OQ COR 09W: Cathodic Protection Remediation-Corrosion Specialist
OQ COR 09W: Cathodic Protection Remediation-Corrosion Specialist
Corrosion Specialist
Study Guide
INTRODUCTION
Cathodic protection systems along the pipeline must be tested and maintained to
ensure adequate protection against corrosion. The pipeline system has many
test stations, casings, rectifiers, foreign line crossings, isolation flange kits and
test points that allow pipeline personnel and the Corrosion Specialists to monitor
these levels. As a result of annual surveys, bi-monthly rectifier/critical bond
readings, Close Interval Surveys and other tests, remedial measures must be
taken to correct the changing conditions along the pipeline. This module will
attempt to describe in moderate detail the procedures necessary to remedy some
of the basic problems encountered while maintaining our cathodic protection
systems. According to the DOT and BP’s OMER I Manual these tasks are
required. It is beyond the scope of this training to describe in detail every
scenario that may be encountered while trying to maintain adequate levels of
cathodic protection. For the purposes of this training module, a brief description
for installing impressed current and sacrificial groundbeds, installing/checking
isolation flange kits, rectifier maintenance and troubleshooting and the handling
of shorted casings will be given. The Rectifier/Critical Bonds, the Conducting an
Annual Survey and the Perform General Pipeline Repair Activities Study Guides
should serve as additional references to this guide.
CORROSION BASICS
Before we get into the remediation process, let’s discuss some basic corrosion
principles that may help you to understand the need for cathodic protection.
Corrosion by definition is the deterioration of a substance (usually a metal), or
its properties, as a result of its reaction with its environment.
By using the concept that current flows from positive to negative through the
circuit external (termed "conventional current flow concept"), corrosion of the zinc
case is caused by the flow of DC current from the zinc case, through the
electrolyte to the graphite post, and completing the electrical circuit through the
external connection from the positive terminal through the light bulb, and back to
the zinc case, where it started. (Some people call this "conventional current"
flow, or "positive charge" flow, which is in the opposite direction to electron flow).
Since this current flows from the zinc into the electrolyte, it causes the zinc to
corrode.... to be eaten away by corrosion. In this case, the resulting current flow
(as electron flow in the meta llic circuit) would be from the more active metal (the
anode) to the less active metal (the cathode). An oxidation (corrosion) reaction
would occur at the anode and a reduction (cathodic protection) reaction would
occur at the cathode. Just like the cathodic protection systems installed along
the pipeline, the anodes corrode or are consumed. They in turn produce and
electrical current that helps to protect the pipeline from external corrosion.
All metals exist in nature in their lowest energy level. This state of existence is
referred to as the "ore" state of the metal. For most metals, this is not a very
usable state. By refining, they become a very useful material (i.e. carbon steel
for our pipelines and ASTs).
It takes a different amount of energy to refine each kind of metal from its ore. Part
of the refining energy stays within the metal following the refining process. The
more energy it takes to refine the metal, the more that is stored inside the
material. Basically, this is what happens when we take a refined metal like our
pipeline (carbon steel) and bury it in the ground. The pipeline will want to revert
back to its original form (iron ore). As it rusts/corrodes the energy that it retained
from the refining process is released.
OUR DEFENSES
Cathodic protection and coatings are used in combination with one another to
reduce or eliminate corrosion. Cathodic protection is used to turn the pipeline
into a cathode. We are basically raising the pipe’s electrical potential high
enough so that it will not theoretically corrode. Cathodic protection helps the
pipeline retain the energy from the refining process. We accomplish this by
installing impressed current (groundbeds and rectifiers) and sacrificial cathodic
protection systems (magnesium anodes) at various locations along the pipeline.
Coatings are our mainline defense against corrosion. It is used to prevent the
pipeline from coming in contact with an electrolyte (soil, water, etc.). If the
OQ Task – Cathodic Protection Remediation Advanced
2
pipeline is 100% coated, then one leg of the corrosion cell is eliminated (no
electrolyte). Much like the same concept in the fire triangle, if there isn’t any
Oxygen, the fire cannot sustain itself. Since achieving a 100% coated pipeline is
not possible, cathodic protection is used in conjunction with coatings to reduce
the potential of a corrosion related leak.
For the purpose of this study guide, we are going to focus on the cathodic
protection aspects for corrosion prevention.
® Coating condition – The better the condition of coating, the greater the
area of influence from the cathodic protection system.
® Soil Resistivity – The lower the soil resistivity, the greater the area of
influence from the cathodic protection system.
® Anode Configuration – The number, arrangement (deep well or
distributed) and placement of anodes affect the area of influence.
® Type of Anode Material – different anode materials and sizes affect the
overall output of the groundbeds.
® Foreign Structures – The lower number of foreign pipeline/structures in
the vicinity of groundbed, the greater the area of influence.
See the Figure No. 2 on the following page for an example of a typical cathodic
protection system:
There are basically two types of anodes used in the cathodic protection of
pipelines, galvanic and impressed current. Galvanic anodes (magnesium, zinc,
etc.) are typically connected directly to the pipeline via an exothermic weld. This
welding procedure is the same procedure used to attach cathodic protection test
leads to the pipeline. One of the advantages to using a sacrificial anode is that it
does not require an external current source to operate. However, the anode’s
driving potential and current capacities are limited. The anode can be laid either
vertically or horizontally. See Figure Nos. 3 & 4 below for typical installation
details:
BP Anodes
Native Backfill
Cathodic Protection Warning Tape
Pipeline
Spliced connections to anode header cable
Figure No. 3 – Typical magnesium anode array that has been vertically installed.
BP Anodes
Test lead for taking PSPs.
Native Backfill
Pipeline
Cathodic Protection Warning Tape
Figure No. 4 – Typical magnesium anode array that has been horizontally installed.
Galvanic anodes will typically arrive from the manufacturer encapsulated inside a
paper bag that has been lined with plastic. Before the anodes are placed inside
the excavation, it is imperative that the plastic lined bag be removed from the
anode. Otherwise, the anodes will not function. Usually galvanic anodes used
along our pipeline will come pre-packaged with a specialized backfill material. A
five-gallon bucket of water should be poured on the anodes prior to backfilling.
The water will help the anodes activate.
Galvanic anodes should be installed a depth of 3-5 feet below the pipe. These
depths will generally reduce the amount of seasonal current variation that results
from changing moisture contents within the soil.
Typical Uses
Galvanic anodes can be used for a variety of applications along the pipeline.
Generally, they are used in situations where small amounts of Cp current are
required and in location that have low soil resistivity. If a large amount of current
is required, an impressed current CP system is recommended. The following
scenarios are examples of typical galvanic anodes installations:
Ø Hot-spot protection
Ø Small areas on well-coated lines
Ø Valve installation
Ø Shorted casings that cannot be cleared
Ø Areas of electrical shielding
Ø Electrical grounding
Ø Stray current interference
However, before using any of the above applications, all design considerations
(soil resistivity, coating condition, current requirements, easement limitations,
etc.) should be explored.
There are a multitude of impressed current anodes out on the market today.
Some of the most popular anodes are mixed-metal oxides, graphite, high silicon
cast iron and platinum. The type and size of anodes used varies greatly from
environment to environment. The anodes can either come bare or prepackaged
depending on the application. All design considerations should be used in the
selection of anodes.
Impressed current cathodic protection systems are usually installed in these two
arrays, surface anode groundbeds (SAGB) and deep anode ground beds
(DAGB). In a SAGB, the anodes can be either laid vertically or horizontally.
OQ Task – Cathodic Protection Remediation Advanced
7
Their orientation is usually determined by subsurface conditions or right of way
(ROW) restrictions. Figure No. 5 below illustrates the typical installation details
for a vertically installed anode. The anode type, size, diameter and depth should
be determined by the Corrosion Specialist or a company approved engineering
firm.
Native backfill
36 Minimum
Cathodic protection
ground cover
warning tape
Splice connection
to header cable
B
Dimension ‘A’ = Depth of
anode per specs.
Well tamped calcined
coke breeze A
Dimension ‘B’ = Anode to be
C Centered in backfill.
Impressed current
Anode per specs. Dimension ‘C’ = Length of
anode per specs.
Since impressed current anodes are all made up of different materials, are
different lengths, come pre-packaged or bare, they should be handled carefully.
Graphite or silicon cast iron anodes are brittle. If not handled carefully, they can
break. All anodes have lead wires that have been spliced into the anode
OQ Task – Cathodic Protection Remediation Advanced
8
material. It is for this reason the anodes should not be handled by their lead
wires. If necessary, the anodes can be lowered into vertical installation by the
lead wire only if extreme care has been taken to maintain the integrity of the lead
wire/ anode connection point.
As the vertical anode is lowered into the hole, care must also be taken to center
the anode inside of the coke breeze. First of all, an equal amount of coke breeze
should be placed around the entire anode. Secondly, an equal amount of coke
breeze should be placed above and below the anode. Finally, the coke breeze
should be well tamped prior to backfill. This minimizes the possibility of bridging
across the hole with void spaces below the bridge. These voids may increase
circuit resistance and ultimately contribute to the reduction in anode life. If any
questions ever arise during anode installation, please contact the area Corrosion
Specialist for clarification.
After the anodes have been placed into the coke breeze and backfilled to the
bottom of the trench, they should be spliced into a header cable using either a
two-part epoxy resin mix that can be poured into a form around the compression
crimp, or a high voltage underground taped splice. The header cable can then
be routed into the rectifier and terminated.
All underground cables connected to the positi ve terminal of the rectifier are
subject to corrosion at any break in the insulation. The slightest current
discharge at any of these points will result in cable breaks. Anode header
cable’s can be cut by a third party contractor, company personnel or even
rodents. Splices at anode locations can fail prematurely due to improper slicing
techniques. Moisture usually intrudes into the spliced connection providing an
avenue for current discharge. It is for this reason that extreme care must be
taken when making splice connection, handling and backfilling cables.
When backfilling over any CP cable, care must be taken to ensure that there are
no sharp rocks or objects in the cable trench that might puncture the insulation.
The first layer of backfill over the cable should have at least 6’ of cover to protect
the cable from subsequent layers of backfill. In very rocky soil conditions, it is
recommended that sand be used for the first 6 inches of backfill over the CP
cable. Horizontal cable runs are typically buried to a depth of at least 24 inches.
Step 1 – Connect Anode to Header Cable Step 2 – Apply electrical insulating putty.
Step 5 – Reapply “Scotch Kote” Step 6 – Apply multiple coats of electrical tape
Step 3 – Pour mixed epoxy resin into mold Step 4 – Plug and tape over the fill location.
until it completely covers the spliced Let the epoxy resin cure prior to backfilli ng.
connection
Various standards for rectifier installations are used by pipeline companies. The
installation practices will vary depending on local codes or conditions and even
individual Corrosion Specialist preferences. The installations examples given in
this study guide are to be used as general guidelines. The Area Corrosion
Specialist should be consulted for specific site details. See Illustration No. 9, 10
and 11 on the following pages for typical rectifier installations.
C D 3 4
B 2
5
A 1
F 6
STRUCTURE ANODE
(-) (+)
Illustration No. 12 Post-mounted rectifier with positive junction box installed below the rectifier
RECTIFIER TROUBLESHOOTING
Simple, common sense upkeep will help keep a rectifier in good working order.
Keeping the paint touched up prevents corrosion of the sheet metal enclosure
and a little periodic lubrication of the hinges and catches will insure their proper
operation. Nicks and dents should be taken care of, not only for appearance
sake, but to prevent eventual rust-through.
Oil immersed rectifiers radiate heat from the sides of the enclosure, so room
should be allowed for this radiation to take place. Thick mastics or other heavy
coatings should never be applied to the sides of the tank. This will insulate the
tank allowing heat build-up, which becomes detrimental to the power
components inside.
The oil should be checked periodically for contamination and for dielectric
strength. Contamination can cause dielectric breakdown or chemical
deterioration of certain components. Periodic checks should be made for
moisture in the bottom of the tank and drained off if necessary.
All rectifier enclosures, whether air or oil cooled, should be properly grounded.
Ungrounded cases are a potential shock hazard. A technician standing on damp
ground could be seriously injured or killed if a short existed in the rectifier,
causing an above ground potential on the case.
Ground rods should be driven adjacent to the rectifier and a good electrical bond
made between the rod and the case.
To troubleshoot, one must first have a working knowledge of the individual parts
and their relation to one another.
To gain such knowledge, let us follow the order in which they appear, starting at
the A.C. input of the rectifier:
The input lightning arrestor may be the first component on the input side of the
rectifier. Lightning arrestors come in a wide variety of sizes, shapes, and forms;
however, most are essentially a set of gapped points across which an arc current
may travel when a voltage surge is great enough in magnitude. Failure of the
arrestor itself is unlikely to directly cause failure of other components following it,
but if the arrestor is destroyed, it leaves the rest of the rectifier circuit vulnerable
to the other voltage surges. Arrestors may be tested, but the equipment needed
to do this is seldom available in the field. Usually, a visual inspection is adequate
to determine if the arrestor is good or bad.
The circuit breakers are the next components in line after the arrestors. A circuit
breaker is a mechanical switch with either a magnetic or thermal trip element. It
is designed so that excessive current through the trip element will open the
mechanical contacts. The switch has two modes of failure, “short” or “open”.
The contacts may weld in the closed position, or an open may develop because
the contacts have burned away or the trip element in series with the contacts has
an open. Voltage or continuity checks can be made across breakers to
determine if one of these inoperative conditions exist.
Following the circuit breakers is the transformer. It consists of two coils of wire
wound around a laminated iron core. One winding, called the “primary”, has the
input voltage applied to it. This in turn induces voltage into the other winding,
called the “secondary”, through a magnetic coupling in the core. Taps placed at
intervals on the secondary allow different voltages to be selected for setting the
rectifier output. The transformer is very rugged and is not failure prone, but
lightning or inadequate insulation can cause failure. If the primary should
develop an open, there will be no voltage induced into the secondary to be
applied to the rectifier stack. If the secondary has an open between the two taps
being used for the stack supply voltage, no voltage will exist across those taps or
any taps that span the open. If the open is beyond the tap setting being used,
however, as long as no further failure develops, the transformer may be used as
is within the range excluding the open. If a short develops in either winding, the
result will be excessive currently in the winding that will eventually cause failure
of the transformer a nd or breaker.
The rectifier stack changes the A.C. to D.C. by inverting alternate halves of the
A.C. wave form, making all portions of the wave form electrically unidirectional.
Selenium or silicon semiconductors accomplish this. These semiconductors may
fail in an open or shorted condition. If they are open, the output of the rectifier
will be either half its previous output or zero, depending on whether half or all of
the stack currently which will burn up wiring or the transformer if the breakers do
OQ Task – Cathodic Protection Remediation Advanced
18
not trip in time (with low tap settings this is possible because of the high
secondary current, but relatively low reflected primary current).
Fuses are placed in a rectifier to protect the more expensive components. A fuse
consists of a low melting point metal element, which is designed to carry specific
current. Current exceeding the rating creates excessive heat, which melts the
element, opening the circuit it is protecting.
Meters are used in a rectifier to indicate the amount of D.C. voltage and current
present in the output. They consist of a coil of very fine wire through which a few
milliamps of current flow when it is energized. Magnetic fields caused by current
flow in the coil attempt to align the coil with a permanent magnetic field, with the
amount of meter deflection being proportional to the current through the coil.
Delicate instruments such as these are susceptible to damage from voltage or
current surges left continuously in the circuit, therefore, switches are usually
recommended to remove the meters from the circuit when not being read. The
movements may be damaged or ruined completely giving the technician a false
indication of trouble in another component. To verify reading of the output
meters, use portable meters of known accuracy and compare readings.
Troubleshooting – Basics
Troubleshooting Equipment
Troubleshooting Procedures
Most rectifier troubles are simple and do not require extensive detailed trouble
shooting procedures. Most common problems are: blown fuses, faulty meters,
loose terminals, open ground bed leads and lightning damage. These troubles
are usually found by a simple visual examination of the rectifier.
For more difficult trouble, however, it is usually better to systematically isolate the
rectifier components until the defective part is found. This amounts to trading a
difficult problem for several simpler ones. This may be done as follows (please
refer to Illustration No. 13 for Point locations.
2. Check across the load side of the circuit breaker at Points B to determine
whether it is defective. The voltage should be the same as that at Points
A.
3. Check the input change taps (Point C) for loose connections and to verify
that the tap change bar (or lead) is adjusted for the correct input voltage.
5. Measure the AC voltage supplied to the rectifier stack (Points F and G).
This voltage should be the same as that measured at the transformer
secondary, but not at the stack AC terminals, check the leads from the
transformer to the stack as follows: Place the AC voltmeter leads between
Point D on the transformer secondary and Point G on the stack. If no
voltage is present, the lead between Points E and G is probably open.
Verify by measuring the AC voltage between Points E and F. If voltage is
present between these points, the open is between Points E and G.
Replace the defective lead.
6. If the circuit breaker trips, the stack may be isolated from the rest of the
DC circuit by removing one of the DC leads at either Point H or Point J. If
the breaker continues to trip, the stack is defective and should be
replaced.
8. If the circuit breaker does not trip when a DC lead on the stack is
removed, but does trip when it is connected, the short circuit is probably in
the external ground-bed or structure leads. This may be verified by
removing one of the external DC leads from the rectifier and turning the
rectifier on again.
12. The meter switches may be checked with an ohmmeter or, after consulting
the wiring diagram, jumper wires may be placed across the switch
terminals. (Care must be taken not to short across both switch terminals
at the same time on units equipped with combination voltammeters).
13. Some rectifiers are equipped with a filter for noise interference or to
improve conversion efficiency. If it is suspected that the choke is
defective, it may be effectively taken from the circuit by placing a heavy
jumper lead across the choke leads.
14. Lightning arrestors in rectifier may be isolated by removing them from the circuit.
The rectifier will operate without them.
Troubleshooting Tips
Many rectifiers problem are relatively obvious to the experienced technicians upon
physical examination. The obvious should never be overlooked! Loose connections,
signs of arcing, strange odors, etc., indicate troubles, which do not require elaborate test
procedures to uncover. Some helpful troubleshooting tips to follow:
1. If no output voltage or current is present, the trouble and remedy may be:
f. Circuit breaker (or thermal overload protector). If the contacts do not close,
they should be repaired or the breaker replaced.
a. Rectifier may be connected for higher input voltage than that being used.
b. Half the stacks or plates open-circuited, making the unit operate as half-
wave, rather than full-wave rectifier.
c. Badly aged stacks.
d. In a three-phase unit, in addition to the above, one phase may:
i. Be open circuited, in which case the current in one AC line will be
considerably less than that in the other two.
ii. Have stacks that are more aged than the other two.
CASED CROSSINGS
Historically, carrier pipelines have been installed inside sections of larger pipe
under railroads and highways that bore heavy traffic. The purpose was threefold.
The larger pipe, termed a casing, was supposed to bear the brunt of the traffic
impact load, preventing damage to the carrier pipe. The casing was supposed to
carry any flammable fluids or gasses away from the traveled roadway and
thereby prevent any fire or explosion that might occur if the vapors should be
ignited by traffic. The pipe could be removed and repaired, or replaced, without
disturbing the roadway. End seals were used in an effort to prevent water and
other contaminates from entering the annulus between the casing and the carrier
pipe and causing corrosion due to differential aeration or any other type of
corrosion that could occur without cathodic protection. A vent pipe was added
near one or both ends of the casing to vent fluids and vapors to the atmosphere.
Even with the improvements in modern construction techniques and the products
on the market today, we are still faced with situations where the carrier pipe and
the casing are shorted together. Unfortunately, over time the casing and carrier
pipe may become shorted. In other words, the casing and carrier pipe are
contacting each other at one or more points. When this happens it becomes very
difficult to cathodically protect the section of pipeline inside of the casing. As a
result, all shorted casings shall be monitored for leaks until the shorted condition
OQ Task – Cathodic Protection Remediation Advanced
25
has been corrected or the casing has been removed. Typically, shorted casings
are identified during annual cathodic protection surveys.
During the annual cathodic protection surveys, casing-to-soil (CSP) and carrier
pipe-to-soil potentials (PSP) are taken at every location that casings exist.
Shorted conditions can usually be identified by having identical or very similar
potentials on the casing and the carrier pipe. However, it should be noted that
additional testing should be performed by the Corrosion Specialist to make the
final determination. These locations should be highlighted during the annual
surveys.
The methods used for the control of corrosion within casings are: Coatings; End
seals; Electrical isolation; Cathodic Protection; and Inhibitors.
Coatings
The coatings used within a casing must provide the following properties if
corrosion protection of the carrier pipe is to be obtained:
Approved casing seals are Thunderline ‘Link Seals’ and ‘CANUSA or RAY-
CHEM’ heat-shrink casing end seals. The Canusa Casing Seal kit (CSK) forms a
waterproof seal that is resistant to vibration, impact, corrosive gases, and
thermo-dynamic effects resulting from the expansion and contraction of carrier
and casing pipes, flanges and mechanical couplers. The CSK consists of several
components including; a heat shrinkable one -piece wraparound sleeve, a
polypropylene support skirting, and a roll of filament tape. Depending on the
specific application, several optional items may also be included in each kit. The
sleeve is made of a cross-linked polyolefin sheet coated with a layer of anti-
corrosion adhesive. It features the patented "Snap-fit" closure that allows for fast
and simple installation without the need for special tools or equipment. The CSK
is available in 500mm (20") or 860mm (34") widths to fit almost all casing/carrier
pipe size combinations.
Casing Isolators
Electrical isolation of the carrier pipe from the casing must be achieved and
maintained if protection of the carrier pipe is expected. The following methods
are employed:
® The carrier pipe’s coating must maintain electrical isolation of the carrier
pipe from the environment, as well as from the casing. If this is not done,
current may discharge from all anodic points and/or may cause a shorted
condition if allowed contact with the casing.
Casing Fillers
Casing fillers are generally made of a substance that is not electrically
conductive and somewhat impervious to moisture. Casing fillers are intended to
OQ Task – Cathodic Protection Remediation Advanced
27
eliminate (by displacement) the corrosive environment within the casing annulus.
The filler material must be compatible with the carrier pipe coating. The most
commonly used casing filler materials are the low melting point waxes or
petrolatum. These materials have been used in the oil and gas industry for over
forty years. They do not require priming, gelling agents, extremely high
installation temperature, or exotic installation equipment and techniques.
Hot installed casing fillers are delivered to the casing job site in a heated tanker
truck and pumped down the casing vent as a hot liquid. As the material cools, it
firms up to a wax consistency, forming a high dielectric, anti-corrosive barrier
between the casing and the carrier pipe.
The most significant contribution of casing fillers is the ability to discourage the
effects of atmospheric corrosion. Even in the absence of ground water in the
casing annulus, moisture and condensation are usually present in the
atmosphere of the casing annuals. The moisture in conjunction with the oxygen
present in the casing may result in the corrosion of the carrier pipe at holidays
and other damaged areas of the coating. By developing a barrier between the
casing and carrier pipe the filler acts as an additional coating material that will
decrease the possibility of corrosion of the carrier pipe.
It is virtually impossible to fill a casing with only one vent, especially if the casing
contains water. The filling of casings with one vent should not be attempted,
since the success is questionable. It is Amoco's intent to install vents on both
ends before casing filler is injected.
Check the end seals to assure that they are intact and able to hold the casing
filler without allowing it to leach into the environment outside the casing.
Remove the water from the casing annulus if possible either through blowing the
casing out with a compressor or by exposing each end of the casing, removing
the end seal and link seals. This will allow the water to drain.
iii. Contact and coordinate work with the property owners and
tenants.
OQ Task – Cathodic Protection Remediation Advanced
29
iv. Determine the low end of the casing if possible. Expose the
low end first.
2. Excavation:
i. Remove old end seals, and test leads. Vents may also need
to be removed if they are plugged or in bad condition.
iii. Remove all solids, such as sludge and mud, from the
annulus of the casing. This may be accomplished by
washing with fresh water under pressure. To accomplish this
properly, one end of the casing should be sealed to
withstand the water pressure.
4. The water line should be attached to the same end of the casing by way of
a temporary vent or nipple. Existing vents may be used if their condition is
such that they were not previously removed.
5. Inspect the pipeline and casing condition.
8. Inspect the pipeline for corrosion. If corrosion damage is found, make the
necessary repairs. If repair of the pipeline is not possible and the extent of
the corrosion damage is severe, replace the pipe. (See the procedures for
new installation in Section VIII, Pipeline Construction and Maintenance)
12. Lift with air bags. The use of air bags reduces the possibility of damage to
the pipeline. The stress exerted on the pipeline is spread over a larger
area of the pipe.
13. Center the carrier pipe in the casing to allow the installation of casing
insulators and link seals.
14. Stabilize the carrier pipe outside of the casing with sand or cement filled
bags.
15. Install the appropriate nonmetallic casing insulators.
16. Seal the pipe/casing annulus space with an appropriate link seal.
17. Apply an approved coating material to vent pipes (up to grade level) link
seal bolts and casing test leads at the point of the exothermic welds.
18. Backfill the work area restoring it to the proper compaction and shape.
Repair any pavement if disturbed. Please see the Completed Casing
Installation in Illustration No. 15 on the following page.
IF Kit Purposes
One of the problems associated with Cathodic Protection (CP) deals with
ensuring that the CP current generated by the various CP systems installed
along the pipeline remains on the pipeline or any other structures intended to
receive that current. If the pipeline is not insulated from its end points or
attachments, the CP current will usually take the path of least resistance (usually
bare structures) to any structure in the area that remains electrically continuous
to the pipeline. The bottom line is any structure that is electrically continuous
with our pipeline will receive CP current. It should be up to the Area Corrosion
Specialist to determine which structures should be protected or tied to our
system.
Ø They must have extremely low moisture absorption and have very
low moisture vapor transmission rate.
ü The number of bolts and type (Stud bolts and/or through bolts)
ü Whether the insulation is desired to insulate the bolts from each flange
face ("insulate both sides"), or from only one flange face ("insulate one
side")
Please see the Illustration No. 16 on the following page for typical isolating
devices.
2. If the union is to replace another union already installed, remove the one
to be replaced and set it aside so it cannot be involved in the re-assembly.
3. Clean the pipe threads thoroughly and apply lubricant with graphite (anti-
sizing compound).
4. Disassemble the new insulating union. Clean and lubricate all threads.
5. Install the body part that has the threaded shoulders. Make sure it is not
cross-threaded. Run it up hand tight, then tighten it with a wrench to its
final torque. Be sure not to damage the threads on its shoulders.
6. Slip the nut on the other pipe end with the threaded end out. Move it back
from the end until it will not be in the way of the next step.
7. Install the remaining body part (Be sure the brass ring is in place behind
its shoulder). Make sure it is not cross-threaded. Run it up hand tight,
then tighten it with a wrench to its final torque. Be sure not to damage the
insulation or the brass ring.
8. Move the nut back over the body part just installed, and engage it onto the
threads of the first body part installed. Make sure it is not cross-threaded,
and tighten it hand tight.
9. Tighten the nut to its required sealing pressure. If it is an "O" ring type,
hand tightening will probably be enough. If it is a ground joint type, a
wrench will probably have to be used, but...do not over tighten, or the
insulation might be damaged. Do not use a hammer to beat on a
handlebar type of nut.
3. Align the flange faces so that they are parallel and concentric with
the boltholes in a lignment.
4. Insert two bolts on each side of the flange far enough below the midway
boltholes to hold the center gasket in place. Temporarily tighten the bolts
hand tight, and properly insert the center gasket.
5. Line up all of the bolt holes by driving two tapered drift pins in
opposite directions to each other into two diametrically opposite bolt
holes.
6. Insert the insulating sleeves into the bolt holes (except the holes which
have the drift pins). If they do not slide in easily, the flanges are not lined
up properly. Do not force sleeves into the boltholes otherwise damage
might occur.
7. Assemble the insulating material on the bolts as follows:
i. • Run one nut on each all thread bolt so that two full threads
are showing beyond the nut.
ii. • From the opposite end of the bolt, place one metal washer
and one insulating washer against the nut.
8. Insert all of the bolts with the nut and washers through the sleeves in the
flange (except in the holes where the drift pins are). Place an insulating
washer and then a metal washer on each bolt. Run a nut on the end of the
bolt. Tighten until all nuts are hand tight.
10. Torque all bolts in their proper sequence until approximately 60% of their
final value.
11. Continue to torque all bolts in the proper sequence until all have been
properly tightened.
14. Properly re-coat any thermite welds, and/or any other area where the
coating was damaged.
ü Measure the potential on each side the insulating device, leaving the
reference cell in the exact same location for each reading (PSP). If there
is no potential difference, the device could be shorted. It could also be
insulated. Check the resistance across the device with an ohmmeter. If it
"zero" ohms, the device is shorted. It if reads some value of resistance, it
is not shorted.
The current pickup area is usually close to the current source. The current is
discharged into the electrolyte outside of the current pickup area. The discharge
point is usually close to a completely different structure that acts as a better
conductor for the current to return back to its source. This other structure might
have the same owner as the offending source.
The d-c interference can be caused by any source of direct current, such as:
• Rectifiers
• Sun Spot (Telluric) Activity
• D-C railroads and transit systems
• Diesel Electric Trains
• Mine operations, Elevators, and Welding Shops
• High voltage d -c transmission lines
Rectifiers
Usually there are only two pipelines involved when a rectifier is the source of
interference; however, sometimes several structures can be involved, and be
damaged as a result of only one offending source. For instance, for a cathodic
protection system, the current pickup area might be the power company
grounding system in the vicinity of the rectifier, and the discharge point(s) might
be either off of their grounding system, or a farmers metal water line, or metal
gas line, or any combination of the three.
Impressed current cathodic protection systems are the most prevalent source of
interference problems. These usually belong to a foreign company; however, if
we are not careful, we can cause interference to others, or even to some of our
own facilities.
The particles, and the movement of the ionization layers, cause a disturbance in
the earth’s magnetic field. This magnetic field disturbance has an effect on any
metallic conductor (such as a pipeline) within its field. The longer the pipeline,
and the better its coating, the more it is effected.
There will also be the effects of a current flow impressed within the pipe wall.
This current seems to act as a wave of electrical energy as the electrons within
the pipe wall are moved, first in one direction, and then the other. There is no
known (recorded) example where this type of current flow has actually caused
any corrosion damage.
The following observations apply to a coated pipeline. The better the coating, the
more it will be effected. (Bare or poorly coated pipelines seem to be effected very
little).
Ø During a "Major Storm" period, which might last from two to five days
per storm, field instrumentation measurements for critical information
will probably have to be suspended for the duration of the storm.
The time scheduled for all important field measurements should be based on the
predictions of the Forecaster's information.
D-C railroads and transit systems use a d-c supply, usually from overhead, to
provide current to run d-c motors, which, in turn, convert their mechanical power
to the driving wheels. They use the rails they run on for the d-c return circuit to
the power station. They depend on the mechanical and electrical connectors
across each rail segment to provide a continuous return circuit. They depend on
the cross ties, setting on a raised bed of highly resistive material, like rock, to
insulate the rails from the earth, so that the current will stay within the rails,
instead of using the earth as part of the return circuit. The more modern of these
systems weld the rails together, and provide an expansion device periodically
along the rails. This greatly reduces the resistance that the old style of electrical
connection between rails had, and provides a much more dependable method of
current return, reducing the current flow through the earth to virtually nil. If there
is no current flow in the earth, there is no pick-up or discharge area for any
pipeline in the vicinity, hence, no loss of metal because of interference.
Some of the d-c railroads and transit systems, when operating, allow
some of their current return path to be through the earth. The moving
motorcar acts somewhat like a moving groundbed, raising the positive
gradient of the earth within its area of influence. This moving gradient in
the earth causes difficulty in reading and analyzing pipe-to-soil
potentials. Some questions are: "Is the pipe picking up current and
become more negative, or has the earth just become more positive, with
the pipe potential actually staying the same?"; "Is the pipe discharging
OQ Task – Cathodic Protection Remediation Advanced
41
current and become more positive, or has the earth just changed its
potential, with the pipe potential actually staying the same?"; and "How
can I move fast enough with my instrumentation to tell the difference?”.
This type of interference causes metering and measurement problems, but only
during the time the engine passes through the immediate area. It might be noted
that the same conditions can also follow d-c railroads and transit systems. The
effect is usually not noticeable for systems that have some current leakage to
earth; however, it can be the most prominent factor for those systems that are
not experiencing any current leakage.
A-C transmission also has a reasonable amount of loss due to its transformer
action inducing power (which has to come from itself) into the surrounding media.
D-C transmission does not have near the loss a-c has. In this way, it is
considered much more efficient. The d-c usually is obtained by stepping a-c up,
by transformers, to the high voltage required, then rectifying it to d-c by the use of
huge mercury-arc rectifier tubes. At the receiving end, it is transformed back into
a-c for its continued journey to its distribution.
OQ Task – Cathodic Protection Remediation Advanced
42
D-C is transmitted over a two-wire system. That is, it has a positive wire and a
negative wire (return) to complete the circuit. It also has an excellent electrical
ground at both the transmitting end and the receiving end. There is still some
leakage to earth even in bipolar transmission. If either the positive or the
negative wire develops a fault, its place is taken by the ground return through the
electrical ground grid at each end. This causes tremendous amounts of d-c
current to flow in the earth, and acts as d-c interference to everything in its path.
It hardly affects a line crossing its corridor, but can do a great amount of damage,
in a short time, to lines lying parallel to it.
Use multiple magnesium anode banks for electrolytic coupling between the lines in
the crossing area.
If, for some reason, a surface potential survey will not suffice in the pipeline-
crossing example above, then IR leads might have to be installed in order to
determine if interference does exist. If this is necessary, use spacing between the
leads that will allow the available voltmeter to read millivolts with accuracy for the
weight of the pipe of the offended line. (Remember, 10 milliamps will consume 0.2
of a pound of steel in one year.)
Install the closest test lead on each side of the crossing outside of the area of
influence of the pipe potential gradient. Use test lead wire that has no
imperfections in its' insulation (and will stay that way). Make absolutely certain the
cadweld connection is well coated.
When testing for interference that is outside of the groundbed gradient, and the
lines do not cross, it is very difficult to find a discharge point, and even then, one
cannot be sure that there is not more that the one that was found. When this event
occurs, IR test leads must be used, and must be installed outside of the groundbed
gradient. In order to do this, conduct an "on-off" P/S potential survey over the
offended line throughout the groundbed gradient area, with the spacing variable to
fit the situation, until there is no negative change in the offended lines' potential
when the rectifier is cycled (See Illustration No. 19).
Install IR drop test leads, on appropriate spacing, on each side of the offending
rectifier, just outside of the indicated groundbed gradient.
Elevators and welding shops are operated from a central point. It is unlikely that
an elevator would cause a pipeline any difficulty, even if it were as close as fifty
feet away from it. Welding shops have a habit of welding all of the metal in their
shop together, so as to provide a good ground for their welding machine. In this
way, they can use a chuck, or a vise, which provides as excellent ground for their
material. Unfortunately, sometimes this also provides problems for pipelines that
are very close to the welding shop, or who cross a natural gas pipeline that
provides gas for the shop and/or surrounding buildings.
Mine operations usually have a central power source, but the hopper cars that use
that source can operate at some distance from the central location. It is very
important for the power system not to leak current into the earth in order to be
absolutely safe to personnel working in the mine. When electrical power was first
used, this was not always the case, and pipelines near the surface of the earth felt
this stray current. From this early beginni ng, mine operations got a bad reputation;
however, they have now cleaned up their act, and no known interference problems
are now evident.
Resistive coupling by fault currents are too unpredictable for any preventative
action to be taken. It would be unthinkable to require the moving of pipelines from
power line corridors or crossings.
There is a possibility of using a Kirk cell, or a zinc or magnesium grounding cell, for
a connection to a bare road casing or to another good electrical ground. If a good
electrical ground is not available, one should be constructed. Do not use any
electrical company's tower footings or grounding system.
Inductive Coupling: There are three primary ways of reducing a-c voltage and
current on a pipeline. These are:
The use of a specially built groundbed, with diodes, will greatly reduce the a-c
voltage and current, without connecting the groundbed to the regular cathodic
protection system. The groundbed works best if neither the anodes, nor the
backfill, has any carbon content. The anodes can be high-silica cast iron, zinc, or
magnesium, and the backfill can be standard magnesium anode backfill.
It should be remembered that the diodes might fail, and leave the groundbed
connected to the pipeline.
This wouldn't hurt the a-c drainage value of the groundbed, but the groundbed
would be connected to the pipeline, and would affect the CP system.
An MOV of the correct size, shunting the diode, would afford protection for the
diode in the event of power surges, etc.
Capacitive Coupling
The line on the skids during construction must be grounded by any effective
means, such as a driven ground rod (in comparatively low resistivity, moist, soil).
The coated buried pipe can be grounded with one, or more, magnesium anodes
with a #8 AWG (Minimum size) TW insulation, lead wire.
Critical bonds are current drain bonds if removed, would cause interference
damage to Amoco Pipeline Company structures or would disconnect one of those
structures from the cathodic protection system. These bonds are installed
between structures that were electrically isolated before bonding, and which, if not
bonded, would remain electrically isolated. It is imperative that these electrical
connections be kept in good operating condition. Maintenance problems are due
to either physical damage caused by equipment, animals, or vandals; by
insufficient wattage rating of parts used; or by faulty assembly of parts. The
installation of the critical bond boxes, etc., should include protective fencing, an
over-rating of the wattage on the parts used, surge current protective devices (if
included), and proper cleaning and tightening of current carrying connections.
These bonds should be read on the same intervals as Cathodic Protection
Rectifiers.
Bonds that are not critical are those, which if disconnected, and left that way for
some length of time, would not cause the structure to suffer metal loss. These
bonds might include some a -c drainage bonds, or bond stations installed for testing
purposes. They are important and should be maintained in the same manner as
other testing and/or bonding facilities, and checked annually.
For typical bond installations, please refer to the “Repair and Maintain Test Lead”
study guide. Remember, before establishing a bond with a foreign facility, one
must notify that company’s corrosion representative prior to installation. If
practical, a resistance bond should be installed to control the amount of current
given to the foreign pipeline company.
3 Record the reading and polarity that is displayed on the meter, in millivolts.
Note: If the positive lead is attached to the half-cell, the recorded millivolt
reading should be positive. If the polarity is reversed the reading will be
negative.
4 Repeat the process by connecting the test leads to the casing test lead. It
is a good practice to also test the casing vent, in the event that the vent is
not attached to the pipeline.
Caution: Just because the Pipe-to-Soil potential reading and the Casing-to-Soil
potential are close to each other doesn't necessarily mean that the casing is
shorted. This test does not provide definitive results as to whether a casing is
shorted, but it may indicate if further investigation is required. This should be
used as a first step in determining the condition of the casing.
The Interrupted Rectifier Method involves interrupting the rectifier and reading
the potential shifts (ON and OFF) of both the carrier pipe and the casing. In order
to perform this method, all rectifiers and bonds affecting the area should be
simultaneously interrupted. This procedure may be useful if a casing is located in
close proximity to a cathodic protection groundbed, since voltage gradients in the
area of the groundbed will affect the voltage reading on the meter.
1 Set interruption cycle, e.g., 6 seconds ON and 3 seconds OFF. This may
be set at any interval that feels comfortable to the person performing the
test.
4 Place the reference electrode near the casing end, attach the positive lead
of the voltmeter to the reference electrode and the negative lead to the
pipeline or pipeline test lead. Record the pipe-to-soil measurement for the
ON and OFF cycles. Indicate the polarity of the readings.
After all the readings have been taken for the different values of applied current,
the resistance of the casing installation can be determined using the equation on
the following page:
After the calculations for the resistance have been made, the determination as to
the condition (shorted or not shorted) can be made. A calculated resistance
greater than 0.080 ohms may indicate an effectively insulated installation, and a
cased crossing with a calculated resistance less than 0.080 ohms may indicate
that a shorted condition may exist and corrective action may need to be taken.
Also keep in mind that the resistance calculated using formula 1 represents an
overall resistance.
Before a determination of the condition of the installation can be made from the
calculated resistance one more step must be taken. This step requires the
graphing of the information gathered during the testing. The graphic
representation will provide a visual means of identifying the condition of the
installation as well as provide documentation.
The graphing may be done manually or with any number of computer programs,
such as Lotus 123 or Microsoft Excel. Figures VII-19A through 19P illustrate
typical results for shorted and not shorted casings.
Listed below are components, which are part of the pipeline, and may be
subjected to pump pressure and could fail during the performance of a
maintenance and repair task:
• Trenching/excavation failures
• Encounter hazardous atmosphere
• Injury on the job
All of the above components can cause one or more of the following Abnormal
Operating Conditions while performing maintenance tasks
AOC: Leak
RESPONSE: Assess situation for hazards and safety, identify and isolate source of
leak if possible. Limit access to the area as much as possible. Take appropriate
immediate action to protect your self, the public, property and the environment.
Contact local Fire/Police for immediate support. Contact Team Leader and District
Manager.
AOC: Fire
RESPONSE: If fire is small in nature, use on-site fire fighting equipment to extinguish.
If fire is beyond local control, immediately call local authorities. Take appropriate
immediate action to protect your self, limit access to the area as much as possible and
call Team Leader and District Manager.