0% found this document useful (0 votes)
64 views1 page

Car Wash

rab

Uploaded by

andimuhakbar711
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views1 page

Car Wash

rab

Uploaded by

andimuhakbar711
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

RENCANA ANGGARAN BIAYA ( RAB )

Nama Pekerjaan : Pembangunan Car Wash 5m x 4m


Lokasi : Site Malili

No. Item Pekerjaan Volume Satuan Harga Satuan Total

A PEKERJAAN UMUM
1 Mobilisasi dan Demobilisasi Alat & Personil 1 ls 3,500,000.00 3,500,000.00
2 Pengukuran & Pemasangan Bouplank 1 ls 1,500,000.00 1,500,000.00
3 Adminitrasi , Dokumentasi & Manajemen Mutu 1 ls 2,500,000.00 2,500,000.00
4 Direksi Keet 1 ls 5,140,000.00 5,140,000.00
5 SMK3 1 ls 5,140,000.00 5,140,000.00
17,780,000.00
B PEKERJAAN TANAH DAN PONDASI
Pek. Galian Tanah 5.4 m3 205,068.00 1,107,367.20
1,107,367.20
C PEKERJAAN BETON BERTULANG
ROLLAG
1 Pondasi Rollag, t= 30cm 0.84 m3 1,200,000.00 1,008,000.00
1,008,000.00
D PEKERJAAN BAJA RINGAN
1 Baja Ringan Double C,75 Incl. Aksesoris (Tiang) 40 m 259,215.75 10,368,630.00
2 Baja Ringan Double C,75 Incl. Aksesoris (Balok) 32 m 259,215.75 8,294,904.00
18,663,534.00
F PEKERJAAN LANTAI
1 Pelat Lantai Beton 8 cm 2.4 m3 1,805,246.20 4,332,590.87
2 Besi Wiremes M7 116.81 kg 83,682.05 9,774,900.26
3 Bekisting 1.76 m2 287,597.46 506,171.53
14,613,662.67
G PEKERJAAN ATAP
1 Pekerjaan Kuda-Kuda C.75 incl. Reng & Aksesoris 100 m2 343,494.16 34,349,416.41
2 Penutup Atap Spandek 100 m2 184,387.26 18,438,726.25
52,788,142.66

H PEKERJAAN ELEKTRIKAL
1 Kabel NYM 2x2,5mm 30 m 28,048.50 841,455.00
2 Lampu Sorot 100watt 2 bh 700,000.00 1,400,000.00
3 Saklar Doble 1 bh 76,756.75 76,756.75
4 Stop kontak 2 bh 62,830.25 125,660.50
5 Stick Grounding 2m 1 btg 2,500,000.00 2,500,000.00
6 Kabel BC 10mm 4 m 120,000.00 480,000.00
5,423,872.25
Total 111,384,578.78
Pembulatan 111,380,000.00
PPN 11% 12,251,800.00
JUMLAH 123,631,800.00