 1:2
i) 100 mm dia. RMT 1 0.01 0.025 2.5 1 0 4
ii) 150 mm dia. RMT 1 0.012 0.03 3 1.2 0 4
iii) 250 mm dia. RMT 1 0.018 0.045 4.5 1.8 0 6
iv) 300 mm dia. RMT 1 0.022 0.055 5.5 2.2 0 8
v) 450 mm dia. RMT 1 0.048 0.12 12 4.8 0 17
vi) 500 mm dia. RMT 1 0.052 0.13 13 5.2 0 18
vii) 600 mm dia. RMT 1 0.064 0.16 16 6.4 0 22
viii) 700 mm dia. RMT 1 0.074 0.185 18.5 7.4 0 26
ix) 800 mm dia. RMT 1 0.084 0.21 21 8.4 0 29
x) 900 mm dia. RMT 1 0.098 0.245 24.5 9.8 0 34
xi) 1000 mm dia. RMT 1 0.11 0.275 27.5 11 0 39
xii) 1100 mm dia. RMT 1 0.122 0.305 30.5 12.2 0 43
xiii) 1200 mm dia. RMT 1 0.136 0.34 34 13.6 0 48
Page 7
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
3 9.75 m deep NO. 1 37.82 9455 0 0 9455
EXTRA FOR DEPTH FOR MANHOLES
1 FROM 2.45m TO 4.25m RMT 1 2.34 585 0 0 585
2 BEYOND 4.25m TO 9.75m RMT 1 3.80 950 0 0 950
3 BEYOND 9.75m RMT 1 4.70 1175 0 0 1175
Page 8
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
CIRCULAR TYPE BRICK MASONARY
MANHOLES
1 INT.BOT.DIA.-91cm & TOP DIA.-56cm
BRICK WORK - 1:4
FOUNDATION CONC. - 1:3:6
INSIDE PLASTER - 12mm 1:3 WITH NEAT
CMNT.
CONC. TOP SLAB - 1:2:4
C.C.CHANNEL - 1:2:4 WITH NEAT CEMENT
a 0.91 m deep NO. 1 5.50 1375 0 0 1375
b 1.67 m deep NO. 1 7.22 1805 0 0 1805
2 INT.BOT.DIA.-122cm & TOP DIA.-56cm
BRICK WORK - 1:4
FOUNDATION CONC. - 1:3:6
INSIDE PLASTER - 12mm 1:3 WITH NEAT
CMNT.
CONC. TOP SLAB - 1:2:4
C.C.CHANNEL - 1:2:4 WITH NEAT CEMENT
a 1.68 m deep NO. 1 10.78 2695 0 0 2695
b 2.29 m deep NO. 1 12.54 3135 0 0 3135
Qty.
1.5282 white
cement
Page 9
CO-EFFICIENTS OF MATERIAL CONSUMPTION
QUANTITY AMOUNT
CEMENT SAND C/AGG. CEMENT WHITE C/SAND C/AGG. TOTAL
SN DESCRIPTION UNIT QTY.
IN BAGS IN CFT. IN CFT. 250 550 40 40 COST
PER BAG PER BAG PER CFT PER CFT
Qty.
474.61 Grey
cement
Page 10