Bill Off Quantity
CST 60 M3
PT.
NO DESCRIPTION QUANTITY VOLUME PRICE TOTAL KETERANGAN
1 Material Mechanical
1 MS PL 15 mm x 4' x 8' 0,5 Lbr 175,0 Kg - Base Plate
2 MS PL 12 mm x 4' x 8' 1,0 Lbr 280,0 Kg - Support
3 MS PL 8 mm x 5' x 20' 2,5 Btg 467,5 Kg - Cone
4 MS PL 6 mm x 5' x 20' 6,0 Lbr 840,0 Kg - Body Shell
5 HB.200 x 200 x 8 x 12 x 12000 mm 3,0 Btg 1.797,0 Kg - Structure
6 UNP. 100 x 50 x 5 x 6000 mm 8,0 Btg 449,6 Kg - Support Roof & Ladder
7 Cheq. PL 4.5 mm x 4' x 8' 6,0 Lbr 660,0 Kg - Platform & Ladder
8 Pipe Ø12" Sch.40 x 6000 mm 1,0 Btg 470,0 Kg - Piping
9 Pipe Ø8" Sch.40 x 6000 mm 1,0 Btg 252,0 Kg - Piping
10 Pipe Ø2" Sch.40 x 6000 mm 20,0 Btg 652,8 Kg - Steam
11 Unp.150 x 75 x 6,5 2,0 Btg 224,0 Kg - Ring Tank
12 L.75 x 75 x 7 8,0 Btg 381,1 Kg - Support Platform
13 L.50 x 50 x 5 4,0 Btg 90,5 Kg - Support Steam Pipe
14 Manhole 4mm c/w Engsel 1,0 Set - Manhole
15 CNP. 125 x 50 x 20 x 2,3 6,0 Btg 162,0 Kg - Gording
16 Zincalum 0,35 x 760 mm 24,0 m - Roofing
17 Skimmer c/w Talang 3,0 Set - Skimmer Oil & Sludge
18 Agitator c/w Shaft ; Bushing & Gear Motor 2,2 Kw 3 Rpm 1,0 Set - Agitator
19 Sight Glass 1,0 Set - Accessories
20 Baut c/w mur Ø ½” x 1½” 1,0 Lot - Accessories
21 Isolasi Rockwoll 1,0 Lot - Rockwoll
22 Flange & Accessories 1,0 Lot - Accessories
SUB TOTAL 6.901,5 Rp -
2 Material Civil
1 Galian 26,5 M3 Kg -
2 Pembesian Ø12 80,0 Btg 848,0 Kg -
3 Bekesting 3,3 m2 Kg -
4 Pengecoran 30,8 M3 Kg -
5 Anchor dia.1" x 500 Long 10,0 Set Kg -
SUB TOTAL - Rp -
3 JASA
- Upah Kerja Fabrication - Erection 1,0 Lot 1,0 Lot Rp 60.000.000,00 60.000.000
- Upah Kerja Sipil 1,0 Lot 1,0 Lot Rp 24.000.000,00 24.000.000
- Consumable & Tools 1,0 Lot 1,0 Lot
SUB TOTAL 84.000.000
GRAND TOTAL 84.000.000