YLDM - 558 - Rig Inspection

Uploaded by

Akram Jmal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views4 pages

YLDM - 558 - Rig Inspection

Uploaded by

Akram Jmal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

RIG INSPECTIONS REPORT

Company
Rig No YLDM-558
Company Man
Well
Company Man
Number
Tool Pusher
Date 21.11.2024
Good Mark 
Inspected
By Condition
1. DERICK 4.Bad
RIGCondition Mark x
ENGINES/PLANT/TOOL
0 0 HOUSE
1.1 Red Crown Lights Operational. 4.1 Fans and belts guarded.
1.2 Crown Block visually inspected. 4.2 Properly grounded.
Crown sheaves greased and in good
1.3 condition. 4.3 Motors clean.
Safety cables attached to tubing board
1.4 fingers. 4.4 Buildings are level and properly positioned.
Monkey board fingers safety chained
1.5 and straight. 4.5 All electrical equipment is explosion-proof.
1.6 Escape buggy installed and accessible. 4.6 Receptacles and plugs are in good condition.
All tools and maintenance parts are stored
1.7 The escape line Flagged. 4.7 properly.
Derrickman’s Full Body Harness
1.8 visually inspected. 4.8 Face shield and goggles at the grinder.
1.9 All sheaves have safety lines. 4.9 Air compressors have all guards in place.

1.1 4.1
0 Kelly hose snubbed both ends. 0 Safety Valve on air receiver tank(s).

1.1 4.1
1 Condition of beams and grits. 1 Auto start sign on all compressors.

1.1 4.1
2 Derrick pins and keepers in place. 2 All electrical panels and covers in place.

1.1 Derrick hydraulic system in good 4.1


3 condition. 3 High Voltage, Noise Hazard signs posted

1.1 Derrick clean and free from oil & 4.1


4 grease. 4 General Conditions:
1.1 5.
5 General condition of wiring. 0 RAMP/CATWALK/PIPE RACKS
1.1 Standpipe properly secured to
6 derrick. 5.1 Ramp is properly secured.
1.1
7 Mast in good condition. 5.2 Condition of V-door stairs.
1.1
8 Lights have safety cables. 5.3 Condition of catwalk deck.
1.1 Tongs hanging lines in good
9 condition. 5.4 Catwalk stairs in place.
1.2 The ladder & guard rail in good
0 condition. 5.5 Catwalk, pipe racks level.
2. TRAVELLING BLOCK
0 5.6 General Condition:
Blocks in good condition, pins & 6.
2.1 keepers in place. 0 RIG FLOOR
2.2 Bails in good condition. 6.1 Warning horn operational.
Elevators, springs, & latches in Stabbing valve, handle & crossover subs
2.3 good condition. 6.2 nearby.
2.4 Condition of hook latch and lock. 6.3 Rig floor clean and orderly.
3.
0 DRAWWORK/CARRIER 6.4 Condition of flooring.
3.1 Drill line is slipped when required. 6.5 Tugger (line, guard and spooler).
Ton Miles chart up to date and
3.2 kept. 6.6 Tong torque gauge line, safety line attached.
Sufficient wraps (7 min.) on drum
3.3 with drill line. 6.7 General Condition:
Sand line in good condition and 7.
3.4 properly flagged. 0 BLOW OUT PREVENTOR
3.5 Braking system in good condition. 7.1 BOP properly bolted to casinghead.
Rams properly sized and functioning
3.6 Winch line in good condition. 7.2 properly.
Drawworks properly greased and Annular rubber checked and in good
3.7 oiled. 7.3 condition.
3.8 Accumulator properly charged and
Guards in place. 7.4 functioning.
3.9 Crown saver operating and Air and Triplex charging pumps functioning
checked daily. properly.
3.1 Gauges working properly and in good
0 Pins and keepers in place. 7.6 condition.
3.1 Accumulator Controls
1 Illumination & Wiring. 7.7 identified/accessible.
3.1 BOP/Annular checked daily (function
2 No oil leaks. 7.8 tested).
3.1 BOP'S, Date of last test:
3 General Conditions: 7.9 _______________________

7.10 Date of last BOP drill: 1-10-2024 12.2 Brakes.


7.11 BOP'S, anchored to sub. 12.3 Controls.
7.12 No leaks or spillage. 12.4 Forks & rack.
Manifold Valve Handles
7.13 installed. 12.5 Back-up alarm.
Flare lines secured and of
7.14 sufficient length.24

13.
7.15 General Condition: 0 RIG & GENERAL SAFETY
8.0 FUEL TANK 13.1 Emergency contact list and ERP posted
8.1 No leaks. 13.2 Daily 5-minute meetings are held.
Diesel fuel and Flammable
8.2 Liquid signs are posted. 13.3 Fall Protection Equipment in good repair.
8.3 Vents open. 13.4 Safe Working Load on all Lifting Equipment
All guards in place and in good working
8.4 Fire extinguisher nearby. 13.5 condition.
Lifting Equipment Inspection Certification
9.0 WATER TANK 13.6 onsite.
Hand railings/stairs installed and in good
9.1 No leaks. 13.7 condition.
Exhaust pointed away from well and
9.2 Pumps guarded. 13.8 shrouded.
9.3 Wiring in good condition. 13.9 Weight indicator reading properly.
13.1
9.4 Condition of ladder. 0 Guy lines properly anchored and clamped.
10. 13.1
0 OIL STORAGE 1 Floor housekeeping.
13.1 Hand tools in good condition and properly
10.1 No oil spills. 2 stored.
Oil drums clearly marked as 13.1
10.2 to contents. 3 Driller's controls clearly labelled.
13.1 Derrick levelled and cantered over well
10.3 Fire extinguisher nearby. 4 properly.
11. 13.1
0 MUD PUMP AND TANK 5 All lines properly clamped and flagged
Shear relief valve correctly 13.1
11.1 pinned and covered. 6 All personnel are using PPE
Relief line sloped to drain and 13.1 Safety valve on floor and proper pressure
11.2 secured. 7 rating.
13.1 Escape buggy in position, in good condition
11.3 Shock hoses secured properly 8 & properly tied.
11.4 Caps, studs, nuts in place and 13.1 Guy lines properly flagged.
secure. 9
13.2
11.5 Manifold in good condition. 0 Fire extinguishers inspected and in position.
13.2
11.6 Exhaust shrouded. 1 Breathing apparatus checked and operable.
Pressure gauge working 13.2
11.7 properly and in full view. 2 First Aid Kit - Complete.
All guards in place and in good 13.2
11.8 condition. 3 Collapsible Rescue Stretcher available.
13.2
11.9 Oilers working properly. 4
11.1 13.2
0 Wiring in good repair. 5 No smoking, and all needed signs posted.
11.1 Mud mixing system working 13.2
1 properly and area clean. 6 General housekeeping & condition of lease:
11.1 Mud agitators working 13.2
2 properly/good condition. 7 Drilling Crew Safety man competency

11.1 Stairs in good condition level 13.2 Does Day Company have a competency
3 and secured. 8 Certificate
11.1 Walkways and platforms secure 13.2 Does Night Company have a competency
4 and with handrails. 9 certificate
11.1 13.3
5 Adequate lighting. 0 3r Party certifications
11.1 Housekeeping on and around 13.3
6 pump and tank area. 1 Tool pushers have competency certificate
11.1 13.3
7 No leaks. 2 Car parked in a good, designated areas
11.1 Goggles, Respirators, Apron and 13.3 Is the Assembly point /Muster point
8 Gloves available 3 adequate
13.3
11.19 General condition: 4 Minimum of two windsock
12. 13.3
0 FORK LIFT 5 Hydrogen Sulphide Management
13.3
12.1 Tires. 6 Safety Training Records

COMMENTS / RECOMMENDATIONS
Rig is Acceptable upon close out of the above comments/ recommendations

Company Man Signature: ___________________


Tool pusher Signature: ________________

Safety Supervisor Signature: