WORKING DAYS TRACKER
Period Covered: December 11 - 25, 2023
        DATE            Time Rendered       Regular Time        Overtime
               Dec-11               23                     9           14
               Dec-12             10.5                     9          1.5
               Dec-13               13                     9               4
               Dec-14               13                     9               4
               Dec-15               13                     9               4
               Dec-16                   8                  3               5
               Dec-17                   0                  0               0
               Dec-18                   0
               Dec-19                   0
               Dec-20                   0
               Dec-21                   0
               Dec-22                   0
               Dec-23                   0
               Dec-24                   0
             Dec-25                  0
  Summary of Time                 80.5                 48            32.5
ORKING DAYS TRACKER
                                  Reason of Overtime
         Concrete Pouring (Straight time)
         Concrete Pouring (Straight time)
         Forms Romoval, Establish of Lay-out, and Installation of Planks
         Installation of planks and Rebars
         Installation of Rebars
         Installation of Rebars
         Installation of Rebars and Formworks Closure
         Installation of Rebars and Formworks Closure
         Preparation of Slab and Installation of Slab Rebars
         Slab Rebars and Formwork closure
         Final Checking and Concrete Pouring (Straight Time)
         ManPower Christmas Party
         No work
         No work
         No work