GBMF06103 Texas Tower-Pre TA - Mar 24 GBMF06103 Texas Tower - Pre TA - Mar 24
GBMF06103 Texas Tower-Pre TA - Mar 24 GBMF06103 Texas Tower - Pre TA - Mar 24
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
GBMF06103 Texas Tower- Pre TA - Mar 24 648.0d 286.0d 0% 01-Jun-22 A 21-Mar-25 0.0d 21-Mar-25, GBMF06103 Texas Tower- Pre TA - Mar 24
GBMF06103.1 Milestones 286.0d 286.0d 0% 01-Feb-24 21-Mar-25 0.0d 21-Mar-25, GBMF06103.1 Milestones
A1000 Project Start date 0.0d A2570, A2640, A2500,
0.0d A3410, 0%
A1040,
01-Feb-24
A1080, A4430,
01-Feb-24
A4470, A1050, A5750,
20.0d A5840,
ProjectA5890
Start date
A1010 Turnaround 35.0d A4820 35.0d 0% 30-Jan-25* 19-Mar-25 0.0d Turnaround
A1030 Complete Project Ready for Operation 0.0d A5710 0.0d 0% 21-Mar-25 0.0d Complete Project Ready for Operation
GBMF06103.2 Project Management 22.0d 22.0d 0% 11-Sep-24 11-Oct-24 115.0d 11-Oct-24, GBMF06103.2 Project Management
A1080 Preparation of BOD 0.0d A1000 A1090 0.0d 0% 11-Sep-24 115.0d Preparation of BOD
A1090 Submission of BOD 5.0d A1080 A1100 5.0d 0% 16-Sep-24 20-Sep-24 115.0d Submission of BOD
A1100 Approval of BOD 15.0d A1090 15.0d 0% 23-Sep-24 11-Oct-24 115.0d Approval of BOD
GBMF06103.4 Pre-TA 604.0d 242.0d 0% 01-Jun-22 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4 Pre-TA
GBMF06103.4.3 Engineering 79.0d 78.0d 0% 07-Feb-24 A 31-May-24 203.0d 31-May-24, GBMF06103.4.3 Engineering
GBMF06103.4.3.4 Civil, Structural & Architectural 82.0d 45.0d 0% 28-Mar-24 A 31-May-24 210.0d 31-May-24, GBMF06103.4.3.4 Civil, Structural & Architectural
A4470 Study of complete structure from the point of 25.0d
dismantling
A1000 the fouling
A4480
members 0.0d 0% 28-Mar-24 A 26-Apr-24 A Study of complete structure from the point of dismantling the fouling members
A4430 Preparation of MTO for foundation bolts 9.0d A1000, A4460
A5780 9.0d 0% 01-Apr-24 11-Apr-24 170.0d Preparation of MTO for foundation bolts
A4480 STAAD PRO Modelling of structure to check stability
35.0d A4470
of structures after
A2430,removal
A5860of fouling
0.0d members.
0% 02-Apr-24 A 16-May-24 A STAAD PRO Modelling of structure to check stability of structures after removal of fouling members.
A4450 Ground Scanning for existing UG facilities 21.0d A5760 21.0d 0% 12-Apr-24 10-May-24 225.0d Ground Scanning for existing UG facilities
A4460 Design for Soil Improvement 21.0d A5760 A2980, A4430 0.0d 0% 17-Apr-24 A 15-May-24 A Design for Soil Improvement
A4440 Study of ground improvement requirement for21.0d
crane A5760
placement 36.0d 0% 26-Apr-24 A 31-May-24 210.0d Study of ground improvement requirement for crane placement
GBMF06103.4.3.2 Mechanical 53.0d 53.0d 0% 07-Feb-24 24-Apr-24 108.0d 24-Apr-24, GBMF06103.4.3.2 Mechanical
A1040 Avalaibility of MR/ critical documents for Charge0.0d
effluent
A1000
heat exchangers
A1110 (E-9401 A/B)
0.0d 0% 07-Feb-24 166.0d Avalaibility of MR/ critical documents for Charge effluent heat exchangers (E-9401 A/B)
A1050 Mechanical Scope 20.0d A1000, A5850
A4510, A4929, A2910,
20.0d A5920 0% 12-Mar-24 10-Apr-24 81.0d Mechanical Scope
A4510 Preparation of Spring Support MR 21.0d A1050 A4530, A2910 21.0d 0% 27-Mar-24 24-Apr-24 109.0d Preparation of Spring Support MR
GBMF06103.4.3.3 Electrical & Instrumentation 30.0d 30.0d 0% 14-Mar-24 24-Apr-24 106.0d 24-Apr-24, GBMF06103.4.3.3 Electrical & Instrumentation
A3410 Study of existing E&I equipment/bulks 9.0d A1000 A3430 9.0d 0% 14-Mar-24 26-Mar-24 106.0d Study of existing E&I equipment/bulks
A3430 Identification of requirement /BOQ for E & I replacement
20.0d A3410 A1220, A5930 20.0d 0% 28-Mar-24 24-Apr-24 106.0d Identification of requirement /BOQ for E & I replacement
GBMF06103.4.5 Procurement 604.0d 242.0d 0% 01-Jun-22 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4.5 Procurement
GBMF06103.4.5.2 Material & Bulks 150.0d 150.0d 0% 11-Apr-24 11-Nov-24 86.0d 11-Nov-24, GBMF06103.4.5.2 Material & Bulks
A5920 Enquiry to Delivery at Site - Piping Bulks (Flanges,
150.0dBolts,
A1050 Gaskets)A5321 150.0d 0% 11-Apr-24 11-Nov-24 81.0d Enquiry to Delivery at Site - Piping Bulks (Flanges, Bolts, Gaskets)
A5930 Enquiry to Delivery at Site - E & I Bulks 120.0d A3430 A5510 120.0d 0% 25-Apr-24 14-Oct-24 106.0d Enquiry to Delivery at Site - E & I Bulks
GBMF06103.4.5.3 Bought out items 545.0d 135.0d 0% 01-Jun-22 A 21-Oct-24 103.0d 21-Oct-24, GBMF06103.4.5.3 Bought out items
GBMF06103.4.5.3.2 Exchangers vendor 386.0d 0.0d 0% 01-Jun-22 A 30-Nov-23 A 30-Nov-23 A, GBMF06103.4.5.3.2 Exchangers vendor
A1110 RFQ for Charge effluent heat exchangers (E-9401
5.0dA/B)
A1040 A1150 0.0d 0% 01-Jun-22 A 07-Jun-22 A
A1150 Issue of PO for Exchangers 0.0d A1110 A3450 0.0d 100% 10-Aug-22 A
A3450 Delivery at ESSAR UK site 0.0d A1150 A2988, A4940, A2760,
0.0d A2970, 0%
A4929 30-Nov-23 A Delivery at ESSAR UK site
GBMF06103.4.5.3.5 Foundation Bolts 76.0d 76.0d 0% 12-Apr-24 26-Jul-24 170.0d 26-Jul-24, GBMF06103.4.5.3.5 Foundation Bolts
A5780 Issue Enquiry for Foundation bolts 5.0d A4430 A5790 5.0d 0% 12-Apr-24 18-Apr-24 170.0d Issue Enquiry for Foundation bolts
A5790 Issue of PO for Foundation bolts 0.0d A5780 A5800 0.0d 0% 17-May-24 170.0d Issue of PO for Foundation bolts
A5800 Delivery at ESSAR UK site 0.0d A5790 0.0d 0% 26-Jul-24 170.0d Delivery at ESSAR UK site
GBMF06103.4.5.3.4 Piping Spring supports/ Flanges 128.0d 128.0d 0% 25-Apr-24 21-Oct-24 109.0d 21-Oct-24, GBMF06103.4.5.3.4 Piping Spring supports/ Flanges
A4530 Issue Enquiry for Spring Supports / Flanges 10.0d A4510 A4570 10.0d 0% 25-Apr-24 08-May-24 109.0d Issue Enquiry for Spring Supports / Flanges
A4570 Issue of PO 5.0d A4530 A4580 5.0d 0% 19-Jun-24 25-Jun-24 109.0d Issue of PO
A4580 Delivery at site 0.0d A4570 0.0d 0% 21-Oct-24 109.0d Delivery at site
GBMF06103.4.5.3.3 Electrical & I materials 118.0d 118.0d 0% 02-May-24 17-Oct-24 105.0d 17-Oct-24, GBMF06103.4.5.3.3 Electrical & I materials
A1220 Issue Enquiry for for E&I 10.0d A3430 A1260 10.0d 0% 02-May-24 15-May-24 106.0d Issue Enquiry for for E&I
A1260 Issue of PO 2.0d A1220 A1270 2.0d 0% 13-Jun-24 14-Jun-24 106.0d Issue of PO
A1270 Delivery at site 5.0d A1260 5.0d 0% 11-Oct-24 17-Oct-24 105.0d Delivery at site
GBMF06103.4.5.3.1 Insulation materials 105.0d 105.0d 0% 11-Apr-24 04-Sep-24 142.0d 04-Sep-24, GBMF06103.4.5.3.1 Insulation materials
A4929 Issue Enquiry for Insulation Material 10.0d A3450, A1050
A4930 10.0d 0% 11-Apr-24 24-Apr-24 142.0d Issue Enquiry for Insulation Material
A4930 Issue of PO 2.0d A4929 A4940 2.0d 0% 27-May-24 28-May-24 142.0d Issue of PO
A4940 Delivery at site 5.0d A3450, A4930 5.0d 0% 29-Aug-24 04-Sep-24 142.0d Delivery at site
Actual Work Critical Remaining Work Summary Page 1 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
GBMF06103.4.5.1 Sub-contractors 242.0d 242.0d 0% 01-Feb-24 A 20-Jan-25 44.0d 20-Jan-25, GBMF06103.4.5.1 Sub-contractors
GBMF06103.4.5.1.2 Agency to Analyse Soil data 58.0d 58.0d 0% 29-Feb-24 A 23-May-24 208.0d 23-May-24, GBMF06103.4.5.1.2 Agency to Analyse Soil data
A5750 Enquiry for Agency for Soil Analysis 5.0d A1000 A5760 5.0d 0% 29-Feb-24 06-Mar-24 149.0d Enquiry for Agency for Soil Analysis
A5770 Design Analysis 30.0d A5760 30.0d 0% 12-Apr-24 23-May-24 216.0d Design Analysis
A5760 Issue of WO 10.0d A5750 A5770, A4460, A4440,
0.0d A4450 0% 12-Apr-24 A 25-Apr-24 A Issue of WO
GBMF06103.4.5.1.5 Civil Works 64.0d 64.0d 0% 01-Feb-24 02-May-24 102.0d 02-May-24, GBMF06103.4.5.1.5 Civil Works
A2430 Enquiry for Civil Works 10.0d A4480 A2470, A2710, A5820
10.0d 0% 01-Feb-24 14-Feb-24 100.0d Enquiry for Civil Works
A2470 Issue of WO 10.0d A2430 A2480 10.0d 0% 22-Mar-24 04-Apr-24 105.0d Issue of WO
A2480 Mobilization 20.0d A2470 A2980, A2995 20.0d 0% 05-Apr-24 02-May-24 105.0d Mobilization
GBMF06103.4.5.1.4 Structural Works 64.0d 64.0d 0% 01-Feb-24 02-May-24 102.0d 02-May-24, GBMF06103.4.5.1.4 Structural Works
A5860 Enquiry for Structural Works 10.0d A4480 A5870, A2710, A5820
10.0d 0% 01-Feb-24 14-Feb-24 100.0d Enquiry for Structural Works
A5870 Issue of WO 10.0d A5860 A5880 10.0d 0% 22-Mar-24 04-Apr-24 105.0d Issue of WO
A5880 Mobilization 20.0d A5870 A2980, A2995 20.0d 0% 05-Apr-24 02-May-24 105.0d Mobilization
GBMF06103.4.5.1.3 Scafolding Works 30.0d 30.0d 0% 15-Feb-24 27-Mar-24 96.0d 27-Mar-24, GBMF06103.4.5.1.3 Scafolding Works
A5820 Issue of WO for Scafolding 10.0d A2430, A5860
A5830 10.0d 0% 15-Feb-24 28-Feb-24 100.0d Issue of WO for Scafolding
A5830 Mobilization 20.0d A5820 A3005 20.0d 0% 29-Feb-24 27-Mar-24 100.0d Mobilization
GBMF06103.4.5.1.7 Mechanical Contractor 69.0d 69.0d 0% 15-Aug-24 21-Nov-24 81.0d 21-Nov-24, GBMF06103.4.5.1.7 Mechanical Contractor
A2500 Enquiry for Mechanical Contractor 10.0d A1000 A2540 10.0d 0% 15-Aug-24 28-Aug-24 87.0d Enquiry for Mechanical Contractor
A2540 Issue of WO 10.0d A2500 A2550 10.0d 0% 24-Oct-24 06-Nov-24 87.0d Issue of WO
A2550 Mobilization 0.0d A2540 0.0d 0% 21-Nov-24 21-Nov-24 87.0d Mobilization
GBMF06103.4.5.1.8 E & I contractor 69.0d 69.0d 0% 15-Aug-24 21-Nov-24 81.0d 21-Nov-24, GBMF06103.4.5.1.8 E & I contractor
A5890 Enquiry for E&I Contractor 10.0d A1000 A5900 10.0d 0% 15-Aug-24 28-Aug-24 87.0d Enquiry for E&I Contractor
A5900 Issue of WO 10.0d A5890 A5910 10.0d 0% 24-Oct-24 06-Nov-24 87.0d Issue of WO
A5910 Mobilization 0.0d A5900 0.0d 0% 21-Nov-24 21-Nov-24 87.0d Mobilization
GBMF06103.4.5.1.12 Insulation contractor 82.0d 82.0d 0% 25-Apr-24 20-Aug-24 113.5d 20-Aug-24, GBMF06103.4.5.1.12 Insulation contractor
A2910 Scope of work/ Requirement to be given to SCM
5.0d A1050, A4510
A2960 5.0d 0% 25-Apr-24 01-May-24 120.5d Scope of work/ Requirement to be given to SCM
A2960 Issue of WO 5.0d A2910 A2970 5.0d 0% 12-Jul-24 18-Jul-24 120.5d Issue of WO
A2970 Mobilization 20.0d A3450, A2960
A2988 20.0d 0% 24-Jul-24 20-Aug-24 120.5d Mobilization
GBMF06103.4.5.1.1 Laser Scanning 48.0d 48.0d 0% 01-Feb-24 10-Apr-24 81.0d 10-Apr-24, GBMF06103.4.5.1.1 Laser Scanning
A5840 Issue of WO for Laser Scanning 30.0d A1000 A5850 30.0d 0% 01-Feb-24 13-Mar-24 83.0d Issue of WO for Laser Scanning
A5850 Mobilization & Laser Scanning 20.0d A5840 A1050 20.0d 0% 14-Mar-24 10-Apr-24 83.0d Mobilization & Laser Scanning
GBMF06103.4.5.1.6 Crane Vendors 237.0d 237.0d 0% 08-Feb-24 20-Jan-25 20.0d 20-Jan-25, GBMF06103.4.5.1.6 Crane Vendors
GBMF06103.4.5.1.6.9 Crane Vendor (250 MT) 48.0d 48.0d 0% 08-Feb-24 17-Apr-24 113.0d 17-Apr-24, GBMF06103.4.5.1.6.9 Crane Vendor (250 MT)
A2710 Scope of work/ Requirement to be given to SCM
5.0d A2430, A5860
A2750 5.0d 0% 08-Feb-24 14-Feb-24 116.0d Scope of work/ Requirement to be given to SCM
A2750 Issue of WO 2.0d A2710 A2760 2.0d 0% 05-Apr-24 08-Apr-24 116.0d Issue of WO
A2760 Crane Deployment 5.0d A3450, A2750
A2995 5.0d 0% 11-Apr-24 17-Apr-24 116.0d Crane Deployment
GBMF06103.4.5.1.6.8 Crane Vendor (650 MT) 94.0d 94.0d 0% 29-Aug-24 15-Jan-25 20.0d 15-Jan-25, GBMF06103.4.5.1.6.8 Crane Vendor (650 MT)
A2640 Scope of work/ Requirement to be given to SCM
5.0d A1000 A2680 5.0d 0% 29-Aug-24 04-Sep-24 27.0d Scope of work/ Requirement to be given to SCM
A2680 Issue of WO 10.0d A2640 A2690 10.0d 0% 28-Oct-24 08-Nov-24 27.0d Issue of WO
A2690 Crane Assembly 30.0d A2680, A2620
A5650 30.0d 0% 05-Dec-24 15-Jan-25 20.0d Crane Assembly
GBMF06103.4.5.1.6.7 Crane Vendor (1250 MT) 97.0d 97.0d 0% 29-Aug-24 20-Jan-25 20.0d 20-Jan-25, GBMF06103.4.5.1.6.7 Crane Vendor (1250 MT)
A2570 Scope of work/ Requirement to be given to SCM
5.0d A1000 A2610 5.0d 0% 29-Aug-24 04-Sep-24 20.0d Scope of work/ Requirement to be given to SCM
A2610 Issue of WO 15.0d A2570 A2620 15.0d 0% 25-Oct-24 14-Nov-24 20.0d Issue of WO
A2620 Crane Assembly 35.0d A2610, A2980
A2690 35.0d 0% 03-Dec-24 20-Jan-25 20.0d Crane Assembly
GBMF06103.9 Construction 246.0d 246.0d 0% 28-Mar-24 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9 Construction
GBMF06103.9.4 Pre-TA 131.5d 131.5d 0% 28-Mar-24 04-Oct-24 114.5d 04-Oct-24, GBMF06103.9.4 Pre-TA
GBMF06103.9.4.3 Civil & Structural 118.0d 118.0d 0% 28-Mar-24 16-Sep-24 92.0d 16-Sep-24, GBMF06103.9.4.3 Civil & Structural
A3005 Scafolding Works 30.0d A5830 A2995 30.0d 0% 28-Mar-24 13-May-24 96.0d Scafolding Works
A2980 Soil Improvement for lifting crane 35.0d A2480, A4460,
A2620
A5880 35.0d 0% 07-May-24 24-Jun-24 132.0d Soil Improvement for lifting crane
A2995 Structure modification (Addition/Removal of members),Temporary
90.0d A2760, A2480,
A5230
supports
A3005, A588090.0d 0% 14-May-24 16-Sep-24 98.0d Structure modification (Addition/Removal of members),Temporary supports
GBMF06103.9.4.1 Insulation 48.0d 48.0d 0% 22-Aug-24 04-Oct-24 189.6d 04-Oct-24, GBMF06103.9.4.1 Insulation
Actual Work Critical Remaining Work Summary Page 2 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
A2988 Scafolding for Insulation 15.0d A3450, A2970 A2989 15.0d 0% 22-Aug-24 05-Sep-24 189.6d Scafolding for Insulation
A2989 Exchanger insulation 30.0d A2988 30.0d 0% 07-Sep-24 04-Oct-24 189.6d Exchanger insulation
GBMF06103.9.2 TA 38.0d 38.0d 0% 29-Jan-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.2 TA
GBMF06103.9.2.2 Gratings removal 1.0d 1.0d 0% 31-Jan-25 31-Jan-25 0.0d 31-Jan-25, GBMF06103.9.2.2 Gratings removal
A5230 Removal of gratings 1.0d A5220, A4830,
A5030
A2995 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removal of gratings
GBMF06103.9.2.1 Mechanical & Piping 35.0d 35.0d 0% 31-Jan-25 20-Mar-25 1.0d 20-Mar-25, GBMF06103.9.2.1 Mechanical & Piping
GBMF06103.9.2.1.3 Heat tracing pipes removal 1.0d 1.0d 0% 31-Jan-25 31-Jan-25 0.0d 31-Jan-25, GBMF06103.9.2.1.3 Heat tracing pipes removal
A5220 Removing the heat tracing pipes 1.0d A5210 A5230 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removing the heat tracing pipes
A5210 Removing the flange connections 1.0d A4830 A5220 1.0d 0% 31-Jan-25 31-Jan-25 0.0d Removing the flange connections
GBMF06103.9.2.1.7 Structure & Piping Removal 8.0d 8.0d 0% 03-Feb-25 12-Feb-25 0.0d 12-Feb-25, GBMF06103.9.2.1.7 Structure & Piping Removal
GBMF06103.9.2.1.7.4 Crane activity-1 1.0d 1.0d 0% 03-Feb-25 03-Feb-25 0.0d 03-Feb-25, GBMF06103.9.2.1.7.4 Crane activity-1
A5030 Tying & holding the structure,welded pipes on north
1.0d &A5230
south side A5000 1.0d 0% 03-Feb-25 03-Feb-25 0.0d Tying & holding the structure,welded pipes on north & south side
GBMF06103.9.2.1.7.2 Below Slab Level 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.2 Below Slab Level
A5000 Unbolting the flanges of pipes on north and south
1.0dside
A5030 A4639 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Unbolting the flanges of pipes on north and south side
GBMF06103.9.2.1.7.1 Slab Level to Structure Level 1 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.1 Slab Level to Structure Level 1
A4639 Pipe cutting on north side 1.0d A5000 A5040, A5020 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Pipe cutting on north side
GBMF06103.9.2.1.7.3 Structure Level 4 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.3 Structure Level 4
A5020 Removal of pipe flange joints with equipment -1.0d
southA4639
side A5040, A5590 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Removal of pipe flange joints with equipment - south side
GBMF06103.9.2.1.7.6 Structure Level 5 1.0d 1.0d 0% 04-Feb-25 04-Feb-25 0.0d 04-Feb-25, GBMF06103.9.2.1.7.6 Structure Level 5
A5590 Removal of piping elbows having flange joints with
1.0dpipe
A5020
and equipment-
A5740,north
A5040side 1.0d 0% 04-Feb-25 04-Feb-25 0.0d Removal of piping elbows having flange joints with pipe and equipment- north side
GBMF06103.9.2.1.7.8 Crane activity-2 2.0d 2.0d 0% 06-Feb-25 07-Feb-25 0.0d 07-Feb-25, GBMF06103.9.2.1.7.8 Crane activity-2
A5740 Lifting & Removal of pipes on north side 2.0d A5590 A5600 2.0d 0% 06-Feb-25 07-Feb-25 0.0d Lifting & Removal of pipes on north side
1.0d
GBMF06103.9.2.1.7.5 Removal of structure fouling members 1.0d 0% 05-Feb-25 05-Feb-25 3.0d 05-Feb-25, GBMF06103.9.2.1.7.5 Removal of structure fouling members
A5040 Unbolting & removal of the members fouling with
1.0dtheA5020,
equipment
A4639,
A5600
A5590 1.0d 0% 05-Feb-25 05-Feb-25 3.0d Unbolting & removal of the members fouling with the equipment
GBMF06103.9.2.1.7.7 Crane activity-3 2.0d 2.0d 0% 11-Feb-25 12-Feb-25 0.0d 12-Feb-25, GBMF06103.9.2.1.7.7 Crane activity-3
A5600 Lifting and removal of structure along with welded
1.0dpipes
A5740, A5040
A5610 1.0d 0% 11-Feb-25 11-Feb-25 0.0d Lifting and removal of structure along with welded pipes
A5610 Placement of the structure on temporary foundation
0.0d A5600 A5640 0.0d 0% 12-Feb-25 12-Feb-25 0.0d Placement of the structure on temporary foundation
A5640 Alignment & bolt torquing on temporary foundation
1.0d A5610 A5650, A5620 1.0d 0% 12-Feb-25 12-Feb-25 0.0d Alignment & bolt torquing on temporary foundation
GBMF06103.9.2.1.2 Old Equipment removal 11.0d 11.0d 0% 13-Feb-25 27-Feb-25 16.0d 27-Feb-25, GBMF06103.9.2.1.2 Old Equipment removal
A5650 Tying & holding Equipment A in place 1.0d A5640, A2690
A5660 1.0d 0% 13-Feb-25 13-Feb-25 0.0d Tying & holding Equipment A in place
A5660 Unbolting of the foundation bolts of equipment1.0d
A A5650 A5670 1.0d 0% 14-Feb-25 14-Feb-25 0.0d Unbolting of the foundation bolts of equipment A
A5670 Lifting and removal of equipment A (2 days reserved
3.0d A5660
for bad weather)
A5680 3.0d 0% 17-Feb-25 19-Feb-25 0.0d Lifting and removal of equipment A (2 days reserved for bad weather)
A5680 Tying & holding Equipment B in place 1.0d A5670 A5690 1.0d 0% 20-Feb-25 20-Feb-25 0.0d Tying & holding Equipment B in place
A5690 Unbolting of the foundation bolts of equipment1.0d
B A5680 A5700 1.0d 0% 21-Feb-25 21-Feb-25 0.0d Unbolting of the foundation bolts of equipment B
A5700 Lifting and removal of equipment B (2 days reserved
3.0d A5690
for bad weather)
A5720, A5250 3.0d 0% 24-Feb-25 26-Feb-25 0.0d Lifting and removal of equipment B (2 days reserved for bad weather)
A5730 Foundation bolts inspection 1.0d A5720 1.0d 0% 27-Feb-25 27-Feb-25 16.0d Foundation bolts inspection
A5720 Cleaning & Chipping of the foundation 1.0d A5700 A5730 1.0d 0% 27-Feb-25 27-Feb-25 16.0d Cleaning & Chipping of the foundation
2.0d
GBMF06103.9.2.1.1 Replacement of old spring supports at temporary foundation 2.0d 0% 14-Feb-25 17-Feb-25 24.0d 17-Feb-25, GBMF06103.9.2.1.1 Replacement of old spring supports at temporary found
A5620 Removal of existing/old spring supports 1.0d A5640 A5630 1.0d 0% 14-Feb-25 14-Feb-25 24.0d Removal of existing/old spring supports
A5630 Installation of new spring supports 1.0d A5620 1.0d 0% 17-Feb-25 17-Feb-25 24.0d Installation of new spring supports
GBMF06103.9.2.1.4 New equipment Installation 6.0d 6.0d 0% 28-Feb-25 07-Mar-25 0.0d 07-Mar-25, GBMF06103.9.2.1.4 New equipment Installation
A5250 Tying & holding new Equipment A in place 1.0d A5700 A5260 1.0d 0% 28-Feb-25 28-Feb-25 0.0d Tying & holding new Equipment A in place
A5260 Lifting and installation of equipment A 1.0d A5250 A5261 1.0d 0% 03-Mar-25 03-Mar-25 0.0d Lifting and installation of equipment A
A5261 Alignment & grouting of equipment A 1.0d A5260 A5270 1.0d 0% 04-Mar-25 04-Mar-25 0.0d Alignment & grouting of equipment A
A5270 Tying & holding new Equipment B in place 1.0d A5261 A5280 1.0d 0% 05-Mar-25 05-Mar-25 0.0d Tying & holding new Equipment B in place
A5280 Lifting and installation of equipment B 1.0d A5270 A5290 1.0d 0% 06-Mar-25 06-Mar-25 0.0d Lifting and installation of equipment B
A5290 Alignment & grouting of equipment B 1.0d A5280 A5300 1.0d 0% 07-Mar-25 07-Mar-25 0.0d Alignment & grouting of equipment B
GBMF06103.9.2.1.5 Structure & piping installation 8.0d 8.0d 0% 10-Mar-25 19-Mar-25 0.0d 19-Mar-25, GBMF06103.9.2.1.5 Structure & piping installation
A5300 Tying & holding of the structure with welded pipes
1.0din place
A5290 A5310 1.0d 0% 10-Mar-25 10-Mar-25 0.0d Tying & holding of the structure with welded pipes in place
A5310 Lifting & erecting the structure with welded pipes
1.0d A5300 A5311 1.0d 0% 11-Mar-25 11-Mar-25 0.0d Lifting & erecting the structure with welded pipes
A5311 Alignment & bolt torquing 1.0d A5310 A5321 1.0d 0% 12-Mar-25 12-Mar-25 0.0d Alignment & bolt torquing
A5321 Fixing of flanges of pipes on north and south side
1.0dbelow
A5311,
slabA5920
levelA5331 1.0d 0% 13-Mar-25 13-Mar-25 0.0d Fixing of flanges of pipes on north and south side below slab level
Actual Work Critical Remaining Work Summary Page 3 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Texas Tower- Pre TA - Mar 24 Classic WBS Layout 29-May-24 17:37
Activity ID Activity Name Original PredecessorsSuccessorsRemaining Schedule Start Finish Total 2024 2025 2026
Duration Duration % Float
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Complete
A5331 Fixing of pipes on north side between slab level
1.0d
& Structure
A5321 level-1A5341 1.0d 0% 14-Mar-25 14-Mar-25 0.0d Fixing of pipes on north side between slab level & Structure level-1
A5341 Fixing of pipe flange joints with equipment - south
1.0dside
A5331
at Structure
A5351
level-4 1.0d 0% 17-Mar-25 17-Mar-25 0.0d Fixing of pipe flange joints with equipment - south side at Structure level-4
A5351 Fixing of piping elbows having flange joints with1.0d
pipe A5341
and equipment-
A5361north side at structure
1.0d level-5
0% 18-Mar-25 18-Mar-25 0.0d Fixing of piping elbows having flange joints with pipe and equipment- north side at s
A5361 Fixing back of removed structural members fouling
1.0d with
A5351
the equipment
A5540 1.0d 0% 19-Mar-25 19-Mar-25 0.0d Fixing back of removed structural members fouling with the equipment
GBMF06103.9.2.1.8 Installation of heat tracing pipes 1.0d 1.0d 0% 20-Mar-25 20-Mar-25 1.0d 20-Mar-25, GBMF06103.9.2.1.8 Installation of heat tracing pipes
A5480 Flange connections 1.0d A5470 1.0d 0% 20-Mar-25 20-Mar-25 1.0d Flange connections
A5470 Laying of heat tracing pipes 1.0d A5540 A5480 1.0d 0% 20-Mar-25 20-Mar-25 1.0d Laying of heat tracing pipes
GBMF06103.9.2.3 Electrical & Instrumentation removal 2.0d 2.0d 0% 29-Jan-25 30-Jan-25 0.0d 30-Jan-25, GBMF06103.9.2.3 Electrical & Instrumentation removal
A4830 Removal of cables & cable trays 2.0d A4822, A4821,
A5210,
A4820
A5230 2.0d 0% 29-Jan-25 30-Jan-25 0.0d Removal of cables & cable trays
A4822 Removing of area lightings (2 nos) 1.0d A4821 A4830 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of area lightings (2 nos)
A4821 Removing of JBs 1.0d A4820 A4830, A4822 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of JBs
A4820 Removing of TTs 1.0d A1010 A4821, A4830 1.0d 0% 30-Jan-25 30-Jan-25 0.0d Removing of TTs
GBMF06103.9.2.9 Electrical & Instrumentation installation 2.0d 2.0d 0% 20-Mar-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.2.9 Electrical & Instrumentation installation
A5510 Installation of area lightings 1.0d A5490, A5930
A5520 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of area lightings
A5500 Installation of JBs 1.0d A5490 A5520 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of JBs
A5490 Installation of TTs 1.0d A5540 A5500, A5510, A5520
1.0d 0% 20-Mar-25 20-Mar-25 0.0d Installation of TTs
A5530 Cable termination 1.0d A5520 A5710 1.0d 0% 21-Mar-25 21-Mar-25 0.0d Cable termination
A5520 Installation of cable trays and cable laying 1.0d A5490, A5500,
A5530
A5510 1.0d 0% 21-Mar-25 21-Mar-25 0.0d Installation of cable trays and cable laying
GBMF06103.9.2.4 Gratings erection 1.0d 1.0d 0% 20-Mar-25 20-Mar-25 0.0d 20-Mar-25, GBMF06103.9.2.4 Gratings erection
A5540 Erection of gratings 1.0d A5361 A5470, A5490 1.0d 0% 20-Mar-25 20-Mar-25 0.0d Erection of gratings
GBMF06103.9.1 RFSU 0.0d 0.0d 0% 21-Mar-25 21-Mar-25 0.0d 21-Mar-25, GBMF06103.9.1 RFSU
A5710 RFSU 0.0d A5530 A1030 0.0d 0% 21-Mar-25 0.0d RFSU
Actual Work Critical Remaining Work Summary Page 4 of 4 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation