NHC Updated 28-12-2024

الجدول الزمني لاعمال اسفلت

Uploaded by

ahmedosama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views2 pages

NHC Updated 28-12-2024

الجدول الزمني لاعمال اسفلت

Uploaded by

ahmedosama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Development of AL-Hawiyah District Poject Classic Schedule Layout 30-Dec-24 18:02

Activity ID Activity Name Planned Performance % Schedule % Start Finish BL1 Start BL1 Finish Earned Value Planned Value Planned Total Cost Schedule Total Float
Duration Complete Complete Cost Cost Variance

NHC-1 Development of AL-Hawiyah District Poject 78d 100% 100% 29-Sep-24 A 28-Dec-24 29-Sep-24 28-Dec-24 SAR2,759,000.00 SAR2,759,000.00 SAR2,759,000.00 SAR0.00 0d

NHC-1.01 Milestones 77d 0% 0% 29-Sep-24 A 28-Dec-24 29-Sep-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d

NHC-1.01.1 Start Milestone 6d 0% 0% 29-Sep-24 A 06-Oct-24 A 29-Sep-24 06-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1000 The Site Receipt Minutes 0d 100% 100% 29-Sep-24 A 29-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1010 Project Start 0d 100% 100% 29-Sep-24 A 29-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1020 Preconstruction Start 0d 100% 100% 29-Sep-24 A 29-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1030 Design & Engineering Start 0d 100% 100% 01-Oct-24 A 01-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1040 Procurement & Materials Start 0d 100% 100% 06-Oct-24 A 06-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.01.2 Finish Milestone 75d 0% 0% 30-Sep-24 A 28-Dec-24 30-Sep-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d
A1060 Design & Engineering Finish 0d 0% 0% 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d
A1070 Procurement & Materials Finish 0d 100% 0% 25-Dec-24 A 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1050 Preconstruction Finish 0d 100% 100% 30-Sep-24 A 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.02 Preconstruction 2d 0% 0% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1080 Mobilization Of Site Office 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1090 Equipement Mobilization 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.03 Design & Engineering 78d 0% 0% 29-Sep-24 A 28-Dec-24 A 29-Sep-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00

NHC-1.03.1 Shop Drawing 2d 0% 0% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1100 Shop Drawing and Profile Submittals 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1110 Shop Drawing and Profile Approved 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.03.2 Method of Statement 2d 0% 0% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1120 Method of Statements Submittals 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1130 Method of Statements Approved 2d 100% 100% 29-Sep-24 A 30-Sep-24 A 29-Sep-24 30-Sep-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.03.3 As Built Drawings 1d 0% 0% 26-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1140 As Built Drawings Submittals 1d 100% 0% 26-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1150 As Built Drawings Approved 1d 100% 0% 28-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.04 Procurement & Materials 76d 0% 0% 29-Sep-24 A 25-Dec-24 A 29-Sep-24 25-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00

NHC-1.04.1 Procurement & Materials Submittals 5d 0% 0% 29-Sep-24 A 03-Oct-24 A 29-Sep-24 03-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1160 SubBase Materials Submittals 5d 100% 100% 29-Sep-24 A 03-Oct-24 A 29-Sep-24 03-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1170 Asphalt Supplier Submittal 4d 100% 100% 29-Sep-24 A 02-Oct-24 A 29-Sep-24 02-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1180 Mix Design Submittal 4d 100% 100% 29-Sep-24 A 02-Oct-24 A 29-Sep-24 02-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.04.3 Procurement & Materials Approved 5d 0% 0% 29-Sep-24 A 03-Oct-24 A 29-Sep-24 03-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1190 SubBase Materials Approved 5d 100% 100% 29-Sep-24 A 03-Oct-24 A 29-Sep-24 03-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1200 Asphalt Supplier Approved 4d 100% 100% 29-Sep-24 A 02-Oct-24 A 29-Sep-24 02-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1210 Mix Design Approved 4d 100% 100% 29-Sep-24 A 02-Oct-24 A 29-Sep-24 02-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.04.2 Fabrication and Delivery to Site 57d 0% 0% 21-Oct-24 A 25-Dec-24 A 21-Oct-24 25-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1220 SubBase Supply 30d 100% 100% 21-Oct-24 A 30-Nov-24 A 21-Oct-24 24-Nov-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1230 MC1 Supply 30d 100% 100% 20-Nov-24 A 24-Dec-24 A 20-Nov-24 24-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1240 Asphalt Supply 30d 100% 100% 21-Nov-24 A 25-Dec-24 A 21-Nov-24 25-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00

NHC-1.05 Construction Works 76d 100% 100% 29-Sep-24 A 25-Dec-24 A 29-Sep-24 25-Dec-24 SAR2,759,000.00 SAR2,759,000.00 SAR2,759,000.00 SAR0.00

NHC-1.05.1 Zone 1 62d 100% 100% 29-Sep-24 A 28-Nov-24 A 29-Sep-24 09-Dec-24 SAR1,190,836.04 SAR1,190,836.04 SAR1,190,836.04 SAR0.00
NHC-1.05.1.1 Item 1-1 Cleaning and Grabbings 21d 100% 100% 29-Sep-24 A 22-Oct-24 A 29-Sep-24 22-Oct-24 SAR77,133.33 SAR77,133.33 SAR77,133.33 SAR0.00
A1250 Cleaning and Grabbings Summary - 1 21d 100% 100% 29-Sep-24 A 22-Oct-24 A 29-Sep-24 22-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.05.1.1.A Cleaning and Grabbings Working 21d 100% 100% 29-Sep-24 A 22-Oct-24 A 29-Sep-24 22-Oct-24 SAR77,133.33 SAR77,133.33 SAR77,133.33 SAR0.00
A1260 Survying Works - 1 18d 100% 100% 29-Sep-24 A 19-Oct-24 A 29-Sep-24 19-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1270 High Level Cutting - 1 8d 100% 100% 06-Oct-24 A 14-Oct-24 A 06-Oct-24 14-Oct-24 SAR23,733.33 SAR23,733.33 SAR23,733.33 SAR0.00
A1280 Low Level Filling - 1 10d 100% 100% 12-Oct-24 A 22-Oct-24 A 12-Oct-24 22-Oct-24 SAR29,666.67 SAR29,666.67 SAR29,666.67 SAR0.00
A1290 Surface Level - 1 8d 100% 100% 12-Oct-24 A 20-Oct-24 A 12-Oct-24 20-Oct-24 SAR23,733.33 SAR23,733.33 SAR23,733.33 SAR0.00
NHC-1.05.1.2 Item 2-1 SubBase 15d 100% 100% 22-Oct-24 A 07-Nov-24 A 22-Oct-24 07-Nov-24 SAR267,000.00 SAR267,000.00 SAR267,000.00 SAR0.00
A1300 SubBase Summary - 1 15d 100% 100% 22-Oct-24 A 07-Nov-24 A 22-Oct-24 07-Nov-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.05.1.2.B Sub Base Layer 15d 100% 100% 22-Oct-24 A 07-Nov-24 A 22-Oct-24 07-Nov-24 SAR267,000.00 SAR267,000.00 SAR267,000.00 SAR0.00

Page 1 of 2 TASK filter: All Activities


© Oracle Corporation
Development of AL-Hawiyah District Poject Classic Schedule Layout 30-Dec-24 18:02
Activity ID Activity Name Planned Performance % Schedule % Start Finish BL1 Start BL1 Finish Earned Value Planned Value Planned Total Cost Schedule Total Float
Duration Complete Complete Cost Cost Variance

A1310 First Layer - 1 6d 100% 100% 22-Oct-24 A 28-Oct-24 A 22-Oct-24 28-Oct-24 SAR76,285.71 SAR76,285.71 SAR76,285.71 SAR0.00
A1320 Second Layer - 1 15d 100% 100% 22-Oct-24 A 07-Nov-24 A 22-Oct-24 07-Nov-24 SAR190,714.29 SAR190,714.29 SAR190,714.29 SAR0.00
NHC-1.05.1.3 Item No3-2 MC1 Work 16d 100% 100% 20-Nov-24 A 28-Nov-24 A 20-Nov-24 08-Dec-24 SAR57,729.73 SAR57,729.73 SAR57,729.73 SAR0.00
A1330 MC1 - 1 16d 100% 100% 20-Nov-24 A 28-Nov-24 A 20-Nov-24 08-Dec-24 SAR57,729.73 SAR57,729.73 SAR57,729.73 SAR0.00
NHC-1.05.1.4 Item No4-2 Asphalt Work 16d 100% 100% 21-Nov-24 A 27-Nov-24 A 21-Nov-24 09-Dec-24 SAR788,972.97 SAR788,972.97 SAR788,972.97 SAR0.00
A1340 Asphalt - 1 16d 100% 100% 21-Nov-24 A 27-Nov-24 A 21-Nov-24 09-Dec-24 SAR788,972.97 SAR788,972.97 SAR788,972.97 SAR0.00
NHC-1.05.2 Zone 2 75d 100% 100% 06-Oct-24 A 25-Dec-24 A 30-Sep-24 25-Dec-24 SAR1,568,163.96 SAR1,568,163.96 SAR1,568,163.96 SAR0.00
NHC-1.05.2.1 Item 1-2 Cleaning and Grabbings 20d 100% 100% 06-Oct-24 A 28-Oct-24 A 06-Oct-24 28-Oct-24 SAR100,866.67 SAR100,866.67 SAR100,866.67 SAR0.00
A1350 Cleaning and Grabbings Summary - 2 20d 100% 100% 06-Oct-24 A 28-Oct-24 A 06-Oct-24 28-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.05.2.1.A Cleaning and Grabbings Working 20d 100% 100% 06-Oct-24 A 28-Oct-24 A 06-Oct-24 28-Oct-24 SAR100,866.67 SAR100,866.67 SAR100,866.67 SAR0.00
A1360 Survying Works - 2 20d 100% 100% 06-Oct-24 A 28-Oct-24 A 06-Oct-24 28-Oct-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1370 High Level Cutting - 2 11d 100% 100% 06-Oct-24 A 17-Oct-24 A 06-Oct-24 17-Oct-24 SAR32,633.33 SAR32,633.33 SAR32,633.33 SAR0.00
A1380 Low Level Filling - 2 13d 100% 100% 10-Oct-24 A 24-Oct-24 A 10-Oct-24 24-Oct-24 SAR38,566.67 SAR38,566.67 SAR38,566.67 SAR0.00
A1390 Surface Level - 2 10d 100% 100% 13-Oct-24 A 23-Oct-24 A 13-Oct-24 23-Oct-24 SAR29,666.67 SAR29,666.67 SAR29,666.67 SAR0.00
NHC-1.05.2.2 Item 2-2 SubBase 28d 100% 100% 22-Oct-24 A 03-Dec-24 A 22-Oct-24 23-Nov-24 SAR356,000.00 SAR356,000.00 SAR356,000.00 SAR0.00
A1400 SubBase Summary - 2 28d 100% 100% 22-Oct-24 A 03-Dec-24 A 22-Oct-24 23-Nov-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.05.2.2.B Sub Base Layer 28d 100% 100% 22-Oct-24 A 03-Dec-24 A 22-Oct-24 23-Nov-24 SAR356,000.00 SAR356,000.00 SAR356,000.00 SAR0.00
A1410 First Layer - 2 9d 100% 100% 22-Oct-24 A 25-Nov-24 A 22-Oct-24 31-Oct-24 SAR114,428.57 SAR114,428.57 SAR114,428.57 SAR0.00
A1420 Second Layer - 2 19d 100% 100% 02-Nov-24 A 03-Dec-24 A 02-Nov-24 23-Nov-24 SAR241,571.43 SAR241,571.43 SAR241,571.43 SAR0.00
NHC-1.05.2.3 Item 3 MC-1 Work 21d 100% 100% 25-Nov-24 A 24-Dec-24 A 05-Nov-24 28-Nov-24 SAR75,770.27 SAR75,770.27 SAR75,770.27 SAR0.00
A1430 MC1 - 2 21d 100% 100% 25-Nov-24 A 24-Dec-24 A 05-Nov-24 28-Nov-24 SAR75,770.27 SAR75,770.27 SAR75,770.27 SAR0.00
NHC-1.05.2.4 Item 4 Asphalt 7 Cm 75d 100% 100% 26-Nov-24 A 25-Dec-24 A 30-Sep-24 25-Dec-24 SAR1,035,527.03 SAR1,035,527.03 SAR1,035,527.03 SAR0.00
A1440 Asphalt - 2 75d 100% 100% 26-Nov-24 A 25-Dec-24 A 30-Sep-24 25-Dec-24 SAR1,035,527.03 SAR1,035,527.03 SAR1,035,527.03 SAR0.00
NHC-1.06 Project Handing Over 1d 0% 0% 28-Dec-24 A 28-Dec-24 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d

NHC-1.06.1 Project Demoblization 1d 0% 0% 28-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1450 DeMobilization Of Site Office 1d 100% 0% 28-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
A1460 Equipement DeMobilization 1d 100% 0% 28-Dec-24 A 28-Dec-24 A 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00
NHC-1.06.2 Project Closeout 0d 0% 0% 28-Dec-24 28-Dec-24 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d
A1470 Project Finish 0d 0% 0% 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d
A1480 Closed Out 0d 0% 0% 28-Dec-24 28-Dec-24 SAR0.00 SAR0.00 SAR0.00 SAR0.00 0d