CONCRETE CHECKLIST /POUR CARD
NOTE : Pour Plan, RMC Batch slips, slump test and Post Concrete Checklist also form part of the Pour Card. All these shall be filed together.
Pour card shall be closed only after checking Post Concrete Works, succesful cube test results and after closing all post concrete quality issues.
QS shall be given copy of all site instructions on quality issues related to the particular pour.
INSPECTION CHECK CARD
CONCRETE CHECKLIST /POUR CARD
Project New Manufacturing Factory for NETZSCH Technologies at Verna IDC.
Client NETZSCH Inspection Report No
PMC (If any) JLL Date
Contractor Harshal Structural Member
Package Civil, Structure and Finishes work BBS.Ref.No.
Description of Work Concrete Work Quantity
Wing Dwg.Ref.No Rev Inspection Request
Level Inspected by
Floor By Time
Location Grid
Sl. No Description Yes No N/A Remarks
Method of work agreed and all parties involved/informed about specified
1
tolerance
2 Check for proper access to the pour
3 Approved checklist for reinforcement
4 Approved checklist for formwork
5 Approved checklist for post tension work
6 Mode of Concrete – Crane / Pump / Manual
7 Availability of sufficient vibrators
8 Availability of polythene sheet to protect the concrete against rain
9 Formwork and Rebar work approved
10 Conduits/ Ducts opening/ Insert Plates/Sleeves
11 Cleanliness of pour area
12 Preparation of old and new concrete joint
13 Mix grade checking as per design mix/specified
14 Proper vibration / compaction
15 Shear key provided
In case of incomplete pour
a Location of construction joint agreed / approved
b Construction joint formed properly
Observations if any :
Above Observations attended to and completed YES NO N/A
Note: The quantity mentioned above is approximate measure and can not be considered for any billing purpose. Only JMS to be considered for billing else GFC drawings are
to be referred for quantity
The above works have been completed and accepted
CONTRACTOR CLIENT
Signature Signature
Name Name
Date Date