GBMF06103 Texas Tower-Pre TA - Mar 24 GBMF06103 Texas Tower - Pre TA - Mar 24

The document outlines the project schedule for the Texas Tower Pre TA, detailing activities, durations, and milestones from June 2022 to March 2025. It includes specific tasks related to engineering, procurement, and project management, with a focus on critical activities and their dependencies. The schedule is organized in a classic WBS layout, providing a comprehensive overview of the project's timeline and progress.

Uploaded by

bhupendra mishra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views4 pages

GBMF06103 Texas Tower-Pre TA - Mar 24 GBMF06103 Texas Tower - Pre TA - Mar 24

The document outlines the project schedule for the Texas Tower Pre TA, detailing activities, durations, and milestones from June 2022 to March 2025. It includes specific tasks related to engineering, procurement, and project management, with a focus on critical activities and their dependencies. The schedule is organized in a classic WBS layout, providing a comprehensive overview of the project's timeline and progress.

Uploaded by

bhupendra mishra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37

Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
GBMF06103 Texas Tower- Pre TA - Mar 24 648.0d 286.0d 0% 01-Jun-22 A 21-Mar-25 0.0d 21-Mar-25, GBMF06103 Texas Tower- Pre TA - Mar 24

GBMF06103.1 Milestones 286.0d 286.0d 0% 01-Feb-24 21-Mar-25 0.0d 21-Mar-25, GBMF06103.1 Milestones
A1000 Project Start date 0.0d A2570, A2640, A2500,
0.0d A3410, 0%
A1040,
01-Feb-24
A1080, A4430,
01-Feb-24
A4470, A1050, A5750,
20.0d A5840,
ProjectA5890
Start date
A1010 Turnaround 35.0d A4820 35.0d 0% 30-Jan-25* 19-Mar-25 0.0d Turnaround
A1030 Complete Project Ready for Operation 0.0d A5710 0.0d 0% 21-Mar-25 0.0d Complete Project Ready for Operation
GBMF06103.2 Project Management 22.0d 22.0d 0% 11-Sep-24 11-Oct-24 115.0d 11-Oct-24, GBMF06103.2 Project Management
A1080 Preparation of BOD 0.0d A1000 A1090 0.0d 0% 11-Sep-24 115.0d Preparation of BOD
A1090 Submission of BOD 5.0d A1080 A1100 5.0d 0% 16-Sep-24 20-Sep-24 115.0d Submission of BOD
A1100 Approval of BOD 15.0d A1090 15.0d 0% 23-Sep-24 11-Oct-24 115.0d Approval of BOD
GBMF06103.4 Pre-TA 604.0d 242.0d 0% 01-Jun-22 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4 Pre-TA

GBMF06103.4.3 Engineering 79.0d 78.0d 0% 07-Feb-24 A 31-May-24 203.0d 31-May-24, GBMF06103.4.3 Engineering
GBMF06103.4.3.4 Civil, Structural & Architectural 82.0d 45.0d 0% 28-Mar-24 A 31-May-24 210.0d 31-May-24, GBMF06103.4.3.4 Civil, Structural & Architectural
A4470 Study of complete structure from the point of 25.0d
dismantling
A1000 the fouling
A4480
members 0.0d 0% 28-Mar-24 A 26-Apr-24 A Study of complete structure from the point of dismantling the fouling members
A4430 Preparation of MTO for foundation bolts 9.0d A1000, A4460
A5780 9.0d 0% 01-Apr-24 11-Apr-24 170.0d Preparation of MTO for foundation bolts
A4480 STAAD PRO Modelling of structure to check stability
35.0d A4470
of structures after
A2430,removal
A5860of fouling
0.0d members.
0% 02-Apr-24 A 16-May-24 A STAAD PRO Modelling of structure to check stability of structures after removal of fouling members.
A4450 Ground Scanning for existing UG facilities 21.0d A5760 21.0d 0% 12-Apr-24 10-May-24 225.0d Ground Scanning for existing UG facilities
A4460 Design for Soil Improvement 21.0d A5760 A2980, A4430 0.0d 0% 17-Apr-24 A 15-May-24 A Design for Soil Improvement
A4440 Study of ground improvement requirement for21.0d
crane A5760
placement 36.0d 0% 26-Apr-24 A 31-May-24 210.0d Study of ground improvement requirement for crane placement
GBMF06103.4.3.2 Mechanical 53.0d 53.0d 0% 07-Feb-24 24-Apr-24 108.0d 24-Apr-24, GBMF06103.4.3.2 Mechanical
A1040 Avalaibility of MR/ critical documents for Charge0.0d
effluent
A1000
heat exchangers
A1110 (E-9401 A/B)
0.0d 0% 07-Feb-24 166.0d Avalaibility of MR/ critical documents for Charge effluent heat exchangers (E-9401 A/B)
A1050 Mechanical Scope 20.0d A1000, A5850
A4510, A4929, A2910,
20.0d A5920 0% 12-Mar-24 10-Apr-24 81.0d Mechanical Scope
A4510 Preparation of Spring Support MR 21.0d A1050 A4530, A2910 21.0d 0% 27-Mar-24 24-Apr-24 109.0d Preparation of Spring Support MR
GBMF06103.4.3.3 Electrical & Instrumentation 30.0d 30.0d 0% 14-Mar-24 24-Apr-24 106.0d 24-Apr-24, GBMF06103.4.3.3 Electrical & Instrumentation
A3410 Study of existing E&I equipment/bulks 9.0d A1000 A3430 9.0d 0% 14-Mar-24 26-Mar-24 106.0d Study of existing E&I equipment/bulks
A3430 Identification of requirement /BOQ for E & I replacement
20.0d A3410 A1220, A5930 20.0d 0% 28-Mar-24 24-Apr-24 106.0d Identification of requirement /BOQ for E & I replacement
GBMF06103.4.5 Procurement 604.0d 242.0d 0% 01-Jun-22 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4.5 Procurement
GBMF06103.4.5.2 Material & Bulks 150.0d 150.0d 0% 11-Apr-24 11-Nov-24 86.0d 11-Nov-24, GBMF06103.4.5.2 Material & Bulks
A5920 Enquiry to Delivery at Site - Piping Bulks (Flanges,
150.0dBolts,
A1050 Gaskets)A5321 150.0d 0% 11-Apr-24 11-Nov-24 81.0d Enquiry to Delivery at Site - Piping Bulks (Flanges, Bolts, Gaskets)
A5930 Enquiry to Delivery at Site - E & I Bulks 120.0d A3430 A5510 120.0d 0% 25-Apr-24 14-Oct-24 106.0d Enquiry to Delivery at Site - E & I Bulks
GBMF06103.4.5.3 Bought out items 545.0d 135.0d 0% 01-Jun-22 A 21-Oct-24 103.0d 21-Oct-24, GBMF06103.4.5.3 Bought out items
GBMF06103.4.5.3.2 Exchangers vendor 386.0d 0.0d 0% 01-Jun-22 A 30-Nov-23 A 30-Nov-23 A, GBMF06103.4.5.3.2 Exchangers vendor
A1110 RFQ for Charge effluent heat exchangers (E-9401
5.0dA/B)
A1040 A1150 0.0d 0% 01-Jun-22 A 07-Jun-22 A
A1150 Issue of PO for Exchangers 0.0d A1110 A3450 0.0d 100% 10-Aug-22 A
A3450 Delivery at ESSAR UK site 0.0d A1150 A2988, A4940, A2760,
0.0d A2970, 0%
A4929 30-Nov-23 A Delivery at ESSAR UK site
GBMF06103.4.5.3.5 Foundation Bolts 76.0d 76.0d 0% 12-Apr-24 26-Jul-24 170.0d 26-Jul-24, GBMF06103.4.5.3.5 Foundation Bolts
A5780 Issue Enquiry for Foundation bolts 5.0d A4430 A5790 5.0d 0% 12-Apr-24 18-Apr-24 170.0d Issue Enquiry for Foundation bolts
A5790 Issue of PO for Foundation bolts 0.0d A5780 A5800 0.0d 0% 17-May-24 170.0d Issue of PO for Foundation bolts
A5800 Delivery at ESSAR UK site 0.0d A5790 0.0d 0% 26-Jul-24 170.0d Delivery at ESSAR UK site
GBMF06103.4.5.3.4 Piping Spring supports/ Flanges 128.0d 128.0d 0% 25-Apr-24 21-Oct-24 109.0d 21-Oct-24, GBMF06103.4.5.3.4 Piping Spring supports/ Flanges
A4530 Issue Enquiry for Spring Supports / Flanges 10.0d A4510 A4570 10.0d 0% 25-Apr-24 08-May-24 109.0d Issue Enquiry for Spring Supports / Flanges
A4570 Issue of PO 5.0d A4530 A4580 5.0d 0% 19-Jun-24 25-Jun-24 109.0d Issue of PO
A4580 Delivery at site 0.0d A4570 0.0d 0% 21-Oct-24 109.0d Delivery at site
GBMF06103.4.5.3.3 Electrical & I materials 118.0d 118.0d 0% 02-May-24 17-Oct-24 105.0d 17-Oct-24, GBMF06103.4.5.3.3 Electrical & I materials
A1220 Issue Enquiry for for E&I 10.0d A3430 A1260 10.0d 0% 02-May-24 15-May-24 106.0d Issue Enquiry for for E&I
A1260 Issue of PO 2.0d A1220 A1270 2.0d 0% 13-Jun-24 14-Jun-24 106.0d Issue of PO
A1270 Delivery at site 5.0d A1260 5.0d 0% 11-Oct-24 17-Oct-24 105.0d Delivery at site
GBMF06103.4.5.3.1 Insulation materials 105.0d 105.0d 0% 11-Apr-24 04-Sep-24 142.0d 04-Sep-24, GBMF06103.4.5.3.1 Insulation materials
A4929 Issue Enquiry for Insulation Material 10.0d A3450, A1050
A4930 10.0d 0% 11-Apr-24 24-Apr-24 142.0d Issue Enquiry for Insulation Material
A4930 Issue of PO 2.0d A4929 A4940 2.0d 0% 27-May-24 28-May-24 142.0d Issue of PO
A4940 Delivery at site 5.0d A3450, A4930 5.0d 0% 29-Aug-24 04-Sep-24 142.0d Delivery at site

Actual Work Critical Remaining Work Summary Page 1 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
GBMF06103.4.5.1 Sub-contractors 242.0d 242.0d 0% 01-Feb-24 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4.5.1 Sub-contractors
GBMF06103.4.5.1.2 Agency to Analyse Soil data 58.0d 58.0d 0% 29-Feb-24 A 23-May-24 208.0d 23-May-24, GBMF06103.4.5.1.2 Agency to Analyse Soil data
A5750 Enquiry for Agency for Soil Analysis 5.0d A1000 A5760 5.0d 0% 29-Feb-24 06-Mar-24 149.0d Enquiry for Agency for Soil Analysis
A5770 Design Analysis 30.0d A5760 30.0d 0% 12-Apr-24 23-May-24 216.0d Design Analysis
A5760 Issue of WO 10.0d A5750 A5770, A4460, A4440,
0.0d A4450 0% 12-Apr-24 A 25-Apr-24 A Issue of WO
GBMF06103.4.5.1.5 Civil Works 64.0d 64.0d 0% 01-Feb-24 02-May-24 102.0d 02-May-24, GBMF06103.4.5.1.5 Civil Works
A2430 Enquiry for Civil Works 10.0d A4480 A2470, A2710, A5820
10.0d 0% 01-Feb-24 14-Feb-24 100.0d Enquiry for Civil Works
A2470 Issue of WO 10.0d A2430 A2480 10.0d 0% 22-Mar-24 04-Apr-24 105.0d Issue of WO
A2480 Mobilization 20.0d A2470 A2980, A2995 20.0d 0% 05-Apr-24 02-May-24 105.0d Mobilization
GBMF06103.4.5.1.4 Structural Works 64.0d 64.0d 0% 01-Feb-24 02-May-24 102.0d 02-May-24, GBMF06103.4.5.1.4 Structural Works
A5860 Enquiry for Structural Works 10.0d A4480 A5870, A2710, A5820
10.0d 0% 01-Feb-24 14-Feb-24 100.0d Enquiry for Structural Works
A5870 Issue of WO 10.0d A5860 A5880 10.0d 0% 22-Mar-24 04-Apr-24 105.0d Issue of WO
A5880 Mobilization 20.0d A5870 A2980, A2995 20.0d 0% 05-Apr-24 02-May-24 105.0d Mobilization
GBMF06103.4.5.1.3 Scafolding Works 30.0d 30.0d 0% 15-Feb-24 27-Mar-24 96.0d 27-Mar-24, GBMF06103.4.5.1.3 Scafolding Works
A5820 Issue of WO for Scafolding 10.0d A2430, A5860
A5830 10.0d 0% 15-Feb-24 28-Feb-24 100.0d Issue of WO for Scafolding
A5830 Mobilization 20.0d A5820 A3005 20.0d 0% 29-Feb-24 27-Mar-24 100.0d Mobilization
GBMF06103.4.5.1.7 Mechanical Contractor 69.0d 69.0d 0% 15-Aug-24 21-Nov-24 81.0d 21-Nov-24, GBMF06103.4.5.1.7 Mechanical Contractor
A2500 Enquiry for Mechanical Contractor 10.0d A1000 A2540 10.0d 0% 15-Aug-24 28-Aug-24 87.0d Enquiry for Mechanical Contractor
A2540 Issue of WO 10.0d A2500 A2550 10.0d 0% 24-Oct-24 06-Nov-24 87.0d Issue of WO
A2550 Mobilization 0.0d A2540 0.0d 0% 21-Nov-24 21-Nov-24 87.0d Mobilization
GBMF06103.4.5.1.8 E & I contractor 69.0d 69.0d 0% 15-Aug-24 21-Nov-24 81.0d 21-Nov-24, GBMF06103.4.5.1.8 E & I contractor
A5890 Enquiry for E&I Contractor 10.0d A1000 A5900 10.0d 0% 15-Aug-24 28-Aug-24 87.0d Enquiry for E&I Contractor
A5900 Issue of WO 10.0d A5890 A5910 10.0d 0% 24-Oct-24 06-Nov-24 87.0d Issue of WO
A5910 Mobilization 0.0d A5900 0.0d 0% 21-Nov-24 21-Nov-24 87.0d Mobilization
GBMF06103.4.5.1.12 Insulation contractor 82.0d 82.0d 0% 25-Apr-24 20-Aug-24 113.5d 20-Aug-24, GBMF06103.4.5.1.12 Insulation contractor
A2910 Scope of work/ Requirement to be given to SCM
5.0d A1050, A4510
A2960 5.0d 0% 25-Apr-24 01-May-24 120.5d Scope of work/ Requirement to be given to SCM
A2960 Issue of WO 5.0d A2910 A2970 5.0d 0% 12-Jul-24 18-Jul-24 120.5d Issue of WO
A2970 Mobilization 20.0d A3450, A2960
A2988 20.0d 0% 24-Jul-24 20-Aug-24 120.5d Mobilization
GBMF06103.4.5.1.1 Laser Scanning 48.0d 48.0d 0% 01-Feb-24 10-Apr-24 81.0d 10-Apr-24, GBMF06103.4.5.1.1 Laser Scanning
A5840 Issue of WO for Laser Scanning 30.0d A1000 A5850 30.0d 0% 01-Feb-24 13-Mar-24 83.0d Issue of WO for Laser Scanning
A5850 Mobilization & Laser Scanning 20.0d A5840 A1050 20.0d 0% 14-Mar-24 10-Apr-24 83.0d Mobilization & Laser Scanning
GBMF06103.4.5.1.6 Crane Vendors 237.0d 237.0d 0% 08-Feb-24 20-Jan-25 20.0d 20-Jan-25, GBMF06103.4.5.1.6 Crane Vendors
GBMF06103.4.5.1.6.9 Crane Vendor (250 MT) 48.0d 48.0d 0% 08-Feb-24 17-Apr-24 113.0d 17-Apr-24, GBMF06103.4.5.1.6.9 Crane Vendor (250 MT)
A2710 Scope of work/ Requirement to be given to SCM
5.0d A2430, A5860
A2750 5.0d 0% 08-Feb-24 14-Feb-24 116.0d Scope of work/ Requirement to be given to SCM
A2750 Issue of WO 2.0d A2710 A2760 2.0d 0% 05-Apr-24 08-Apr-24 116.0d Issue of WO
A2760 Crane Deployment 5.0d A3450, A2750
A2995 5.0d 0% 11-Apr-24 17-Apr-24 116.0d Crane Deployment
GBMF06103.4.5.1.6.8 Crane Vendor (650 MT) 94.0d 94.0d 0% 29-Aug-24 15-Jan-25 20.0d 15-Jan-25, GBMF06103.4.5.1.6.8 Crane Vendor (650 MT)
A2640 Scope of work/ Requirement to be given to SCM
5.0d A1000 A2680 5.0d 0% 29-Aug-24 04-Sep-24 27.0d Scope of work/ Requirement to be given to SCM
A2680 Issue of WO 10.0d A2640 A2690 10.0d 0% 28-Oct-24 08-Nov-24 27.0d Issue of WO
A2690 Crane Assembly 30.0d A2680, A2620
A5650 30.0d 0% 05-Dec-24 15-Jan-25 20.0d Crane Assembly
GBMF06103.4.5.1.6.7 Crane Vendor (1250 MT) 97.0d 97.0d 0% 29-Aug-24 20-Jan-25 20.0d 20-Jan-25, GBMF06103.4.5.1.6.7 Crane Vendor (1250 MT)
A2570 Scope of work/ Requirement to be given to SCM
5.0d A1000 A2610 5.0d 0% 29-Aug-24 04-Sep-24 20.0d Scope of work/ Requirement to be given to SCM
A2610 Issue of WO 15.0d A2570 A2620 15.0d 0% 25-Oct-24 14-Nov-24 20.0d Issue of WO
A2620 Crane Assembly 35.0d A2610, A2980
A2690 35.0d 0% 03-Dec-24 20-Jan-25 20.0d Crane Assembly
GBMF06103.9 Construction 246.0d 246.0d 0% 28-Mar-24 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9 Construction

GBMF06103.9.4 Pre-TA 131.5d 131.5d 0% 28-Mar-24 04-Oct-24 114.5d 04-Oct-24, GBMF06103.9.4 Pre-TA
GBMF06103.9.4.3 Civil & Structural 118.0d 118.0d 0% 28-Mar-24 16-Sep-24 92.0d 16-Sep-24, GBMF06103.9.4.3 Civil & Structural
A3005 Scafolding Works 30.0d A5830 A2995 30.0d 0% 28-Mar-24 13-May-24 96.0d Scafolding Works
A2980 Soil Improvement for lifting crane 35.0d A2480, A4460,
A2620
A5880 35.0d 0% 07-May-24 24-Jun-24 132.0d Soil Improvement for lifting crane
A2995 Structure modification (Addition/Removal of members),Temporary
90.0d A2760, A2480,
A5230
supports
A3005, A588090.0d 0% 14-May-24 16-Sep-24 98.0d Structure modification (Addition/Removal of members),Temporary supports
GBMF06103.9.4.1 Insulation 48.0d 48.0d 0% 22-Aug-24 04-Oct-24 189.6d 04-Oct-24, GBMF06103.9.4.1 Insulation

Actual Work Critical Remaining Work Summary Page 2 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
A2988 Scafolding for Insulation 15.0d A3450, A2970 A2989 15.0d 0% 22-Aug-24 05-Sep-24 189.6d Scafolding for Insulation
A2989 Exchanger insulation 30.0d A2988 30.0d 0% 07-Sep-24 04-Oct-24 189.6d Exchanger insulation
GBMF06103.9.2 TA 38.0d 38.0d 0% 29-Jan-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.2 TA
GBMF06103.9.2.2 Gratings removal 1.0d 1.0d 0% 31-Jan-25 31-Jan-25 0.0d 31-Jan-25, GBMF06103.9.2.2 Gratings removal
A5230 Removal of gratings 1.0d A5220, A4830,
A5030
A2995 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removal of gratings
GBMF06103.9.2.1 Mechanical & Piping 35.0d 35.0d 0% 31-Jan-25 20-Mar-25 1.0d 20-Mar-25, GBMF06103.9.2.1 Mechanical & Piping
GBMF06103.9.2.1.3 Heat tracing pipes removal 1.0d 1.0d 0% 31-Jan-25 31-Jan-25 0.0d 31-Jan-25, GBMF06103.9.2.1.3 Heat tracing pipes removal
A5220 Removing the heat tracing pipes 1.0d A5210 A5230 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removing the heat tracing pipes
A5210 Removing the flange connections 1.0d A4830 A5220 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removing the flange connections
GBMF06103.9.2.1.7 Structure & Piping Removal 8.0d 8.0d 0% 03-Feb-25 12-Feb-25 0.0d 12-Feb-25, GBMF06103.9.2.1.7 Structure & Piping Removal
GBMF06103.9.2.1.7.4 Crane activity-1 1.0d 1.0d 0% 03-Feb-25 03-Feb-25 0.0d 03-Feb-25, GBMF06103.9.2.1.7.4 Crane activity-1
A5030 Tying & holding the structure,welded pipes on north
1.0d &A5230
south side A5000 1.0d 0% 03-Feb-25 03-Feb-25 0.0d Tying & holding the structure,welded pipes on north & south side
GBMF06103.9.2.1.7.2 Below Slab Level 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.2 Below Slab Level
A5000 Unbolting the flanges of pipes on north and south
1.0dside
A5030 A4639 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Unbolting the flanges of pipes on north and south side
GBMF06103.9.2.1.7.1 Slab Level to Structure Level 1 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.1 Slab Level to Structure Level 1
A4639 Pipe cutting on north side 1.0d A5000 A5040, A5020 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Pipe cutting on north side
GBMF06103.9.2.1.7.3 Structure Level 4 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.3 Structure Level 4
A5020 Removal of pipe flange joints with equipment -1.0d
southA4639
side A5040, A5590 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Removal of pipe flange joints with equipment - south side
GBMF06103.9.2.1.7.6 Structure Level 5 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.6 Structure Level 5
A5590 Removal of piping elbows having flange joints with
1.0dpipe
A5020
and equipment-
A5740,north
A5040side 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Removal of piping elbows having flange joints with pipe and equipment- north side
GBMF06103.9.2.1.7.8 Crane activity-2 2.0d 2.0d 0% 06-Feb-25 07-Feb-25 0.0d 07-Feb-25, GBMF06103.9.2.1.7.8 Crane activity-2
A5740 Lifting & Removal of pipes on north side 2.0d A5590 A5600 2.0d 0% 06-Feb-25 07-Feb-25 0.0d Lifting & Removal of pipes on north side
1.0d
GBMF06103.9.2.1.7.5 Removal of structure fouling members 1.0d 0% 05-Feb-25 05-Feb-25 3.0d 05-Feb-25, GBMF06103.9.2.1.7.5 Removal of structure fouling members
A5040 Unbolting & removal of the members fouling with
1.0dtheA5020,
equipment
A4639,
A5600
A5590 1.0d 0% 05-Feb-25 05-Feb-25 3.0d Unbolting & removal of the members fouling with the equipment
GBMF06103.9.2.1.7.7 Crane activity-3 2.0d 2.0d 0% 11-Feb-25 12-Feb-25 0.0d 12-Feb-25, GBMF06103.9.2.1.7.7 Crane activity-3
A5600 Lifting and removal of structure along with welded
1.0dpipes
A5740, A5040
A5610 1.0d 0% 11-Feb-25 11-Feb-25 0.0d Lifting and removal of structure along with welded pipes
A5610 Placement of the structure on temporary foundation
0.0d A5600 A5640 0.0d 0% 12-Feb-25 12-Feb-25 0.0d Placement of the structure on temporary foundation
A5640 Alignment & bolt torquing on temporary foundation
1.0d A5610 A5650, A5620 1.0d 0% 12-Feb-25 12-Feb-25 0.0d Alignment & bolt torquing on temporary foundation
GBMF06103.9.2.1.2 Old Equipment removal 11.0d 11.0d 0% 13-Feb-25 27-Feb-25 16.0d 27-Feb-25, GBMF06103.9.2.1.2 Old Equipment removal
A5650 Tying & holding Equipment A in place 1.0d A5640, A2690
A5660 1.0d 0% 13-Feb-25 13-Feb-25 0.0d Tying & holding Equipment A in place
A5660 Unbolting of the foundation bolts of equipment1.0d
A A5650 A5670 1.0d 0% 14-Feb-25 14-Feb-25 0.0d Unbolting of the foundation bolts of equipment A
A5670 Lifting and removal of equipment A (2 days reserved
3.0d A5660
for bad weather)
A5680 3.0d 0% 17-Feb-25 19-Feb-25 0.0d Lifting and removal of equipment A (2 days reserved for bad weather)
A5680 Tying & holding Equipment B in place 1.0d A5670 A5690 1.0d 0% 20-Feb-25 20-Feb-25 0.0d Tying & holding Equipment B in place
A5690 Unbolting of the foundation bolts of equipment1.0d
B A5680 A5700 1.0d 0% 21-Feb-25 21-Feb-25 0.0d Unbolting of the foundation bolts of equipment B
A5700 Lifting and removal of equipment B (2 days reserved
3.0d A5690
for bad weather)
A5720, A5250 3.0d 0% 24-Feb-25 26-Feb-25 0.0d Lifting and removal of equipment B (2 days reserved for bad weather)
A5730 Foundation bolts inspection 1.0d A5720 1.0d 0% 27-Feb-25 27-Feb-25 16.0d Foundation bolts inspection
A5720 Cleaning & Chipping of the foundation 1.0d A5700 A5730 1.0d 0% 27-Feb-25 27-Feb-25 16.0d Cleaning & Chipping of the foundation
2.0d
GBMF06103.9.2.1.1 Replacement of old spring supports at temporary foundation 2.0d 0% 14-Feb-25 17-Feb-25 24.0d 17-Feb-25, GBMF06103.9.2.1.1 Replacement of old spring supports at temporary found
A5620 Removal of existing/old spring supports 1.0d A5640 A5630 1.0d 0% 14-Feb-25 14-Feb-25 24.0d Removal of existing/old spring supports
A5630 Installation of new spring supports 1.0d A5620 1.0d 0% 17-Feb-25 17-Feb-25 24.0d Installation of new spring supports
GBMF06103.9.2.1.4 New equipment Installation 6.0d 6.0d 0% 28-Feb-25 07-Mar-25 0.0d 07-Mar-25, GBMF06103.9.2.1.4 New equipment Installation
A5250 Tying & holding new Equipment A in place 1.0d A5700 A5260 1.0d 0% 28-Feb-25 28-Feb-25 0.0d Tying & holding new Equipment A in place
A5260 Lifting and installation of equipment A 1.0d A5250 A5261 1.0d 0% 03-Mar-25 03-Mar-25 0.0d Lifting and installation of equipment A
A5261 Alignment & grouting of equipment A 1.0d A5260 A5270 1.0d 0% 04-Mar-25 04-Mar-25 0.0d Alignment & grouting of equipment A
A5270 Tying & holding new Equipment B in place 1.0d A5261 A5280 1.0d 0% 05-Mar-25 05-Mar-25 0.0d Tying & holding new Equipment B in place
A5280 Lifting and installation of equipment B 1.0d A5270 A5290 1.0d 0% 06-Mar-25 06-Mar-25 0.0d Lifting and installation of equipment B
A5290 Alignment & grouting of equipment B 1.0d A5280 A5300 1.0d 0% 07-Mar-25 07-Mar-25 0.0d Alignment & grouting of equipment B
GBMF06103.9.2.1.5 Structure & piping installation 8.0d 8.0d 0% 10-Mar-25 19-Mar-25 0.0d 19-Mar-25, GBMF06103.9.2.1.5 Structure & piping installation
A5300 Tying & holding of the structure with welded pipes
1.0din place
A5290 A5310 1.0d 0% 10-Mar-25 10-Mar-25 0.0d Tying & holding of the structure with welded pipes in place
A5310 Lifting & erecting the structure with welded pipes
1.0d A5300 A5311 1.0d 0% 11-Mar-25 11-Mar-25 0.0d Lifting & erecting the structure with welded pipes
A5311 Alignment & bolt torquing 1.0d A5310 A5321 1.0d 0% 12-Mar-25 12-Mar-25 0.0d Alignment & bolt torquing
A5321 Fixing of flanges of pipes on north and south side
1.0dbelow
A5311,
slabA5920
levelA5331 1.0d 0% 13-Mar-25 13-Mar-25 0.0d Fixing of flanges of pipes on north and south side below slab level

Actual Work Critical Remaining Work Summary Page 3 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
A5331 Fixing of pipes on north side between slab level
1.0d
& Structure
A5321 level-1A5341 1.0d 0% 14-Mar-25 14-Mar-25 0.0d Fixing of pipes on north side between slab level & Structure level-1
A5341 Fixing of pipe flange joints with equipment - south
1.0dside
A5331
at Structure
A5351
level-4 1.0d 0% 17-Mar-25 17-Mar-25 0.0d Fixing of pipe flange joints with equipment - south side at Structure level-4
A5351 Fixing of piping elbows having flange joints with1.0d
pipe A5341
and equipment-
A5361north side at structure
1.0d level-5
0% 18-Mar-25 18-Mar-25 0.0d Fixing of piping elbows having flange joints with pipe and equipment- north side at s
A5361 Fixing back of removed structural members fouling
1.0d with
A5351
the equipment
A5540 1.0d 0% 19-Mar-25 19-Mar-25 0.0d Fixing back of removed structural members fouling with the equipment
GBMF06103.9.2.1.8 Installation of heat tracing pipes 1.0d 1.0d 0% 20-Mar-25 20-Mar-25 1.0d 20-Mar-25, GBMF06103.9.2.1.8 Installation of heat tracing pipes
A5480 Flange connections 1.0d A5470 1.0d 0% 20-Mar-25 20-Mar-25 1.0d Flange connections
A5470 Laying of heat tracing pipes 1.0d A5540 A5480 1.0d 0% 20-Mar-25 20-Mar-25 1.0d Laying of heat tracing pipes
GBMF06103.9.2.3 Electrical & Instrumentation removal 2.0d 2.0d 0% 29-Jan-25 30-Jan-25 0.0d 30-Jan-25, GBMF06103.9.2.3 Electrical & Instrumentation removal
A4830 Removal of cables & cable trays 2.0d A4822, A4821,
A5210,
A4820
A5230 2.0d 0% 29-Jan-25 30-Jan-25 0.0d Removal of cables & cable trays
A4822 Removing of area lightings (2 nos) 1.0d A4821 A4830 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of area lightings (2 nos)
A4821 Removing of JBs 1.0d A4820 A4830, A4822 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of JBs
A4820 Removing of TTs 1.0d A1010 A4821, A4830 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of TTs
GBMF06103.9.2.9 Electrical & Instrumentation installation 2.0d 2.0d 0% 20-Mar-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.2.9 Electrical & Instrumentation installation
A5510 Installation of area lightings 1.0d A5490, A5930
A5520 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of area lightings
A5500 Installation of JBs 1.0d A5490 A5520 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of JBs
A5490 Installation of TTs 1.0d A5540 A5500, A5510, A5520
1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of TTs
A5530 Cable termination 1.0d A5520 A5710 1.0d 0% 21-Mar-25 21-Mar-25 0.0d Cable termination
A5520 Installation of cable trays and cable laying 1.0d A5490, A5500,
A5530
A5510 1.0d 0% 21-Mar-25 21-Mar-25 0.0d Installation of cable trays and cable laying
GBMF06103.9.2.4 Gratings erection 1.0d 1.0d 0% 20-Mar-25 20-Mar-25 0.0d 20-Mar-25, GBMF06103.9.2.4 Gratings erection
A5540 Erection of gratings 1.0d A5361 A5470, A5490 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Erection of gratings
GBMF06103.9.1 RFSU 0.0d 0.0d 0% 21-Mar-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.1 RFSU
A5710 RFSU 0.0d A5530 A1030 0.0d 0% 21-Mar-25 0.0d RFSU

Actual Work Critical Remaining Work Summary Page 4 of 4 TASK filter: All Activities