DG198 DIRIYAH SQUARE
PAINTING SUBCONTRACT - SUPPLY & INSTALLATION
(ALL INCLUSIVE RATES)
BILL Section Page Unit Rate Unit Rate Unit Rate TOTAL AMOUNT
Area Item ref. DESCRIPTION QTY U.M. Remarks
ref. ref. ref. (Supply portion) (Install portion) (all-inclusive) (SAR)
BASEMENT
SECTION - J FINISHES
Internal Finishes
Wall Finishes
Finishes to walls, as shown in enhanced finishes drawings,to manufacturer's recommendation; all in
accordancewith drawings and specification
47.00 166,221.14
Basement B2 J 7 A Adobe render finish, type AR 1 comprised of SP-02 type wall perforations 12.00 35
3,536.62 m2
47.00 44,989.81
Basement B2 J 7 B Light colored render, type TRM-151 957.23 m2 12.00
35
Ceiling Finishes
Gypsum panels; RAL 9010/painted matte; including finishes, fittings, fixings and necessary
accessories to complete theinstallation; all in accordance with the drawings andspecification
41.50 74,949.00
Basement B2 J 8 A To ceilings; type CLG-101 : CL-01 1,806.00 m2 11.50
30
Fire rated suspended ceilings; RAL 90116/painted matte; including finishes, fittings, fixings and
necessary accessories to complete theinstallation; all in accordance with the drawings andspecification
42.00 53,256.00 New Item as per IFC
To ceilings; type CLG-521 1,268.00 m2 12.00
30
Decorations
Wall Decorations
Prepare and apply VOC low paint (anti fungal), RAL 9010pure white/ fenomastic hygiene silk; number
of coatings andapplication to manufacturer's recommendation; all inaccordance with the drawings and
specification
47.00 446,531.02
Basement B2 J 10 D To walls; type PT-101 9,500.66 m2 12.00
35
Prepare and apply emulsion paint; RAL 7047; number of coatings and application to manufacturer's
recommendation; all in accordance with the drawings and specification
47.00 18,650,590.29
Basement B2 J 10 E To walls; type PT-103 396,821.07 m2 12.00
35
Prepare and apply emulsion paint; RAL 7047; number of coatings and application to manufacturer's
recommendation; all in accordance with the drawings and specification
47.00 532,570.63
Basement B2 J 10 F To walls; type PT-104 11,331.29 m2 12.00
35
Ceiling Decorations
Prepare and apply moisture resistant (anti fungal) VOC lowpaint, RAL 9010 pure white/ fenomastic
hygiene silk; numberof coatings and application to manufacturer'srecommendation; all in accordance
with the drawings andspecification
47.00 90,955.34
Basement B2 J 11 A To soffits; type PT-102 1,935.22 m2 12.00
35
Prepare and apply emulsion paint; number of coatings andapplication to manufacturer's
recommendation; all inaccordance with the drawings and specification
47.00 205,213.75
Basement B2 J 11 B To soffits; type CLG-201 4,366.25 m2 12.00
35
Prepare and apply (anti fungal) VOC lowpaint, RAL 9010 pure white/ fenomastic hygiene silk;
numberof coatings and application to manufacturer'srecommendation; all in accordance with the
drawings andspecification
47.00 25,415,847.37
Basement B2 J 11 C To soffits; type PT-101 : PT-01 540,762.71 m2 12.00
35
Prepare and apply paint; anti-carbonation; light colored; numberof coatings and application to
manufacturer's recommendation;all in accordance with the drawings and specification
47.00 1,706,657.42
Basement B2 J 11 D To soffits; type PT-151 36,311.86 m2 12.00
35
DG198 DIRIYAH SQUARE
PAINTING SUBCONTRACT - SUPPLY & INSTALLATION
(ALL INCLUSIVE RATES)
BILL Section Page Unit Rate Unit Rate Unit Rate TOTAL AMOUNT
Area Item ref. DESCRIPTION QTY U.M. Remarks
ref. ref. ref. (Supply portion) (Install portion) (all-inclusive) (SAR)
Additional Items
Any items that may not be covered elsewhere in the PriceBreakdown which the Tenderer deemed to
be necessary inorder to carry out the works in full compliance with thedrawings and Specifications
must be itemised and pricedbelow.
Internal Finishes
Wall Finishes
Finishes to walls, as shown in enhanced finishes drawings,to manufacturer's recommendation; all in
accordancewith drawings and specification
47.00 196,836.00
Basement B2 J 14 B Adobe render, Ref. FW-10/11/12; To Columns AT welcome halls 4,188.00 m2 12.00
35
Ceiling Finishes
Gypsum board ceiling with Bulk Head; painted; includingfinishes, fittings, fixings and necessary
accessories tocomplete the installation; all in accordance with the drawingsand specification
47.00 1,112,960.00
Basement B2 J 14 D To soffits; type PT-101 ; Drop-off & valet Area 23,680.00 m2 12.00
35
Wall Decorations
Prepare and apply emulsion paint; Anti Carbonation; number of coatings and application to
manufacturer's recommendation; all in accordance with the drawings and specification
47.00 62,592.72
Basement B2 J 15 C To walls; type W6 1,331.76 m2 12.00
35
47.00 210,184.00
To walls; type PT-151 4,472.00 12.00
35 New Item as per IFC
GYRATORY TUNNEL
SECTION J - FINISHES
Internal Finishes
Wall Finishes
Prepare and apply emulsion paint; number of coatings andapplication to manufacturer's
recommendation; all inaccordance with the drawings and specification
C To walls; type PT-103 12.00 35 47.00 684,348.20
Gyratory Tunnel B3 J 6
14,561 m2
Ceiling Decorations
Prepare and apply emulsion paint; number of coatings andapplication to manufacturer's
recommendation; all inaccordance with the drawings and specification
To soffits; type PT-101 12.00 35 47.00 804,452.00
Gyratory Tunnel B3 J 6 D
17,116 m2
SAR 50,459,154.69
Cells to be filled by Bidder