PRADHAN MANTRI AWAS
YOJANA
HOUSING FOR ALL (URBAN)
[PMAY - HFA (U)]
WEST BENGAL
Fund sharing –Beneficiary Led Constructions (BLC)
❑ Cost break up for construction of Dwelling Units:
All figures in Rs. Lakhs
Central State Beneficiary Total
Share Share Contribution
ULBs having population more than 5 lakhs 1.50 1.83 0.35 3.68
ULBs having population less than 5 lakhs 1.50 1.93 0.25 3.68
ULBs in Hilly Areas 1.50 2.66 0.25 4.41
❑ Cost break up for Infrastructure Development (ID):
Unit cost for ID: 10% of DU Cost
All figures in Rs. Lakhs
Central State ULB Total
Share Share Contribution
ULBs having population more than 5 lakhs - 0.184 0.184 0.368
ULBs having population less than 5 lakhs - 0.184 0.184 0.368
ULBs in Hilly Areas - 0.2205 0.2205 0.441
OVERVIEW OF SANCTIONED
BENEFICIARY LED
CONSTRUCTIONS (BLC)
PROJECTS
Overview of sanctioned Projects
FY in which projects No. of Sanctioned No. of Approved No. of
are sanctioned Projects Beneficiaries Beneficiaries
attached in
PMAY-MIS
2015 – 16 108 74,880 68,370
2016 – 17 42 68,664 54,742
2017 – 18 86 59,929 57,545
2018 - 19 119 1,28,443 1,01,624
TOTAL 355 3,31,916 2,95,636
Physical Progress
FY 2015 – 16 FY 2016 – 17 FY 2017-18 FY 2018-19 TOTAL
➢ Approved DUs 74,880 68,664 59,929 1,28,443 3,31,916
➢ No. attached 68,370 54,742 57,545 1,01,624 2,95,636
➢ Total Grounded
67,008 49,086 50,036 22,939 1,89,069
DUs
➢ Foundation
344 6,337 11,571 986 19,238
Level
➢ Lintel Level 696 5,281 11,237 510 17,724
➢ Roof Level 4,075 10,928 12,228 316 27,550
➢ Completed 64,675 29,700 12,102 513 1,06,990
➢ Occupied (out
64,675 29,700 12,102 513 1,06,990
of Completed)
Revision of Projects: Removal of beneficiaries
■ FY 2015-16:
➢ A total of 74,880 beneficiaries were approved across 108 projects, out of
which 68,370 beneficiaries have been attached online.
➢ Out of the above, 66,911 beneficiaries have been confirmed by ULBs towards
construction of DUs.
➢ A total of 1471 Beneficiaries have opted out from the list of beneficiaries
attached for 46 projects out of 108 projects sanctioned due to reasons like
land issues, migration to other states, inability to pay beneficiary share etc..
These 1471 beneficiaries have to be removed from PMAY – MIS to achieve
final figure.
➢ BLC DPR approved for Bhatpara Municipality of North 24 Parganas district
comprising of 289 beneficiaries, will not be implemented. Hence, the entire
project may be treated as cancelled.
Revision of Projects: Removal of
beneficiaries
■ FY 2016-17:
➢ A total of 68,664 beneficiaries were approved across 42 projects, out of
which 54,742 beneficiaries have been attached online.
➢ Out of the above, 54,742 beneficiaries have been confirmed by ULBs
towards construction of DUs.
➢ A total of 53 Beneficiaries have opted out from the list of beneficiaries
attached for 42 projects out of 42projects sanctioned due to reasons
like land issues, migration to other states, inability to pay beneficiary
share etc.. These 53 beneficiaries have to be removed from PMAY –
MIS to achieve final figure.
Legal Heir cases in BLC projects
❑ FY 2015-16:
➢ A total of 216 beneficiaries are to be replaced by their respective legal
heirs due to death of the beneficiaries which are across 34 projects
➢ Following documents / testimonials are submitted :
➢ A database containing the details of deceased beneficiaries
alongwith their legal heir
➢ Death certificates of the deceased beneficiaries
➢ Legal heir certificates of the successors
Financial Progress for Projects sanctioned in FY 2015-16
Fund received (1st & 2nd instalments):
➢ Central Share: Rs.837.77 Crores
➢ State Share (incl. ID): Rs. 1811 -16 Crores
➢ Total fund received: Rs.2018.92 Crores
Fund released to ULBs:
➢ Central Share: Rs.965.90 Crores
➢ State Share (incl. ID): Rs.1362.34 Crores
➢ Total fund released: Rs.2328.24 Crores*
Utilization:
➢ Total fund utilized: Rs.2204.82 Crores (95%)
* Additional fund of Rs.310.19 Crores has been released to the better performing ULBs having projects
sanctioned in FY 2015-16 from the allotted fund for projects sanctioned in FY 2016-17 & 2017 – 18
Financial Progress for Projects sanctioned in FY 2016-17
Fund received (all figures in Rs. Crores):
➢Central Share: Rs.629.24 Crores
➢State Share (incl. ID): Rs.877.69 Crores
➢Total Fund received : Rs.1506.93 Crores
Fund released to ULBs:
➢ Central Share: Rs.551.73 Crores
➢ State Share (incl. ID): Rs.776.38 Crores
➢ Total fund released: Rs.1328.11 Crores
Utilization:
➢ Total fund utilization: Rs.1096.32 Crores (83%)
Financial Progress for Projects sanctioned in FY 2017-18
➢Fund received (all figures in Rs. Crores):
➢Central Share: Rs.341.65 Crores
➢State Share (incl. ID): Rs.481.57Crores
➢Total Fund received : Rs.823.22 Crores
➢Fund released to ULBs:
➢Central Share: Rs.402.40Crores
➢State Share (incl. ID): Rs.567.72 Crores
➢Total fund released: Rs.970.12 Crores
➢Utilization:
➢Total fund utilization: Rs. 712.14 Crores (73%)
Financial Progress for Projects sanctioned in FY 2018-19
Fund received (all figures in Rs. Crores):
➢Central Share: Rs.459.64 Crores
➢State Share (incl. ID): Rs.649.58Crores
➢Total Fund received : Rs.1109.22 Crores
➢Fund released to ULBs:
➢Central Share: Rs.122.01Crores
➢State Share (incl. ID): Rs.173.42 Crores
➢Total fund released: Rs.295.43 Crores
Utilization Status
■ FY 2015-16:
– Total Central Share received as 1st & 2nd Installment : Rs.837.77 Crores
– UC Submitted to MoHUA, GoI :Rs.777.72 Crores
(93%)
– Request for release of 3rd & Final Installment :Rs.285.42 Crores
■ FY 2016-17:
– Total Central Share received as 1st Installment 1st & 2nd Installment:
Rs.648.48 Crores
– UC amounting Rs. 411.98 Crores (100%) has already been submitted to
MoHUA ,GOI with a request for release of 2 nd Installment of Rs.411.98
Crores
– Requirement of Fund for approved AHP Projects :
Request has already been sent to MoHUA, GoI for immediate release of Rs. 6.34
Crore against the approved project cost as 1st Installment (40% of Rs. 15.84 Crore)
NEW PROPOSALS
UNDER BENEFICIARY
LED CONSTRUCTION
(BLC) FOR FY 2019-20
New Proposals under BLC for FY 2019 – 20
■ DPR submitted by ULBs : 34
■ Total number of beneficiaries to be covered : 26,393
Financial involvement (Rs. In Crores)
■ Total Project Cost : 1080.94
■ Total Central share involved : 395.90
■ Total State share (including ID) involved : 569.93
■ Total ULB Share (for ID) involved : 49.13
■ Total Beneficiary contribution to be mobilized : 65.98
■ Requirement of Central Share as 1st instalment (40%) : 158.36
■ Requirement of State Share including ID 1st instalment (40%) : 227.97
NEW PROPOSALS UNDER
BANGLAR BARI
& AFFORDABLE HOUSING
IN PARTNERSHIP FOR FY
2019-20
Banglar Bari and AHP by Development
Authorities / Developer for FY 2019-20
Name LOcatio No of Unit Total Central State DA Benefic Ist Ist
of DA n Dus Cost/D Project share share Share iary Intallm Installme
us Cost @1.5/L @ 2.79 Share ent of nt of
K per LK/per Central Matching
Dus DUs share(4 State
0%) Share
(40%)
KMDA Hatath 192 6.48 395.52 96.00 178.56 48.00 372.48 115.20 214.27
Pally,Ult
adanga
under
KMC
Some glimpses of completed Dwelling Units
Bansberia Municipality, Suri Municipality,
Hoogly District Birbhum District
Some glimpses of completed Dwelling Units
Barrackpore Municipality,
North 24 Parganas District
Ramjibanpore Municipality,
Paschim Medinipur District
Some glimpses of completed Dwelling Units
Contai Municipality,
Purulia Municipality,
Purba Medinipur District
Purulia District
Some glimpses of completed Dwelling Units
Old Malda Municipality,
Malda District
Krishnagar Municipality,
Nadia District
THANK YOU