Jsa Putra Jaya

Uploaded by

Veri Yulianto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

JOB SAFETY ANALYSIS

VESSEL /WORK-SITE DATE TIME RESPONSIBLE PERSON/ COMPANY JSA NO.

BARGE KCN 7/ TUJ - PLTU


NAME: LIN YUN FAT / PT. KAI SIGN:

JOB/TASK BEING ASSESSED TABLE 1 – RISK RATING TABLE 2 – RISK CLASSIFICATION

Highly
SEVERITY LIKELIHOOD Un-likely Likely RISK RATING RESULT
Likely
LOADING CRANE
ONSHORE AND NO Injury/Damage/Pollution L L M L LOW Acceptable to commence task, but control measures may be needed.

OFFSHORE MINOR Injury/Damage/Pollution L M H M MEDIUM Task should only proceed once control measures are implemented.
Do not proceed. Task must be redefined, further control measures
MAJOR Injury/Damage/Pollution M H H H HIGH
must be implemented to further reduce risk.

WEATHER (If weather criteria is out of working limits, exercise SWA) ATTACHED CHECKLISTS/PROCEDURES (Circle either Yes of No)

Sea State: Direction: 500m Zone: Yes / No Pre-Lift: Yes / No PTW: Yes / No

Wind Force: Direction: Toolbox Talk: Yes / No Pre-Arrival/Departure: Yes / No Bunkering: Yes / No

Visibility: Rain: Hand Protection: Yes / No Fitness for Duty: Yes / No Procedure: Yes / No

RISK
STEP DESCRIPTION HAZARD ID. HAZARD DESCRIPTION CONTROL MEASURES (MITIGATION)
RATING
1 Prepare Mechanical - Hand injury by engine movement. - Follow Hand Safety checklist, TIF, Proper PPE L
- machinery Electrical - Electric chock from generator. - Post the Hazard sign at area, Proper PPE
- equipment pressure - Pressure from oil pipe line leak. - Follow PMS for check equipment.
chemical - Chemical from during charge battery - Proper PPE
Sound
- Noise sound from engine. - Proper PPE, wear ear plug.
Motion - Head crash with pipe during walking in - Proper PPE, wear bump cap.
engine room.
Gravity - Toll equipment fall hit foot. - TIF, Proper PPE.
Temp. - Hot temperature in engine room. - Check ventilation system are in good condition,
Follow PMS.

- SWA to exercise in danger

1
RISK
STEP DESCRIPTION HAZARD I.D. HAZARD DESCRIPTION CONTROL MEASURES (MITIGATION)
RATING
2 During Approaching Mechanical - Engine failure. - Monitoring all engine are in good condition by engine L
Electrical - Generator & Bow thuster failure. watch, follow PMS from check equipment.
Temp. - Hot temp. from sun light. - Wear proper PPE and equipment for protection sun
chemical - Smoke from engine. light.
Radiation - Sun light. - Wear mask.
Sound - Noise sound from engine. - Wear complete cover all.
Motion - Ship rolling due to swell. - Proper PPE, wear ear plug.
- Follow 500 m. zone checklist, check weather
report, TIF.
- SWA to exercise in danger or risk.
3 During load – discharge cargo Mechanical - Engine failure. - Monitoring all engine are in good condition by engine L
Electrical - Generator & Bow thruster failure. watch, follow PMS from check equipment.
- Electrical cable connection containers spark - Completely checked/observed electrical cable
or ground if loading onboard connection between food containers and electrical
receptacle station before switch on/off
- Pressure from oil pipe line leak. - Always check and maintain temperature
- Hot temp. from sun light. - Always exercise SWA if unsafe conditions
pressure - Smoke from engine. - Follow PMS for checking equipment.
Temp. - Sun light. - Wear proper PPE and equipment for protection sun
chemical - Noise sound from engine. light.
Radiation - Cargo fall to crews on deck. - Wear mask.
Sound - Cargo hit crews. - Wear complete cover all.
Gravity - Tagline entangled deck crew. - Proper PPE, wear ear plug.
Motion - Tagline swing hit crews. - Do not stand in line of fire.
- Tagline poor condition broken during pulling then - Follow JSA ,
slip. -, check tagline condition

- SWA to exercise in danger or risk.

2
4 Securing of Cargo and Leave station Mechanical - Engine failure. - Monitoring all engine are in good condition by engine L
Electrical - Generator failure. watch, follow PMS from check equipment.
pressure - Pressure from oil pipe line leak. - Follow PMS for check equipment.
Temp. - Hot temp. from sun light. - Wear proper PPE and equipment for protection sun
chemical - Smoke from engine. light.
Radiation - Sun light. - Wear mask.
Sound - Noise sound from engine. - Wear complete cover all.
Gravity - Lashing gear fall to crews. - Proper PPE, wear ear plug.
Motion - Ship rolling due to swell. - Follow Hand off, checklist, TIF, Proper PPE
- SWA to exercise in danger or risk.

5 During Approach Jetty TUJ /facility Mechanical - - Engine failure. maybe crash with LQ, Platform or - Monitoring all engine are in good condition by engine L
Electrical Jetty watch, follow PMS from check equipment.
- Electric shock or generator shutdown - Wear proper PPE and equipment for protection sun light.
Temp. - Wear mask.
chemical - Hot temp. from engine. - Wear complete cover all.
Radiation - Smoke from engine. - Proper PPE, wear ear plug.
Sound - Radiation from the sun.(UV) - Follow 500 m. zone checklist, check weather report, TIF.
Motion - Noise sound from engine running. - SWA to exercise in danger or risk.
Gravity - Ship rolling ,Body movement
- Falling down

6 During mooring operation (made fast and cast Mechanical - Engine failure. maybe crash with LQ, Platform or - Monitoring all engine are in good condition by engine L
off) Electrical Jetty watch, follow PMS from check equipment.
pressure - Electric shock or generator shutdown - Follow PMS for check equipment.
Temp. - Pressure from oil pipe line leak. - Wear proper PPE and equipment for protection sun light.
chemical - Hot temp. from sun light. - Wear mask.
Radiation - Smoke from engine. - Wear complete cover all.
Sound - Radiation from the sun.(UV) - Proper PPE, wear ear plug.
Gravity - Noise sound from engine running. - Keep an eye while walk on deck and work area.
Motion - Fall down on deck. - Follow JSA ,
- Ship rolling ,Body movement Cargo hit crews. - Follow PMS , check tagline condition
- Tagline entangled deck crew.
- Tagline swing hit crews. - SWA to exercise in danger or risk.
- Tagline poor condition broken during pulling then
slip.

3
7 Securing all lines and leave station Mechanical - Engine failure. maybe crash with LQ, Platform or - Monitoring all engine are in good condition by engine L
Electrical Jetty watch, follow PMS from check equipment.
pressure - Electric shock or generator shutdown - Follow PMS for check equipment.
Temp. - Pressure from oil pipe line leak. - Wear proper PPE and equipment for protection sun light.
chemical - Hot temp. from sun light. - Wear mask.
Radiation - Smoke from engine. - Wear complete cover all.
Sound - Radiation from the sun.(UV) - Proper PPE, wear ear plug.
Gravity - Noise sound from engine running. - Follow Hand off, checklist, TIF, Proper PPE
Motion - Lashing gear fall to crews. Slip &trip - Check weather report, TIF
- Ship rolling ,Body movement,pinchpoint - SWA to exercise in danger or risk.

If any conditions change during the task, all staffs are responsible for calling a time out and allowing a re-assessment to be made.
All staff involved in the JSA process should sign below, stating that they have participated in the process and agree to the risks identified & control measures required.

No. NAME RANK SIGN No. NAME RANK SIGN


ABDULLAH WINCH
1 LIN YUN FAT REP. PT. KAI 7
OPERATOR
RONISIUS K. WINCH
2 PIPIT REP. PT. KAI 8
OPERATOR
MASTER ALBERSON S. WINCH
3 CAPT. KAMSUL 9
KCN7 OPERATOR
CRANE SASTENIS L. WINCH
4 K.ARIYANTO 10
OPRTR OPERATOR
CRANE
5 IMRAN YAHYA 11
OPERATOR
WINCH
6 SARMAN 12
OPRTR

JSA reviewed

Signature

JSA closeout
Name