139
APPENDIX E1
                                              [See rules 17(5)(e),20(1)&88 (1)]
                              COMPLETION CERTIFICATE BY THE OWNER
                                                           CERTIFICATE
Certified that the development or redevelopment of land and/or construction or
reconstruction or addition or alteration of building / erection of Telecommunication tower or
pole structure has been completed on . . . . . . . . . . . . . . . . . as per the approved plan and permit
number . . . . . . . . . . . .. . .. . .dated . . . . . . . . . . . . . . . .
Place:                                                                  Signature
Date:                                                                   Name and address of owner.
  This is a digitally signed Gazette.
  Authenticity may be verified through https://compose.kerala.gov.in/