0% found this document useful (0 votes)
29 views9 pages

First Project

Uploaded by

henago2270
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views9 pages

First Project

Uploaded by

henago2270
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

APPROVAL COLUMN

PRELIMINARY LAYOUT DEVELOPMENT


OF
CASSAVA PROCESSING PLANT
FOR
DUFIL PRIMA FOODS PLC

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
COVER PAGE
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A100 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
APPROVAL COLUMN

268727

23950

23825
GR
409
58 78 78 7

30000

30000
29875

29875
29875
23575 1500 168300 2800 72552
GR
1500

4550 1500
IS IS IS IS
GR
28050 165125 75552
GR GR GR GR
27925 75427

69387

69387

69387
7362369387

69387

69387

74100
3

7 89 1 6
73623

8 4 01
GR FUTUTE DEVELOPMENT
81732

81732
88963

84125

475
84250

11 1
GR GR
IS

75 3
106375

12 5
GR

54125
54375

FUTUTE DEVELOPMENT
GR

131348
72500

72727
40KL/UG TANK
27184 20000 25543
142619

142619
4235
32509 12200 28018

10613
27184 5325 2475 25543

3150
FUTUTE DEVELOPMENT GAS STATION

14613
GR

HOSE PIPE
HOSE PIPE HOSE PIPE


.0
90
112466

27184 20000 25543

4000

TUBE SKID TRAILER ON STAND BY

TRAILER ON STAND BY

TRAILER ON STAND BY
4000 20075
5000
5035

27184 20000 25543


01
GR
CH

45000

45000

45000
02
GR

18375
18375

18375
18125

18125
IS 01 02
PROPOED BUILDING

37615
24836
03

27975
04 72852 CH GR
3558 13751200

28050 7515 167825 72852


1700

3558 2575
2000 4133
4255

23700 1500 2975 23055 27348 2265


2616 11000 1151 GR
1500 6133

6133
6133

GR 5067 2265 7822 6264 GR 202.00° 6133 100945 250 17311 90 7000 15001248 20000 25668
.0
0
15002000

MUSTER °
7543

POINT GR
823 5000

20,000 LITRES 16109

65596
OVERHEAD TANKS
27925 CAPACITY TANK 167700 GR 24311 2748 20000 25543

3962
IS
5000

5000

01 02 03 04 05 158.00°
6217

6259
835
20473

20473

20473

20473
CH

20848

WEIGH BRIDGE
.0

CH CH
90

11217

11217

200,000 LITRES
55636
55601

GR CLEAN WATER GR

25 6 2 6
6000

6000

90

CAPACITY TANK
.0

90


.0
90
12840

2700 2700 2700 2700 2649 2650 GR


.0

.0
9730

6217

6217

°
GR 177 3

90
90 .00 0°
5000

68 158.00°
20352 1
.0

10050

6961
6961
0
6511 1500 3500 11258 01 02 031609904 05 06 35 0 0 GR
9340

°
SURFACE TANK GR GR
8081

GR 20000 25543 0


.0
1500 2895
.0

90
25075 26030 22248 3500 GR 136458 7000 48291
90

WEIGH BRIDGE ATTENDANT


4395

4395

GR
90

3123

3123
.0

8 3 10
22.00°

61155 GR 9148 9600 44659 19647 59052 10050 17050 38366


1500

3000 1500
3000 1500
40044
40119

40119

40119
IS8
93

GR IS IS
489

IN-GATE 03 DRIVEWAY IN-GATE 02 CH IN-GATE 01


IS DRIVEWAY DRIVEWAY CH DRIVEWAY

6164
7000

7000

7000

7000

7000

7000
7000

7000

7000

7000

7000

7000
DRIVEWAY CH CH CH CH
8500

CH

1500 4000
1500 4000

27981

27981

379
24950 26109 9569 5736 1670 158012 20656 9026 1670 11204

1 7
4
5 846
1500

1500

1500

1500

1500

1500

1500
IS IS IS IS IS IS IS
19645

CH IS 90
.0
7942

7942

0
GR °

6020
9442

6442

SECURITY OFFICE TO DETAIL

12982
12520

12520

12520
250477 6125
11020
11020

11020

11020

11020
11020
1500 26109 1500
11145

11145

11145
GR GR GR GR GR
3203 1500

3078 1500

3203 1500

IS 790
IS 61257

5000

5000
GR
4703

23575 1500 27609 143066 250 54602 12000


3203

GR
268727

001 SITE PLAN


A100 1 : 600

SITE ANALYSIS
SYMBOL DESCRIPTION NOTES AREA OF SITE 38,325.500sqm
• AREA OF FUTURE DEVELOPMENT 11,971.561sqm
CH CONCRETE HARDSTAND • REFERENCE LEVEL OF +000 TO BE ESTABLISHED ON SITE IN ACCORDANCE TO
EXISTING SITE TOPOGRAPHY
AREA OF PROPOSED DEVELOPMENT 3,041.828sqm
IS INTERLOCKING STONE • SPOT LEVELS ON THE DRAWINGS ARE INDICATIVE OF SPOT DIFFERENCES ONLY AND AREA OF ANCILLIARY BLOCKS 110.676sqm
SHOULD BE SET OUT IN RELATION TO EXISTING SITE TOPOGRAPHY TOTAL AREA PROPOSED DEVELOPED 3,152.504sqm
GR GREEN AREA
• SITE REFERNCES OF +000 MUST BE AT LEAST 150MM HIGHER THAN THE
GC GRANITE CHIPPINGS EXISTING ROAD TOTAL AREA NOT DEVELOPED 35,172.996sqm
% AREA DEVELOPED 8.3%
% AREA NOT DEVELOPED 91.7%
Project Title Building Type REVISIONS
Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
SITE PLAN
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 1 : 600 IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A100 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
APPROVAL COLUMN

R2200

GR IS

PROPOSED BUILDING
GR
27975

13751200
28050 7515

1700

2575
4133
4255
4255
23700 1500 2975 23055
GR 27348 GR 2265
GR

6133

6133

6133
6133
2616 11000 1151 5067 2265 7822 6264

3558
3558
10078
202.00°

2000
1500 2000
53596 MUSTER

7543
20,000 LITRES POINT

5000
5000

1500
OVERHEAD TANKS 16109 GR
CAPACITY TANK
27925 01 02 03 04 05

5000

5000
158.00°

6217

6259
CH

835
823
20473
CH


.0
53167

90

11217
11217
GR 200,000 LITRES

6000

6000
6000
220KL CLEAN CAPACITY TANK 25 62

90
.0
90

.0
6

12840


GR 2700 2700 2700 2700 2649 2650

9730

6217

6217
WATER SURFACE °
17 73

5000
.00

TANK
90
.0
68
1 158.00°

350 0
01 02 03 1609904 05 06

9340
0 °
6511 1500 3500 GR11258 20352

8081
GR


1500 2895
35416

.0
90
25075 26030 22248 3500

4395

4395

90

3123

3123
.0
GR

22.00°
GR

1500
61155 9148 9600 44659 19647
40044
40119
93
489

23450 27530 20748 5000 47709 19647


65222 7757 3500
IN-GATE 03
IS DR I VEWAY DR I VEWAY

7000

7000

7000

7000

7000

7000

7000
7000
GR DR I VEWAY CH CH CH CH

30739

8500
24950 26109 9569 5736 1670 8695 47709 19647
4 65222
5846

23915

23915

1500

1500

1500

1500

1500
IS IS
CH

19645
IS
7942

7942

9442

6442

12520
11020
11020

11020
11145

11145
1500 26109 1500 12663
GR GR
1500

3078 1500

1500
IS IS GR
4703

23575 1500 27609 12663


3203

3203

3203
GR

001 SITE PLAN CALLOUT 01


A100A 1 : 300

SYMBOL DESCRIPTION NOTES


• SITE ANALYSIS
CH CONCRETE HARDSTAND • REFERENCE LEVEL OF +000 TO BE ESTABLISHED ON SITE IN ACCORDANCE TO AREA OF SITE 38,325.500sqm
EXISTING SITE TOPOGRAPHY AREA OF FUTURE DEVELOPMENT 11,971.561sqm
IS INTERLOCKING STONE • SPOT LEVELS ON THE DRAWINGS ARE INDICATIVE OF SPOT DIFFERENCES ONLY AND
SHOULD BE SET OUT IN RELATION TO EXISTING SITE TOPOGRAPHY
AREA OF PROPOSED DEVELOPMENT 3,041.828sqm
GR GREEN AREA
• SITE REFERNCES OF +000 MUST BE AT LEAST 150MM HIGHER THAN THE AREA OF ANCILLIARY BLOCKS 110.676sqm
GC GRANITE CHIPPINGS EXISTING ROAD TOTAL AREA PROPOSED DEVELOPED 3,152.504sqm
TOTAL AREA NOT DEVELOPED 35,172.996sqm
% AREA DEVELOPED 8.3%
% AREA NOT DEVELOPED 91.7%
Project Title Building Type REVISIONS
Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
SITE CALLOUT
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 1 : 300 IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A100A E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
0
APPROVAL COLUMN

23950
23825

23825
0
78 51

29875
29875
2800 72552

4550 1500

4550 1500
GR
NOTES

6050
2800 72552
75427 •
IS
• REFERENCE LEVEL OF +000 TO BE ESTABLISHED ON SITE IN ACCORDANCE TO

72

78 91 6 74 10 0
EXISTING SITE TOPOGRAPHY

69387

69387

69387
7362369387

69387

69387
831

6
73623

73735

84 0 5
• SPOT LEVELS ON THE DRAWINGS ARE INDICATIVE OF SPOT DIFFERENCES ONLY AND
SHOULD BE SET OUT IN RELATION TO EXISTING SITE TOPOGRAPHY
84125

475
• SITE REFERNCES OF +000 MUST BE AT LEAST 150MM HIGHER THAN THE

111
GR GR
EXISTING ROAD

579
12 5
IS
GR SYMBOL DESCRIPTION
54125

121348
CH CONCRETE HARDSTAND

122848
IS INTERLOCKING STONE
72500

72427

26884 20000 25543 GR GREEN AREA

142619
4235

32209 12200 28018


GC GRANITE CHIPPINGS
10613

29684 5325 2475 25543


3150

2925
GAS STATION
14613

14613

GR
IS HOSE PIPE HOSE PIPE
HOSE PIPE

.0
90

2800 26884 20000 25543


4000

TUBE SKID TRAILER ON STAND BY

TRAILER ON STAND BY

TRAILER ON STAND BY

29884 20000 25543


01
CH
GR SITE ANALYSIS
AREA OF SITE 38,325.500sqm
45000

45000

45000

02
18375
18375

18375

01 02
RAW MATERIAL BAY AREA OF FUTURE DEVELOPMENT 11,971.561sqm
37615
24836

24836

03
17136 29748
1M HEAP HEIGHT = 95 TONS
2M HEAP HEIGHT = 190 TONS
AREA OF PROPOSED DEVELOPMENT 3,041.828sqm
04
72552 CH GR AREA OF ANCILLIARY BLOCKS 110.676sqm
72727

17311 7000
IS
15001248 20000 25668 TOTAL AREA PROPOSED DEVELOPED 3,152.504sqm
60708

90
.0
0 °

TOTAL AREA NOT DEVELOPED 35,172.996sqm


65596

24311 2748 20000 25543


3962

% AREA DEVELOPED 8.3%


5551
20473

20473

20473
20848

CH WEIGH BRIDGE
17311 7000 15001248 20000 25543
GR 0 % AREA NOT DEVELOPED 91.7%

.0

90
90

.0

10050

6961
6961

GR GR

.0
90

17311 7000 48291 GR


7261 10050 17050 82 84 38366
3000 1500
3000 1500

1500
40119

IS5 IS IS
17311 7000 48291
IN-GATE 02 CH WEIGH BRIDGE ATTENDANT
72727
DR I VEWAY
6164
7000

7000

7000

7000

7000

7000

CH CH
1500 4000
1500 4000

27981

27981

37 9

20656 9026 1670 11204


71
1500

1500

1500

1500

IS IS IS IS
90
6020

.0

SECURITY

12982

12520
12645

6125 OFFICE TO
11020

11020
11020

11020
11145

GR GR DETAIL
001 SITE PLAN CALLOUT 02 790
7
5000

5000

5000

A100B 1 : 400 54602 12000 6125

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
SITE CALLOUT
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 1 : 400 IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A100B E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
165000 APPROVAL COLUMN

005 004 002


7385 157730 003
23 22 21 20 A104 19 18 17 16 A104 15 14 13 12 11 10 A104
9 8 7 6 5 4 A104 3 2 1
7385 230 157270 230
EXPANSION JOINT EXPANSION JOINT EXPANSION JOINT
7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500

2810 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 2920
A

230
500
2580 2000 5500 2000 CASSAVA
5500 CHIPS 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 2690 230 2580 2000 5500 2000 2690
STORAGE BIN CONVEYOR
R2
FUTURE 142270 230 14770

+1.20m
20
FLOUR

4000
0
R2200
FLOUR BINS STORAGE

7115
CODING AREA
BIN +1000

7985

7985

9485
10895
19395 45630 77245 230 14770

11575

2385
+2.00m

WAREHOUSE
Z - SECTION
19395 4800 1800 4410 1800 13275 1050 3035 1050 14410 CONVEYOR7000 85245

DAILY
9
H
.

+1000
0
1

1500
18230
18000

18230

17770

17770

17770

17770

18000
18230
+1.00m

4000

4000
5845
+1000

760 1050 2075


5485 7505 5990

2910
4340 1800 400 3780 1800 300 MALE LOCKER HIGH CARE PROD. MGR
QA LAB

4000
+0

3885

3885

3885
21 m² 23 m²
14995 4400 6310 5880 TOILET
23 m²
23 m² 29 m²
6770
SLAG TANK

2235
6315 3610 1050 8251251050 6330 1025 1050 3915
2170 1800 200 4570 1050225

2385
+2.80m

1500
LOBBY ENG / PACKAGING STORE

9670
32060

1300
9325
42 m² 55 m²

4000
8290
AIR COM & PDB'S

8060
PACKING MILLING SECTION PUMP HOUSE GENERATOR

6875

6645

7115
AREA
003 TOILET 003
+1000 +1000 PRODUCTION ENG. MGR +1000

4000
11 m² OFFICE
A103 20 m² 85245 A103

3910

3910

3900

3910

3910
RECEPTION LAUNDRY

4140
18 m² 11 m² RECEPTION

2195
29 m²
2360 4000 3720 2000 2915 4170 6540 2000 3880 900 900 860 1475 6495 2770 6000 700 6770 5555 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 2690 230 2580 2000 5500 2000 2690

500
B

230
7385 2590 4000 3720 2000 5500 2000 7045 2000 STEEL16225
STAIRS TO S/ENGRS 4000 4025 +1000 6000 11205 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 5500 2000 2920

230 14995 230 4170 460 6310 460 5880 230 2960 DETAILS
2301475230 6495 230 4495 230 2770 230 7495 230 4990 230 6770 230 85245 230
APPROVED ALUMINUM
APPROVED ALUMINUM APPROVED SANDCRETE LOUVRE WINDOW WITH FLY SCREEN 1000MM THICK RC CONCRETE TO S/ENGNRS DETAILS
7385 157730 ROLLER SHUTTER DOOR
ROLLER SHUTTER DOOR HOLLOW BLOCK WALL
005 +100 003
7500 157500 002
A104 004
A104
002 A104 A104

001 03 FACTORY FLOOR PLAN A102


A102 1 : 350

005 004
20 A104 19 18 17 16 A104 15 14 13
EXPANSION JOINT 45630
4800 1800 4410 1800 13275 1050 3035 1050 14410 7000

3780 1800 300 960 950 950 900 900 900 5845 125 1050 3035 1050 225 7505

1500
1500

2075
5485 5990
3025

4340 1800 170 3780 1800 300


MALE LOCKER HIGH CARE
PROD. MGR

4000
3885

3885

3885

3885
23 m² 21 m²
4400 6310 5880 100790 275 850 245 850 225 850 200 850 180 850 45
TOILET QA LAB 23 m²
23 m² +1000 29 m²

760 1050
6770

2235
3610 1050 825 125 1050 6330 1025 1050 3915
2170 1800 200 6315 4570 1050 225

4170 +1000 11115 1050 4065 1050 1180 1050 7585 1050 3915 ENG / PACKAGING STORE
LOBBY
1300

1300
9555
9325

42 m² 32060 55 m²

AIR COM & PDB'S


19
+1000
GENERATOR

8290
PUMP HOUSE

8060

8060
18

925 150
850 50
17

6495 125 1050 1595 125 1050 3815


6875

16 19
2960 475 850 150
6645

15 18
14 4495 17
2260

003 003

FEMALE LOCKER
A103
13
PRODUCTION 16
A103
TOILET LOGISTICS ENG. MGR
1360
12 15
11
RECEPTION 14 7495 OFFICE
25 850 200 11
850m²180 850 5 25 m² 20 m²

3900

3900
3910

3910

3910

3910

3910
LAUNDRY

4140
10 13
18 m² RECEPTION
6 m²
+1000 09
082375 2120 11 m² 12
3200 4295

2835
11 29 m²
07 10
495 4000 6000 700
1500

4170 6310 2000 3880 06 05 04 03 02 01 09 08 07 06 05 04 03 02 01


4990 5055 1715
900 900 860 1475 6495 2695 1800 2770 795 3300 1800 900 700
B

500
1375 2420
+1000

1500
1530
01 02 03 04 05 06
+1000 06

2000 7045 2000 16225 4000 4025 05


04
6000 11205 2000
03
005
230 4170 460 A104
6310 460 5880 230 2960 230 1475 230 6495 230 4495 230 2770 230 02 7495 230 4990 230 6770 230
01

002 ADMIN GROUND FLOOR PLAN


A102 1 : 125 004
A104

004

18 17 16 A104
45860 15 14 13
460 3785 230 7310 230 8760 230 4680 230 6305 230 3920 230 3605 230 5195 230

230
850 150

80

4015 7310 8875


TOILET LOBBY 4680 6305 3920 3605 5195
1800

2000
2070

2300

8 m² 18 m²
1070

4720 1050 410 2585

3880

3880
FACTORY MNGR. KITCHENETTE

4395
24 m² 14 m²
5245

4245 7310 4720 1050 180


HR OFFICE
+4150 5055 1050 200200 1050 15 m² 2670 200 1050 2355
CAFETERIA
3195

3195

81 m²

1050 280
11555
STAIR HALL 14295

10055
1300

1300

1300
9545

9545

9545

9545

9545

9545
3340 1050 455 6710 LOBBY CONFERENCE RM

1050
19 m²

1960

1960
19 4295 10000 22 m² 50 m²
18
7665

TRAINING RM 17
7315

7315

16
3340 1050 225 44 m² 15 ACCOUNTS DEPT.
19
18
2600 1050 125 2335 850 200

1820
003 4615 14
45 m² 17
STAFF TOILET 003

5435
+4150 13 16 3775 13 m² 850 200
A103 12 15 STAIR HALL 250 850 1235 A103
KITCHEN
4300

4135
14 m²
4100

4100 14
4050

11

3905
3820

18 m² 10 13
3475 +4150

3475
09
08
12
11
MEETING RM MGR TOILET
07 10
15 m² 8 m²
06 05 04 03 02 01 09 08 07 06 05 04 03 02 01

4615 6710 5950 2585 4680 3775 1580 1575 5195

280
B
003 ADMIN UPPER FLOOR PLAN
A102 1 : 125
Building Type 004 06
Project Title REVISIONS NOTES
Architect
A104
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
FLOOR PLAN LAYOUT
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 As indicated IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A102 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
APPROVAL COLUMN
005
004
A104 003 002
A104
A104 A104

23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
165000
7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500

150
A

9000

9000
10000
2250 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 2250 2250 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 2250
18000

18000
VOID VOID
1235 8805

9000

9000
003 003
A103 A103

145
B

9010 6000 30000 45000 45000 45000


10000

005
165000
003 002
A104 ENTRANCE CANOPY 004 ENTRANCE CANOPY A104 A104
A104

001 05 LOWER ROOF PLAN


A103 1 : 350

005
A104

23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
165000
7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500
A
9000
18000

18000
2250 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 4500 3000 2250
9000

003 003
A103 A103

B
165000
002 07 UPPER ROOF PLAN
A103 1 : 350 005
A104

23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500 7500

Level 7
27000
29000

Level 5
7300 ACCOUNTS DEPT. STAIR HALL MEETING RM STAFF TOILET MGR TOILET CONFERENCE RM
CAFETERIA STAIR HALL 45 m² 14 m² 15 m² 13 m² 8 m² 50 m²
KITCHEN 81 m² 19 m²
18 m²
Level 4
6000

7000

6865
4150 TOILET LOGISTICS
PRODUCTION OFFICE
Level 3 FEMALE LOCKER RECEPTION LAUNDRY RECEPTION ENG. MGR ENG / PACKAGING STORE
11 m² 25 m² 18 m² 11 m² 29 m² 20 m² 55 m²
6 m²
Level 2
2200
1000

1000

Level 1
0 001
003 Section 01 A104
A103 1 : 350

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
ROOF PLAN LAYOUT / SECTION
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 1 : 350 IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A103 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
23 22 21 20 19 18 17 16 15 14 13 12 APPROVAL COLUMN

15000
Level 5
7300
CAFETERIA ACCOUNTS DEPT. STAIR HALL MEETING RM STAFF TOILET MGR TOILET
TRAINING RM STAIR HALL 14 m²
8 m² CONFERENCE RM

3000
KITCHEN 81 m² 45 m² 15 m² 13 m²

10000
18 m²
44 m² 19 m² 50 m²
Level 4
6000

7000

4150
TOILET PRODUCTION OFFICE ENG. MGR ENG / PACKAGING STORE
LOGISTICS LAUNDRY

3000
Level 3 11 m² 20 m² 55 m²
25 m² RECEPTION 11 m² RECEPTION
2200 18 m² 29 m²
Level 2
1000

1000
Level 1
0
001 Callout 1 @Section 01
A104 1 : 200

B A
B A 18000
18000

5000
5000
A B

2000

2000
15000
Level 5 Level 7

12000
13000
7300
15000

Level 5 27000

3150

4900
7300
3150
4900

9000

Level 4

6300
10000

8000
4150
7000

1000 1200 1950


Level 4
8000

900
4150 Level 3
1200 1950

1200
2200
900

Level 3

2220
Level 2
2200 1000
Level 2 Level 1

19000
1000 0

17000
19000
19000
Level 1
0

002 Section 02 003 Section 03

28000
A104 1 : 200 A104 1 : 200

29000
27000
B A
18000

2000
2000

Level 5
7300

4900

9000
Level 5
7300 Level 4

8000

8000
4150
ACCOUNTS DEPT.

3150
4400

900
45 m²
3000

Level 3
4900

2200
10000

2200
Level 2
7000

1000
Level 4
8000

8000

4150 2000
Level 1
200

0
HIGH CARE
PRODUCTION
900

LOBBY
3000

21 m²
Level 3
2400

RECEPTION 42 m²
2200 18 m²
3400

1200

Level 2
1000 005 Section 05
A104 1 : 200
Level 1
0

004 Section 04
A104 1 : 125

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
SECTIONS
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 As indicated IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A104 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
APPROVAL COLUMN

B A

Level 7
27000

14000
19700

29000
27000
5000
Level 5
7300

3150

10000
Level 4
4150

1000 1200 1950


Level 3
2200
Level 2
1000

Level 1
001 APPROACH ELEVATION 0
A105 1 : 200

23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1

Level 7
27000
29000

15000
Level 5
7300

3150
10000

10000
Level 4

8000

1950
4150
Level 3
Level
2200 2
Level
1000 1
0

002 FRONT ELEVATION


A105 1 : 350

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
ELEVATION
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 As indicated IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A105 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F
APPROVAL COLUMN

A 18000 B

Level 7
27000

29000
27000

Level 5
7300

Level 4
4150

Level 3
2200
Level 2
1000
Level 1
0

001 LEFT SIDE ELEVATION


A106 1 : 200

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Level 7
27000

29000
27000
15000

Level 5
13000

7300
10000

Level 4
8000

7000
4150
Level 3
Level
2200 2
Level
1000 1
0

002 REAR ELEVATION


A106 1 : 350

Project Title Building Type REVISIONS


Architect NOTES
FACTORY FACILITY Revision Date
Drawing Title A 1. DIMENSIONS TO BE CHECKED ON SITE
PRELIMINARY LAYOUT DEVELOPMENT 27,ALARA STREET, ONIKE
ELEVATION
B
2. DIMENSIONS ARE TAKEN TO STRUCTURAL
SURFACES OR CENTRE LINES AND DO NOT INCLUDE FINISHES
OF YABA,LAGOS. Drawn Date Scale Checked
EXCEPT WHEREOTHERWISE STATED.
CASSAVA PROCESSING PLANT
Tel:08077469471,09069090865 AUGUST 2019 As indicated IO
C
Email-
D
FOR vizualplusstudios@gmail.com,vizualplusstudios@yahoo.co.u Project No. Drawing Number
k VP/15/008/A106 E
DUFIL PRIMA FOODS PLC
Sheet Size
A2 F