Project No. : 080/GTU.
PIM/SP/VII/2024             REV
                                                                                                                   DOC. NO. :
                              FIELD INSPECTION AND TEST PLAN FOR CIVIL                                             Date : October 22,2024
                                                                                                                         Prepared            Approved
                                                                                                                            RH                 DNL
      H      : Hold Point                                             A : Document Approval                                     P             : Perform / Prepare
      W : Witness based on RFI                                        R : Document Review                                       Company        : PT. PUPUK ISKANDAR MUDA
      SW : Spot/Random Witness                                        V : Document / Data Verification                          TOC           : PT. GEARINDO TIGA UTAMA
      F : Inspection During FAT                                       I : Inspection
                                                                                                                                      RESPONSIBILITY
                                                        METHOD OF     LEVEL OF ACCEPTANCE       VERIFYING
No.                 INSPECTION ACTIVITY/TEST ITEM                                                                                                                    REMARK
                                                        INSPECTION        / REFERENCE           DOCUMENT
                                                                                                                       CONTRACTOR                      COMPANY
1     MATERIAL
1.1   Material Submit :
                                                                       Comply with Project
      a. Concrete                                         Inspect                            Laboratory Report              I                           V&A
                                                                          Specification
                                                                       Comply with Project
      b. Job Mix Design and Trial Mix                     Inspect                            Laboratory Report              I                           V&A
                                                                          Specification
                                                                       Comply with Project   Laboratory Report /
      c. Rebar                                          Certificate                                                         I                           V&A
                                                                          Specification        Mill Certificate
                                                                       Comply with Project   Visual & Dimention
      f. Welding Material (Type,size,SMAW)                Review                                                            I                           V&A
                                                                          Specification             Report
1.2   Test
                                                                       Comply with Project
      c. Welder Performance Qualification Test (WPQT)      Test                                WPQT Report                  P                            W
                                                                          Specification
                                                                       Comply with Project
      d. Welder Certificate                               Review                             Welder Certificate             R                            V&R
                                                                          Specification
                                                                       Comply with Project
      e Tensile Test & Bend Test Test for Rebar 19mm      Review                               Test Certificate             R                            V&R
                                                                          Specification
                                                                           Comply with Project
      e. Slump Test                                              Inspect                             QC-S-08         I   V&A
                                                                              Specification
                                                                           Comply with Project
      f. Compressive Strength Test                               Inspect                             QC-S-09         I   V&A
                                                                              Specification
2     FABRICATION
                                                                           Comply with Project
2.1   Material Identification and Dimensional Check              Inspect                         QC-S-05 / QC-S-06   I   V&A
                                                                              Specification
                                                                           Comply with Project
2.2   Cutting / Bending Rebar Inspection                         Inspect                             QC-S-06         I   SW
                                                                              Specification
                                                                           Comply with Project
2.3   Support Tray Fabrication                                   Inspect                             QC-S-03         I   SW
                                                                              Specification
                                                                           Comply with Project
2.4   Dimensional Inspection                                     Inspect                         QC-S-05 / QC-S-06   I   SW
                                                                              Specification
3     SITE PREPARATION
3.2   Survey, Elevation, Leveling and Coordinat                  Inspect   Comply with Spec.         QC-S-01         I   V&A
                                                                           Comply with Spec.,
3.3   Stake Out                                                  Inspect                             QC-S-01         I   SW
                                                                             AFC drawing
4     INSTALLATION AND TEST
      Dimensional, Leveling, Verticality and etc of inspection             Comply with Spec.,
4.1                                                              Inspect                         QC-S-01 / QC-S-06   I   SW
      after rebar installation                                               AFC drawing
                                                                           Comply with Spec.,
4.2   Compacted soil                                             Inspect                             QC-S-02         I   SW
                                                                             AFC drawing
                                                                           Comply with Spec.,
4.3   Leveling Concrete                                          Inspect                             QC-S-04         I   SW
                                                                             AFC drawing
                                                                           Comply with Project
4.4   Alignment and Placement Anchort                            Inspect                            QA.QC-01         I   SW
                                                                              Specification
4.5   WELDING INSPECTION
                                                                      Comply with Spec.,
      a. Visual 100 %                                       Inspect                            QA.QC-03       I   SW
                                                                          drawing
5     CONCRETE WORK
      Form work dimensi, elevation, levelling, thickness,             Comply with Project
5.1                                                         Inspect                         QC-S-01/QC-S-07   I   SW
      flatness and smooth surface of levelling                           Specification
                                                                      Comply with Project
5.2   Rebar Installation                                    Inspect                            QC-S-06        I   SW
                                                                         Specification
                                                                      Comply with Project
5.3   Formwork Installation                                 Inspect                            QC-S-07        I   SW
                                                                         Specification
                                                                      Comply with Project
5.4   Pit Cable Excavation                                  Inspect                            QC-S-10        I   SW
                                                                         Specification
                                                                      Comply with Project
5.5   Pit Cable Back Fill                                   Inspect                            QC-S-11        I   SW
                                                                         Specification
                                                                      Comply with Project
5.6   Pit Cable Cover                                       Inspect                            QC-S-12        I   SW
                                                                         Specification
                                                                      Comply with Project
5.7   Pouring Concrete                                      Inspect                            QC-S-08        I   SW
                                                                         Specification
                                                    PEMBANGUNAN TANGKI AMMONIA
                                                                  ACEH UTARA - INDONESIA
     PT. PUPUK ISKANDAR MUDA
                                                                      SURVEY REPORT
Project Title          :                                                                                    Date        :
Work Title             :                                                                                    Report No. :
Main Contractor        :                                                                                    Page        : 1 0f 3
Project Owner          :
                       :
REFERENCES             :
         Item Name     :                                                                                    Location    :
         Drawing No.   :                                                                                     Revision :
                                                Coordinate Design                  Coordinate Actual                Different
 No.            DESCRIPTION                                                                                                         Remarks
                                               East            Nort              East             Nort        E (mm)       N (mm)
                                  Contractor                                                                Owner
                           Prepared & Inspected by,                                                  Witness & Approved by,
Date :                                Date :                            Date :                              Date :
                                                                                                          Date :
                                                                                              QC-S-01
                PEMBANGUNAN TANGKI AMMONIA
                              ACEH UTARA - INDONESIA                                  Report No. :
                                                                                      Job. No. :
Subject : LEVELING REPORT (TOP GALIAN PONDASI TRANSFORMER 5000 Kva & 150 KVa)
Location/Area           :
Owner                   :
Contractor              :
Ref. Drawing            :
Page.                   : 2 of 3
                                   HI   B-S    F-S     ELEVATION     ELEVATION         Dev.
No.       DESCRIPTION                                                                                   REMARK
                               (mm)     (mm)   (mm)    BM, CP/TP   Design    Actual    (mm)
                       Contractor                                                  OWNER
                Prepared & Inspected by,                                    Witness & Approved By,
Date:                         Date:                    Date:                          Date:
                                              PEMBANGUNAN TANGKI AMMONIA
                                                    ACEH UTARA - INDONESIA
     PT. PUPUK ISKANDAR MUDA
                                                       SURVEY REPORT
Project Title       :                                                         Date         :
Work Title          :                                                         Report No.   :
Main Contractor     :                                                         Page         :
Project Owner       :
Drawing No.         :
Sketsa              :
                               Contractor                                            Owner
                        Prepared & Inspected by,                             Witness & Approved by,
Date :                               Date :                  Date :                        Date :
                                                                                                                 QC - S - 002
                                                                                                  Report No.
                       PEMBANGUNAN TANGKI AMMONIA
                                                                                                  NH3T-PIM-GTU-E&I-XI-CP-01
                                                                                                  Date : November 1,2024
                             COMPACTION INSPECTION REPORT                                         Project No. : 080/GTU.PIM/SP/VII/2024
Description               : Compaction Inspection Report for Transformer 5000 kVA Foudation
Client                    : PT. PUPUK ISKANDAR MUDA
Contractor                : PT. GEARINDO TIGA UTAMA
Location                  : NH3T TANK
REFERENCES
               Drawing No.           : P2-6442-T2-DW-64FB2002.4-3001-R-IFA
               Revision              :-
               Sheet                 : 1 of 1
                                                                   RESULT                          ACCEPT
NO                  INSPECTION ITEMS                                                                                         REMARKS
                                                        Accepted            Rejected      Cont.             Owner
 1   Fill material quality
 2   Area location marking for layer thickness
 3   Soil spreading methods
 4   Thickness of loose soil
 5   Water spreading methods
 6   Optimum water content
 7   Compactor trip number
                                            EQUIPMENT
                               Total Unit        :                                     pc(s)
Sheep Foot Compactors          Running Unit      :                                     pc(s)      Water Source Check
                               Stand Unit        :                                     pc(s)                           Accepted   Rejected
                               Total Unit        :                                     pc(s)
                                                                                                  Water Quantity Due
Vibratory Compactors           Running Unit      :                                     pc(s)      to Wet Compaction
                                                                                                        Check
                               Stand Unit        :                                     pc(s)                           Accepted   Rejected
COMMENT
     Prepared / Inspected by,                        Witnessed / Reviewed by,                               Acknowledge by,
     PT. GEARINDO TIGA UTAMA                         PT. GEARINDO TIGA UTAMA                                PT. PUPUK ISKANDAR MUDA
     Name :                                          Name :                                                 Name :
     Date :                                          Date :                                                 Date :
                                                                                                                                                                                                                                                                                      QC-S-003
                                                                                                 PEMBANGUNAN TANGKI AMMONIA                                                                                                                                          Report No.
                                                                                                                                                                                                                                                                     NH3T/PIM/GTU/E&I/XI/STF/01
                                                                                                                                                                                                                                                                     Date : November 21, 2024
                                                                                                 VISUAL / DIMENTIONAL INSPECTION REPORT                                                                                                                              Project No
                                                                                                          (Support Tray Fabrication/Welding Work)                                                                                                                    080/GTU.PIM/SP/VII/2024
                Drawing No.      : P2-6442-T2-LD-64FB2002.4-1003-R-IFA                                                                                                                                                           Location         : NH3T
                Description      : Inspection for Support Tray Fabrication                                                                                                                                                       Sheet            : 1 of 1
               Inspection Date   : November 22, 2024
                                                                                                                                                                               Electrode Consumable
                                                                                                                                                                                                                                                                                  Result
                                      Type of                                                    Welder                                 Root                                           Hot                                           Capping
Weld No.           WPS No.                                Size           Date Weld   Alignment                                                                                                                                                                                                     Remarks
                                    connection                                                   Stamp
                                                                                                                  Diameter       Manufacture        Specification   Diameter        Manufacture       Specification   Diameter      Manufacture      Specification        Pass             Faill
      Prepared / Inspected by,                                                                                                 Reviewed by,                                                                                                                          Acknowledge by,
      PT. GEARINDO TIGA UTAMA                                                                                                  PT. GEARINDO TIGA UTAMA                                                                                                               PT PUPUK ISKANDAR MUDA
      Name :                                                                                                                   Name :                                                                                                                                Name :
      Date :                                                                                                                   Date :                                                                                                                                Date :
                                                                          QC-S-004
                                                               Date           : Nov. 1,2024
              PEMBANGUNAN TANGKI AMMONIA                       Report No.     :
                                                               NH3T/PIM/GTU/E&I/XI/LC/01
                                                               Project No     :
              LEVELING CONCRETE INSPECTION REPORT
                                                               080/GTU.PIM/SP/VII/2024
     Description     :
     Inspection Date :
     Location         :
     Reference Drawing :
                                                                   RESULT           SIGN
NO                            ITEM TO CHECK
                                                                 YES    N/A     Cont.    Owner
 1 Quality of Material
 2 Surface Preparation
 3 Proportioning & Mixing
 4 Elevation, extent, thickness & Surface
 5 Smoothness
 6 Cleaning
Remarks :
 Prepared / Inspected by,           Witnessed / Reviewed by,   Acknowledge by,
 PT. GEARINDO TIGA UTAMA            PT PUPUK ISKANDAR MUDA     PT PUPUK ISKANDAR MUDA
 Name :                             Name :                     Name :
 Date :                             Date :                     Date :
                                                                                QC-S-005
                                                                      Doc. No.
                PEMBANGUNAN TANGKI AMMONIA
                                                                      NH3T/PIM/GTU/E&I/X/FW/01
                                                                      Date :
                                                                      Project No.
Subject            : FORM WORK INSTALATION
                                                                      080/GTU.PIM/SP/VII/2024
Location/Area      : NH3T Area
Owner              : PT. Pupuk Iskandar Muda
Contractor         : PT. Gearindo Tiga Utama
Ref. Drawing       : P2-6442-T2-DW-64FB2002.4-3001-R-IFA
Name Of Type       : Transformer NER Foundation 150 kVA
                                                RESULT         SIGN
 No               ITEM TO CHECK                                                     REMAKS
                                              YES     N/A   Cont.   Owner
  1   Dimention
  2   Tickhness Form Work
  3   Leght,Widht ( Reference To Dwg)
  4   Elevation, extent, & Surface
  5   Smoothness
  6   Qualty
  7   Form Work Support
  8   Cleaning
NOTE :
 Prepared / Inspected by,            Reviewed by,                   Acknowledge by,
 PT. GEARINDO TIGA UTAMA             PT. GEARINDO TIGA UTAMA        PT PUPUK ISKANDAR MUDA
                                                                                           QC-S-006
                                                                             Doc. No.
                    PEMBANGUNAN TANGKI AMONIA
                                                                             NH3T/PIM/GTU/E&I/X/RI/001
                                                                             Date: October 25, 2024
Subject                       : REBAR INSTALLATION                           Project No.
Project Title                 : PEMBANGUNAN TANGKI AMMONIA                   080/GTU.PIM/SP/VII/2024
Description                   :   Rebar Installation for Transformer Foundation 150 kVA
Location/Area                 :   NH3 TANK / MSB
Owner                         :   PT. PUPUK ISKANDAR MUDA
Reference Drawing             :   Drawing for Transformer NER Foundation 150 kVA
                                                                           RESULT           ACCEPTED
No.                                 INSPECTION                                                           REMARKS
                                                                         YES NO N/A       DATE    SIGN
  1   Size/Length/Quality
  2   Bending Radius/Shape
  3   Spacing Between Re-bars
  4   Lap Splacing (Length/Location)
  5   Extra Length
  6   Hook (Extra Length/Shape)
  7   Hoop/Stirrup (Shape/Location/Pitch/Hook)
  8   Starter Bar (Shape/Length/Location)
  9   Concrete Cover
 10   Slab (Direction/&Lower)
 11   Reinforcing for Opening
 12   Column/Beam (Untorsionality)
 13   Quality of Cleaning
 14   Adequacy of Spacer Block, Steel Chairs, Steel Spacer, etc.
 15   Dewatering
      NOTE :
Prepared / Inspected by,                     Reviewed by,                        Acknowledge by,
PT. GEARINDO TIGA UTAMA                      PT. GEARINDO TIGA UTAMA             PT. PUPUK ISKANDAR MUDA
Name :                                       Name :                              Name :
Date :                                       Date :                              Date :
                                                                                                             QC-S-008
                                                                                              Report No :
                        PEMBANGUNAN TANGKI AMMONIA                                            NH3T/PIM/GTU/E&I/XII/PC/01
                                                                                              Date        : December 3, 2024
                                                                                              Project No. :
                          POURING CONCRETE RECORD                                             080/GTU.PIM/SP/VII/2024
Owner                : PT. PUPUK ISKANDAR MUDA
Contractor           : PT. GEARINDO TIGA UTAMA
Location         : NH3T / MSB2
Concrete Class   :
Specified Strength of Concrete : …………………………………Mpa ( …………psi )
                                                              Time               Cylinder       Slump      Poured      Total
     Date             Description / Area / Block                                                                  3
                                                      Batch Plan     On Site   Speciment No      cm        Vol. (m )   (m3)
    Remarks :
Prepared / Inspected by,                           Reviewed by,                                   Acknowledged,
PT GEARINDO TIGA UTAMA                             PT GEARINDO TIGA UTAMA                         PT PUPUK ISKANDAR MUDA
Name :                                             Name :                                         Name :
Date :                                             Date :                                         Date :
                                                                                                    QC-S-009
                                                                                         Report No.
                                                                                                 :
                     PEMBANGUNAN TANGKI AMMONIA                                          NH3T/PIM/GTU/E&I/XI/SR/01
                                                                                         Date : December 3, 2024
                                                                                         Project No
                                                                                                 :
                          COMPRESSIVE STRENGTH TEST
                                                                                         080/GTU.PIM/SP/VII/2024
 Report No :
 1. General
    Date / Time :                      :
    Design Compressive Strength        : K-420                                                        (28 days)
    Mix Design No                      : 08/JMD-JMF/II/LB&S/TS/PNL/2024
    Placing Location / Purpose         :
    Test Method                        : ASTM
 2. Test Result of Concrete
    1. Fresh Concrete Test
       Slump                                  :                                                       ( cm )
       Air Content                            :                                                       (%)
                                                                                                        0
       Fresh Concrete Temperature             :                                                       ( C)
                                                                                                        0
       Ambient Temperature                    :                                                       ( C)
       Test Cylinder Number                   :
    2. Compressive Strength Test
                                                               ........ Day Strength
           Specimen No.                       Weight    Breaking       Strength        Strength
                                Test Date                                                              Result
                                               (Kg)     Load (kN)       (MPa)          (kg/cm²)
         * Test Machine No. :
 3. Test Result
                                 Acceptable
                                 Not Acceptable
Prepared / Inspected by,                      Reviewed by,                                   Acknowledge by,
PT GEARINDO TIGA UTAMA                        PT GEARINDO TIGA UTAMA                         PT PUPUK ISKANDAR MUDA
Name :                                        Name :                                         Name :
Date :                                        Date :                                         Date :
                                                                               QC-S-010
                                                                   Report No.      :
                 PEMBANGUNAN TANGKI AMMONIA
                                                                   NH3T/PIM/GTU/E&I/XI/EPC/01
                                                                   Date : November 28,2024
                                                                   Project No      :
            EXCAVATION PIT CABLE INSPECTION REPORT
                                                                   080/GTU.PIM/SP/VII/2024
     Description     : Transformer 150kVA PIT Cable Installation
     Inspection Date : November 30,2024
     Location / Area : NH3 Tank / MSB2
     Reference Drawing : P2-6442-T2-DW-64FB2002.4-1009-R-IFA
                                                                      RESULT              SIGN
NO                           ITEM TO CHECK
                                                                    YES    N/A      Cont.   Owner
 1 Dimentional and Visual Check
 2 Depth of Excavation Check
 3 Condition of compaction bottom surface
 4 Quality of cleaning
Remarks :
 Prepared / Inspected by,          Reviewed by,                       Acknowledge by,
 PT. GEARINDO TIGA UTAMA           PT. GEARINDO TIGA UTAMA            PT PUPUK ISKANDAR MUDA
 Name :                            Name :                             Name :
 Date :                            Date :
                                                                                   QC-S-011
                                                                      Report No.      :
                 PEMBANGUNAN TANGKI AMMONIA
                                                                      NH3T/PIM/GTU/E&I/XI/PCB/01
                                                                      Date : December 3,2024
                                                                      Project No      :
 PIT CABLE BRICKLAYING / BACKFILLING INSPECTION REPORT
                                                                      080/GTU.PIM/SP/VII/2024
     Description     : Transformer 150kVA PIT Cable Bricklaying/Backfilling
     Inspection Date : November 30,2024
     Location / Area : NH3 Tank / MSB2
     Reference Drawing : P2-6442-T2-DW-64FB2002.4-1009-R-IFA
                                                                          RESULT              SIGN
NO                            ITEM TO CHECK
                                                                        YES    N/A      Cont.   Owner
 1 Quality of Material
 2 Stability against brick placing
 3 Alignment Surface and Wall brick
 4 Surface and Alignment
 5 Backfilling soil
 6 Quality of cleaning
Remarks :
 Prepared / Inspected by,            Reviewed by,                         Acknowledge by,
 PT. GEARINDO TIGA UTAMA             PT. GEARINDO TIGA UTAMA              PT PUPUK ISKANDAR MUDA
 Name :                              Name :                               Name :
 Date :                              Date :                               Date :
                                                                                   QC-S-012
                                                                     Report No.      :
                 PEMBANGUNAN TANGKI AMMONIA
                                                                     NH3T/PIM/GTU/E&I/XI/PCI/01
                                                                     Date : November 29,2024
                                                                     Project No      :
             PIT CABLE COVER INSPECTION REPORT
                                                                     080/GTU.PIM/SP/VII/2024
     Description     : Transformer 150kVA PIT Cable Cover Installation
     Inspection Date : November 30,2024
     Location / Area : NH3 Tank / MSB2
     Reference Drawing : P2-6442-T2-DW-64FB2002.4-1009-R-IFA
                                                                           RESULT             SIGN
NO                           ITEM TO CHECK
                                                                         YES    N/A     Cont.   Owner
 1 Quality of Material
 2 Dimentional and Visual Check
 3 Surface Check
 4 Quality of cleaning
 5 Stability against cover placing
Remarks :
 Prepared / Inspected by,            Reviewed by,                         Acknowledge by,
 PT. GEARINDO TIGA UTAMA             PT. GEARINDO TIGA UTAMA              PT PUPUK ISKANDAR MUDA
 Name :                              Name :                               Name :
 Date :                              Date :