PPA Section 7 Contract Condition
PPA Section 7 Contract Condition
Table of Clauses
A. General Provisions 4
1. Definitions 4
2. Appointment 6
3. Relationship Between the Parties 7
4. Due Diligence 7
5. Fraud and Corruption 7
6. Interpretation 8
B. The Contract 9
7. Contract Documents 9
8. Governing Law 10
9. Language 10
10. Notices and written communications 10
11. Authority of Member in Charge 10
12. Engineer and Engineer's Representative 11
13. Assignment 11
14. Subcontracting 12
15. Modifications by Change Orders 12
16. Change in Laws and Regulations 14
17. Taxes and Duties 14
18. Force Majeure 14
19. Breach of Contract 16
20. Suspension 16
21. Termination 17
22. Payment upon Termination 19
23. Arrangements on Termination 19
24. Cessation of Rights and Obligations 19
25. Cessation of Works 20
26. Settlement of Disputes 20
27. Liquidated Damages 20
28. Confidentiality 21
29. Miscellaneous 22
C. Obligations of the Public Body 23
1.1 The headings and titles of these General Conditions of Contract shall not limit, alter or affect the
meaning of the Contract
1.2 The following words and expressions shall have the meanings hereby assigned to them:
(a)"Bill of Quantities" means the document forming part of the Bid and containing an
itemized breakdown of the works to be carried out in a unit price
contract, indicating a quantity for each item and the corresponding
unit price;
(b) "Completion" means the fulfillment of the Contract by the Contractor in accordance
with the terms and conditions set forth in the in the GCC Clause 87;
(c)"Contract Documents" means the documents listed in the GCC, including all attachments,
appendices, and all documents incorporated by reference therein, and
shall include any amendments thereto;
(d) "Contract Manager" means a person designated as such by the Contractor from time to
time as notified in writing to the Public Body to act as the duly
authorized representative of the Contractor for all purposes connected
with the Contract, including any authorized representative of such
person;
(e) "Contract Price" means the accepted contract amount stated in the Public Body's Letter
of Acceptance. The amount represents the initial estimate payable for
the execution of the works or such other sum as ascertained by the
final statement of account as due to the Contractor under the contract;
(f) "Contract" means the binding Contract Agreement entered into between the
Public Body and the Contractor, comprising Contract Documents
referred to therein, including all attachments, appendices, and all
documents incorporated by reference therein,
(g) "Contractor" means a natural or juridical person under contract with a Public Body
to supply works;
(h) "Day" means calendar day;
(i) "Dayworks" mean varied work inputs subject to payment on an hourly basis for
the Contractor's employees and equipment, in addition to payment for
associated materials and plants;
(j) "Defect" Defect is any part of the Works not completed in accordance with the
Contract;
(k) "Defects Liability is the period stated in the Special Conditions of Contract immediately
Period" following the date of provisional acceptance, during which the
Contractor is required to complete the works and to remedy defects
or faults as instructed by the Engineer;
(l) "Drawings" mean the drawings of the Works, as included in the Contract, and any
additional and modified drawings issued by (or on behalf of) the
Public Body in accordance with the Contract, include calculations and
other information provided or approved by the Engineer for the
carrying out of the works.
2.1 The Public Body appoints the Contractor to carry out the Works:
(a) Promptly (and in any event within any time targets as may be set out in the Section 6,
Schedule of Requirements) and in a professional and courteous manner so as to reflect and
promote the image of the Public Body;
(b) Strictly in accordance with the Schedule of Requirements and all provisions of the Contract;
and
(c) In accordance with all applicable laws and regulations of the Federal Democratic Republic
of Ethiopia and Good Industry Practice; and
(d) In accordance with the policies, rules, and procedures of the appropriate Authority as
amended from time to time.
3.1 Nothing contained herein shall be construed as establishing a relationship of master and servant or
of principal and agent as between the Public Body and the Contractor. The Contractor, subject to
this Contract, has complete charge of Personnel and Sub-Contractors, if any, carrying out the Works
and shall be fully responsible for the Works carried out by them or on their behalf hereunder. The
Contractor shall not incur any liabilities on behalf of the Public Body or enter into any contract or
obligation on behalf of the Public Body.
4. Due Diligence
5.1 It is the Government of the Federal Democratic Republic of Ethiopia’s policy to require that Public
Body, as well as bidders/suppliers, to observe the highest standards of ethics during the procurement
and the execution of contracts. In pursuance of this policy, the Government of the Federal
Democratic Republic of Ethiopia represented by the Public Procurement and Property
Administration Agency (herein referred to as the Agency) requires that Public Bodies shall include
in bidding documents, provisions against corrupt practices.
5.2 If the Public Body determines that the Contractor and/or its Personnel, sub-contractors, services
providers and suppliers has engaged in corrupt, fraudulent, collusive, coercive, or obstructive
practices, in competing for or in executing the Contract, then the Public Body may, after giving 14
days notice to the Contractor, terminate the Contractor's employment under the Contract, and the
6. Interpretation
6.1 In interpreting these GCC, words indicating one gender include all genders. Words indicating the
singular also include the plural and words indicating the plural also include the singular. Headings
have no significance. Words have their normal meaning under the language of the Contract unless
specifically defined. The Engineer shall provide instructions clarifying queries about these GCC.
6.2 If sectional completion is specified in the Special Conditions of Contract, references in the General
Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply
7.1 The documents forming the Contract shall be interpreted in the following order of precedence in
the event of any conflict between the documents comprising this Contract:
(a) Agreement, including all appendices;
(b) Letter of Acceptance by the Public Body to the Contractor;
(c) The Special Conditions of Contract;
(d) The General Conditions of Contract;
(e) Bid Submission Sheet with Annexes;
(f) Technical Proposal with technical specifications;
(g) The design documentation (drawings);
(h) For Unit-price contracts: The Bill of Quantities and Price Schedule (after correction of
arithmetical errors);
For Lump-sum contracts: The Breakdown of the Lump-sum Price (after correction of
arithmetical errors);
(i) Any other document listed in the SCC as forming part of the Contract.
8. Governing Law
8.1 The Contract, its meaning and interpretation, and relation between the Parties shall be governed by
and interpreted in accordance with the laws of the Federal Democratic Republic of Ethiopia, unless
otherwise stated in SCC.
9. Language
9.1 The Contract as well as all written and oral communication and documents relating to the Contract
exchanged by the Contractor and the Public Body, shall be in language specified in the SCC.
Supporting documents and printed literature that are part of the Contract may be in another
language, but any documents provided in another language must be accompanied by an accurate
translation into language specified in the SCC. For purposes of interpretation of the Contract, this
translation shall govern.
9.2 The Contractor shall bear all costs of translation to the governing language and all risks of the
accuracy of such translation.
10.1 Any notice, request or consent required or permitted to be given or made pursuant to this Contract
shall be in writing. The term “in writing” means communicated in written form with proof of receipt.
10.2 Any such notice, request or consent shall be deemed to have been given or made when delivered in
person to an authorized representative of the Party to whom the communication is addressed, or
when sent to such Party at the address specified in the SCC.
10.3 A Party may change its address for notice hereunder by giving the other Party notice in writing of
such change to the address specified in the SCC.
11.1 In case the Contractor consists of a joint venture/consortium/ association of two or more entities,
all such entities shall be jointly and severally bound to fulfill the terms of the contract according to
the law of the Federal Democratic Republic of Ethiopia. The Members hereby authorize the entity
specified in the SCC to act on their behalf as leader with authority to bind the joint venture or
consortium in exercising all the Contractor’s rights and obligations towards the Public Body under
this Contract. The composition or the constitution of the joint venture or consortium shall not be
altered without the prior consent of the Public Body.
12.1 Except where otherwise specifically stated and subject to any restriction in the SCC, any action
required or permitted to be taken, and any document required or permitted to be executed, under
this Contract by the Public Body or the Contractor may be taken or executed by the Engineers
named in the SCC. Except as expressly stated in the SCC, the Engineer shall not have authority to
relieve the Contractor of any of his obligations under the Contract.
12.2 Any notice, information or communication given to or made by an Engineer shall be deemed to
have been given or made by the Public Body.
12.3 The Engineer may delegate any of his duties and responsibilities to Engineer's representative after
notifying the Contractor, and may cancel any delegation after notifying the Contractor.
12.4 The role of the Engineer’s representative shall be to supervise and inspect works and to test and
examine the materials employed and the quality of workmanship. Under no circumstances will the
Engineer's representative be empowered to relieve the Contractor of his obligations under the
contract or – except where express instructions to that effect are given in the SCC – order works
resulting in an extension of the period of performance or additional costs to be paid by the Public
Body or introduce variants in the nature or scale of the works.
12.5 Any communication given by the Engineer's representative to the Contractor in accordance with the
terms of such delegation shall have the same effect as though it had been given by the Engineer,
provided that:
(a) Any failure on the part of the Engineer's representative to disapprove any work, materials or
plant shall not prejudice the authority of the Engineer to disapprove such work, materials or
plant and to give the instructions necessary for the rectification thereof;
(b) The Engineer shall be at liberty to reverse or vary the contents of such communication.
12.6 Instructions and/or orders issued by the Engineer shall be by way of administrative orders. Such
orders shall be dated, numbered and entered by the Engineer in a register, and copies thereof
delivered by hand, where appropriate, to the Contractor's representative.
13. Assignment
13.1 An assignment is a written agreement by which the Contractor transfers its contract or part thereof
to a third party.
13.2 The Contractor shall not, without the prior written consent of the Public Body, assign the Contract
or any part thereof, or any benefit or interest thereunder, except in the following cases:
(a) A charge, in favor of the Contractor's bankers, of any monies due or to become due under the
Contract; or
(b) Assignment to the Contractor's insurers of the Contractor's right to obtain relief against any
other person liable in cases where the insurers have discharged the Contractor's loss or
liability.
13.3 For the purpose of GCC Clause 13.2 the approval of an assignment by the Public Body shall not
relieve the Contractor of his obligations for the part of the Contract already performed or the part
not assigned.
13.4 If the Contractor has assigned his Contract without authorization, the Public Body may, without
giving formal notice thereof, apply as of right the sanctions for breach of Contract provided for in
GCC Clauses 19 and 21.
14. Subcontracting
14.1 A sub-contract shall be valid only if it is a written agreement by which the Contractor entrusts
performance of a part of the Contract to a third party.
14.2 In the event the Contractor requires sub-contracting of the works to Sub-Contractors that are not
included in the Contract, the Contractor shall obtain the prior written approval and clearance of
Public Body for all Sub-Contractors. The work to be sub-contracted and the identity of the
subcontractors shall be notified to the Public Body. The Public Body shall with due regard to the
provisions of GCC Clause 10 within 15 days of receipt of the notification, notify the Contractor of
its decision, stating reasons should he withhold such authorization.
14.3 The terms of any sub-contract shall be subject to and conform to the provisions of this Contract.
14.4 Sub-Contractors must satisfy the eligibility criteria applicable to the award of the contract and they
can not be in any of the situations excluding them from participating in contract.
14.5 Subject to GCC Clause 66, the Public Body shall have no contractual relations with the Sub-
Contractors.
14.6 The Contractor shall be responsible for the acts, defaults and negligence of his Sub-Contractors and
their agents or employees, as if they were the acts, defaults or negligence of the Contractor, his
agents or employees. The approval by the Public Body of the sub-contracting of any part of the
contract or of the Sub-Contractor to perform any part of the works shall not relieve the Contractor
of any of his obligations under the contract.
14.7 If a Sub-Contractor has undertaken any continuing obligation for a period exceeding that of the
Defects Liability Period under the contract towards the Contractor in respect of the work executed
or the goods, materials, plant or services supplied by the Sub-Contractor, the Contractor shall, at
any time after the expiration of the Defects Liability Period, transfer immediately to the Public
Body, at the Public Body's request and cost, the benefit of such obligation for the unexpired duration
thereof.
14.8 If the Contractor enters into a subcontract without approval, the Public Body may apply, as of right
without giving formal notice thereof, the sanctions for breach of contract provided for in GCC
Clauses 19 and 21.
14.9 If a Sub-Contractor is found by the Public Body or the Engineer to be incompetent in discharging
its duties, the Public Body or the Engineer may request the Contractor forthwith, either to provide
a Sub-Contractor with qualifications and experience acceptable to the Public Body as a replacement,
or to resume the implementation of the tasks itself.
15.1 The Engineer shall have power to order any modification to any part of the works necessary for the
proper completion and /or functioning of the works. Such modifications may include additions,
omissions, substitutions, changes in quality, quantity, form, character, kind, position, dimension,
level or line and changes in the specified sequence, method or timing of execution of the works. No
16.1 Unless otherwise expressly agreed in the SCC, if, after the deadline for submission of the Bid, any
law, regulation, ordinance, order or bylaw having the force of law is enacted, promulgated,
abrogated, or changed in the Federal Democratic Republic of Ethiopia where the Site is located
(which shall be deemed to include any change in interpretation or application by the competent
authorities) that subsequently affects the Completion Date and/or the Contract Price, then such
Contract Price shall not be correspondingly increased or decreased and/or the Completion Date shall
not be adjusted to the extent that Contractor has thereby been affected in the performance of any of
its obligations under the Contract.
17.1 Unless otherwise specified in the SCC, the Contractor shall bear and pay all taxes, duties, and levies
imposed on the Contractor, by all municipal, state or national government authorities, both within
and outside the Federal Democratic Republic of Ethiopia, in connection with the Works to be carried
out under the Contract,.
18.1 For the purposes of the Contract, “Force Majeure” shall mean an event or events which are beyond
the reasonable control of a Contractor, and which makes a Contractor’s performance of its
19.1 Either party commits a breach of contract where it fails to discharge any of its obligations under the
specific contract.
19.2 Where a breach of contract occurs, the party injured by the breach shall be entitled to the following
remedies:
(a) Compensation / Claim for liquidated damages as specified in GCC Clause 27; and/or
(b) Termination of the contract.
19.3 In any case where the Public Body is entitled to damages, it may deduct such Suspension damages
from any sums due to the Contractor or call on the appropriate guarantee.
20. Suspension
20.1 The Contractor shall, on the order of the Engineer, suspend the progress of the works or any part
thereof for such time or times and in such manner as the Engineer may consider necessary.
20.2 During the period of suspension, the Contractor shall take such protective measures as may be
necessary to safeguard the works, plant, equipment and site against any deterioration, loss or
damage. Additional expenses incurred in connection with such protective measures shall be added
to the contract price, unless such suspension is:
(a) otherwise provided for in the contract; or
(b) necessary by reason of some default of the Contractor; or
(c) necessary by reason of normal climatic conditions on site; or
(d) necessary for the safety or the proper execution of the works or any part thereof insofar as
such necessity does not arise from any act or default by the Engineer or the Public Body or
from any of the exceptional risks referred to in GCC Clause 44.
20.3 The Contractor shall not be entitled to such additions to the contract price unless he notifies the
Engineer, within 30 days after receipt of the order to suspend the works, of his intention to make a
claim for them.
20.4 The Engineer, after consultation with the Public Body and the Contractor, shall determine such
extra payment and/or extension of the period of performance to be made to the Contractor in respect
of such claim as shall, in the opinion of the Engineer, be fair and reasonable.
20.5 If the period of suspension exceeds 120 days and the suspension is not due to the Contractor's
default, the Contractor may, by notice to the Engineer, request permission to proceed within thirty
(30) days or terminate the contract.
21. Termination
Termination by the Public Body
21.1 Termination shall be without prejudice to any other rights or powers under the contract of the Public
Body and the Contractor.
21.2 In addition to the grounds for termination defined in these General Conditions, the Public Body
may, by not less than thirty days written notice of termination to the Contractor stating the reason
for termination of the contract and the date on which such termination becomes effective. (except
in the event listed in paragraph (o) below, for which there shall be a written notice of not less than
sixty days), such notice to be given after the occurrence of any of the events specified in this GCC
Sub-Clause 21.2 (a) to (p), terminate the Contract if:
(a) The Contractor fails to carry out any or all of the Works within the period specified in the
Contract, or within any extension thereof granted by the Public Body pursuant to GCC Clause
73;
(b) The Contractor fails to remedy a failure in the performance of their obligations as specified
in a notice of suspension pursuant to GCC Clause 20 within thirty days of receipt of such
notice of suspension of assignment or within such further period as the Public Body may has
subsequently approved in writing;
(c) The Contractor becomes (or, if the Contractor consists of more than one entity, if any of its
Members becomes) insolvent or bankrupt or enters into any agreements with their creditors
for relief of debt or take advantage of any law for the benefit of debtors or go into liquidation
or receivership whether compulsory or voluntary, other than for a reconstruction or
amalgamation;
(d) The Contractor fails to comply with any final decision reached as a result of direct informal
negotiation pursuant to GCC Sub-Clause 26.2 hereof;
(e) The Contractor is unable, as the result of Force Majeure, to carry out the Works for a period
of not less than sixty (60) days;
(f) The Contractor assigns the contract or sub-contracts without the authorization of the Public
Body;
(g) The Contractor has been guilty of grave professional misconduct proven by any means which
the Public Body can justify;
(h) The Contractor has been declared to be in serious breach of contract financed by the Federal
Democratic Republic of Ethiopia's budget for failure to comply with its contractual
obligations.
(i) The Contractor has been engaged in corrupt or fraudulent practices in competing for or in
executing the Contract.
22.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the
Engineer shall issue a certificate for the value of the work done and Materials ordered less advance
payments received up to the date of the issue of the certificate and less the percentage to apply to
the value of the work not completed, as indicated in the SCC. Additional Liquidated Damages shall
not apply. If the total amount due to the Public Body exceeds any payment due to the Contractor,
the difference shall be a debt payable to the Public Body.
22.2 If the Public Body terminates the Contract in the event specified in GCC Sub-Clause 21.2 (o) or
because of a fundamental breach of Contract by the Public Body, the Engineer shall issue a
certificate for the value of the work done, Materials ordered, the reasonable cost of removal of
Equipment, repatriation of the Contractor’s personnel employed solely on the Works, and the
Contractor’s costs of protecting and securing the Works, and less advance payments received up to
the date of the certificate.
22.3 In the event the Public Body terminates the Contract pursuant to the GCC Sub-Clause 21.2 (c)
termination will be without compensation to the Contractor, provided that such termination will not
prejudice or affect any right of action or remedy that has accrued or will accrue thereafter to the
Public Body.
23.1 The Public Body and the Contractor agree that termination or expiry of the Contract shall not affect
either Party's obligations which the Contract provides shall survive the expiration or termination of
the Contract.
23.2 All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed to be
the property of the Public Body if the Contract is terminated because of the Contractor’s default.
23.3 After termination or expiry all data, documents and records (whether stored electronically or
otherwise) relating in whole or in part to the provided Works shall be delivered by the Contractor
to the Public Body provided that the Contractor shall be entitled to keep copies thereof to the extent
that the information contained therein does not relate solely to the Works or to the extent that the
Contractor is required by law to maintain copies thereof or to the extent that the Contractor was
possessed of such data documents and records prior to the date of the Contract. In addition, the
Contractor shall co-operate fully with the Public Body during the handover leading to the
termination of the Contract. This co-operation shall extend to full access to all documents, reports,
summaries and any other information required to achieve an effective transition without disruption
to routine operational requirements.
24.1 Upon termination of the Contract pursuant to GCC Clauses 21, or upon the issue of the Final
Acceptance Certificate pursuant to GCC Clause 89 hereof, all rights and obligations of the Parties
hereunder shall cease, except
(a) Such rights and obligations as may have accrued on the date of termination or expiration;
(b) The obligation of confidentiality set forth in GCC Clause 28 hereof;
25.1 Upon termination of the Contract by notice of either Party to the other pursuant to GCC Clause 21
the Contractor shall, immediately upon dispatch or receipt of such notice, take all necessary steps
to bring the Works to a close in a prompt and orderly manner, make the Site safe and secure, leave
the Site as soon as reasonably possible, and make every reasonable effort to reduce expenditures
for this purpose to a minimum.
25.2 The Engineer shall, as soon as is possible after termination, certify the value of the works and all
sums due to the Contractor as at the date of termination.
25.3 In the event of termination a report of work performed by the Contractor shall be drawn up by the
Engineer as soon as possible after inspection of the works, and inventory taken of temporary
structures, materials, plant and equipment. The Contractor shall be summoned to be present during
the inspection and the taking of the inventory. The Engineer shall also draw up statements of
emoluments still owed by the Contractor to workers employed by him in relation to the contract and
of sums owed by the Contractor to the Public Body.
26.1 During any dispute, including a dispute as to the validity of the Contract, it is mutually agreed that
the Contractor shall continue its performance of the Contract (unless the Public Body requests in
writing that the Contractor does not do so).
26.2 The Public Body and the Contractor shall make every effort to resolve amicably by direct informal
negotiation any disagreement, controversy or dispute arising between them under or in connection
with the Contract or interpretation thereof.
26.3 If a dispute arises between the Public Body and the Contractor in relation to any matter which cannot
be resolved by the Engineer and the Contractor's Contract Manager either of them may refer such
dispute to the procedure described in GCC Sub-Clause 26.4.
26.4 In the second instance each of the Public Body and the Contractor shall appoint more senior
representatives than those referred to in Sub-Clause 26.3 to meet solely in order to resolve the matter
in dispute. Such meeting(s) shall be minuted and shall be chaired by the Public Body (but the
chairman shall not have a casting vote). Such meeting(s) shall be conducted in such manner and at
such venue (including a meeting conducted over the telephone) as to promote a consensual
resolution of the dispute in question at the discretion of the chairman.
26.5 If the Parties fail to resolve such a dispute or difference amicably within twenty-eight (28) days
from the commencement of such procedure, either party may require that the dispute be referred for
resolution through the courts in accordance with Ethiopian Law.
26.6 Only those Public Bodies that are allowed by law to proceed to arbitration can do so.
27.1 Except as provided under GCC Clause 18, if the Contractor fails to carry out any or all of the Works
within the period specified in the Contract, the Public Body may without prejudice to all its other
remedies under the Contract, deduct from the Contract Price, as liquidated damages the following:
28. Confidentiality
28.1 The Public Body and the Contractor shall keep confidential and shall not disclose to any third party
any documents, data, or other information furnished directly or indirectly by the other party hereto
in connection with the Contract, whether such information has been furnished prior to, during or
following completion or termination of the Contract if their disclosure would be contrary to law,
would impede law enforcement, would not be in public interest, would prejudice legitimate
commercial interest of the parties or would inhibit fair competition.. Notwithstanding the above, the
Contractor may furnish to its sub-contractors such documents, data, and other information it
receives from the Public Body to the extent required for the sub-contractor to perform its work
under the Contract, in which event the Contractor shall obtain from such sub-contractor an
undertaking of confidentiality similar to that imposed on the Contractor under this Clause.
28.2 The Public Body shall not use such documents, data, and other information received from the
Contractor for any purposes unrelated to the Contract. Similarly, the Contractor shall not use such
documents, data, and other information received from the Public Body for any purpose other than
carrying out the Works in accordance with the Contract.
28.3 The obligation of a party under this Clause, however, shall not apply to any Confidential
Information that:
(a) The Public Body or Contractor need to share with any other institutions participating in the
financing of the Contract;
(b) Now or hereafter enters the public domain other than by breach of the Contract or other act
or omissions of that Party;
(c) Is obtained by a third party who is lawfully authorized to disclose such information;
(d) Can be proven to have been possessed by that party at the time of disclosure and which was
not previously obtained, directly or indirectly, from the other party; or
(e) Is authorized for release by the prior written consent of the other party.
28.4 The Parties shall not be prevented from using any general knowledge, experience or skills which
were in their possession prior to the commencement of the Contract;
28.5 The Contractor authorizes the Public Body to disclose the Confidential Information to such
person(s) as may be notified to the Contractor in writing by the Public Body from time to time to
the extent only as is necessary for the purposes of auditing and collating information so as to
ascertain a realistic market price for the Works carried out in accordance with the Contract, such
exercise being commonly referred to as "benchmarking". The Public Body shall use all reasonable
endeavors to ensure that such person(s) keeps the Confidential Information confidential and does
not make use of the Confidential Information except for the purpose for which the disclosure is
29. Miscellaneous
29.1 Any decision, act or thing that the Public Body is required or authorized to take or do under the
Contract may be taken or done by any person authorized, either generally or specifically, by the
Public Body to take or do that decision, act or thing, provided that upon receipt of a written request
the Public Body shall inform the Contractor of the name of any person so authorized.
29.2 The Contractor may from time to time upon the request of the Public Body, execute any additional
documents and do any other acts or things which may reasonably be required to implement the
provisions of the Contract.
29.3 Any provision of the Contract which is held to be invalid or unenforceable in any jurisdiction shall
be ineffective to the extent of such invalidity or unenforceability without invalidating or rendering
unenforceable the remaining provisions hereof and any such invalidity or unenforceability in any
jurisdiction shall not invalidate or render unenforceable such provisions in any other jurisdiction.
29.4 The failure by the Public Body and Contractor to insist upon the strict performance of any provision,
term or condition of the Contract or to exercise any right or remedy consequent upon the breach
thereof shall not constitute a waiver of any such breach or any subsequent breach of such provision,
term or condition.
29.5 Each Party shall bear its own expenses in relation to the preparation, execution and implementation
of the Contract including all costs legal fees and other expenses so incurred.
29.6 The Contractor warrants represents and undertakes to the Public Body that there are no pending or
threatened actions or proceedings before any court or administrative agency which would materially
30.1 The Contractor may request the assistance of the Public Body in obtaining copies of laws,
regulations and information on local customs, orders or by-laws of the Federal Democratic Republic
of Ethiopia, which may affect the Contractor in the performance of his obligations under the
Contract. The Public Body may provide the assistance requested to the Contractor at the
Contractor's cost.
30.2 Unless otherwise specified in the SCC, the Public Body may make all efforts necessary to facilitate
the procurement by the Contractor of:
(a) all required visas and permits, including work and residence permits, and such other
documents as shall be necessary to enable the Contractor, Sub-Contractors or Personnel to
carry out the Works;
(b) any such other assistance as may be specified in the SCC.
30.3 Except where otherwise provided in the SCC, within 30 days of the signing of the Contract, the
Engineer shall provide to the Contractor, free of charge, a copy of the drawings prepared for the
implementation of tasks as well as two copies of the specifications and other contract documents.
The Contractor may purchase additional copies of these drawings, specifications and other
documents, insofar as they are available. Upon the final acceptance, the Contractor shall return to
the Engineer all drawings, specifications and other contract documents.
30.4 Unless it is necessary for the purposes of the Contract, the drawings, specifications and other
documents provided by the Public Body shall not be used or communicated to a third party by the
Contractor without the prior consent of the Engineer.
30.5 The Engineer shall have authority to issue to the Contractor administrative orders incorporating
such supplementary documents and instructions as shall be necessary for the proper and adequate
execution of the works and the remedying of any defects therein.
31.1 The Public Body shall, in due time and in conformity with the progress of the works, place the site
and access thereto at the disposal of the Contractor in accordance with the program of
implementation of tasks referred to in these GCC. If possession of a part is not given by the date
stated in the approved work program, the Public Body will be deemed to have delayed the start of
the relevant activities, and this will be a Compensation Event.
31.2 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the
Site and to any place where work in connection with the Contract is being carried out or is intended
to be carried out.
32. Payment
32.1 In consideration of the Works performed by the Contractor under this Contract, the Public Body
shall make to the Contractor such payments and in such manner as is provided by GCC Paragraph
E of this Contract.
33.1 Where there is a delay in the payment to the Contractor's employees of wages and salaries owing
and of the allowances and contributions laid down by the law of the Federal Democratic Republic
of Ethiopia, the Public Body may give notice to the Contractor that within 15 days of the notice the
Contractor has to pay such wages, salaries, allowances and contributions.
34.1 The Contractor shall, with due care and diligence, and in accordance with the provisions of the
Contract, design the works to the extent stated in the Contract, and execute, complete and remedy
any defects in the works. The Contractor shall provide all control and supervision of the works,
personnel, materials, plant, equipment and all other items, whether of a temporary or permanent
nature required in and for such design, execution, completion and remedying of any defects, insofar
as specified in, or can be reasonably inferred from, the Contract.
34.2 The Contractor shall take full responsibility for the adequacy, stability and safety of all operations
and methods of construction under the Contract.
34.3 The Contractor shall respect and abide by all laws and regulations in force in the Federal Democratic
Republic of Ethiopia and shall ensure that his personnel, their dependants, and his local employees
also respect and abide by all such laws and regulations. The Contractor shall indemnify the Public
Body against any claims and proceedings arising from any infringement by the Contractor, its Sub-
Contractors or their employees of such laws and regulations.
34.4 The Contractor shall ensure that Works conform to applicable environmental and quality standards,
that no chemical or other product/equipment is used in such a way as to cause negative impact on
the environment in general and occupational health hazards and shall employ the most recent
technology, safe and effective equipment, machinery, materials and methods, as necessary.
34.5 The Contractor shall obtain the Public Body's prior approval in writing before taking any of the
following actions:
(a) Entering into a subcontract for carrying out any part of the Works, it being understood that
the Contractor shall remain fully liable for carrying out the Works by the Sub-Contractor;
(b) Any other action that may be specified in the SCC.
35. Eligibility
35.1 The Contractor and its Sub-Contractors shall have the nationality of an eligible country pursuant to
Section 5 of the Bidding Documents. A Contractor or Sub-Contractor shall be deemed to have the
nationality of a country if it is a citizen or constituted, incorporated, or registered, and operates in
conformity with the provisions of the laws of that country.
35.2 The Contractor and its Sub-Contractors shall provide Personnel who shall be citizens of eligible
countries and use goods with their origin from an eligible country.
36.1 The Contractor shall, at all times, act loyally and impartially in respect of any matter relating to this
Contract and as a faithful adviser to the Public Body in accordance with the rules and/or code of
conduct of its profession as well as with appropriate discretion. The Contractor shall, in particular,
at all times refrain from making any public statements concerning the Works without the prior
approval of the Public Body, and from engaging in any activity which conflicts with its obligations
towards the Public Body under the contract. It shall not commit the Public Body without its prior
written consent, and shall, where appropriate, make this obligation clear to third parties.
36.2 If the Contractor or any of its Sub-Contractors, personnel, agents or servants offers to give or agrees
to offer or to give or gives to any person, any bribe, gift, gratuity or commission as an inducement
or reward for doing or forbearing to do any act in relation to the contract or any other contract with
the Public Body, or for showing favor or disfavor to any person in relation to the contract or any
other contract with the Public Body, then the Public Body may terminate the contract, without
prejudice to any accrued rights of the Contractor under the contract.
36.3 The payments to the Contractor under the contract shall constitute the only income or benefit it may
derive in connection with the contract and neither it nor its personnel shall accept any commission,
discount, allowance, indirect payment or other consideration in connection with, or in relation to,
or in discharge of, its obligations under the contract.
36.4 The Contractor shall not have the benefit, whether directly or indirectly, of any royalty, gratuity or
commission in respect of any patented or protected article or process used in or for the purposes of
the contract or the project, without the prior written approval of the Public Body.
36.5 The Contractor and its staff shall maintain professional secrecy, for the duration of the contract and
after completion thereof. In this connection, except with the prior written consent of the Public
Body, neither the Contractor nor the personnel employed or engaged by it shall at any time
communicate to any person or entity any confidential information disclosed to them or discovered
by them, or make public any information as to the recommendations formulated in the course of or
37.1 The Contractor shall himself control and supervise the works or shall appoint a Contract Manager
to do so. Such appointment shall be submitted to the Engineer for approval.
37.2 The Contract Manager shall be suitably qualified in accordance with the Schedule of Requirements.
In addition a work history/biography will be submitted to the Engineer for approval.
37.3 The Contractor shall forthwith give notice in writing to the Engineer of the identity of the person
appointed as Contract Manager for approval. The approval may at any time be withdrawn. Should
the Engineer refuse to approve, or withdraw approval of the appointment, he shall set out the
grounds on which his decision is based, and the Contractor shall submit an alternative appointment
without delay. The address of the Contractor's representative shall be deemed to be the address for
service given by the Contractor.
37.4 If the Engineer withdraws his approval of the Contractor's Contract Manager, the Contractor shall,
as soon as is practicable, after receiving notice of such withdrawal, remove the Contract Manager
from the works and replace him with another Contract Manager approved by the Engineer.
37.5 The Contractor's Contract Manager shall have full authority to make any decision necessary for the
execution of the works, to receive and carry out administrative orders and to countersign the work
register referred to in GCC Clause 79 or attachment, where appropriate. In any event, the Contractor
shall be responsible for ensuring that the works are carried out satisfactorily including ensuring that
the specifications and administrative orders are adhered to by his own employees and by his sub-
Contractors and their employees.
37.6 Any notice, information, instruction or other communication given or made to the Contract Manager
shall be deemed to have been given or made to the Contractor.
37.7 The Contractor shall inform the Engineer of the identity of any person authorized to act for any
period as deputy for the Contract Manager before the start of that period.
37.8 The Contractor shall provide a sufficient complement of supervisory staff in addition to the Contract
Manager, to ensure that the Contractor’s staff engaged in and about the provision of the Works at
the Site are adequately supervised and properly perform their duties at all times.
37.9 All persons appointed to managerial and supervisory positions in accordance with the Schedule of
Requirements must be to the acceptance of the Engineer who will have the right to veto the
appointment of any candidate who is deemed to be unsuitable.
38.1 The persons employed by the Contractor must be sufficient in number, and permit the optimum use
of the human resources. Such employees must have the skills and experience necessary to ensure
due progress and satisfactory execution of the works.
38.2 The Contractor shall make his own arrangements for the engagement of all staff and labor. The rates
of remuneration and the general working conditions, as laid down by the law of the Federal
democratic Republic of Ethiopia, shall apply as a minimum to employees on the Site.
38.3 The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred
to in the SCC, to carry out the functions stated in the Schedule of Requirements or other personnel
approved by the Engineer. The Engineer will approve any proposed replacement of key personnel
only if their relevant qualifications and abilities are substantially equal to or better than those of the
personnel listed in the Schedule of Requirements.
38.4 The Contractor acknowledges that the Key Personnel are essential to the proper provision of the
Works to the Public Body. The Contractor shall ensure that the role of any Key Personnel is not
vacant for any longer than [10] Working Days and that any replacement shall be as or more qualified
and experienced as the previous incumbent of such role and is fully competent to carry out the tasks
assigned to the role of the member of Key Personnel whom he or she has replaced.
38.5 The Contractor shall immediately replace all employees indicated by the Engineer, in a letter stating
reasons, as likely to jeopardize the satisfactory execution of the works
38.6 If the Engineer asks the Contractor to remove a person who is a member of the Contractor’s staff
or work force, stating the reasons, the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the work in the Contract.
38.7 The Public Body shall not be liable for the cost of replacing any member of the Contractor’s staff
and the Contractor shall indemnify the Public Body against all Employee Liabilities that may arise
in this respect.
39.1 At its own expense, the Contractor shall indemnify, protect and defend, the Public Body, its agents
and employees, from and against all actions, claims, losses or damage arising from any act or
omission by the Contractor in the performance of the Works, including any violation of any legal
provisions, or rights of third parties, in respect of patents, trade marks and other forms of intellectual
property such as copyrights.
39.2 At its own expense, the Contractor shall indemnify, protect and defend the Public Body, its agents
and employees, from and against all actions, claims, losses or damages arising out of the
Contractor’s failure to perform its obligations provided that:
(a) The Contractor is notified of such actions, claims, losses or damages not later than 30 days
after the Public Body becomes aware of them;
(b) The ceiling on the Contractor’s liability shall be limited to an amount equal to total Contract
Price as stated in the SCC, but such ceiling shall not apply to actions, claims, losses or
damages caused by the Contractor’s willful misconduct;
(c) The Contractor’s liability shall be limited to actions, claims, losses or damages directly
caused by such failure to perform its obligations under the contract and shall not include
liability arising from unforeseeable occurrences incidental or indirectly consequential to such
failure.
40.1 The Contractor shall provide, in the joint names of the Public Body and the Contractor, insurance
cover against loss or damage for which he is liable under the contract in the amounts and deductibles
stated in the SCC. Such insurance shall, unless the SCC provide otherwise, cover:
(a) the Works, together with Materials and Plant for incorporation therein, to the full replacement
cost against all loss or damage from whatever cause arising other than from Force Majeure
or risks attributable under the contract to the Public Body;
(b) an additional sum of 15% of such replacement cost, or as may be specified in the SCC, to
cover any additional costs of and incidental to the rectification of loss or damage including
professional fees and the cost of demolishing and removing any part of the works and of
removing debris of whatever nature;
(c) the Contractor's Equipment and other things brought onto the Site by the Contractor, for a
sum sufficient to provide their replacement at the Site.
40.2 The Contractor shall take out insurance covering his liability with regard to industrial accidents and
civil liabilities to any person employed by him on the works, to the Public Body and any employee
of that authority, arising from the execution of the works. Such liability shall be unlimited in the
case of personal injuries.
40.3 The Contractor shall take out insurance covering liability with regard to risks and civil liability
resulting from an act or omission attributed to him, to his legal successors or agents. Such insurance
shall be for at least the amount stated in the SCC. Furthermore, he shall ensure that all his sub-
contractors have taken out a similar insurance.
40.4 By requiring such insurance, Public Body shall not be deemed or construed to have assessed the
risk that may be applicable to the Contractor under this Contract. The Contractor shall assess its
own risks and if deemed to be appropriate and/or prudent, should maintain adequate limits and/or
broader insurance coverage than that stipulated above. The Contractor is not relieved of any liability
or other obligations assumed or pursuant to the Contract by reason of its failure to obtain or maintain
insurance in sufficient amounts, duration, or types.
40.5 Insurance shall be provided at the Contractor’s expense and shall not be charged directly to the
Public Body.
40.6 All the insurance referred to in this Clause shall be taken out within 30 days of the notification of
the award of the Contract, and shall be subject to approval by the Public Body. Such insurance shall
41.1 Completing the work program given as part of the Bid, the Contractor shall within the time stated
in the SCC provide the Engineer with a program of implementation of the tasks, broken down by
activity and by month and include the following information:
(a) the order in which the Contractor proposes to carry out the works;
(b) the time limits within which submission and approval of the drawings are required;
(c) an organization chart containing the names, qualifications and curricula vitae of the staff
responsible for the Site,
(d) a general description of the method including the sequence, by month and by nature which
the Contractor proposes to carry out the works;
(e) a plan for the setting out and organization of the Site, and
(f) such further details and information as the Engineer may reasonably require.
41.2 The Engineer shall return these documents to the Contractor with his approval or any relevant
remarks within ten days of receipt, except where the Engineer, within those ten days, notifies the
Contractor of his wish for a meeting.
41.3 An update of the program shall be a program showing the actual progress achieved on each activity
and the effect of the progress achieved on the timing of the remaining work, including any changes
to the sequence of the activities.
41.4 The Contractor shall submit to the Engineer for approval an updated program at intervals no longer
than the period stated in the SCC. If the Contractor does not submit an updated Program within this
period, the Engineer may withhold the amount stated in the SCC from the next payment certificate
and continue to withhold this amount until the next payment after the date on which the overdue
Program has been submitted.
41.5 The approval of the program by the Engineer shall not relieve the Contractor from any of his
obligations under the contract. The Contractor may revise the program and submit it to the Engineer
again at any time. A revised program shall show the effect of modifications and Compensation
Events.
43.1 The Contractor shall be deemed to have inspected and examined the Site and its surroundings and
to have satisfied himself before submitting his Bid, as to the nature of the ground and sub-soil, and
to have taken into account the form and nature of the Site, the extent and nature of the work and
materials necessary for the completion of the works, the means of communication with and access
to the site, the accommodation he may require and in general to have obtained for himself all
necessary information as to risks, contingencies and all other circumstances influencing or affecting
his tender.
43.2 The Contractor shall be deemed to have satisfied himself before submitting his tender as to the
correctness and sufficiency of the tender and of the rates and prices stated in the bill of quantities
or price schedule which shall, except in so far as it is otherwise provided in the Contract, cover all
his obligations under the contract.
43.3 Since the Contractor is deemed to have determined his prices on the basis of his own calculations,
operations and estimates, he shall carry out without additional charge any work which is the subject
of any item whatsoever in his tender for which he neither indicates a unit price nor a firm sum.
44.1 If during the execution of the works the Contractor encounters artificial obstructions or physical
conditions which could not reasonably have been foreseen by an experienced Contractor, and if the
Contractor is of the opinion that additional costs will be incurred and/or an extension of the period
of implementation of the tasks will be necessary as a result of this, he shall give notice to the
Engineer in accordance with GCC Clauses 69 and/or 73. The Contractor shall specify in such notice
the artificial obstructions and/or physical conditions, giving details of the anticipated effects thereof,
the measures he is taking or intends to take and the extent of the anticipated delay in or interference
with the execution of the works.
44.2 Following receipt of the notice, the Engineer may inter alia:
(a) Require the Contractor to provide an estimate of the cost of the measures he is taking or
intends to take;
(b) Approve measures referred to in GCC Sub-Clause 44.2 (a) with or without modification;
(c) Give written instructions as to how the artificial obstructions or physical conditions are to be
dealt with;
(d) Order a modification, a suspension, or termination of the contract.
44.3 To the extent that the Engineer shall decide that the whole or part of the said artificial obstructions
or physical conditions could not reasonably have been foreseen by an experienced Contractor, the
Engineer shall:
(a) take into account any delay suffered by the Contractor as a result of such obstructions or
conditions in determining any extension of the period of implementation of tasks to which
the Contractor is entitled under GCC Clause 73; and/or
(b) in case of artificial obstructions or physical conditions other than weather conditions,
determine additional payments due to the Contractor in accordance with GCC Clause 69.
45.1 The Contractor shall have the right to forbid access to the Site to any person not involved in the
performance of the contract, with the exception of persons authorized by the Engineer or the Public
Body.
45.2 The Contractor shall ensure the safety on sites during the whole period of execution and shall be
responsible for taking the necessary steps, in the interests of his employees, agents of the Public
Body and third parties, to prevent any loss or accident which may result from carrying out the works.
45.3 The Contractor shall take all essential steps, on his own responsibility and at his expense, to ensure
that existing structures and installations are protected, preserved and maintained. He shall be
responsible for providing and maintaining at his expense all lighting, protection, fencing and
security equipment which proves necessary for the proper implementation of the tasks or which
may reasonably be required by the Engineer.
45.4 If, during the implementation of the tasks, urgent measures are necessary to obviate any risk of
accident or damage or to ensure security following any accident or damage, the Engineer shall give
formal notice to the Contractor to do what is necessary. If the Contractor is unwilling or unable to
undertake the necessary measures, the Engineer may carry out the work at the expense of the
Contractor to the extent that the Contractor is liable.
45.5 While carrying out the Works, the Contractor shall comply, and shall ensure that its employees
comply with, the requirements of relevant Health and Safety and other relevant legislation,
45.6 The Contractor shall nominate a Health and Safety Representative to liaise with the Engineer on all
Health and Safety matters.
45.7 The Contractor’s staff shall follow a system of accident recording in accordance with the
Contractor’s own accident reporting procedures.
45.8 All notifiable accidents shall immediately be brought to the attention of the Engineer.
45.9 The Contractor shall ensure the co-operation of its personnel in all prevention measures designed
against fire, or any other hazards, and shall notify the Public Body of any change in the Contractor's
working practices or other occurrences likely to increase such risks or to cause new hazards.
45.10 The Contractor shall provide such first aid facilities and ensure that his staffs abide by such first aid
procedures as shall be required by the Public Body.
46.1 On his own responsibility and at his expense, the Contractor shall take all the precautions required
by good construction practice and by the prevailing circumstances to safeguard adjacent properties
and avoid causing any abnormal disturbance therein.
46.2 The Contractor shall indemnify the Public Body against the financial consequences of all claims by
neighboring landowners or residents to the extent that the Contractor is liable and to the extent that
the damage to adjacent properties is not the result of a hazard created through the design or method
of construction imposed by the Public Body or the Engineer upon the Contractor
47.1 The Contractor shall ensure that the works and installations do not cause damage to, or obstruct
traffic on, communication links such as roads, railways, waterways and airports, except as permitted
under the SCC. He shall, in particular, take account of weight restrictions when selecting routes and
vehicles.
47.2 Any special measures which the Contractor considers necessary or which are specified in the SCC
or which are required by the Public Body in order to protect or strengthen sections of roads, tracks
or bridges, shall be at the expense of the Contractor, whether or not they are carried out by the
Contractor. The Contractor shall inform the Engineer of any special measures he intends to take
before carrying them out. The repair of any damage caused to roads, tracks or bridges by the
transport of materials, plant or equipment shall be at the expense of the Contractor.
48.1 Where, in the course of carrying out the works, the Contractor encounters bench-marks indicating
the course of underground cables, conduits and installations, he shall keep such bench-marks in
position or replace them, should execution of the works have necessitated their temporary removal.
Such related operations require the authorization of the Engineer.
48.2 The Contractor shall be responsible for the preservation, removal and replacement, as the case may
be, of the cables, conduits and installations specified by the Public Body in the contract and for the
cost thereof.
48.3 Where the presence of cables, conduits and installations has not been specified in the contract but
is revealed by bench-marks and references, the Contractor shall be under a general duty of care and
similar obligations regarding preservation, removal and replacement to those set out above. In this
case, the Public Body shall compensate him for expenditure, to the extent that such work is
necessary for the execution of the contract.
48.4 However, the obligations to remove and replace cables, conduits and installations and the
expenditure resulting therefrom shall not be the responsibility of the Contractor if the Public Body
decides to accept that responsibility. The same shall apply where this obligation and the expenditure
resulting therefrom devolve upon another specialist administration or an agent.
48.5 When any work on the site is likely to cause disturbances in or damage to a public utility service,
the Contractor shall immediately inform the Engineer in writing, giving a reasonable period of
notice so that suitable measures can be taken in time to allow work to continue normally.
50.1 Where the contract includes demolition work, materials and articles obtained therefrom shall, unless
the SCC and /or the law of the Federal Democratic Republic of Ethiopia otherwise provide and
subject to the provisions of GCC Clause 51, be the property of the Contractor.
50.2 If the SCC reserve to the Public Body the right of ownership of materials or all or part of the articles
obtained from the demolition work, the Contractor shall take all the necessary precautions to ensure
that these are preserved. He shall be liable for any destruction of, or damage to, such materials or
articles caused by him or his agents.
50.3 Irrespective of the use to which the Public Body intends to put the materials or articles, in respect
of which he reserves the right of ownership, all costs incurred in transporting and storing them and
all warehouse charges at the place indicated by the Engineer shall be borne by the Contractor for
any carriage not exceeding 100 meters.
50.4 Except where the SCC provide otherwise, the Contractor shall, at his expense, progressively remove
rubble and other demolition materials, rubbish and debris from the Site.
51. Discoveries
51.1 Discoveries of any interest whatsoever made during excavation or demolition work shall be brought
immediately to the attention of the Engineer. The Engineer shall decide how such discoveries are
to be dealt with, taking due account of the law of the Federal Democratic Republic of Ethiopia.
51.2 The Public Body reserves the right of ownership of materials found during the excavation and
demolition work carried out on land belonging to him, subject to compensating the Contractor for
any special efforts.
51.3 Artifacts, antiquities and natural, numismatic, or other objects which are of scientific interest, and
also rare objects or objects made of precious metals found during excavation or demolition work
shall be the property of the Public Body.
51.4 In the event of disagreements, the Public Body shall have sole authority to decide as to the
qualifications set out in GCC Clauses 51.1 and 51.3.
52.1 The Contractor shall carry out at his expense all the temporary works to enable the Works to be
carried out. He shall submit specification and drawings showing the proposed temporary work to
the Engineer, who is to approve them if they comply with the specification and drawings. The
Contractor shall take into account any observations made to him by the Engineer while assuming
responsibility for these drawings.
52.2 The Contractor shall be responsible for design of Temporary Works.
53.1 Subject to the SCC and to the technical specifications, the Contractor shall make available to the
Engineer, the personnel and equipment necessary for carrying out any soil survey which the
Engineer considers reasonably necessary. The Contractor shall be compensated for the actual cost
of the manpower and equipment used or made available in such work, if not already provided for
in the contract.
54.1 The Contractor shall, in accordance with the requirements of the Engineer, afford all reasonable
opportunities for carrying out their work to any other Contractors employed by the Public Body or
any other public authorities who may be employed on or near the Site in the execution of any work
not included in the contract, or of any contract which the Public Body may enter into in connection
with, or ancillary to, the works.
54.2 If, however, the Contractor, on the written request of the Engineer, makes available to any such
Contractor, or public authority, or to the Public Body, any roads or ways for the maintenance of
which the Contractor is responsible, or permits the use by any such other persons of the Contractor's
temporary works, scaffolding or other equipment on the site, or provides any other service of
whatsoever nature, which was not provided for in the contract, the Public Body shall pay to the
Contractor in respect of such use or service, such sums and/or grant such extension of time, as shall,
in the opinion of the Engineer, be reasonable.
54.3 The Contractor shall not by reason of this Clause be relieved of any of his obligations under the
Contract nor shall he be entitled to any claims other than those provided for in GCC Clause 54.2.
54.4 In no circumstances may difficulties arising with regard to one contract entitle the Contractor to
modify or delay implementation of other contracts. Similarly, the Public Body may not take
advantage of such difficulties to suspend payments due under another contract.
55.1 Except where otherwise provided in the SCC, the Contractor shall indemnify the Public Body and
the Engineer against any claim resulting from the use as specified in the contract of patents, licenses,
drawings, designs, models, or brand or trade marks, except where such infringement results from
compliance with the design or specification provided by the Public Body and /or the Engineer.
56.1 The Contractor shall keep, and shall cause its Sub-Contractors to keep, accurate and systemic
accounts and records in respect of the Contract, in accordance with internationally accepted
accounting principles and in such form and detail as will clearly identify all relevant time charges
and costs.
56.2 For the purpose of the examination and certification of the Public Body's accounts; or any
examination of the economy, efficiency and effectiveness with which the Public Body has used its
resources, the Federal Auditor General and the Public Procurement and Property Administration
Agency or its auditors may inspect all accounts and records relating to the performance of the
Contract and the submission of the Proposal to provide the Works which are owned, held or
otherwise within the control of the Contractor and may require the Contractor to produce such oral
or written explanation as he considers necessary. The Contractor acknowledges that it will fully
cooperate with any counter fraud policy or investigation carried out by authorized body at any time.
57.1 The Contractor shall comply with all applicable data protection legislation. In particular the
Contractor agrees:
(a) To maintain appropriate technical and organizational security measures;
(b) To only process Personal Data for and on behalf of the Public Body, in accordance with the
instructions of the Public Body and for the purpose of performing its obligations under the
Contract;
(c) To allow the Public Body to audit the Contractor's compliance with the requirements of this
Clause on reasonable notice and/or to provide the Public Body with evidence of its
compliance with the obligations set out in this Clause.
57.2 The Contractor agrees to indemnify and keep indemnified the Public Body against all claims and
proceedings and all liability, loss, costs and expenses incurred in connection therewith by the Public
Body as a result of any claim made or brought by any individual or other legal person in respect of
any loss, damage or distress caused to that individual or other legal person as a result of the
Contractor's unauthorized processing, unlawful processing, destruction of and/or damage to any
Personal Data processed by the Contractor, its employees or agents in the Contractor's performance
of the Contract or as otherwise agreed between the Parties.
58.1 The Contractor shall, within fifteen (15) days from signing the contract, provide a Performance
Security for the due performance of the Contract in the amount specified in the SCC.
58.2 Notwithstanding the provision of Sub-clause above a conditional insurance bond shall be accepted
as Performance Security.
58.3 The proceeds of the Performance Security shall be payable to the Public Body as compensation for
any loss resulting from the Contractor’s failure to complete its obligations under the Contract.
58.4 The Performance Security shall be denominated in currency specified in the SCC, and shall be in
the form of cash, cheque certified by a reputable bank, letter of credit, or Bank Guarantee in the
format specified in the SCC.
59.1 Payments shall be made in currency as specified in the SCC. The SCC shall lay down the
administrative or technical conditions governing advance payments, interim and/or final payments
made in accordance with the GCC.
59.2 Payments due by the Public Body shall be made to the bank account mentioned on the Bidder
Certification of Compliance form completed by the Contractor.
59.3 Payments to the Contractor of the amounts due under each of the interim payment certificates and
the final statement of account issued by the Engineer shall be made by the Public Body within 90
days of such certificate of statement being delivered to the Public Body. The date of payment shall
be the date on which the paying institution's account is debited. The payment certificate shall not
be admissible if one or more essential requirements are not met.
59.4 Interim payment certificates or final statement of account must be accompanied with copies of
invoices and other appropriate supporting materials of the amounts payable.
59.5 The Contractor's invoice shall be correctly rendered if:
60.1 If the SCC so provide, advance payment shall be granted to the Contractor, at his request, for
operations connected with the implementation of the tasks, in the cases listed hereinafter:
(a) as a lump-sum advance enabling Contractor to meet expenditure resulting from the
commencement of the contract;
(b) if Contractor affords proof of the conclusion of a contract for the purchase or order of
materials, plant, equipment, machines and tools, necessary for the execution of the contract,
and of any other substantial prior expenses such as the acquisition of patents or study costs.
60.2 The SCC shall state the amount of the advance payment which shall not exceed 30% of the total
contract price.
61.1 The sum which shall be retained from interim payments by way of guarantee to meet the
Contractor's obligations during the Defects Liability Period, and the detailed rules governing that
guarantee, shall be stipulated in the SCC, provided that it shall, in no case, exceed 10% of the
contract price.
61.2 Subject to the approval of the Public Body, the Contractor may, if he so wishes, substitute, not later
than the date fixed for the commencement of the works, these retention sums by a retention
guarantee issued in accordance with GCC Clause 58.
61.3 The sum retained or the retention guarantee shall be released within 45 days of the issuing of the
signed final statement of account referred to in GCC Clause 65.
62.1 Adjustments of contract prices shall be allowed after twelve (12) months from the effective date of
the Contract where it is verified that the performance of the contract requires more than 18 months.
Where:
PA = The amount of the Price adjustment to be paid to, or recovered from, the
Contractor, in currency specified in SCC;
NV= The fraction which represents Non Variable element of the Contract Price that is
free of contract price adjustment, as specified in the Contractor's Bid;
A= The fraction of the Contract Price subject to adjustment in accordance with
movements of the selected Average Labor Category Earnings Index;
64.1 Unless otherwise specified in the SCC, the Contractor shall submit monthly statement for interim
payment to the Engineer at the end of each period referred to in GCC Clause 64.7 in a form approved
by the Engineer. The monthly statement shall include the following items, as applicable:
(a) The estimated contract value of the permanent works implemented up to the end of the period
in question;
(b) An amount reflecting any price adjustment pursuant to GCC Clause 62;
(c) An amount to be withheld as retention sum under GCC Clause 61;
(d) Any credit and/or debit for the period in question in respect of plant and materials on Site
intended for, but not yet incorporated in, the permanent works in the amount and under the
conditions set out in GCC Clause 64.2;
(e) An amount to be deducted on account of the advance payment repayment under the
provisions of GCC Clause 60; and
(f) Any other sum to which the Contractor may be entitled under the Contract.
64.2 The Contractor shall be entitled to such sums as the Engineer may consider proper in respect of
plant and materials intended for, but not yet incorporated in, the permanent works provided that:
(a) The plant and materials conform with the specifications for the permanent works and are set
out in batches in a way that they may be recognized by the Engineer;
(b) Such plant and materials have been delivered to the Site, and are properly stored and protected
against loss or damage or deterioration to the satisfaction of the Engineer;
(c) The Contractor's record of requirements, orders, receipts and use of plant and materials under
the contract are kept in a form approved by the Engineer and such records are available for
inspection by the Engineer;
(d) The Contractor submits with his statement, the estimated value of the plant and materials on
Site together with such documents as may be required by the Engineer for the purpose of
valuation of the plant and materials and providing evidence of ownership and payment
therefore; and
(e) Where the SCC so provide, ownership of the plant and materials referred to in GCC Clause
83 shall be deemed to be vested in the Public Body.
64.3 Approval by the Engineer of any interim payment certified by him in respect of plant and materials
pursuant to this GCC Clause shall be without prejudice to the exercise of any power of the Engineer
under the Contract to reject any plant or materials which are not in accordance with the provisions
of the Contract.
64.4 The Contractor shall be responsible for any loss or damage to, and for the cost of storing and
handling of, such plant and materials on site and shall effect such additional insurance as may be
necessary to cover the risk of such loss or damage from any cause.
64.5 Within 30 days of receipt of the said statement for interim payment, it shall be approved or amended
in such manner that, in the Engineer's opinion, the application reflects the amount due to the
Contractor in accordance with the Contract. In cases where there is a difference of opinion as to the
value of an item, the Engineer's view shall prevail. On determination of the amount due to the
Contractor, the Engineer shall, within the same 30 days deadline, issue and transmit to the Public
Body for payment and to the Contractor for information, an Interim Payment Certificate for the
65.1 Unless otherwise agreed in the SCC, the Contractor shall not later than 90 days after the issue of
the Final Acceptance Certificate referred to in GCC Clause 89, submit to the Engineer a draft final
statement of account with supporting documents showing in detail the value of the work done in
accordance with the Contract, together with all further sums which the Contractor considers to be
due to him under the Contract in order to enable the Engineer to prepare the final statement of
account.
65.2 Within 60 days after receipt of the draft final statement of account and of all information reasonably
required for its verification, the Engineer shall prepare the final statement of account, which
determines:
(a) the amount which in his opinion is finally due under the Contract; and
(b) after establishing the amounts previously paid by the Public Body and all sums to which the
Public Body is entitled under the Contract, the balance, if any, due from the Public Body to
the Contractor, or from the Contractor to the Public Body, as the case may be.
65.3 The Engineer shall issue to the Public Body or to its duly authorized representative, and to the
Contractor, the final statement of account showing the final amount to which the Contractor is
entitled under the Contract. The Public Body or its duly authorized representative and the Contractor
shall sign the final statement of account as an acknowledgement of the full and final value of the
work implemented under the Contract and shall promptly submit a signed copy to the Engineer.
However, the final statement of account shall not include amounts in dispute which are the subject
of negotiations or amicable settlement.
65.4 The final statement of account signed by the Contractor shall constitute a written discharge of the
Public Body confirming that the total in the final statement of account represents full and final
settlement of all monies due to the Contractor under the Contract, other than those amounts which
are the subject of amicable settlement. However, such discharge shall become effective only after
any payment due in accordance with the final statement of account has been made and the
performance security referred to in GCC Clause 58 has been returned to the Contractor.
65.5 The Public Body shall not be liable to the Contractor for any matter or thing whatsoever arising out
of, or in accordance with, the Contract or execution of the works, unless the Contractor shall have
included a claim in respect thereof in his draft final statement of account.
66.1 When the Engineer receives a claim from a Sub-Contractor duly approved under GCC Clause 14 to
the effect that the Contractor has not met his financial obligations so far as the Sub-Contractor is
concerned, the Engineer shall give notice to the Contractor either to pay the Sub-Contractor or to
inform him of the reasons why payment should not be made. Should such payment not be made, or
reasons not be given within the period of notice, the Engineer may, after satisfying himself that the
67.1 Once the time-limit referred to in GCC Clause 59.3 has expired, the Contractor – unless the
Contractor is a public body which is partly or wholly financed by the Federal Government Budget
– shall upon demand, submitted within two months of receiving late payment, be entitled to late-
payment interest at the rediscount rate applied by the National bank of Ethiopia on the first day of
the month in which the time-limit expired, plus three and a half percentage points. The interest shall
be payable for the time elapsed between the expiry of the payment deadline and the date on which
the Public Body’s account is debited. .
67.2 Any default in payment of more than 120 days from the expiry of the period laid down in GCC
Clause 67.1 shall entitle the Contractor either not to perform the Contract or to terminate it.
68.1 All orders for payments to third parties may be carried out only after an assignment made in
accordance with GCC Clause 13. The assignment shall be notified to the Public Body.
68.2 Notification of beneficiaries of the assignment shall be the sole responsibility of the Contractor.
68.3 In the event of a legally binding attachment of the property of the Contractor affecting payments
due to him under the contract, without prejudice to the time limit laid down in GCC Clause 67, the
Public Body shall have 30 days, starting from the day when it receives notification of the definitive
lifting of the obstacle to payment, to resume payments to the Contractor.
69.1 If under the Contract there are circumstances which the Contractor considers entitle him to
additional payment, the Contractor shall:
(a) if he intends to make any claim for additional payment, give to the Engineer notice of his
intention or make such claim within 15 days after the said circumstances become known to
the Contractor, stating the reason for his claim; and
70.1 Subject to the SCC, the Works to be carried out shall be as specified in the Section 6, Schedule of
Requirements.
70.2 The Contractor shall construct and install the Works at sites and locations as are specified in the
SCC in accordance with the Specifications and Drawings or as agreed by the Parties in writing.
71.1 The Public Body shall fix the Start Date on which execution of the Works is to commence in the
SCC or by administrative order issued by the Engineer.
71.2 The Start Date for commencing execution of the Works shall be not later than 120 days following
notification of award of contract unless agreed otherwise by the parties.
72.1 The period of execution of Works shall commence on the Start Date fixed in accordance with GCC
Clause 71.1 and shall be as laid down in the SCC, without prejudice to extensions of the period
which may be granted under GCC Clause 73.
72.2 The Contractor shall carry out the Works in accordance with the Program of implementation of
tasks submitted by the Contractor, as updated with the approval of the Engineer, and complete them
by the Intended Completion Date.
72.3 If provision is made for distinct periods of implementation for separate lots, in cases where one
Contractor is awarded more than one lot per contract, the periods of implementation for the separate
lots will not be accumulated.
73.1 The Contractor may request an extension of the Intended Completion Date if he is or will be delayed
in completing the contract by any of the following causes:
(a) Exceptional weather conditions in the Federal Democratic Republic of Ethiopia;
74.1 The following shall be Compensation Events allowing for time extension:
(a) The Public Body does not give access to a part of the Site by the Site Possession Date stated
in the Contractor’s approved work program;
(b) The Public Body modifies the Schedule of other Contractors in a way that affects the work
of the Contractor under the Contract;
(c) The Engineer orders a delay or does not issue Drawings, Specifications, or instructions
required for execution of the Works on time;
(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work,
which is then found to have no Defects;
(e) The Engineer unreasonably does not approve a subcontract to be let;
(f) The Engineer gives an instruction for dealing with an unforeseen condition, caused by the
Public Body, or additional work required for safety or other reasons.
(g) Other Contractors, public authorities, utilities, or the Public Body do not work within the
dates and other constraints stated in the Contract, and they cause delay;
(h) The advance payment is delayed;
(i) The Engineer unreasonably delays issuing Interim Payment Certificates;
(j) Other Compensation Events described in the SCC or determined by the Public Body and
force majeure.
75. Acceleration
75.1 When the Public Body wants the Contractor to finish before the Intended Completion Date, the
Engineer will obtain priced proposals for achieving the necessary acceleration from the Contractor.
If the Public Body accepts these proposals, the Intended Completion Date will be adjusted
accordingly and confirmed by both the Public Body and the Contractor.
75.2 If the Contractor’s priced proposals for acceleration are accepted by the Public Body, they are
incorporated in the Contract Price and treated as a modification.
76.1 Either the Engineer or the Contractor may require the other to attend a formal management meeting,
to discuss the Public Body's levels of satisfaction in respect of the Works carried out under the
Contract, to review the plans for remaining work, and to agree any necessary action to address areas
of dissatisfaction. The Contractor will not obstruct or withhold its agreement to any such necessary
action. Such meetings shall be attended by duly authorized and sufficiently senior employees of
both the Public Body and the Contractor together with any other relevant attendees. The Parties
shall agree a standing agenda for such Reviews.
76.2 The Engineer shall record the business of management meetings and provide copies of the record
to those attending the meeting and to the Public Body. The responsibility of the parties for actions
to be taken shall be decided by the Engineer either at the management meeting or after the
management meeting and stated in writing to all who attended the meeting.
77.1 The Contractor shall warn the Engineer at the earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the work increase the Contract Price or delay
the execution of the Works. The Engineer may require the Contractor to provide an estimate of the
expected effect of the future event or circumstance on the Contract Price and Completion Date. The
estimate shall be provided by the Contractor as soon as reasonably possible.
77.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the
effect of such an event or circumstance can be avoided or reduced by anyone involved in the work
and in carrying out any resulting instruction of the Engineer.
78.1 If the Contractor fails to complete the works within the time period(s) specified in the Contract the
Public Body shall, without formal notice and without prejudice to his other remedies under the
contract be entitled to liquidated damages for every day or part thereof which shall elapse between
the end of the period specified for implementation of tasks or extended Intended Completion Date
under GCC Clause 72 and the actual date of completion, at the rate and up to the maximum amount
specified in the GCC Clause 27. If the works have been the subject of partial acceptance in
accordance with GCC Clause 86, the liquidated damages specified in the GCC Clause 27 may be
79.1 A work register shall, unless otherwise provided by the SCC, be kept on the site by the Engineer,
who shall enter in it at least the following information:
(a) the weather conditions, interruptions of work owing to inclement weather, hours of work,
number and type of workmen employed on the site, materials supplied, equipment in use,
equipment not in working order, tests carried out, samples dispatched, unforeseen
circumstances, as well as orders given to the Contractor;
(b) detailed statements of all the quantitative and qualitative elements of the work done and the
supplies delivered and used, capable of being checked on the Site and relevant in calculating
payments to be made to the Contractor.
79.2 The statements shall form an integral part of the work register but may, where appropriate, be
recorded in separate documents. The technical rules for drawing up the statements shall be as set
out in the SCC.
79.3 The Contractor shall ensure that statements are drawn up, in good time and in accordance with the
SCC, in respect of work, services and supplies which cannot be measured or verified subsequently;
failing this, he shall accept the decisions of the Engineer, unless, at his own expense, he provides
evidence to the contrary.
79.4 Entries made in the work register as work progresses shall be signed by the Engineer and
countersigned by the Contractor or his representative. If the Contractor objects, he shall
communicate his views to the Engineer within 15 days following the date on which the entry or the
statements objected to be recorded. Should Contractor fail to countersign or to submit his views
within the period allowed, the Contractor shall be deemed to agree with the notes shown in the
register. The Contractor may examine the work register at any time and may, without removing the
document, make or receive a copy of entries which he considers necessary for his own information.
79.5 The Contractor shall, on request, provide the Engineer with the information needed to keep the work
register in good order.
80.1 All goods purchased under the contract shall have their origin in any eligible source country as
defined in the Section 5 of the Bidding Documents.
80.2 The works, components and materials shall conform to the specifications, drawings, surveys,
models, samples, patterns and other requirements in the SCC which shall be held at the disposal of
the Public Body or the Engineer for the purposes of identification throughout the period of
performance.
81.1 The Contractor shall ensure that the components and materials are delivered to the site in time to
allow the Engineer to proceed with acceptance of the components and materials. The Contractor is
deemed to have fully appreciated the difficulties which he might encounter in this respect, and he
shall not be permitted to advance any grounds for delay in fulfilling his obligations.
81.2 The Engineer shall be entitled, either by himself or his agent, to inspect, examine, measure and test
the components, materials and workmanship, and check the progress of preparation, fabrication or
manufacture of anything being prepared, fabricated or manufactured for delivery under the contract
in order to establish whether the components, materials and workmanship are of the requisite quality
and quantity. This shall take place at the place of manufacture, fabrication, preparation or on the
site or at such other places as may be specified in the contract.
81.3 For the purposes of such tests and inspections, the Contractor shall:
(a) provide to the Engineer, temporarily and free of charge, such assistance, test samples, parts,
machines, equipment, tools or materials and labor as are normally required for inspection and
testing;
(b) agree, with the Engineer, on the time and place for tests;
(c) provide access for the Engineer at all reasonable times to the place where the tests are to be
carried out.
81.4 If the Engineer is not present on the date agreed for tests, the Contractor may, unless otherwise
instructed by the Engineer, proceed with the tests, which shall be deemed to have been made in the
Engineer's presence. The Contractor shall forthwith forward duly certified copies of the test results
to the Engineer, who shall, if he has not attended the test, be bound by the test results.
81.5 When components and materials have passed the tests referred to in this GCC Clause, the Engineer
shall notify the Contractor or endorse the procedure's certificate to that effect.
81.6 If the Engineer and the Contractor disagree on the test results, each shall give a statement of his
views to the other within 15 days after such disagreement arises. The Engineer or the Contractor
may require such tests to be repeated on the same terms and conditions or, if either party so requests,
by an expert to be selected by common consent. All test reports shall be submitted to the Engineer
who shall communicate the results of these tests without delay to the Contractor. The results of the
re-testing shall be conclusive. The cost of the re-testing shall be borne by the party whose views are
proved wrong by the re-testing.
82. Rejection
82.1 Components and materials which are not of the specified quality shall be rejected. A special mark
may be applied to the rejected components or materials. This shall not be such as to alter them or
affect their commercial value. Rejected components and materials shall be removed by the
Contractor from the site within a period which the Engineer shall specify, failing which they shall
be removed by the Engineer as of right at the expense and risk of the Contractor. Any work
incorporating rejected components or materials shall be rejected.
82.2 The Engineer shall, during the progress of the works and before the works are taken over, have the
power to order or decide:
(a) the removal from the Site, within such time limits as may be specified in the order, of any
components or materials which, in the opinion of the Engineer, are not in accordance with
the contract;
(b) the substitution of proper and suitable components or materials; or
(c) the demolition and proper re-execution, or satisfactory repair, notwithstanding any previous
test thereof or interim payment therefore, of any work which, in respect of components,
materials, workmanship or design by the Contractor for which he is responsible, is not, in the
opinion of the Engineer, in accordance with the Contract.
82.3 The Engineer shall, as soon as reasonably practicable, give to the Contractor notice in writing of his
decision specifying particulars of the alleged defects.
82.4 The Contractor shall with all speed and at his expense make good the defects so specified. If the
Contractor does not comply with such order, the Public Body shall be entitled to employ other
persons to carry out the same and all expenses consequent thereon or incidental thereto may be
deducted by the Public Body from any monies due or which may become due to the Contractor.
82.5 The provisions of this GCC Clause shall not affect the right of the Public Body to claim under GCC
Clauses 19 and 78.
83.1 All equipment, temporary works, plant and materials provided by the Contractor shall, when
brought on the Site, be deemed to be exclusively intended for the execution of the works and the
Contractor shall not remove the same or any part thereof, except for the purpose of moving it from
one part of the site to another, without the consent of the Engineer. Such consent shall, however,
not be required for vehicles engaged in transporting any staff, labor, equipment, temporary works,
plant or materials to or from the Site.
83.2 The SCC may provide that all equipment, temporary works, plant and materials on Site owned by
the Contractor or by any company in which the Contractor has a controlling interest shall, for the
duration of the execution of the works, be:
(a) vested in the Public Body; or
(b) made subject to a lien in favor of the Public Body; or
(c) made subject to any other arrangement regarding priority interest or security.
84.1 Verification of the works by the Engineer with a view to provisional or final acceptance shall take
place in the presence of the Contractor. The absence of the Contractor shall not be a bar to
verification on condition that the Contractor has been summoned in due form at least 30 days prior
to the date of verification.
84.2 Should exceptional circumstances make it impossible to ascertain the state of the works or otherwise
proceed with their acceptance during the period fixed for provisional or final acceptance, a statement
certifying such impossibility shall be drawn up by the Engineer after consultation, where possible,
with the Contractor. The verification shall take place and a statement of acceptance or rejection
shall be drawn up by the Engineer within 30 days following the date on which such impossibility
ceases to exist. The Contractor shall not invoke these circumstances in order to avoid his obligation
to present the works in a state suitable for acceptance.
85.1 The works shall not be accepted until the prescribed verifications and tests have been carried out at
the expense of the Contractor. The Contractor shall notify the Engineer of the date on which such
verification and tests may commence.
85.2 Works which do not satisfy the terms and conditions of the Contract, or in the absence of such terms
and conditions, which are not carried out in accordance with trade practices in the Federal
Democratic Republic of Ethiopia, shall, if required, be demolished and rebuilt by the Contractor or
repaired to the satisfaction of the Engineer, otherwise this shall be done as of right after due notice
at the expense of the Contractor, by order of the Engineer. The Engineer may also require the
demolition and reconstruction by the Contractor, or repair to the satisfaction of the Engineer, under
the same conditions of work, in which unacceptable materials have been used, or carried out in the
periods of suspension provided for in GCC Clause 20.
86.1 The Public Body may make use of the various structures, parts of structures or sections of the works
forming part of the contract as and when they are completed. Any taking over of the structures, parts
of structures or sections of the works by the Public Body shall be preceded by their partial
provisional acceptance. However, works may in cases of urgency be taken over prior to acceptance
provided an inventory of outstanding work is drawn up by the Engineer and agreed to by the
Contractor and the Engineer beforehand. Once the Public Body has taken possession of a structure,
a part thereof or section of the works, the Contractor shall no longer be required to make good any
damage resulting otherwise than from faulty construction or workmanship.
86.2 The Engineer may, at the request of the Contractor and if the nature of the works so permits proceeds
with partial provisional acceptance, provided that the structures, parts of structures or sections of
the works are completed and suited to the use as described in the Contract.
86.3 In the cases of partial provisional acceptance referred to in GCC Sub-Clauses 86.1 and 86.2 the
Defects Liability Period provided for in GCC Clause 88 shall, unless the SCC provide otherwise,
run as from the date of such partial provisional acceptance.
87.1 The works shall be taken over by the Public Body when they have satisfactorily passed the tests on
completion and a certificate of provisional acceptance has been issued or is deemed to have been
issued.
87.2 The Contractor may apply, by notice to the Engineer, for a certificate of provisional acceptance not
earlier than 15 days before the works, in the Contractor's opinion, are complete and ready for
provisional acceptance. The Engineer shall within 30 days after the receipt of the Contractor's
application either:
(a) issue the certificate of provisional acceptance to the Contractor with a copy to the Public
Body stating, where appropriate, his reservations, and, inter alia, the date on which, in his
opinion, the works were completed in accordance with the Contract and ready for provisional
acceptance; or
(b) reject the application giving his reasons and specifying the action which, in his opinion, is
required of the Contractor for the certificate to be issued.
87.3 If the Engineer fails either to issue the certificate of provisional acceptance or to reject the
Contractor's application within the period of 30 days, he shall be deemed to have issued the
certificate on the last day of that period. The certificate of provisional acceptance shall not be
deemed to be an admission that the works have been completed in every respect. If the works are
divided by the contract into sections, the Contractor shall be entitled to apply for separate certificates
for each of the sections.
87.4 Upon provisional acceptance of the works, the Contractor shall dismantle and remove temporary
structures as well as materials no longer required for use in connection with the performance of the
contract. He shall also remove any litter or obstruction and redress any change in the condition of
the Site as required by the contract.
87.5 Immediately after provisional acceptance, the Public Body may make use of all the works as
completed.
88.1 The Contractor shall be responsible for making good any defect in, or damage to, any part of the
works which may appear or occur during the Defects Liability Period and which arises either from:
(a) the use of defective plant or materials or faulty workmanship or design of the Contractor;
and/or
(b) any act or omission of the Contractor during the Defects Liability Period.
88.2 The Contractor shall at his own cost make good the defect or damage as soon as practicable. The
Defects Liability Period for all items replaced or renewed shall recommence from the date when
the replacement or renewal was made to the satisfaction of the Engineer. If the contract provides
for partial acceptance, the Defects Liability Period shall be extended only for the part of the works
affected by the replacement or renewal.
88.3 If any such defect appears or such damage occurs, during the period referred to in GCC Clause 88.1,
the Public Body or the Engineer shall notify the Contractor. If the Contractor fails to remedy a
defect or damage within the time limit stipulated in the notification, the Public Body may:
(a) carry out the works himself, or employ someone else to carry out the works, at the
Contractor's risk and cost, in which case the costs incurred by the Public Body shall be
deducted from monies due to or from securities held against the Contractor or from both; or
(b) terminate the Contract.
88.4 If the defect or damage is such that the Public Body has been deprived substantially of the whole or
a part of the benefit of the works, the Public Body shall, without prejudice to any other remedy, be
entitled to recover all sums paid in respect of the parts of the works concerned together with the
cost of dismantling such parts and clearing the Site.
88.5 In case of emergency, where the Contractor cannot be reached immediately or, having been reached,
is unable to take the measures required, the Public Body or the Engineer may have the work carried
out at the expense of the Contractor. The Public Body or the Engineer shall as soon as practicable
inform the Contractor of the action taken.
88.6 Where the SCC stipulates that the maintenance work, necessitated by normal wear and tear, shall
be carried out by the Contractor, such work shall be paid for from a provisional sum. Deterioration
resulting from the circumstances provided for in GCC Clause 44 or from abnormal use shall be
excluded from this obligation unless it reveals a fault or defect justifying the request for repair or
replacement under GCC Clause 88.
88.7 The defects liability shall be stipulated in the SCC. If the duration of the Defects Liability Period is
not specified, it shall be 365 days. The Defects Liability Period shall commence on the date of
provisional acceptance.
88.8 After provisional acceptance and without prejudice to the defects liability referred to in this GCC
Clause, the Contractor shall no longer be responsible for risks which may affect the works and
which result from causes not attributable to him. However, the Contractor shall be responsible as
from the date of provisional acceptance for the soundness of the construction, as laid down in the
in the Ethiopian law.
89.1 Upon the expiry of the Defects Liability Period, or where there is more than one such period, upon
the expiry of the latest period, and when all defects or damage have been rectified, the Engineer