PA00TQ32
PA00TQ32
DISCLAIMER
The authors’ views expressed in this publication do not necessarily reflect the views
of the United States Agency for International Development or the United States
Government.
TABLE OF CONTENTS
1   SUMMARY..................................................................................................................... 1-1
2 INTRODUCTION............................................................................................................ 2-1
4 ALTERNATIVES............................................................................................................ 4-8
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                            i
             4.3.3        Cropping ............................................................................................ 4-24
             4.3.4        Irrigation Water Requirements and Water Rights .............................. 4-24
    4.4      SRI Alternative ................................................................................................. 4-24
             4.4.1        Operation, Maintenance and Management ....................................... 4-25
             4.4.2        Cropping ............................................................................................ 4-26
             4.4.3        Irrigation Water Requirements and Water Rights .............................. 4-27
    4.5      Improved Intensified Rain-Fed Agriculture Alternative ..................................... 4-28
    4.6      No Action Alternative ........................................................................................ 4-28
    4.7      Alternatives Eliminated from Analysis .............................................................. 4-28
             4.7.1        Full Sprinkler Irrigation with Central Pumping ................................... 4-29
    4.8      Mitigation Measures ......................................................................................... 4-29
    4.9      Comparison of Environmental Impacts of Alternatives ..................................... 4-31
    4.10     Preferred Alternative ........................................................................................ 4-34
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                            ii
              6.2.1        Impacts During Mobilization and Construction .................................... 6-1
              6.2.2        Impacts During Operation .................................................................... 6-4
    6.3       Impacts of Improved Intensified Rain-Fed Agriculture Alternative ................... 6-17
              6.3.1        Impacts During Mobilization and Construction .................................. 6-17
              6.3.2        Impacts During Operation .................................................................. 6-17
    6.4       Impacts of No Action ........................................................................................ 6-18
    6.5       Significant Impacts ........................................................................................... 6-18
    6.6       Irreversible or Irretrievable Commitments of Resources .................................. 6-19
    6.7       Possible Conflicts with Land Use Plans, Policies and Controls for the Area .... 6-19
    6.8       Cumulative Impacts .......................................................................................... 6-19
9 REFERENCES............................................................................................................... 9-1
ANNEXES
    ANNEX A:              NEMC’s Scoping Report Approval
    ANNEX B:              Fauna Observations In and Near the Project Area
    ANNEX C:              Relevant Sections of the Scoping Statemwent
    ANNEX D:              Mgongola Irrigation Scheme Environmental Flow Assessment in
                          the Wami River
TABLES
    Table 1.1:            Comparison of Alternatives ................................................................... 1-5
    Table 1.2:            Mitigation Measures for Operation of Preferred Alternative .................. 1-6
    Table 3.1:            Pesticides Generally Sold By Agro-Dealers In Morogoro ..................... 3-7
    Table 4.1:            Canal Network..................................................................................... 4-13
    Table 4.2:            Flow Measurement Structures ............................................................ 4-15
    Table 4.3:            Drainage Channels ............................................................................. 4-16
    Table 4.4:            Proposed Structures ........................................................................... 4-17
    Table 4.5:            Internal Roads ..................................................................................... 4-18
    Table 4.6:            Characteristics of AGG Extension ....................................................... 4-26
    Table 4.7:            Mitigation Measures for Mobilization and Construction Common to
                          the Proposed Action and All Irrigation Alternatives ............................. 4-30
    Table 4.8:            Mitigation Measures for Operation ...................................................... 4-31
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                          iii
   Table 4.9:    Environmental Impacts Associated with Mobilization and
                 Construction ........................................................................................ 4-32
   Table 4.10:   Quantitative Comparison of the Impacts of Alternatives During
                 Operation ............................................................................................ 4-32
   Table 4.11:   Qualitative Comparison of the Impacts of Alternatives ....................... 4-33
   Table 5.1:    Soils in Mgongola Irrigation Scheme Area ............................................ 5-3
   Table 5.2:    Minimum Monthly Discharges of Mkindo River (m3/s)........................... 5-6
   Table 5.3:    Existing Permitted Water Users Upstream and Downstream of the
                 Confluence of the Wami and Diwale rivers ........................................... 5-8
   Table 5.4:    Dry Year Recommended Average Discharges for the Wami River
                 at Mtibwa and Mandera EFA Sites ...................................................... 5-10
   Table 5.5:    Water Quality Data from EFA Sites ..................................................... 5-11
   Table 5.6:    Fauna Observed In and Near the Project Area ................................... 5-14
   Table 6.1:    Potentially Significant Impacts Identified in the Scoping Statement ...... 6-2
   Table 6.2:    Low-Flow Year Residual Flows and Recommended Average
                 Discharge (RAD) at the Mtibwa EFA Site (m3/s) ................................. 6-13
   Table 7.1:    Mobilization and Construction Mitigation Measures for the
                 Proposed Action and All Irrigation Alternatives ..................................... 7-2
   Table 7.2:    Operation Mitigation Measures for the Proposed Action and All
                 Action Alternatives ................................................................................ 7-7
   Table B.1:    Bird Observations In and Near the Project Area ...................................B-1
   Table B.2:    Mammal Observations In and Near the Project Area ............................B-2
   Table B.3:    Reptile Observations In and Near the Project Area ..............................B-3
   Table B.4:    Amphibian Observations In and Near the Project Area ........................B-3
   Table C.1:    Consolidated List of Potential Environmental Issues ........................... C-4
   Table D.1:    Driest Year Recommended Average Discharge (RAD) at Wami
                 River at the Mtibwa EFA Site ............................................................... D-1
   Table D.2:    Catchment and Flow Characteristics at Diwale and Mkindo
                 Gauging Stations.................................................................................. D-2
   Table D.3     Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa
                 EFA Site, End of 2016 Scenario .......................................................... D-6
   Table D.4:    Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa
                 EFA Site, 5 to 10 Years in Future Scenario ......................................... D-7
   Table D.5:    Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa
                 EFA Site with Sprinkler Irrigation, Current Abstractions Scenario ....... D-8
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                iv
FIGURES
   Figure 3.1:   General Location of Mgongola Irrigation Scheme ................................. 3-3
   Figure 3.2:   Specific Location of the Mgongola Irrigation Scheme ........................... 3-5
   Figure 4.2:   Location of Project Manager’s Office and Other Support Facilities ..... 4-11
   Figure 4.3:   Possible Borrow Pit Locations ............................................................. 4-12
   Figure 4.4:   General Layout of the Main Canal ...................................................... 4-14
   Figure 4.5:   Typical Tertiary Canal and Drain Cross-section .................................. 4-16
   Figure 5.1:   Wami River Basin.................................................................................. 5-1
   Figure 5.2:   Annual Rainfall in Morogoro Town, 1922-1988 ..................................... 5-4
   Figure 5.3:   Annual Rainfall in Morogoro Region, 1980-2006 .................................. 5-4
   Figure 5.4:   Monthly Mean Flow Rate of Mkindo River ............................................ 5-6
   Figure 5.5:   Mkindo River Daily Flows (2009/2010) ................................................. 5-6
   Figure 5.6:   Wami River Basin with EFA Sites ....................................................... 5-10
   Figure 5.7:   Google View of Vegetation in the Project Area ................................... 5-13
   Figure 5.8:   Land Use in the Project Area .............................................................. 5-17
   Figure 6.1:   Schematic Location and Relation of Factors for EFA Analysis on
                 the Wami River at Mtibwa EFA Site .................................................... 6-11
   Figure D.1:   Schematic of the Diwale/Wami Watershed from the Dakawa Gauge
                 to the Mtibwa EFA Site......................................................................... D-3
   Figure D.2:   Recorded Monthly River Flows at Dakawa 1953-1983 ........................ D-5
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                            v
Acronyms and Abbreviations
22 CFR 216      Title 22 of the U.S. Code of Federal Regulations, Part 216
AGG             Agriculture Green Growth, an initiative of SAGCOT
AWD             Alternating Wet/Dry, an irrigation regime
CFR             Code of Federal Regulations
EA              Environmental Assessment
EFA             Environmental Flow Assessment
EIA             Environmental Impact Assessment
FAO             Food and Agriculture Organization of the United Nations
FTF             Feed the Future
GoT             Government of Tanzania
IEE             Initial Environmental Examination
IRRIP           Irrigation and Rural Roads Infrastructure Project
IUCN            International Union for the Conservation of Nature
iWASH           Integrated Water, Sanitation and Hygiene Program, a USAID-funded
                project
JICA            Japan International Cooperation Agency
LGA             Local Government Authority
MAFC            Ministry of Agriculture, Food Security and Cooperatives
MZITSU          Morogoro Zonal Irrigation and Technical Services Unit
NAFAKA          Tanzania Staples Value Chain Activity, a USAID-funded project that is
                part of the FTF program
NEMC            National Environment Management Council
O&M             Operations and Maintenance
PERSUAP         Pesticide Evaluation Report and Safe Use Action Plan
PPE             Personal Protective Equipment
RAD             Recommended Average Discharge
SAGCOT          Southern Agricultural Growth Corridor of Tanzania
SEHASP          Site Environment, Health and Safety Plan
STDs            Sexually Transmitted Diseases
STIs            Sexually Transmitted Infections
TANROADS        Tanzania National Roads Agency
uPVC            Unplasticized Polyvinylchloride (pipe)
USAID           United States Agency for International Development
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              vi
WRBWO                 Wami-Ruvu Basin Water Office
WSDP                  Water Sector Development Program
WUA                   Water Users Association
Units of Measurement
ha      hectare
kg      kilogram
kg/ha kilogram/hectare
km      kilometer
kw      kilowatt
l       liter
l/s     liters/second = 0.001 m3/s
l/s/h   liter/second/hectare
m       meter
m2      square meter
m3      cubic meter
m3/s    cubic meter/second = 1,000 l/s
mm      millimeter
mt      metric tonne
mt/ha metric tonnes/hectare
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME               vii
1        SUMMARY
This Environmental Assessment (EA) has been prepared by the Engineering
Services for the Tanzania Irrigation and Rural Roads Infrastructure Project (IRRIP1)
for the construction of an irrigation scheme at Mgongola in Hembeti Ward, Mvomero
District, Morogoro Region, Tanzania. Construction of the Mgongola irrigation
scheme is an activity being undertaken as part of the Feed the Future (FTF) program
of the Tanzanian Mission of the United States Agency for International Development
(USAID/Tanzania).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            1-1
In line with the goals of FTF – which are aligned with GoT strategies – and the
objective of IRRIP1, the specific objectives of the construction of the Mgongola
irrigation scheme are to:
            Enable water to be supplied on a consistent basis to the existing cultivated
             area;
            Enable water to be drained from the area as required for optimal crop
             production;
            Provide the structures required to control water flow and to measure water
             used, so as to give better conditions for water management, crop growth
             and higher yields;
            Reconfigure field layouts to improve on-farm water management;
            Provide reliable access to the fields during rainy season to allow farmers
             to deliver inputs and remove harvests, so as to improve crop production
             and reduce marketing costs;
            Mitigate the adverse environmental and social impacts caused by the
             current farming practices; and
            Establish the physical environment for the Mgongola irrigation scheme to
             be constructed and operated in an environmentally sustainable manner.
1.1.4       Need to Which the Project Is Responding
Cultivated rice has a semi-aquatic ancestry and is therefore extremely sensitive to
water shortages, so that when the soil water content drops below saturation, lowland
rice varieties develop symptoms of water stress. As a result, lowland rice (paddy
rice) is grown in level fields which are flooded with water throughout most of the
growing season. The reason for flooding rice fields is that paddy rice varieties
maintain better growth and produce higher yields when grown in flooded soils, than
when grown in dry soils. The water layer also helps to suppress weeds.
A typical water management pattern for paddy rice is as follows (Brouwer et al. 1989,
IRRI 2013)
            The root zone is saturated the month before sowing or transplanting.
            A water layer is established after transplanting. Sometimes a water layer
             of 100 mm is established after transplant and maintained throughout the
             growing season. In other cases the water layer is reduced to 20 to 50 mm
             during the latter part of the vegetative stage and brought back to 100 mm
             during the mid-season stage. Generally, water layers greater than 100mm
             are detrimental to plant growth.
            Fields are typically drained 10-20 days before harvest, to facilitate
             harvesting.
The farmers in Mgongola grow rain-fed lowland rice in bunded fields that are flooded
by rainwater and seasonal wetlands from nearby rivers for at least part of the
cropping season. Rain-fed/wetland lowland rice production is dependent upon the
natural availability of water, making it extremely sensitive to uncertainty in timing,
duration, and intensity of rainfall. The rice fields in Mgongola also suffer from
uncontrolled flooding from the rivers that surround them, causing water levels to
exceed 100 mm. Because of these environmental impacts, rice production from the
rain-fed/wetland fields in Mgongola is low, contributing to poverty in the area.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            1-2
Shifting to irrigated lowland rice production via an engineered irrigation and drainage
scheme will stabilize the farmers’ access to water, eliminate flooding and provide
better water management capabilities. This could double rice production with an
associated increase in income (Otenga & Sant'Annab 1999).
1.2           Alternatives
This EA assesses the Proposed Action, four action alternatives and the No Action
alternative. The action alternatives include three irrigation alternatives and one non-
irrigation alternative. The Proposed Action and the three irrigation alternatives will
take 20 months to mobilize, construct and hand over to a Water User Association
(WUA) for operation. Turn over to the WUA will include training, operation and
maintenance manuals, and procedures for water management and distribution. A
quantitative comparison of the alternatives is provided at the end of this section in
Table 1.1. As the table shows, all of the alternatives, including the No Action
Alternative, have negative values for the “% of RAD” impact indicator. A negative
value for this indicator indicates that the Recommended Average Discharge (RAD) at
the Mtibwa Environmental Flow Assessment (EFA) site cannot be met, i.e., the flow
will be less than the flow determined to be necessary to provide for ecological and
small user needs. This is true even for the No Action alternative, because the flow in
the Wami River has been over-allocated. So there is not sufficient flow available for
any new irrigation scheme at Mgongola.
1.2.1         Proposed Action
The Proposed Action is designed to construct a gravity-fed irrigation scheme for
growing paddy rice on the 620 ha (gross1) area in the project area using flood
irrigation. It is an extension of the pilot project (Mkindo I and Mkindo II), which has
successfully demonstrated that smallholder irrigation-based paddy production in
Mgongola is a viable development activity. It will involve:
              Rehabilitation of the existing Mkindo I headworks on the Mkindo River;
              Remodeling of 725 m of the existing Mkindo I main canal;
              Construction of 3.4 km of reinforced concrete lined main canals;
              Construction of 9.6 km of unlined secondary canals;
              Construction of 11.1 km of open channel drains;
              Construction of associated in-field tertiary canals and drains;
              Field levelling;
              Construction of 14.5 km of earthen flood embankment;
              Construction of 16.0 km of gravel-surfaced internal access roads and
               feeder roads; and
              Construction and equipping of an office building to be used for
               construction supervision and then handed over to the Mgongola Water
               Users Association for use in scheme management.
Paddy rice will continue to be the main crop grown; however, other crops may be
cultivated as part of a system of integrated soil, crop and water management;
1   The 620 ha area is the gross area inside the project boundaries and includes the canals and interior
     roads. The actual irrigated area will be 589 hectares.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                             1-3
however, the heavy soils in the project area are far better suited to paddy cultivation
than any other crop.
1.2.2       Piped Main Canal Alternative
The Piped Main Canal alternative differs from the Proposed Action only in that it
constructs a piped main canal, thus reducing evaporation from and unauthorized
tapping of the main canal and increasing conveyance efficiency. All of the other
components of the scheme will be identical to those of the Proposed Action.
1.2.3       Sprinkler Irrigation Alternative
The Sprinkler Irrigation alternative provides the same infrastructure as the Proposed
Action (canals, drainage, flood protection, road improvements, etc.), but adds 17
pumping points at tertiary canals to allow portable diesel pumps to pressurize small
hand-moveable sprinkler irrigation units covering individual basins. This alternative is
designed to secure greater irrigation efficiency for the scheme. A system-wide
pressurized sprinkling alternative was also evaluated, but this modular approach as
an add-on to a flood irrigation system was more cost effective and allows flexibility for
implementation.
This alternative is designed to be operated with portable diesel engines and suction
pumps feeding a portable sprinkling system which would be capable of irrigating a 36
ha area. The pumps and sprinkler systems are not supplied by the project, but rather
farmers who want to use sprinkler irrigation will need to buy this equipment.
Sprinkler irrigation is not suitable for the particular paddy rice varieties preferred by
the local farmers, so this alternative assumes that those farmers who opt to use
sprinklers will switch to dry-foot rice. For this alternative to be successful, it requires
adoption by the farmers of a new crop, a new crop management system and a new
irrigation technology.
1.2.4       SRI Alternative
The System of Rice Intensification (SRI) alternative has the same irrigation
infrastructure as the Proposed Action, however, cultivation practices and water
management will follow SRI prescriptions consisting of:
            Growing seedlings in nurseries.
            Transplanting 8- to 12-day-old seedlings.
            Planting only one seedling per hill in hills spaced widely apart in a grid.
            Controlling weeds with a rotating hand hoe, which also aerates the soil.
            Applying compost to increase the soil’s organic matter content.
            Using Alternating Wet/Dry (AWD) irrigation application.
This alternative requires development and implementation of a concerted, multi-year
extension program operated in conjunction with local government extension agents.
This is required because the SRI prescription significantly varies from the cultivation
system the farmers are presently using as well as from the irrigation practices used in
the neighboring Mkindo irrigation schemes, which the farmers are familiar with.
1.2.5       Improved Intensified Rain-Fed Agriculture Alternative
The Improved Intensified Rain-Fed Agriculture alternative would not build an
irrigation infrastructure in the Mgongola Project area. Instead of providing irrigation,
this alternative would provide a yet to be designed extension program to promote
improved agricultural practices to the farmers in the area. The program would
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 1-4
  incorporate components that have been promoted by NAFAKA, another USAID-FTF
  project.
  1.2.6        No Action Alternative
  The No Action alternative means that USAID would not construct an irrigation
  scheme or initiate activities to improve rain-fed agriculture in Mgongola. In this case,
  the farmers would continue to use their current rain-fed cultivation practices in the
  project area to grow rice.
                                                               ALTERNATIVES
                                                  Piped
                                   Proposed       Main       Sprinkler                   Improved        No
            Impact                  Action        Canal     Irrigationa       SRIa       Rain-Feda      Action
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                     1-6
al. 2012). This conflict is likely to increase. Local Government Authorities and the
Morogoro Zonal Irrigation and Technical Services Unit will need to work with the
farmers in the Mgongola project area and the pastoralists from Kambala to develop
acceptable alternatives for securing access to water and feed for the cattle during the
dry season.
The assessment of fertilizer and pesticide use on the local rivers and their
ecosystems at and downstream from the Mgongola project area was based on
professional judgment, as there is no water quality data for the river in the vicinity of
the of the project area that would allow analysis. It would be prudent to collect water
quality data and do an analysis of these impacts during at least one cropping season.
If a problem is identified, then a subsequent routine monitoring program should be
established and on-farm use controls implemented.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            1-7
2        INTRODUCTION
This Environmental Assessment (EA) has been prepared by the Engineering
Services for the Tanzania Irrigation and Rural Roads Infrastructure Project (IRRIP1)
for the construction of the irrigation scheme at Mgongola in Hembeti Ward, Mvomero
District, Morogoro Region, Tanzania. Construction of the Mgongola irrigation
scheme is an activity being undertaken as part of the Feed the Future (FTF) program
of the Tanzanian Mission of the United States Agency for International Development
(USAID/Tanzania).
FTF is the United States Government’s global hunger and food security initiative.
The program supports country-driven approaches to address the root causes of
hunger and poverty. It is aimed at forging long-term solutions to chronic food
insecurity and inadequate nutrition. Through this initiative, the United States is
helping countries including Tanzania to transform their own agricultural sectors to
grow enough food to sustainably feed their people.
Tanzania has an ambitious plan to prioritize agriculture for economic growth. The
Government of Tanzania (GoT) has endorsed the development and promotion of the
Southern Agriculture Growth Corridor of Tanzania (SAGCOT) as an inclusive, multi-
stakeholder partnership to rapidly develop the region’s agricultural potential. The
SAGCOT initiative is further linked to the Agricultural Sector Development Program
through Tanzania’s Comprehensive African Agriculture Development Program
investment plan. FTF is fully aligned with GoT’s initiatives and focuses on making
targeted investments across a broad spectrum of agriculture and nutrition
interventions to help ensure long-term sustainability of poverty reduction and nutrition
goals.
USAID/Tanzania identified irrigated rice as the priority value chain for investment in
its FTF program (USAID 2010, pg. 8). Rice was selected as the primary value chain
based on a regional analysis indicating that Tanzania has a comparative advantage
in rice production, although there are opportunities to enhance competitiveness. It is
the second most important food in terms of consumption in the Tanzanian diet, and
has been increasing as a proportion of the Tanzanian diet, and also has potential to
provide for regional market demand. Since nearly one in five farmers are involved in
rice production, advances in this value chain – by improving inputs and techniques,
and irrigation and rural road infrastructure – can support broad-based growth.
FTF interventions cover a broad range of activities centered around (1) developing
the rice sector to spur growth; (2) increasing food security through improved
productivity, processing, transport, and storage in the maize and rice sectors; and (3)
improving the nutritional status of Tanzanians, particularly women and children,
through the development of the horticulture sector.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            2-1
such, an EA is required before project implementation. A Scoping Statement for this
EA was developed and submitted to USAID on 28 March 2014.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                       2-2
3          PURPOSE OF THE PROPOSED ACTION
As required by USAID’s Environmental Procedures in 22 CFR 216.6(c)(2), this
section specifies the underlying purpose and need to which USAID is responding in
proposing the project and its alternatives.
USAID/Tanzania’s FTF documentation states that despite a decade of economic
growth at 6-7%, about one-third of Tanzania’s population continues to live in poverty.
Malnutrition is high, with stunting rates among children under-five at 42% and
maternal anemia at 58%. Agriculture contributes to nearly one-third of gross
domestic product, employs approximately 75% of the population, and has enormous
potential to reduce poverty and improve lives.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            3-1
            Reconfigure field layouts to improve on-farm water management;
            Provide reliable access to the fields during rainy season to allow farmers
             to deliver inputs and remove harvests, so as to improve crop production
             and reduce marketing costs;
            Mitigate the adverse environmental and social impacts caused by the
             current farming practices; and
            Establish the physical environment for the Mgongola irrigation scheme to
             be constructed and operated in an environmentally sustainable manner.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            3-2
km) (Figure 3.1). The specific project site is situated between the Mkindo-Dizingwi
River to the north and the Mgongola River to the south (Figure 3.2). Two villages,
Mkindo Village and Dihombo Village are near the eastern boundary of the project
site. Elevation ranges from 345 m to 365 m above sea level. The site is located
between latitudes 37°32’E and 37°36’E and longitudes 6°16’S and 6°18’S.
3.4.2    Background
Irrigated paddy rice was introduced to the farmers in the Mgongola area in the mid-
1980s via a development project funded by the Netherlands Government. The
project was designed as a pilot program to determine the viability of smallholder
irrigation-based paddy production in the area. The project constructed a diversion
intake structure on the Mkindo River and a 2.5-km main canal with a siphon crossing
the Dizingwa River. It also supported on-farm works, which included land levelling
and formation of paddy ridges on 40 ha (17 ha serving 42 families north of the
Dizingwa River and 23 ha serving 50 families south of it). The irrigated area north of
the river is called Mkindo I and the irrigated area south of the river is called Mkindo II
(Figure 3.2).
Since its construction, the area under irrigated cultivation has been expanded to 110
ha. At some point in the past 25 years the siphon crossing the Dizingwa River has
failed, and Mkindo II now takes water directly from the Dizingwa River. In 2012, the
headworks and main canal underwent rehabilitation under the supervision of the
Morogoro Zonal Irrigation and Technical Services Unit (MZITSU). MZITSU fully
rehabilitated the gates at the headwork and expanded and concrete-lined the main
canal from the intake to the end of Mkindo I (1.2 km).
The Mkindo irrigators are organized into the Mkindo Farmers Agricultural and
Marketing Cooperative Society. This cooperative society was established in 1984 to
manage the Mkindo irrigation schemes and to look for markets for its products. It
was registered as a cooperative with the MAFC in 1997. In 1997 it had 97 members
and the area under irrigation was 60 ha, instead of the 110 ha under irrigation today.
The cooperative is managed by a committee elected by fellow members every three
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              3-3
years. The committee makes water and cropping scheduling decisions for the
scheme.
The Mkindo irrigation schemes were designed as pilot projects to demonstrate that
small-holder irrigation schemes were a viable development opportunity in the
Mgongola area. The schemes have been successful, allowing the farmers in the
schemes to produce more rice than the farmers around them that rely upon rain-fed
production.
In the late 1990s, the then Ministry of Agriculture and Cooperatives (now the Ministry
of Agriculture, Food Security and Cooperatives [MAFC]) with support from the Japan
International Cooperation Agency (JICA) prepared a master plan for smallholder
irrigation projects in the central Wami River Basin. Mgongola was one of the
potential projects for which a feasibility study was prepared (JICA 1998). That study
proposed a new irrigation scheme east of Mkindo I and II in the area between the
Mkindo-Dizingwi River and the Mgongola River. It is this project which the GoT and
USAID/Tanzania identified for implementation under FTF, and which is the subject of
this Environmental Assessment.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         3-4
Figure 3.2:   Specific Location of the Mgongola Irrigation Scheme
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                          3-5
3.4.3       Existing Agricultural Practices in the Project Area
The project area is currently used for rain-fed paddy rice cultivation by as many as
725 farmers. The farmers in this area generally use Supa India seed, a common
local aromatic variety in Tanzania, although other local seed (Supa Mbeya, Supa
Shinyanga, and Domo la fisi) are also used to a lesser extent. A limited number of
farmers use the improved seed, Saro 5 (TXD 306). Sowing of rice seed is done via
broadcast seeding from December to January, depending on the availability of rain,
as germination is dependent upon rainfall. Harvesting is done in May and June.
Land preparation, cultivation and harvesting is generally done by hand, although
some land preparation may be done by hired tractors. The farmers generally do not
use fertilizers or pesticides, although herbicides may be used for weed control and
manual bird scaring is done during the ripening stage of the paddy. (JICA 1998, de
Bruin 2012)
Ponding, a desired condition in the fields after germination, is dependent upon
seasonal flooding, which varies from year to year. Rain-fed rice farmers create
bunds in their fields before the rains to trap flood water as the flooding recedes (de
Bruin et al. 2012). Flooding can also be a problem, as farmers have no way of
draining water when it is not desirable. Keraita et al. (2012) reports seeing flood
water 0.5-m deep in rain-fed rice fields in the Hembeti area (very near to the
Mgongola project area) during harvest period, when paddy fields should be dry.
In 2013 the USAID-funded NAFAKA project, part of the FTF program, commissioned
a consultancy on the status of agricultural practices in the Mvomero District (IFDC
2013). The consultancy found that:
            Few farmers in the district (less than 5%) use fertilizer for rain-fed paddy
             rice, due to limited availability at the village level, poor purchasing power,
             lack of credit, poor roads, and lack of understanding about fertilizer use.
            Rain-fed paddy rice farmers tend to have weed problems (particularly
             grasses) and use herbicides to address those problems (see Table 3.1),
             but generally were not successful at controlling the weeds.
            Generally rain-fed paddy rice farmers do not use fungicides or
             insecticides, even though paddy rice in the district is subject to several
             diseases (bacterial blight, leaf blast, neck blast, sheath blight, brown spot
             false smut, and grain discoloration) and insect pests (brown plant hopper,
             stem borer, green hoppers, leaf folder, cut worms, termites, thrips, mealy
             bug and beetles). Most agro-dealers stock a limited number of fungicides
             and insecticides useful in paddy rice production (see Table 3.1).
            Paddy growers in rain-fed areas are not properly levelling their lands,
             which leads to uneven moisture distribution leading to gaps and dwarf
             growth.
            Seed rate used by paddy growers is 120 to 150 kg/h of seed, which are 6
             times what would be required using improved sowing practices.
            Farmers prefer to grow traditional rice varieties, which give poor yields
             than improved varieties but have an aromatic nature preferred by the
             consumers. Seed sowing is collected each year during harvest.
            Growing improved varieties requires purchasing certified quality seeds,
             which are generally unavailable. Even when improved varieties are used,
             the farmers still collect seed for sowing during the harvest, rather than
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                3-6
           purchasing new seed each year. This practice reduces yields over time as
           the hybrids lose some of their characteristics with each succeeding
           generation.
          Almost all of the labor is done by hand.
          Poor harvesting practices have led to decreased quality of rice and a
           resulting lower value for the rice.
Although these practices are general to the Mvomero District, they are most likely
common to the rain-fed farmers in the project area.
The PERSUAP for NAFAKA found that “Most small- and medium-scale farmers
rarely use PPE other than boots, long pants, a shirt and a hat” (ACDI/VOCA 2012, pg.
17). It is most likely that this is the situation for the farmers in the project area.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           3-7
4             ALTERNATIVES
As required in 22 CFR 216.6(c)(3), this section presents the Proposed Action and
reasonable alternatives that meet the purpose and need of the Proposed Action, as
well as the no action alternative. This section also includes a brief description of the
reasons for eliminating those alternatives which were not included in the detailed
analysis. For the Proposed Action and the action alternatives, this section presents
general mitigation measures. (Specific mitigation measures are presented in
Section 7.1 of this EA.) The section concludes with a comparative analysis of the
environmental impacts of the Proposed Action and each alternative.
2   The 620 ha area is the gross area inside the project boundaries and includes the canals and interior
     roads. The actual irrigated area will be 589 hectares.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                             4-8
Figure 4.1: General Layout of the Proposed Action
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME          4-9
              Construction of 14.5 km of earthen flood embankment surrounding the
               irrigable area and main canal alignment;
              Construction of 16.0 km of gravel-surfaced internal access roads and
               feeder roads; and
              Construction and equipping of an office building to be used for
               construction supervision and then handed over to the Water Users
               Association for use in scheme management.
The specifications for these components are elaborated in the following subsections.
Mobilization and construction of the Proposed Action is anticipated to occur over 20
months (assuming all construction contracts run concurrently). Construction will be
scheduled to the extent possible around the existing agricultural activities, as well as
the rainy seasons. The contractor(s) will be required to plan their works in such a
way that the 725 m of the existing Mkindo I main canal can operate in its original
condition or in its remodeled state throughout each irrigation season. As such, no
temporary canal diversions are foreseen. However, should temporary canal
diversions be required, they will be programmed by the contractor in consultation with
the Project Manager in such a way as to minimize the interruption of flows to the
downstream irrigators and under no account will the contractor be allowed to
jeopardize the irrigated crops reliant upon the water.
Temporary diversion of the Dizingwi River will be required where the Main Canal and
access road cross over the river (Figure 4.1). It is envisaged that this will be easiest
during the dry season when flows are generally at their lowest.
The Proposed Action would have an estimated construction cost of $ 5,015,000. It
would have an estimated irrigation water conveyance efficiency of 88% (weighted
average by length: 90% for the Main Canal and 85% for the Secondary and Tertiary
Canals3), with application efficiencies of 60%. This gives an overall expected
irrigation efficiency of 53%.
4.1.1         General Construction Activities
The following activities are generally common to all construction activities:
              Set up and operation of offices, housing, workshops, equipment
               maintenance and materials storage facilities etc. These facilities will
               remain after construction and be turned over to Water Users Association
               for use in scheme management;
              Establishment of safe access to different parts of the site;
              Location and preparation of borrow pits for embankment fill and road
               surfacing materials; and
              Import of construction materials, such as sand, aggregate, cement,
               reinforcing steel and gravel and onsite secure storage.
Land is available for the construction of the contractor’s site office, camp, workshops
and materials storage free of cost for the duration of the contract and defects liability
3   The relatively high conveyance efficiencies for the Secondary and Tertiary Canals are due to the high
     clay component of the soil through which they run.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                            4-10
period. The land is located in between the main canal and secondary canal 1, near
to where secondary canal 1 begins (Figure 4.2).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        4-11
 Figure 4.3:     Possible Borrow Pit Locations
To secure sand and gravel a few off-site activities will be required such as storage for
fuel and lubricants to run the equipment involved in abstraction, handling and
haulage of gravel for grading of service roads.
The drains are expected to be a key source of fill material for building canal
embankments, flood bunds, and farm roads. It is expected that all excavation from
drains will be required for fill where suitable. Where more fill is still required, it will
need to be sourced from borrow trenches or pits alongside the flood embankments,
outside of the scheme.
4.1.1.2 Water for Works
Water will be required for the works (e.g. for compaction and concrete batching). It is
anticipated that, since the project will benefit Mkindo I and II and they will be part of
the project management structure (see Section 4.1.6), water for works will be drawn
from the nearby Mkindo River under the existing Mkindo I and II water right. It is
estimated that 75 m3/day of water will be required for construction works, 0.1% of the
daily water right for Mkindo I and II. In some situations, the source of water for offsite
work locations (borrow areas for instance) may require the installation of intakes
close by. In all cases, the contractor(s) will be required to secure necessary permits
for water use during construction.
4.1.2    Irrigation and Drainage Components
4.1.2.1 Headworks
Irrigation water for the Proposed Action will be diverted from the Mkindo River at the
headworks for the Mkindo I irrigation scheme. The headworks are just upstream of a
natural fall which is located approximately 2 km upstream from the trunk road B127
(see Figure 4.1) There is an existing concrete intake equipped with two slide gates
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                               4-12
and two spillways cum sand-flushing gates. Immediately after the intake gates, a
side overflow spillway has been provided to drain excess water to the Mkindo River.
The headworks is of sufficient size to accommodate the proposed irrigation scheme
as well as Mkindo I and II. As noted in Section 3.4.2, the headworks underwent
rehabilitation under the supervision of MZITSU in 2012, however, an inspection of the
gates shows them to be badly corroded and the seals are leaking. The Proposed
Action will rehabilitate the headworks to correct these problems.
4.1.2.2 Main Canal
The main canal will flow 4.0 km from the headworks to the secondary canal 3,
providing water to Mkindo I and II and secondary canals 1 and 2 on its way (Table
4.1 and Figure 4.4). It will be designed for 24-hour continuous supply when irrigation
is required. It will have a concrete lining, in accordance with Government of
Tanzania (GoT) requirements.
Lining of the main canal at Mgongola has been proposed. It must be noted, as
discussed in CDM Smith 2012a, that lining the canal for water conservation reasons
(seepage-reduction) is not justified. However, the Mgongola project is following a
participatory approach and canal lining has been identified as a priority requirement
by:
          MAFC;
          MZITSU; and
          Mkindo Irrigators’ Organization.
These GoT organizations argued that the lining of main canals is a Tanzanian high-
level policy. When MZITSU rehabilitated the main canal for Mkindo in 2012 using its
own budget, it lined the canal with concrete and stone masonry.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        4-13
 Figure 4.4:    General Layout of the Main Canal
The first 725 m of the main canal will be the first 725 m of the existing Mkindo I main
canal. MZITSU expanded the capacity and lined this section of the main canal in
2012 in preparation for development of the Mgongola irrigation scheme. This stretch
of the main canal is in good condition, although there are some minor cracks and
places which the banks to be raised and storm water cross structures need to be
provided. The Proposed Action will repair the cracks, raise the banks where
necessary, and provide necessary storm water cross structures. This stretch of the
canal varies in cross-sectional shape between trapezoidal and rectangular depending
on the surrounding ground/rock type and topography.
At 725 m, the Proposed Action will construct a division structure with control gates to
divert water into the main canal for the Mgongola irrigation system and the main
canal for Mkindo I and II. Other than providing for this division of water into the
existing Mkindo I and II main canal and a flow measuring structure shortly
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          4-14
downstream from the division, the Proposed Action will not include any
improvements for the rest of the Mkindo I and II irrigation schemes.
From the division at 725 m, the Mgongola main canal will run in a generally
southeastern direction, south of the Mkindo Village. Three foot bridges and one road
bridge will be constructed over the canal south of the village to provide access to
land south of the canal. The canal will cross trunk road B127 through an existing 1.2-
m diameter culvert (built in advance by TANROADS during their upgrading of the
B127 in 2012), and then it will cross the Dizingwi River through an inverted siphon.
After crossing the river, the main canal will flow an additional 600 meters to
secondary canal 1. From secondary canal 1 it will flow generally south for another
1.5 km where the secondary canal 2 head regulator marks the end of the main canal
and the beginning of secondary canal 3.
The main canal will have a trapezoidal cross-section from the division at 725 m to
secondary canal 3. It will have flow measurement structures as shown in Table 4.2
to allow flow to the three secondary canals to be closely managed.
                            Chainage
  Canal                       (m)        Type                  Comments
                                                               Downstream of division
  Mkindo Main Canal             10       Broad Crested Weir
                                                               structure
                                         Full Width Sharp      Drop structure downstream of
  Mgongola Main Canal          755
                                         Crested Weir          division structure
                                                               Downstream of secondary
  Mgongola Main Canal          2,563     Broad Crested Weir
                                                               canal 1 head regulator
  Secondary Canal 3            100       Broad Crested Weir    Beginning of secondary canal 3
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         4-15
In addition to the two drains inside the scheme, drain 3 (Figure 4.1 and Table 4.3)
will be constructed along the right hand side, in the direction of flow, of the main
canal. Drain 3 will be open channel and unlined and will serve as a cut-off drain to
take drainage water from the area to the west of the scheme southwards to the
Mgongola River.
The tertiary canals and drains form part of the farmer contribution to the project but
preliminary design assistance will be provided under the Proposed Action. However,
the head regulator for each tertiary canal will be located in the secondary canal and
provided by the Proposed Action.
Following construction of the tertiary canals, the farmer contribution will also include
land levelling, bunds and any additional field channels required. Due to the small
size of the plots (approximately 1 ha), farmers will be able to level their fields
manually using hand hoes. Land levelling must be carried out for several years
following construction and then again periodically in the future. For this reason it is
appropriate that it should be part of the farmer responsibility from the beginning.
However, it is recognized that considerable technical support will need to be provided
to the farmers during this process.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           4-16
  4.1.2.6 Structures
  A summary of structures to be constructed for MIS is shown below in Table 4.4.
                           Number
Structure                                Gated or Ungated             Discharge Measurement
                           Required
Superpassage                  5               Ungated                            No
Division Structure            1               Ungated                            No
RCC Check-Drop
                             20                 Gated                            No
(for canals)
                                                                     Sharp-crested weir combined
RCC Drop (for canals)         4               Ungated               at MC chainage 755 m for flow
                                                                    measurement. Otherwise, No.
Footbridge                    3               Ungated                            No
Road Bridge                   1               Ungated                            No
Siphon/Box Culvert            1               Ungated                            No
SC Head Regulator             2                 Gated                            No
Broad Crested Weir            3               Ungated                           Yes
Check Structure               1                 Gated                            No
Outlet from SC               51                 Gated                            No
Combined Drop,                          Ungated (except for
                              1                                                  No
Culvert, Check                        outlets to tertiary canals)
Road Culvert (double)         3               Ungated                            No
Masonry Drop
                             14               Ungated                            No
(for drains)
Abbreviations:
  RCC Reinforced Cement Concrete
  SC Secondary Canal
  ENVIRONMENTAL ASSESSMENT
  CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              4-17
     Table 4.5: Internal Roads
The newly constructed portions of the main canal will have a gravel road on the left
hand side, in the direction of flow, for its entire length. The road will be along the top
of the embankment, will have a width of 6 m and will have a gravel wearing course
with a thickness of 0.2 m. The road will cross the Dizingwi River with a double-cell
box culvert immediately alongside the siphon structure through which the main canal
will flow. The road will connect to regional road B127 (Magole – Turiani Road).
Gravel roads will also be constructed along the secondary canals on both sides,
unless there is a flood bund on one side in which case the road will only be on the
side without a flood bund. These roads will have a width of 4.5 m and a gravel
wearing course with a thickness of 0.2 m. To reduce earthworks and improve access
to fields, the access roads running along the secondary canals are located 0.5 m
above existing ground level, adjacent to the canal embankment, rather than along the
top of the embankments.
The road labeled as “Contractor’s Access Road” in Figure 4.1 is an existing dirt road
that can be used during construction. No improvements are planned for this road.
4.1.5          Demobilization
At the conclusion of construction of the irrigation works, all construction equipment
such as bulldozers, concrete mixers, rollers and the like will be shifted to another site
or to storage places under the control of the contractor. Along with this, rehabilitation
of any damaged areas will be carried out before commissioning the project, in line
with the construction contract documents.
4.1.6          Operation, Maintenance and Management
Once the scheme is constructed it will be turned over to a Water Users Association
(WUA) for operation and maintenance. The plan is for the WUA to include the
current farmers in the Mgongola project area4 as well as those farming in Mkindo I
and Mkindo II, so that the entire irrigated area can be managed by one WUA. The
Mkindo I and Mkindo II farmers currently have their own irrigation organization, but
they are willing to disband that organization and join the new WUA.
MZITSU is coordinating the setting-up and training of the combined WUA. To that
end, they have worked with the farmers to organize an Interim Committee to
establish the WUA. With support from MZITSU, the Mvomero Local Government
Authority (LGA), and NAFAKA, the committee has:
               Established a bank account;
4   At least 725 farmers currently grow rain-fed paddy rice in the project area. Each of them will receive a
    plot in the irrigation scheme, so that no current users are displaced. Plots will be allocated to each
    farmer proportional in size and at the same location as the area they are currently farming in the
    project area.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                              4-18
            Collected Tanzanian 3,730,000shillings in membership fees from
             participating farmers (TSH 5,000 each from 746 farmers);
            Signed a Memorandum for the formation of the WUA; and
            Drafted and approved the Constitution of the WUA.
The Interim Committee is currently working with MZITSU, the LGA, and NAFAKA to:
            Secure a consolidated land tenure certificate
            Develop a training program;
            Establish financial management procedures, including collection of water
             fees and other dues;
            Establish water management practices and cropping patterns for the
             scheme; and
            Develop support for post-harvest processing and marketing.
The Proposed Action will prepare a Management, Operations and Maintenance
Manual for the WUA, which will comply with the National Irrigation Act (2013) as
approved by Parliament in its August-September 2013 session and include an
Environmental Management Plan to define the on-going requirements for operation
of the scheme in accordance with Integrated Water Resource Management
principles, health and safety and environmental requirements.
Among other operational issues and maintenance the manual will cover:
            Distribution of water throughout the project area;
            Monitoring of irrigation water flows and quality and of the quality of the
             drainage water leaving the irrigated area; and
            Operation and maintenance of irrigation and drainage infrastructure.
The Proposed Action does not include a cultivation improvement program. Such a
program is beyond the current scope of IRRIP1. NAFAKA, another USAID-FTF
project, however, has conducted improved cultivation activities with Mkindo irrigation
scheme farmers and would provide USAID with a vehicle for pursuing improved
cultivation activities in the Mgongola irrigation scheme as a partner activity. Such
activities would improve the crop yield associated with irrigation.
4.1.7       Cropping
IRRIP1 reviewed a number of alternative crops for use at Mgongola. This review, in
conjunction with the findings from the soil survey report (JICA 1998), concluded that
the heavy soils in the project area are far better suited to paddy cultivation than any
other crop. However, NAFAKA has introduced demonstration plots within the Mkindo
I and II irrigation scheme to investigate alternative crops such as maize, sorghum,
and sunflowers.
NAFAKA is working at the newly formed WUA to develop improved cropping and on-
farm water management practices for paddy rice production. IRRIP1 has worked
with NAFAKA at the field level in Mkindo I and II to optimize the size of irrigated plots
and layout of field canals and drains.
It is anticipated that, as the agricultural demonstrations and developments advance,
a number of different cropping scenarios, combining rice with other crops in rotation
throughout the year, may be tested. The layout of the irrigation infrastructure for the
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                4-19
Proposed Action is flexible enough to allow a variety of other crops to be grown
without any changes to the system other than revised irrigation scheduling
associated with the different crop type(s).
4.1.8        Irrigation Water Requirements and Water Rights
The proposed cropping pattern for the Mgongola irrigation scheme is single-cropping
of paddy rice during the rainy season, February to June, following land preparation in
January. Mkindo I and II would continue to operate under its existing cropping
pattern: double cropping of paddy under fully irrigated conditions with the first crop
grown during the rainy season from January to June, and the second crop grown
from July to December.
IRRIP1 estimated the irrigation water requirement for the proposed cropping patterns
using daily rainfall data and climatological data. The estimates were carried out on a
10-day basis using CROPWAT 4.05 in accordance with the following procedures:
             Calculate potential evapotranspiration from climate data;
             Estimate consumptive use of water by multiplying potential
              evapotranspiration by crop coefficient, including percolation rate in case of
              paddy rice;
             Estimate effective rainfall from daily rainfall;
             Calculate net irrigation water requirement deducting the effective rainfall
              from the estimated consumptive use of water plus percolation; and
             Calculate irrigation water requirement taking irrigation efficiency into
              account.
Following the above procedures, the peak irrigation water requirement at the head of
the system was calculated and adopted at 2.0 l/s/ha. The outcomes of these
calculations are dependent on a large number of highly variable inputs. The
MZITSU, from their local experience working with irrigation schemes, have
developed a policy of design water requirement of 1.5 to 2.0 l/s/ha, so the 2.0 l/s/ha
value appears to be reasonable.
The Mgongola irrigation scheme will develop 589 ha (net) of irrigated paddy.
Considering the additional existing Mkindo I and Mkindo II developments with a
combined irrigated area of approximately 110 ha, the total area to be supplied at the
headworks is 699 ha. This corresponds to a flow of approximately 1.4 m3/s at the
headworks, to supply the entire irrigated area during the rainy season and 0.2 m3/s at
the headworks, to supply Mkindo I and Mkindo II during the dry season.
The Mkindo irrigation organization has a water right to abstract 0.624 m3/s for 24
hours per day with no restrictions on abstractions during the dry-season flows. Once
the new WUA is formed and has obtained a consolidated land tenure certificate for
the entire irrigated area, it is expected to apply for an extension of the existing water
permit to cover the additional lands represented by the Mgongola irrigation scheme.
That permit would increase the water right to 1.4 m3/s during the rainy season (an
additional 0.776 m3/s).
5   CROPWAT is a decision support tool developed by the Land and Water Development Division of the
    Food and Agriculture Organization of the United Nations for calculation of crop water requirements
    and irrigation requirements based on soil, climate and crop data.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                         4-20
objective of this alternative is to improve the conveyance efficiency and thus
conserve water.
During preparation of the EA, several piped alternatives were analyzed, including
piping both the main and secondary canals and using steel and concrete piping. The
alternative of using steel pipes and piping only the main canal was determined to be
the most effective piping alternative. Although the unit costs for concrete pipes are
cheaper than steel pipes for all but diameters less than 450 mm, steel pipes are more
easily jointed, are lighter for making the necessary river crossing, and are effectively
impermeable. There are numerous problems associated with reinforced concrete
pipes and these tend to increase with the diameter of the pipe. In addition, concrete
pipes cannot be expected to hold pressure even at low heads, and the piped main
canal will be under about 6 m of pressure at some locations. Although steel pipes
may suffer from corrosion, in the Mgongola area this is not seen as a major concern.
The Piped Main Canal alternative has an estimated cost of $5,695,000. Conveyance
efficiency is expected to be 92% (weighted average by length: 97% for the Main
Canal, 85% for the Secondary Tertiary canals) and application efficiencies are
expected to be 60%. This gives an overall expected irrigation efficiency of 55%.
The General Construction Activities, Flood Control, Farm Roads, Demobilization, and
Cropping specifications will be the same as those for the Proposed Action. The
specifications for Irrigation and Drainage Components; Operation, Maintenance and
Management; and Irrigation Water Requirements and Water Rights will be different,
as noted below.
4.2.1       Irrigation and Drainage Components
The specifications for secondary canals, drains and incidental land levelling will be
the same as for the Proposed Activity. The rehabilitation of the main canal, however,
will be as follows:
            Piping the main canal from the diversion to the Mkindo Scheme to the end
             of the main canal;
            Construction of a settling basin to trap and remove sediment before it
             enters the pipe;
            Furnishing and installing a single 1-meter diameter steel pipe set on a
             gravel bed within the alignment of the main canal in the Proposed Action
             with manholes at a minimum of 500 m; and
            Construction at each secondary canal offtake of a manhole, a flow
             measurement device, and a sliding gate to control outflow.
4.2.2       Operation, Maintenance and Management
The Operation, Maintenance and Management specifications for the Piped Main
Canal alternative are the same as those for the Proposed Action with the addition of
the following:
            Large diameter pipes are relatively easy to inspect internally and adequate
             access points will be provided. However, maintenance staff will need to
             be fully trained on confined space entry, and equipped with generators,
             lighting and breathing apparatus in order to carry them out safely.
            The day-to-day operation of the enclosed conduit should be easier than an
             open channel and less maintenance such as desilting and channel
             clearance will be required. However, if sediment does enter the pipe then
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            4-21
                its removal will be a major undertaking, particularly since the pipe has only
                a 1-meter diameter.
               Special care must also be taken to prevent the growth of bushes or trees
                whose roots may penetrate the pipe joints.
4.2.3          Irrigation Water Requirements and Water Rights
The overall irrigation water efficiency of the Piped Main Canal alternative is 55%,
which is 2% more efficient than the Proposed Action. This will reduce the irrigation
water requirement by 0.043 m3/s, reducing the required additional water right to
0.733 m3/s.6
6   The improved efficiency will only apply to the 589 ha of newly irrigated land.
7   Higher than the Proposed Action due to the use of PVC piping for Tertiary Canals.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                               4-22
            Construction of a concrete pumping point (sump) at each of these tertiary
             canals in line after the water meter.
In addition, this alternative assumes that the farmers will have to pay for the portable
sprinkling unit capable of servicing a 36-hectare area. Each unit would consist of:
            Mobile diesel engine and suction pump to 6 bar;
            Sprinkler and 2-m riser;
            200-mm diameter unplasticized polyvinylchloride (uPVC) or pressure pipe;
            50-mm diameter PE pipe; and
            Couplings.
4.3.2       Operation, Maintenance and Management
The Operation, Maintenance and Management specifications for the Sprinkler
Irrigation alternative are the same as those for the Proposed Action with the addition
of the following:
            Irrigation using hand-move sprinklers is a time-consuming and labor-
             intensive activity as someone must be on hand to move the sprinkler after
             each set. In practice one person could handle the sequential movement of
             10 laterals resulting in one 9-ha basin being irrigated in 6 hours; however,
             the process must continue over night if the minimum system sizing is to be
             maintained. Each basin would then need to be irrigated every 4 days and
             thus one person could manage 36 ha of irrigation.
            To maximize water conservation it has been assumed that dry-foot rice will
             be grown (no ponding of water). This will mean that additional labor will
             be required to weed the rice and/or additional herbicides (in comparison
             with paddy rice cultivation) must be used to control broad-leaf weeds.
            The Sprinkler Irrigation alternative provides groups of WUA members with
             the option of using sprinklers, by providing pumping points at 17 tertiary
             canals to allow portable diesel pumps to pressurize small hand-moveable
             sprinkler irrigation units covering individual basins. The project, however,
             does not provide the pumps or sprinkler systems. So farmers cultivating
             36 contiguous ha with access to one of the 17 pumping points will have to
             join forces to purchase the necessary pumping equipment, at a cost of
             $2,917/ha.
These additional management issues are a radical departure from the current
irrigation system used in the Mgongola area, on the Mkindo schemes. Introducing
such a radically different system would take considerable extension work and
training. Without an extension program, it is unlikely that any farmers would adopt
the sprinkler technology. This EA does not include a description of or the cost for
such an extension program.
A benefit of this sprinkler approach is that it is an add-on to a flood irrigation system,
so farmers do not have to make the transition immediately, or all at the same time.
Indeed, the sprinkling system can be implemented on 36 hectares at a time, allowing
early adopters to move forward, while more conservative farmers continue with the
current practices.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            4-23
In addition, this alternative requires farmers to invest in sprinkler systems for its
implementation, but until farmers are able to see tangible benefits associated with
managing water efficiently there is little incentive for them to make such investments.
Maximum irrigation efficiency seldom comes until a realistic charge is levied for water
consumption. If the WUA sets up a fee/water use rather than a fee/ha fee structure,
the incentives for using irrigation water efficiently will be established. However, this
is a highly contentious issue in Tanzania where farmers are used to receiving their
water for a nominal fixed fee per hectare to recover system operation and
maintenance costs.
4.3.3       Cropping
“Long straw” rice varieties of the type preferred by local farmers are likely to be
inappropriate for sprinkler irrigation unless overhead sprinklers are adopted or else
low-drift sprinklers used. Standard sprinklers “throw” the water sideways where it is
likely to knock over long-straw varieties (aka “lodge”). Lodged rice can result in
reduced yield potential. It is harder to harvest mechanically because it must first be
picked up off the ground. One solution to this would be to convert to overhead
moveable irrigation systems or else grow shorter varieties of rice.
            Overhead moving systems (linear move) would be difficult to transport
             from one basin to the next but would offer substantial savings in effort with
             regard to moving sets of individual sprinkler laterals about. However, this
             system is substantially more expensive to buy and maintain and the
             moveable tires supporting the towers of the boom may become bogged in
             the black cotton soils of the Dakawa farm.
            Short-straw rice varieties offer many potential benefits to the farmers such
             as a reduced growing season (90 days in comparison with 120-150 days)
             and potentially higher yielding; however, they are generally not aromatic,
             so farmers and the local people do not like them. Nevertheless, there is a
             great potential for export if this mindset can be changed.
Local farmers produce rice for personal consumption (subsistence) as well as for the
market. The local farmers prefer the taste of the “long straw” rice. As will changing
the irrigation system, changing the type of rice grown will also require considerable
extension work and training.
4.3.4       Irrigation Water Requirements and Water Rights
Farmers will initially require the full amount of irrigation water necessary for growing
rice using flood irrigation, so in the initial stages of operation, this alternative will have
the same irrigation water requirements as the Proposed Action. But as farmers
group together and purchase and install sprinkler systems, their water use efficiency
will increase from 53% to 73%. If all of the farmers in the 589 ha of newly irrigated
area install sprinkling systems, the overall the irrigation water requirement would be
re reduce by 0.32 m3/s, reducing the required additional water right to 0.456 m3/s.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                4-24
Cornell University and the International Fund for Agricultural Development. It has
been implemented in 50 countries. It was introduced in East Africa in Rwanda in
2008 and subsequently in Kenya, Burundi, and Tanzania (Katamba et al. 2013).
The SRI cultivating system consists of:
            Growing seedlings in nurseries.
            Transplanting 8- to 12-day-old seedlings.
            Planting only one seedling per hill in hills spaced widely apart in a grid.
            Controlling weeds with a rotating hand hoe, which also aerates the soil.
            Applying compost to increase the soil’s organic matter content.
            Using Alternating Wet/Dry (AWD) irrigation application.
The SRI alternative has the same estimated cost as the Proposed Action,
$5,695,000. This cost, however, does not include the cost of a multi-year extension
program to promote SRI among the participating farmers. Such a program has not
yet been designed, so the potential cost has not been estimated. The SRI alternative
may begin with the same irrigation water efficiency as the Proposed Action, as
farmers will be familiar with the practices used in the area by other irrigators,
however, the efficiencies could rapidly increase as farmers adopt SRI practices.
Ultimately, if all farmers adopt SRI, conveyance efficiency is expected to be 88%
(weighted average by length: 90% for the Main Canal, 85% for the Secondary and
Tertiary canals) and application efficiencies are expected to be 80%. This gives an
overall expected irrigation efficiency of 70%.
The General Construction Activities, Irrigation and Drainage Components, Flood
Control, Farm Roads, and Demobilization specifications will be the same as those for
the Proposed Action. The specifications for Cropping; Operation, Maintenance and
Management; and Irrigation Water Requirements and Water Rights will be different,
as noted below.
4.4.1       Operation, Maintenance and Management
The Operation, Maintenance and Management specifications for the SRI alternative
are the same as those for the Proposed Action with the addition of an intensive,
multi-year agricultural extension program in cooperation with MZITSU to promote SRI
practices among the Mgongola irrigation scheme farmers.
Although implementation of SRI has been able to demonstrate improved yields (at
least in relation to traditional practices) with less use of water and other agricultural
inputs (seed, chemical fertilizers and pesticides), it has not been readily adopted by
rice farmers both abroad (Berkhout and Glover 2011) and in Tanzania (Katambara et
al. 2013). In general there are several reasons for low adoption rates, but key among
them are risk aversion and costs.
Adopting a new cultivation practice is a risky venture, particularly for a low-income
subsistence farmer for whom a bad result could mean famine. Cost is another critical
barrier, particularly for the low-income subsistence farmer. In the case of SRI, there
is little upfront cost to be borne, but there is increased labor in development of
nurseries and seedling planting for those farmers who currently directly broadcast
seed in their fields (as is the case in the Mgongola project area). There is also
increased labor involved in weed control.
In the case of SRI, another critical barrier to adoption is that many of its practices run
contrary to “best management practices” for paddy rice production that have been
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 4-25
promoted for years. These include the age and number of seedlings planted in hills,
the spacing of the hills, the irrigation water management regime, the use of only
compost for fertilizer, and relying on hand-weeding rather than herbicides for weed
control. This can make SRI appear to be a controversial cultivation scheme (and
indeed, it has been controversial in the literature), and if the local experts (extension
officers) are not supportive, then it is very difficult to implement.
These barriers can be overcome, but only with a concerted, multi-year extension
program operated in conjunction with local government extension agents. Such a
program is beyond the current scope of IRRIP1. To implement this program, USAID
will need to expand the scope of IRRIP1 to include such a program or use another
vehicle such as NAFAKA to do the same. NAFAKA began conducting SRI activities
in Mvomero and Kilombero Districts in 2011 and would provide USAID with a vehicle
for pursuing an SRI extension program for the Mgongola irrigation scheme. Such a
program would be in-line with the GoT’s SAGCOT Agriculture Green Growth (AGG)
initiatives.
This EA does not present a description of or cost for the extension program, as it has
not yet been designed. Whatever program is designed it should conform to the AGG
characteristics as shown in Table 4.6.
4.4.2     Cropping
The SRI alternative will, like the Proposed Action, grow paddy rice. The rice,
however, will be cultivated in a significantly different manner. SRI is based on five
components (SRI-RICE 2014):
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 4-26
            The use of nursery-grown seedlings (as opposed to the current practice of
             no nurseries). It can be used with any variety of paddy-rice (i.e., it is not
             limited to improved varieties).
            Planting seedlings in the fields (as opposed to the current practice of
             broadcast seeding):
              o when they are 8-12 days old (as opposed to the conventional
                 improved practices recommendation of 21-30 days);
              o one per hill (as opposed to the conventional improved practices
                 recommendation of 3-5 seeds per hill); and
              o on a grid at wide spacing (25 cm x 25 cm as opposed to the
                 conventional improved practices recommendation of hills in rows 10
                 to 15 cm apart).
            Use of organic fertilizer (compost), although many reports indicate that
             farmers using SRI generally supplement with urea.
            Reduced water use:
              o Field flooded at 1-2 cm after transplanting, and maintained until plants
                are ~10 cm tall (~10 days after transplanting).
              o Alternating Wet/Dry (AWD) water management during most of the
                growing season, where fields are periodically flooded, but then
                allowed to “dry” out between flooding (just dry on the surface, so that
                the roots stay moist). A Kenyan government brochure recommends a
                cycle of 3 days of 1-2 cm ponding followed by 7 days of drying (Mati
                2012).
              o When flowering begins, a thin layer (1-2cm) of water is applied and
                maintained on the field for 2-3 weeks.
              o Then back to the AWD.
              o 2-3 weeks before harvest irrigation stops to allow the field to dry for
                harvest (same as conventional practices) (need drainage system to
                remove water)
            Hand weeding. Due to the lack of ponding, weeds will be a
             problem. Weeding is done with a special, hand held rotary-head weeder
             to remove weeds, aerate the soil and improve field leveling. Some SRI
             farmers, however, still use herbicides.
Some proponents of SRI claim that its adoption has increased yields per ha by 2-3
times. But many researchers have challenged these results as being based on
unscientific studies and lack of definition of baseline yields. These researchers have
conducted studies that show that the yield increases from SRI are no better than
what can be gained with conventional best practices (improved seed, transplanting,
and proper fertilizer and herbicide use) with conventional rice irrigation (Bouman et
al. 2007, McDonald et al. 2006).
4.4.3       Irrigation Water Requirements and Water Rights
Proponents and detractors alike, however, concur that SRI uses less water for
production, with reported reductions ranging from 15 to 50% (with even critics
reporting 15 to 30% reductions in water use without significant impact on production
[Bouman et al. 2007 pg. 20]). There also seems to be agreement that SRI requires
more labor (primarily due to weeding and spreading organic fertilizers) but reduces
the quantity needed of seed per ha.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              4-27
This EA uses a mid-range estimate of a 25% reduction in in-field application needs.
This results in a reduction of 0.287 m3/s, reducing the required additional water right
to 0.489 m3/s.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                             4-29
mitigation measures during mobilization and construction, as there will be no
mobilization and construction.
The mitigation measures for the Proposed Action and all action alternatives during
operation are the same, except for water quantity available to downstream users and
water use conflicts. The mitigation measures associated with these two impacts are
not necessary for the Improved Intensified Rain-Fed Agriculture alternative. The
mitigation measures for the action alternatives during operation are presented in
Table 4.8.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                4-30
Table 4.8: Mitigation Measures for Operation
            Impact                               General Mitigation Measure
Soil Salinity (Sprinkler    Monitor soil salinity at the end of each irrigation season and take
Irrigation)                 remedial actions if salinity reaches critical levels.
Effects of Pesticides and   Implementation of the NAFAKA PERSUAP
Fertilizer Use              Sensitization of farmers on fertilizer use
                            Same as for Effects of Pesticides and Fertilizer Use
Water Contamination         Periodic water quality monitoring downstream of drainage
                            discharges
Water Quantity Impacts to
Downstream Users and        Monitor water withdrawals by Mgongola irrigation scheme
Ecosystems (Irrigation      Monitor downstream flows
Alternatives)
Effects on Aquatic          Same as for Effects of Pesticides and Fertilizer Use
Species                     Water quality monitoring downstream of drainage discharges
                            Create a livestock corridor providing access to rivers in dry season
                            Designate grazing and watering areas outside of the project
Land Use Conflicts –
                            boundaries
Cultivation/Grazing
                            Establish an NGO composed of farmers and herders to address
                            cultivation/grazing conflicts
Scheme Management
Capacity (Irrigation        Develop and implement a capacity building program for the WUA
Alternatives)
WRBWO Capacity to           Continue capacity building for the WRBWO.
Control Water               Deploy and pilot the use of remote instrumentation for monitoring
Abstractions (Irrigation    flows, abstractions, discharges etc. on the Mkindo River and the
Alternatives)               Mtibwa EFA site
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                   4-31
  Table 4.9: Environmental Impacts Associated with Mobilization and
             Construction
                                               Positive Impacts
  Opportunities for Temporary
  Employment
                                              Negative Impacts
  Soil Erosion                          Soil Pollution                        Loss of Topsoil
  Water Contamination                   Solid Waste Generation                Dust and Air Pollution
  Noise Pollution                       Effects on the Aquatic Species        Worker/Community Health
  Change of Community                                                         and Safety
     Lifestyle
                                                               ALTERNATIVES
                                                  Piped
                                   Proposed       Main       Sprinkler                   Improved        No
            Impact                  Action        Canal     Irrigationa       SRIa       Rain-Feda      Action
  ENVIRONMENTAL ASSESSMENT
  CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                              4-32
Table 4.11: Qualitative Comparison of the Impacts of Alternatives
                                                         ALTERNATIVES
                                              Piped
                              Proposed        Main        Sprinkler               Improved        No
         Impact                Action         Canal      Irrigation*     SRI      Rain-Fed       Action
Reliable Supply of
                                  +2             +2           +2          +2           0            0
Irrigation Water
Opportunities for
                                  +2             +2           +2          +2          +1            0
Employment
Improved Market
Outlets
                                  +2             +2           +2          +2           0            0
Note:
* Ranked assuming that all farmers adopt sprinkler irrigation, otherwise this alternative has the same
  impacts as the Proposed Action.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        4-34
5        AFFECTED ENVIRONMENT
As required in 22 CFR 216.6(c)(4), this section presents a succinct description of the
environment in the project area that may be affected by the Proposed Action and its
alternatives.
5.1      Boundaries
The project covers the construction of an irrigation scheme in Mgongola as shown in
Figure 3.2. The special boundary of the project and its alternatives for most of the
physical and environmental impacts will be limited to the 620-ha area. However, the
project’s impacts on water resources may influence the downstream environmental
flows and water users in the Wami River Basin (Figure 5.1), extending the spatial
boundaries for the water resources analysis well beyond the project boundaries.
The social impacts will be primarily borne by four nearby villages – Mkindo, Dihombo,
Hembeti, and Kambala – and secondarily by the Hembeti Ward in the Mvomero
District. So the boundary for the socio-economic analysis will be the four villages and
the Hembeti Ward.
Temporal boundaries refer to project life span and the reversibility of impacts. The
irrigation infrastructure is anticipated to have a design life of between 30 and 50
years, assuming proper maintenance, management and upkeep. After that time
period, the scheme will require other major works to be carried out. However, the
immediate mobilization and construction activities are anticipated to occur over a 20-
month period.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          5-1
5.2         Physical Environment
5.2.1       Topography
The irrigation scheme lies on the Mkata Flood Plain, between the Mkindo and
Dizingwi river to the north and the Mgongola River to the south (between latitudes
37o32’E and 37o36’E and longitudes 6o16’S and 6o18’S). Elevation ranges from 345
m to 365 m above sea level. The terrain is generally flat with an overall slope of
1/200 to 1/500 to the east. It is subject to flooding during the rainy season (February-
June). According to interviews with local farmers of the area, annual flood water
depth is approximately 0.3 m on the Mkindo River and 0.5 m to 1.0 m on the
Mgongola River.
5.2.2       Geology and Soils
The project area lies on the border of an area composed of igneous and
metamorphic rocks overlain by more recent sedimentary rocks same as those found
in Mwinyi, Merela and Kwambe quarry sites. The rock and stone materials from
these sources are suitable for making aggregates for concrete and gravel wearing
course.
Soil mapping was conducted for the feasibility study (JICA 1998). The soils that were
encountered were classified according the FAO/UNESCO soil classification:
            Eutric Cambisols (Mapping unit Mgl-l)
            Eutric Fluvisols (Mapping unit Mgl-2)
            Eutric Fluvisols associated with Eutric Gleysols (Mapping unit Mgl-3)
The characteristics of these soils and their presence in the surveyed area are
presented in Table 5.1. The feasibility study (JICA 1998) concluded that the soils
were more suitable for paddy rice production than for any other crop.
Mgl-1 soils are the most prominent soils, comprising about 86% of the area within the
project boundaries. These soils are currently used for and well suited for paddy rice
production.
The Mgl-3 soils are less common within the project boundaries, only occurring in a
narrow strip on the southern boundary and comprising about 7% of the area. The
existing Mkindo irrigation schemes are predominantly on the Mgl-3 soils, and they
have proven to be well suited for irrigated paddy rice production. In their natural
state, the location of a high ground water table where these soils occur prevents
them from draining freely, especially during the rainy season. This poor drainability
does not negatively impact paddy rice production, which thrives with water ponding.
The Mgl-2 soils in the project area are located in two small areas on the western
boundary and near the southeastern boundary and comprise about 7% of the total
area. Although still suitable for rice production, the Mgl-2 soils are more permeable
than the other two classes.
Most of the land in the project area is periodically flooded during the rainy season
(February-June) by the surrounding rivers. During the dry season, these areas dry
up quickly with soils developing deep and wide cracks on the surface.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                             5-2
 Table 5.1: Soils in Mgongola Irrigation Scheme Area
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 5-3
  Figure 5.2:    Annual Rainfall in Morogoro Town, 1922-1988
  Source:   Wami-Ruvu Basin Water Office
Morogoro Region lies between the central highlands and the coastal region and it will
experience a mixture of impacts related to climate changes. The USAID-funded
Integrated Water, Sanitation and Hygiene (iWASH) Program has conducted climate
change and climate vulnerability assessments for the Wami Basin. It has released a
draft interim report, “Climate in the Wami and Ruvu Basins, Tanzania: Current
Characteristics and Future Projections” (iWASH 2013b). A review of that report
indicates climate change will cause no appreciable decrease in historical rainfall but
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         5-4
will increase uncertainty on its onset and regularity. This concurs with other available
climatological data and existing hydrological studies, indicating there does not appear
to be any evidence of a long-term downward trend in rainfall.
The region also already experiences significant climate variability. The region has
been affected by droughts about once in 4 years. Relatively recent droughts have
occurred for example in 1999-2000, 1996-97, 1992, 1987, 1985, 1983, 1975-76 and
1971 but with slight increase of rainfall in year 2006 (Figure 5.2 and Figure 5.3).
During the worst drought years, annual rainfall has been about 600 mm or 30%
below the long-term mean annual rainfall of about 890 mm. Monthly rainfall has
varied even more. During the 20th century, monthly rainfall in rainy years has been
over three times the average. In dry years the monthly rainfall has been less than a
third of average, or there was no rainfall at all. It is also worth noting that shorter dry
spells lasting from 1 to 2 weeks (which do not necessarily show clearly in the monthly
rainfall data) during critical periods of the growing season can reduce crop yields
significantly.
5.2.4    Water Resources
The irrigation scheme lies in the Wami River Basin (Figure 5.1) on the Mkata Flood
Plain which is drained to the east by the Wami River and its tributaries, including the
Mkindo River (and its tributary, the Dizingwa River) and the Mgongola River, between
which the project area lies (Figure 3.1).
5.2.4.1 Mkindo River
The Mkindo River is the water source for the existing Mkindo I irrigation scheme and
also for the proposed Mgongola development. It flows eastward and empties into the
Diwale River before it joins the Wami River. It seasonally overflows its banks onto
the floodplain in which the project area lies. According to interviews with local
farmers of the area, annual flood water depth is approximately 0.3 m.
The annual historical mean flows for the Mkindo River as reported in the 1998
feasibility study are shown in Figure 5.4. Estimated daily mean flows are shown in
Figure 5.5 for the period November 2009 through to December 2010. The data in
Figure 5.5 seems to correlate strongly with that in Figure 5.4. Minimum monthly
flows for three dry-year scenarios (1 in 2 years, 1 in 5 years, and 1 in 10 years) are
shown in Table 5.2.
5.2.4.2 Dizingwi River
The Dizingwi River is a perennial tributary of the Mkindo River. Its water is always
stagnant and slow-moving in the Mkindo area. Currently, the Mkindo II scheme takes
water from the Dizingwi River because the siphon structure which should allow the
Mkindo main canal to cross the Dizingwi River has failed. No flow data exists for the
Dizingwi River, but it apparently has sufficient flow to serve Mkindo II, which has an
estimated irrigation water requirement of 0.1 m3/s.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              5-5
   Figure 5.4:               Monthly Mean Flow Rate of Mkindo River
    Source: JICA 1998, pg. D-III-4
    16
           Daily Flow (cumecs)
    14
12
10
     0
         Nov2009 Dec2009 Jan2010 Feb2010 Mar2010 Apr2010 May2010 Jun2010 Jul2010   Aug2010 Sep2010 Oct2010 Nov2010 Dec2010
  Return
  Period
  (years)           Jan          Feb      Mar         Apr        May         Jun         Jul        Aug        Sep           Oct    Nov    Dec
    10             1.04          1.45     1.75        5.07       3.38       2.37         1.54       1.10       0.69          0.59   0.50   1.03
     5             1.46          1.79     2.34        6.27       4.33       2.84         1.79       1.33       0.89          0.78   0.75   1.46
     2             2.80          2.65     4.15        9.42       7.12       4.05         2.37       1.93       1.46          1.34   1.67   2.85
Source: JICA 1998
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                          5-6
5.2.4.3 Mgongola River
The Mgongola River is an intermittent river that runs along the southern boundary of
the proposed Mgongola scheme and flows from west to east. It flows only during the
rainy season, when it flows into the Diwale River downstream from the confluence of
the Mkindo and Diwale rivers. It habitually inundates the Mgongola project area in
the rainy season. According to interviews with local farmers of the area during
2011/2012, the flood depth along the river at the peak is 0.8 m to 1.0 m in the area
upstream of the proposed Mgongola scheme and 0.5 m in the area downstream of
the Mgongola scheme. The Mgongola River is the primary source of drinking water
for livestock from Kambala Village, 7 km south of the project area. No flow data
exists for the Mgongola River.
5.2.4.4 Water Demand and Water Rights on the Mkindo, Diwale and Wami
        River
There are only two water rights on the Mkindo and Diwale rivers. The Wami-Ruvu
Basin Water Office (WRBWO) granted the Mkindo farmers’ cooperative a water right
in 2002 to abstract 0.624 m3/s from the Mkindo River with no restrictions on
abstractions during the dry-season flows (WRBWO 2015). The water used by the
Mkindo irrigation schemes is most likely less than their water right, as they have an
irrigation requirement of only 0.22 m3/s; however, there are no records of actual
water use by the cooperative.
The Mtibwa Sugar Estate also has a 1.5 m3/s water right to abstract water from the
Diwale River below the junction with the Mkindo River8. The USAID-funded report,
Profile of the Wami River Sub-basin (TCMP 2008, p9), states that the actual
maximum daily abstraction is 1.5 m3/s, falling to 0.5-0.75 m3/s in the rainy season9.
The Diwale River joins the main Wami River upstream of the Mtibwa EFA site.
The Dizungu Sugar Estate is located north of the project area on the banks of the
Mkindo River. It has approximately 300 ha of sugar under cultivation. It apparently
uses surface water from the Mkindo River for irrigation, but there is no record of it
being issued a water right or information on the size of its abstraction (if it indeed has
an abstraction).
There are currently no other major water users on the Mkindo and Diwale drainages.
Two small fish ponds are supplied water directly from the Mkindo main canal through
100-mm diameter pipes through the wall of the concrete lining. According to the
Mkindo water users group, water is abstracted at these points until there is
approximately 1-m depth of water in each fish pond at which point the pipes are
plugged with grass and the water is contained. Assuming that each pond has a plan
area of 10 m x 20 m, that seepage rates are low and peak evaporation is 6.7
mm/day, then the water abstraction can be considered negligible (<0.1 l/s). As of
July 2013 only one of these ponds was in operation. The owner had abandoned the
second pond but continued to use the remaining pond in a sub-optimal manner.
The Mkindo River flows into the Diwale River, which flows into the Wami River.
Population growth in the Wami Basin both upstream and downstream of the
confluence with the Diwale River has resulted in increased pressure being placed
upon the water resources of the basin. A number of abstractions have occurred
upstream of the confluence in recent years, some with and others without water
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                        5-7
rights. This has resulted in the depletion of flows throughout the Wami Basin, most
noticeably during the dry season when Wami River flows are at a minimum.
The list of all other permitted water users upstream and downstream of the
confluence of the Wami and Diwale rivers is presented in Table 5.3.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        5-8
5.2.4.5 Wami River Environmental Flow Assessment
The WRBWO is ultimately responsible for taking into account other users, present
and future, and for issuing and reviewing abstraction licenses. In 2007, the
WRBWO, in collaboration with the University of Dar es Salaam and Florida
International University, began an Environmental Flow Assessment (EFA) process
for the Wami River sub-Basin in order to better understand the flow needs of
ecosystems. The first round of the EFA for the Wami River was carried out in April-
December 2007 and reported in the Initial EFA Synthesis Report (Sarmett et al.
2008). The second round of investigations was completed in April and May 2011 and
reported in August 2013 (iWASH 2013a) to obtain wet season data. Phase II was
able to fill gaps in understanding that were identified in the 2008 report, update
analyses of the hydrologic record, and revisit the original environmental flow
recommendations. The wet season findings did not have a significant impact on the
initial flow recommendations.
The EFA method and the subsequent flow regime recommendations rely on bringing
the various experts and key stakeholders together to agree on the 'desired state' of
each section of the river. This is not just an exercise in simply assessing how much
water can be taken from the river at a particular point, and how much should be left –
it is also a series of political and managerial decisions on the balance between using
available water for productive/developmental purposes, versus maintaining the river’s
ecological systems at an acceptable standard.
Of the sites assessed in the EFA, the Mgongola irrigation scheme is located
upstream of and near to the Mtibwa site on the Wami River. An additional EFA
assessment site is located further downstream at Mandera (see Figure 5.6). The dry
year recommended average discharges (RAD) to maintain environmental flows10 in
the Wami River at Mtibwa and Mandera from the 2008 and 2013 assessments are
presented in Table 5.4.
10    iWASH 2013 defines environmental flow requirements to include ecological, geomorphological, and
     human domestic needs.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                         5-9
      Figure 5.6:        Wami River Basin with EFA Sites
      Source: iWASH 2013a
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        5-10
   Table 5.5: Water Quality Data from EFA Sites
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME        5-11
The samples in Table 5.5 were taken during the rainy season when the Mgongola
area was being cultivated. The results indicate that there are no water quality
problems (elevated nutrients or salinity) in the Wami River downstream from the
project area.
5.2.5    Air and Noise
The project area is rural with few sources of air pollution or noise. No homes,
schools, medical facilities or other noise sensitive receivers are located in or near the
project area.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           5-12
     Figure 5.7:   Google View of Vegetation in the Project Area
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                         5-13
5.3.2    Wildlife
Since the project will be implemented in the area that has been subjected to
recurrent agricultural activities alternated by livestock grazing during the dry season,
there was no justification of carrying out any substantial fauna survey in the project
area. However through literature review and opportunistic observation of fauna
around the project area and upstream in the Mkindo Forest Reserve, several species
of birds, mammals, amphibians and reptiles were identified as being present in or
near the project area. In total, 62 observations of fauna were made, 52 within the
Forest Reserve and 10 observations in the grassland and farmland surrounding the
reserve. The observations are tabulated in Annex B and summarized in Table 5.6.
One frog species was found to be endemic to the Eastern Arc Mountains (Callulina cf
kreffti) while one primate species (Galagoides zanzibaricus) is near-endemic to the
Eastern Arc Mountains and is also listed as Vulnerable to extinction by IUCN.
According to local residents, wildlife inside the project area boundaries is dominated
by common species (e.g., baboons, wild pigs, and birds).
5.3.3    Protected Areas
The only protected area or nature reserve within the immediate vicinity of the project
area is the Mkindo Forest Reserve, which lies approximately 2 km northwest of
project area’s northern boundary. The boundary of the gazetted (in 2007) Wami-
Mbiki Wildlife Management Area lies 25-30 kilometers to the east of the project.
The Mkindo Forest Reserve Mkindo is categorized as a National Protection Forest
Reserves. As such it is reserved for the protection of watersheds, soil conservation
and wild plants. It covers an area of 5,244 ha in the Nguru South Mountains, part of
the Eastern Arc Mountains, and it is the source of the Mkindo River. The Forest
Reserve is under a low level of pressure from illegal cutting of poles and timber.
Other types of disturbance are grazing, charcoal burning, mining, cultivation and
paths. Of these, grazing is of greatest concern. Cattle are brought into the reserve
during the dry season. Grazing is also linked to forest fires.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          5-14
5.4.1    Administrative Boundaries
The Mgongola project area geographically belongs to Hembeti Ward which
comprises eight villages. Out of the eight villages only three, namely Mkindo,
Dihombo and Hembeti, will be direct beneficiaries of the project as they own plots in
the project area. The residents of the Kambala village, however, will be directly
impacted, as many of them are pastoralists and graze their cattle in the project area
during the dry season.
5.4.2    Demographic Characteristics
From the results of the Tanzania Population and Housing Census carried out in
2012, the population of the Hembeti Ward was 21,057, out of which 10, 311 were
males and 10,746 were females. The average household size for the ward was 4.3.
The JICA feasibility study (JICA 1998), drawing upon 1996 data, reported the
population in the three villages most impacted by the project (Mkindo, Dihombo and
Hembeti) as 8,470, with Mkindo Village having the largest population of 4,220. The
average household size in these villages in 1996 was 5.0. Fifty-three percent of the
population in the villages was under the age of 15.
A more recent study by the AgWater Solutions Project (Keraita et al. 2012) found that
rain-fed farmers in Mkindo were typically married with an a primary-level education
and an average household of 7.2 family members, as compared to 5.5 for irrigators.
For both groups the average number of household members who contribute to
farming activities is 3.
Kambala is another village potentially impacted by the project. It is located 16 km
south of the project area, but the residents of the village graze their cattle in the
project area during dry season. It has an estimated population of 2,800 (Mung’ong’o
2003). No information is available on how many of those individuals graze their
cattle in the Mgongola project area during the dry season.
An estimated 725 farmers are currently farming in the Mgongola project area.
Assuming an average household size of 7.2 (Keraita et al. 2012), this means that the
project could directly impact 5,220 individuals.
The situation of housing in the study area exhibits typical semi-urban and rural
setting. About 58% of houses in the villages are semi-permanent constructed by
poles and mud with galvanized sheets, while the remained 42% comprises of houses
made of cement bricks, with cement floor, plaster and roofed with iron sheets.
5.4.3    Land Use
The greater part of the Mvomero district is cultivated and the remaining parts are
protected areas (forests, game reserves etc.). Some areas in the district are left
uncultivated because they are on very steep slopes and some are constantly flooded.
The Department of Agriculture of the Mvomero District Council estimated in 2011 that
the Mgongola area had 2,720 ha suitable for irrigation. Of that, only 110 ha in the
Mkindo schemes are being irrigated.
Livestock grazing is also practiced in the district in wooded and open grasslands, as
well as on cultivated land during the dry season. Land is more intensively used in the
low lands and Mngeta slopes.
As can be seen in Figure 5.8, the entire area inside the project boundaries is
currently used for rain-fed rice production. All of the area is cultivated, with only a
scattering of trees (often only individual trees) on the borders of fields (Figure 5.7).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            5-15
During the dry season, much of the area is used for grazing cattle, owned by the
farmers themselves, or by pastoralists from Kambala village. The Kambala cattle are
grazed on communal village land from January to June, but a majority of the animals
are moved to other areas, such as the project area, from July to December. There is
an unwritten “agreement” between livestock keepers and farmers that once the
farmers have harvested their crops, livestock keepers gain access to grazing in the
farms. In recent years, however, that informal arrangement has deteriorated,
causing some conflicts between farmers and cattle herders. Some residents
indicated that there was no charge for the use of the land, but others indicated that
pastoralists paid farmers for the use of the land.
5.4.4    Land Ownership and Tenure
The tenure system in the study area is generally based on traditional inheritance,
land allocation by village council, land purchasing, and land borrowing or renting.
The most common tenure regime in the scheme is the one based on “customary
tenure” where land rights are transferred according to an ancestral tenure of land
and/or the traditional inheritance accepted by the village council. The 1998 JICA
study team estimated that the average landholding size per farm household for
Mgongola is 1.62 ha (rain-fed plus irrigated areas). The average plot size in the
project area is 0.9 ha/household.
The AgWater Solutions Project study (Keraita et al. 2012) found average plot sizes in
the Mkindo rain-fed area to be 1.1 ha. It also found that most of the farmers in the
Mkindo irrigation schemes also had rain-fed plots outside of the schemes. Many of
these may be in the Mgongola project area, as it abuts to the Mkindo schemes.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            5-16
      Figure 5.8:   Land Use in the Project Area
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME         5-17
5.4.5    Economic Activities
Household interviews indicated that agriculture is the primary occupation of 99% of
the households in the villages near the project area. These households reported that
97% of their income is from agricultural production. Even for the households with
other sources of income agriculture contributed more than half of their income and
expenditure.
The residents of Mkindo, Dihombo and Hembeti villages are generally farmers. The
residents of Kambala village are generally pastoralists.
Most farmers grow rice for subsistence as well as for sale in the market. On
average, the rain-fed farmers in the region consume 60% of the rice they grow. In
addition to rice, rain-fed farmers may grow food crops such as groundnuts, beans,
cocoyam, cassava, vegetables and maize. All these are produced in the wetland
areas along the rivers. They may also have small gardens near their houses and
fruit trees scattered around the villages.
Rice is the staple food crop. Because of topographic differences, which create
different crop suitability in the watershed, most farmers have some rice fields in the
lower lying areas and some fields for maize in the higher lying areas. This is a risk
mitigating strategy. When there is too much rain in one period and little drainage,
rice will be affected negatively because the water level will be too high but the maize
crop on the higher lying land will do better. When it is too dry the water accumulates
in the lower lying areas making a harvest of rice possible, but making maize harvest
lower (de Bruin et al. 2012).
The rains in 2008 were very low and rice was generally not harvested by the farmers
in the project area (de Bruin et al. 2012).
Part of the livelihood strategy of rain-fed farmers is livestock keeping. All of them
keep a small number of animals. The animals graze along the roads and on the
fringes of the forest. Goats graze along the roads close to the villages. Dairy cattle
are kept next to the house. During the dry season they may graze in the fallow rice
fields.
As mentioned in Subsection 5.4.3, rain-fed farmers may also lease their rice fields to
those mainly dependent on keeping livestock. The land is let for 3 to 4 months
during the dry season and will again be used for crops during the wet season.
However, some respondents indicated that the herders did not pay the farmers for
the use of their land. As a result, there has been conflict between farmers and
herders.
Predominantly crop production in the area is done by family labor, although
seasonally hired laborers may be used for land preparation, transplanting and
harvesting. Women, as well as men, participate in farming. Women are involved in
all aspects of farming except for the heavy work during harvesting and the selling of
products. These activities are still largely carried out by men.
There is no industry in any of the villages, although there are some grain storage
facilities and rice and maize milling facilities. Other off-farm income sources include
micro- and small-enterprises; petty business; small-scale workshops; limited salaried
positions; raising poultry, pigs and/or goats for sale; and hiring out as day labors to
third parties.
Micro- and small-scale enterprises includes retail shops, small restaurants, petty
trade and selling of local brew. Several retail shops situated in village centers stock
a wide range of goods including foodstuffs, household utensils, school supplies,
textiles and spare parts for bicycles. Construction materials such as corrugated iron
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          5-18
sheets and cement are also stocked by some shops in the area. Shops adopt
various techniques to keep the operation costs low. For example, shops are often
located in one of the rooms within a home, and usually attended and managed by
members of the household. Procurement of goods to be sold in shops is generally
done in bulk to optimize transport costs, but sometimes household members procure
and transport small amounts of goods using motorcycles or public transport.
There are few small restaurants and numerous food vendors in the study area. The
restaurants serve soft drinks, tea, snacks and meals, basically to external visitors and
limited number of village residents. During the peak of the agricultural season, the
restaurant operators withdraw temporarily from their restaurant activities to attend
agriculture. Food vending, snacks and evening coffee/tea selling are also very much
affected during this time because the desirable customers migrate to temporary
camps in the farm plots. Selling of beer and local brew, locally known as komoni, is
common in village centers where people meet in the evening for refreshment.
Petty trade includes selling a range of products in small quantities in homes, at the
local market, or along the streets. The food products sold include maize and
cassava flour, vegetables, dry cassava, fresh and dried fish, fruits, and bananas.
Other products sold by petty traders include household utensils and textiles, and
clothing, mainly second hand clothes.
Small-scale workshops refer to tailoring, carpentry, bicycle repair and blacksmiths.
Tailors are mostly called upon to mend clothing. According to the respondents,
tailoring is not a lucrative business and the operators are busy only when pupils are
beginning a new school year and when religious ceremonies are held, especially if
they fall in the crop-marketing season.
Carpentry workshops are mainly involved in production of furniture (beds, chairs,
drawers, tables) as well as doors and windows. Furniture most often made on order
from within the villages or in nearby villages. Most of the timbers used by the
carpenters in the village are obtained within the district.
Blacksmith deal with repairing and welding of tools such as metal kitchen appliances,
hoes, knives, and machetes brought to them by owners. In some cases they use
scrap metal to manufacture tools for sale.
Bicycle repairing is a lucrative income earning activity. According to the obtained
information almost all the people who own bicycles have basic knowledge in repair,
but there about five artisans repairing and selling minor bicycle parts. Major bicycle
parts are commonly available in retail shops in the village and sometimes are
purchased from Morogoro town.
Prominent occupations recognized for salaried employment are found in the sectors
of education, home affairs and local government. These sectors employ teachers,
police, village executive officers, ward executive officers and medical personnel. The
study noted that most of the employees originate from within Mvomero district.
5.4.6    Income and Expenditure
The average income in Mvomero District is estimated at Tshs. 450,000 (2010)
income per capita. This includes the value of cash and in-kind production and
transfer payments (District Profile, 2011).
During the interviews with residents in the project area, they were reluctant to reveal
information on incomes to strangers. The majority of villagers who were willing to
talk about income showed strong uncertainty in estimating their incomes and
expenditure, even those referring to short duration of time such as a day or two.
They did indicate, however, that incomes and expenditure vary strongly with
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          5-19
seasons, with harvest season being the greatest time of both income and
expenditures.
The economy in the project area is basically subsistent, with the households failing to
demarcate between amounts of food that come from their own production and that
from the market. Several transactions and transfers, including remittances from
relatives living in other villages or cities, are in-kind rather than cash. Villages are not
able to determine precisely the monetary value of such incomes and expenses.
5.4.7    Water, Sanitation and Solid Waste Disposal
All of the villages in the project area take domestic water from the rivers near the
villages (Mkindo Village from Mkindo River, Dihombo Village from Dizingwa River,
and Hembeti Village from Mgongola River). None of the villages have village-wide
piped water. None of the villages have village sewer systems.
The most commonly used excreta facilities in the project area are pit latrines. More
than 80% of pit latrines in the study area are of poor quality.
There are no sanitary facilities in the fields where people spend more than 5 months
farming, weeding and harvesting. During farming activities people defecate outdoors
in their fields or nearby bushes.
There is no sanitary landfill in or near the project area for disposing of solid waste.
None of the villages have solid waste collection systems. Some individuals dispose
of solid waste in pits (15%), but the majority (82%) use plots/farms as a dumping site.
5.4.8    Health
As summarized by the 1998 JICA study, health service facilities in the Mgongola area
fall short of WHO-recommended minimum requirements. In the district there is one
hospital (Bwagala in Turiani) and a few health centers and dispensaries. Mkindo and
Hembeti villages have dispensaries, but Dihombo village does not.
Malaria has the highest incidence of disease in the district, accounting for 50% of all
reported disease cases. Another 10% of reported disease cases are associated with
other water-borne diseases, including intestinal diseases and diarrhoea diseases.
JICA 1998 found that the rate for schistosomiasis (bilharzia) was 2.5%. Acute
respiratory infections and pneumonia account for another 26% of total reported
disease cases.
5.4.9    Energy
There are different kinds of energy, which are used by people of Mvomero district.
These include electricity, fuel wood, kerosene, solar and bio-gas. Fuel wood and
charcoal is the dominant energy source for the majority of people in Mvomero district
and the study area in particular for household cooking and other domestic purposes.
Electrical power is also available to three of the villages (Hembeti, Mkindo and
Dihombo) from the national grid through the national service provider, the Tanzania
Electric Supply Company, although very few people have managed to connect. JICA
1998 reported that only 20 houses in Mkindo, 10 in Hembeti and 3 in Dihombo had
electrical connections. This situation has undoubtedly improved, but still electrical
power is the exception rather than the rule in the project area.
Kambala has no access to electrical power.
5.4.10   Transport and Communication
The three villages (Hembeti, Mkindo and Dihombo) in the project area are connected
via a main road (B-127) to the trunk road from Morogoro to Dodoma, which is the
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              5-20
main means of transport in and out of the district. The village of Kambala is served
only by a road that is accessible only during the dry season. In the project area there
are farm access roads which facilitate transportation of farming inputs and outputs to
and from the trunk road. However during rainy seasons these farm access roads are
not passable.
Telecommunication networks are available in the project area. Many companies are
operating in the area and in the district in general, including Tanzania Telephone &
Communication Limited, Vodacom, Airtel, Tigo, and Zantel. Radio and television are
also available, including Radio Abood, Tanzania Broadcasting Corporation, Radio
One, Independent Television of Tanzania and Channel 10.
5.4.11   Vulnerable Groups
Women in Mvomero District have the primary responsibility for agriculture, small
business, and household activities. Despite these responsibilities, their participation
in decision-making is limited, even though they occupy about 30% of seats in the
village councils. The presence of women in leadership roles in the villages is limited
due to large families without financial resources coupled with some passive
traditional cultural and religious beliefs discriminating against women, giving them
limited access to household money and other resources, even though they are the
primary providers.
Married women in the village surveyed lack access to and control over available
resources. For example, although women are responsible for agricultural production,
men are generally the legal owners of the land and can block women from carrying
out their work. Livestock is another example. Men are responsible for all decisions
regarding animals, including when to buy and sell the livestock. About 80% of
women interviewed reported men as the sole decision-maker in financial matters.
The remaining reported both husband and wife make decisions together.
5.4.12   Capacity of the WUA
The WUA that will manage the new irrigation scheme has yet to become operational,
but there is a WUA in existence that manages the Mkindo I and Mkindo II irrigation
schemes. That WUA will disband once the new irrigation system is operational and
its members will become members of the new WUA that will manage Mgongola
irrigation scheme as well as the Mkindo irrigation schemes. So although the new
WUA is not operational, it will have up to 100 members with experience in managing
a WUA.
The existing Mkindo WUA was organized in 1984 by the farmers in Mkindo I as the
Mkindo Farmers Irrigation Agricultural Marketing Primary Cooperative Society Ltd. In
1986, the farmers in Mkindo II joined the WUA. By 1997, it had 97 members. In
1997 the WUA registered with the Ministry of Agriculture and Cooperatives (the
predecessor of the MAFC). The WUA has written and approved by-laws and is
managed by a 10-member Executive Committee composed of the Chairman, Vice-
Chairman, Secretary, Treasurer and six at-large members, elected by the
membership. The WUA collects annual fees from its members. (JICA 1998)
Two times per year, about 1.5 months before planting, the WUA holds a general
meeting for all of its members, chaired by the village agricultural extension officer. At
the meeting decisions are made concerning planting schedule, irrigation
commencement and termination dates, and maintenance activities. The
maintenance activities are undertaken by the members as communal works, usually
for a period of one week each. The WUA uses a penalty structure, whereby
members that do not participate in the maintenance communal works are fined.
(JICA 1998)
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           5-21
The Mkindo Farmers Training Centre is located in Mkindo village. Here farmers can
receive training on new farming techniques. The Centre has provided training to
farmers on new and more efficient techniques for rice production. For some this has
increased their production, for others there is still more to learn. The government has
extension officers to disseminate knowledge and advice throughout the rural areas.
However the extension officers lack the means of travelling through the area. This
makes it difficult for farmers to get the advice they need when they need it. There
are many extension officers but the lack of transport facilities means extension is not
carried out to its full potential. (de Bruin et al. 2012)
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         5-22
6           ENVIRONMENTAL CONSEQUENCES
As required by 22 CFR 216.6, this section provides the analytic basis for the
comparison of consequences presented in Section 4.9 of this EA. It describes the
environmental and social impacts of the Proposed Action and its alternatives,
including the No Action alternative.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                               6-1
 Table 6.1: Potentially Significant Impacts Identified in the Scoping
            Statement
                                                  Non-Significant Issues that Should Have
       Potentially Significant Impact
                                                        Mitigation Measures in the EA
 During Mobilization and Construction (Irrigation Alternatives)
 Negative Impacts:
  Soil salinity (Sprinkler Irrigation)
  Effects of pesticide and fertilizer use
  Water contamination
  Water quantity impacts on downstream
   users and ecosystems (Irrigation
   Alternatives)
  Effects on aquatic species
  Land use conflict – cultivation/grazing
  Scheme management capacity (Irrigation
   Alternatives)
  WRBWO capacity to control water
   abstractions (Irrigation Alternatives)
  Change of community lifestyle
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              6-2
are likely to be washed away during the rainy season and also in dry conditions
through wind erosion. If cut and fill sites are not protected, loose soils can equally be
washed away into the canals and later into the Mkindo, Mgongola and Dizingwa
rivers. The risk of soil erosion is considered high, particularly during high and intense
rainfall, given the proximity of the rivers, the scale of the earthworks and the
characteristics of the overburden in the area which is easily erodible.
Soil Pollution
Vehicles and equipment used during construction may impact the soil with oil and
fuel spills. Trucks hauling construction materials such as aggregates, sand and
gravel and equipment being move to and from a work site may pass through
agricultural fields and impact agricultural soil with oil and fuel spills. In addition,
areas where fuels, lubricants and chemicals are stored or where vehicles and
equipment are fueled or serviced can be sources of hazardous substance releases to
the soil. Improper disposal of concrete wastes resulting from on-site concrete
batching or cleaning of ready-mix concrete vehicles can also contaminate soil.
Loss of Top Soil
Construction of irrigation and drainage structures will require fill material. As
mentioned in Sections 4.1.1.1 and 4.1.2.5, fill material will generally be taken from
drain excavations or off-site locations. During the construction of secondary and
tertiary canals, however, some fill material may be taken from adjacent fields,
particularly if the field is in need of land levelling. In these cases, the potential exists
for the destruction of top soil.
Water Contamination
If erosion occurs and/or soil is polluted, as discussed above, it is possible that the
Dizingwa, Mkindo and Mgongola rivers may be impacted with sediment,
leaked/spilled lubricants, fuels and hazardous substances. Other sources of
potential water pollution are:
          Washing vehicles or equipment in or nearby the river;
          Improper disposal of concrete wastes resulting from on-site concrete
           batching or cleaning of ready-mix concrete vehicles;
          Surface run-off from on-site stockpiled sand and gravel; and
          Inadequate disposal of solid wastes and wastewater generated during
           construction from workers.
Solid Waste Generation
Solid waste will be generated from site vegetation clearance and during construction.
The vegetation and other rubbish that will be cleared from the site will lead to the
generation of large volumes of waste that require proper disposal.
Various wastes generated during construction will need to be managed and disposed
of properly. These will include solid waste from packaging materials, wood and steel
crates, cardboard, wrapping materials, boxes, sacks, drums, cans and chemical
containers and any other unused materials. Workers will also generate domestic
solid waste.
Dust and Air Pollution
The vehicles and machines used in the construction of civil works will produce
exhaust smoke, fumes and dust that may be unpleasant to the surrounding
communities.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                6-3
Noise Pollution
The vehicles and machines used in the civil works will produce noise that may be
unpleasant to communities who live near the project area.
Biological Environment
Effects on Aquatic Species
As for the aquatic organisms, the only animals that could be impacted by the project
activities include fish and amphibians due to siltation of the rivers (which could clog
their breathing apparatus) and pollution from leaked/spilled lubricants, fuels and
hazardous substances. Vegetative removal and soil excavation could lead to
siltation of the rivers during the rainy season.
Socio-Economic Environment
Displacement of Economic Activities
Construction activities can disrupt current farming practices the project area.
Building the main canal and flood control structures will disrupt the flood flows into
the area, on which the farmers rely for creating ponding for their rice fields.
Disturbance of Graves
During scoping some participants expressed concerns that graves in the project area
could be disturbed during construction. IRRIP1 determined that there were no
marked graves in the project area, but there may be unmarked graves that could be
encountered during construction activities.
Worker/Community Health and Safety Impacts
Workers at the site will be exposed to several safety hazards, including open
trenches, openly stored or moving construction materials, and moving construction
equipment.
Workers’ camps may be a source of social unrest and environmental problems such
as transmission and spread of diseases (e.g. HIV/AIDs, sexually transmitted
infections (STIs) or sexually transmitted diseases (STDs)) to the resident community
by the project personnel and vice versa.
Also, construction sites can be dangerous places for the safety of residents of nearby
communities. These residents may not be aware of the hazards and they may
simply be interested in observing the equipment and activities. Children are often
eager to see construction equipment at work. Such children’s curiosity may lead to
safety hazards ranging from minor to major injuries such as bruises and fractures.
Change of Community Lifestyle
The construction of the Mgongola irrigation scheme will have an impact on the day-
to-day lives of the Mkindo and Dihombo villages. An influx of workers to the area will
bring increased economic activity, with and associated positive impact. But the
workers may also bring with them behaviors which disrupt the community and puts
them and the community at increased risk for HIV/AIDS.
6.2.2    Impacts During Operation
6.2.2.1 Positive Impacts
Reliable Supply of Water
Construction of the Mgongola irrigation scheme will help to ensure a reliable supply
of water to irrigate the 589-ha area. Currently the farmers are reliant upon flood
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                               6-4
water and rain to produce their crops. The timing and quantity of water delivered via
flooding and rainfall is unpredictable. Climate change is projected to increase the
unreliability of these sources of water by increasing uncertainty of the onset of rainfall
and its regularity (iWASH 2013b). Thus farmers will be facing increasing uncertainty
regarding water availability.
The irrigation works will include provision for flow measurement in the main and
secondary canals. It will also include controls (e.g., gates) in the canal system.
These will enable the discharge into the system to be regulated and the water
delivered to each secondary canal to be monitored and controlled thus improving
overall conveyance effectiveness and water use efficiency.
Increased Rice Production
The literature and experience in Africa and around the world has shown that irrigated
paddy rice produces yields 2 to 3 times higher than rain-fed paddy rice production
(Nguyen 2010, MoFA 2009, and Eklou et al. 2008). This is due to the ability to
manage water, a critical factor in rice production.
In the Mgongola area irrigated paddy rice is currently producing 2-3 times the mt/ha
per harvest as rain-fed paddy rice production (de Bruin et al. 2012, Keraita et al.
2012). As noted in Section 3.4.3, current rain-fed paddy rice production in the
project area is reported to be 1.6 to 3.0 mt/ha (JICA 1998, Keraita et al. 2012). In
comparison, the same studies reported rice production on the nearby Mkindo
irrigation schemes to be from 3.8 to 6.0 mt/ha during the rainy season.
At the time of the JICA study, 22% of the farmers in the irrigated area were
participating in a Food and Agriculture Organization (FAO) program that provided
improved seed and fertilizer inputs. The farmers in the FAO program realized an
average yield 5.2 mt/ha (JICA 1998, Table 1.3.2). The other farmers in the irrigated
schemes, using seed and input practices similar to those used by the rain-fed
farmers, realized an average yield of 3.4 mt/ha.
Keraita et al. (2012) found that irrigation doubled the yield per hectare. The JICA
study also found that farmers in the Mkindo irrigation schemes using traditional seed
and inputs had slightly more than double the yield of farmers in the project area
growing rain-fed paddy rice with traditional seed and inputs (3.4 vs. 1.6 mt/ha). So it
is reasonable to assume that irrigation alone can be expected to double rice yields.
This is due to improved ability to manage water inputs via irrigation.
If in addition to irrigation farmers adopt improved practices such as planting improved
seed and using fertilizer and herbicides (when necessary), their yields could increase
even more. The JICA study found that adopting such practices could improve yield
by an additional 53% (from 3.4 to 5.2 mt/ha).
For the comparative purposes, this EA has chosen to use the JICA rain-fed yield of
1.6 mt/ha as a baseline, No Action yield. This is based on the fact that the data for
Keraita (2012) was collected in 2009 and 2010, years in which yields in the area
were generally higher than usual. Yield for irrigation alone is assumed to double to
3.2 mt/ha and the yield from irrigation plus improved cultivation practices is assume
to increase by another 53% to 4.9 mt/ha.
Proponents of SRI have claimed 2-3 time increases in yield (SRI-RICE 2014).
Several academic studies, however, have indicated that these increases are not
significantly different from those that may be gained from paddy rice irrigation using
conventional best management practices (Bouman et al. 2007, McDonald et al.
2006). For the purposes of comparison, therefore, this EA has assumed that rice
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                             6-5
production with SRI would be equivalent to that for irrigation with improved cultivation
practices, 4.9 mt/ha.
In summary, the potential increases in rice production associated with the irrigation
alternatives are as follows:
          Proposed Action, Piped Canal and Sprinkler Irrigation
            o Irrigation alone: 3.2 mt/ha
            o Irrigation and Improved Cultivation: 4.9 mt/ha
          SRI: 4.9 mt/ha
Increased rice production will lead to increased income for the farmers. Keraita
(2012) found that average income from farming in households that farmed in the
Mkindo irrigation schemes was $3.62 per day, as compared to $1.61 per day for
households that only practiced rain-fed paddy rice farming. Similar results have been
seen in other areas of Tanzania (Keraita 2012).
Opportunities for Employment
Long-term jobs will be created by the project in the form of employment at the WUA
and potentially employment of wage laborers. The WUA will have full-time paid
positions for a manager and possibly technical personnel. Doubling or even tripling
rice production in the irrigated area may create opportunities for wage labor during
cultivation and harvest. Generally such increased labor needs will be provided by
family members, but in peak periods at least some farmers may hire wage laborers.
The income from these employment opportunities will multiply through the villages as
the new wage earners spend their wages.
With increased production and employment opportunities, the standard of living in the
surrounding villages will improve and with improving social services, more people will
be attracted to stay in the village, especially youth. As such, construction of the
Mgongola irrigation scheme will complement the government’s efforts to improve the
standard of living, poverty alleviation and food security at household level. The
increase in income will lead to construction of improved houses with good sanitary
services which may reduce water-borne diseases.
Through observation during site visits in the communities, it was apparent that rice
farming has a positive development in house construction. Many people with poor
houses are either renovating or constructing new and modern houses. Some of
them revealed that after harvest, different economic activities including petty trading,
building houses, and buying motorcycles are carried out in the village
Improvement of Market Outlets
Improvement of farm access roads so that they will be passable in the rainy season
will allow farmers to more easily transport their harvest from the field to the market
and deliver inputs to the fields (seed, workers and equipment).
Reduced Flooding
Flooding was identified in the Scoping Statement as a significant negative impact of
the current situation. Although flood water is necessary for rain-fed paddy rice
production, too much flooding or flooding coming at the wrong time in the growing
cycle can harm or destroy a crop. The perimeter flood protection embankment will
eliminate flooding of fields during flood events, thus avoiding the negative impacts of
flooding.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              6-6
Reduced Water Logging
Currently many fields in the project area are unlevelled and have no or insufficient
drains. This has resulted in water logging in some places in the project area, causing
reductions in crop yields. The project will build secondary drains and train the
farmers in construction of tertiary drains serving their plots. In addition, farmers
participating in the project will receive training on field levelling. As farmers practice
what they learn in these training sessions, they will improve overall drainage from
their plots and reduce or eliminate places in their fields that have poor drainage. This
will reduce or eliminate the current water logging problems.
6.2.2.2 Negative Impacts
Physical Environment
Soil Salinity
Soil salinity was identified in the Scoping Statement as a potentially significant impact
of the project. Upon further evaluation, however, increased soil salinity will not be an
impact of Proposed Action and all of the flood irrigation alternatives. Generally paddy
rice irrigation does not tend to create soil salinity, as sufficient water is applied to
wash salts below the root zone. The most common practice for addressing soil
salinity in irrigated fields is to leach accumulated salts below the root zone by
applying excess water. In paddy rice production, excess water is regularly applied as
part of the irrigation regime to meet the needs of the plants and control weed growth.
Even with SRI methods, there are extended periods when water is ponded on the
field, thus providing for leaching of any salts below the root zone. So accumulations
of salts in the soil will not be an impact.
With the Sprinkler Irrigation alternative, however, if farmers adopt sprinkling they
could encounter salinity problems overtime. This will be due to the fact that they will
no longer be applying water in quantities that will move the salts below the root zone,
allowing salts in the irrigation water to become concentrated in the root zone. This
could, however, take a considerable time to develop, as the irrigation water from the
Mkindo River is not particularly high in salts.
Effects of Pesticides and Fertilizer Use and Water Contamination
The construction of the Mgongola irrigation scheme, to be conducted by IRRIP1, will
not involve the procurement, promotion or use of pesticides. Currently the Mgongola
farmers do not use pesticides and fertilizers in their fields; however, they may choose
to do so in the future to increase agricultural production. Such practices are common
on the nearby Mkindo I and II irrigated areas. This could increase the use of
pesticides and fertilizers, which may lead to:
          Increased nutrients such as nitrogen and phosphorus, entering the rivers;
           and
          Increased exposure by humans and the environment to toxic pesticides.
Nutrient increase in the rivers can damage the ecosystems. Nitrates and phosphates
may stimulate rapid growth of aquatic vegetation and algae blooms. Rapid growth of
aquatic vegetation may deplete oxygen and result in the death of fish and other
aquatic life. Fortunately, there is no evidence of rapid growth of aquatic vegetation or
fish kills downstream from the project area. But, neither is there any water quality
monitoring data from the same area, nor a systematic program for collecting that data
in the future, so it is difficult to fully assess this impact.
IRRIP1 does not have a Pesticide Evaluation Report and Safer Use Action Plan
(PERSUAP) as it does not work directly with farmers on farming practices. NAFAKA,
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                             6-7
however, does have a PERSUAP. Any work with the WUA farmers on improving
farming practices under the FTF program will be carried out by NAFAKA, under the
conditions of its PERSUAP.
The only pesticides reportedly used in the area are 2,4-D to kill weeds, and Selecron
(profenofos) and Karate (lambdacyhalothrinto) to combat insect pests. 2,4-D is in the
list of herbicides that are Accepted/Approved by the NAFAKA PERSUAP.
Profenofos and lambdacyhalothrinto are not on the list. Lambdacyhalothrinto was
specifically evaluated and excluded from the Accepted/Approved list. Profenofos
was not evaluated.
If farmers adopt sprinkling under the Sprinkler Irrigation alternative the amount of
water draining off the fields would be reduced or eliminated, thus reducing or
removing the pathway for these contaminants to flow into the Mgongola River. Thus,
the potential for water contamination from pesticides and fertilizer use will be less for
the Sprinkler Irrigation alternative than for the other irrigation alternatives.
SRI promotes the use of organic fertilizers and hand weeding. This could reduce the
amount of herbicides used by farmers. As organic fertilizer tends to have lower
concentrations of nitrogen and phosphorus, the adoption of SRI could also reduce
the amount of nitrogen and phosphorus available to runoff from the fields. Thus, the
potential for water contamination from pesticides and fertilizer use will be less for the
SRI alternative than for the other flood irrigation alternatives.
Water Quantity Impacts on Downstream Users and Ecosystems
The most significant potential negative impact of the project is its impacts on
environmental flows in the Wami River downstream of the project area. To
understand the potential impacts of the Proposed Action and its alternatives on
environmental flow, IRRIP1 assessed the flow requirements of the project in light of
the results of the EFA for the Wami River (Sarmett et al. 2008 and iWASH 2013a,
collectively referred to as the EFA). The IRRIP1 assessment of the Mgongola
irrigation scheme’s relationship with the EFA is included as Annex D. The area for
the analysis is hydrologically bounded by the Dakawa gauge (1G1) upstream and the
Mtibwa EFA site (see Figure 5.6) downstream.
In order to fully assess whether the irrigation scheme would reduce flows to below
the recommended EFA flows, IRRIP analyzed the impact of the project abstractions
on the recommended average discharge (RAD) values at the Mtibwa EFA site (see
Figure 5.6). The analysis was conducted using monthly data for the 5 months in the
rainy season when water is withdrawn for irrigation (mid-March through July). The
data was further restricted to the 1-in-5 low flow years, rather than average flows. So
4 years out of every 5 years the flows would be expected to be greater than those
used in the analysis.
To assess the impact of the abstraction for the Mgongola irrigation scheme on the
Mtibwa EFA site a number of factors need to be considered, including:
          Flow on the main Wami River at the Dakawa gauging station (1G1) (see
           Figure 5.1);
          Flow on the Diwale River captured predominantly by gauges 1GB1A on
           the Diwale River and 1GB2 on the Mkindo River, a tributary of the Diwale
           River (see Figure 5.1);
          Abstraction rates for the Dakawa irrigation scheme;
          Abstraction rates for the existing Mkindo irrigation scheme;
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            6-8
             Abstraction rates for the proposed Mgongola irrigation scheme;
             Abstraction rates for the Mtibwa Sugar Estate;
             Abstraction rates for the Dizungu Sugar Estate; and
             RAD values for the Mtibwa EFA site.
Figure 6.1 shows the schematic location and relationship of these factors. An input-
output methodology was used to analyze the data where the inputs were the flows at
the gauging stations and the outputs were the abstractions. The flows minus the
abstractions can then be compared to the RAD at the Mtibwa EFA site to determine
their impact.
Flows
Flow data on the Wami River is available for several years from the Dakawa gauge
(1G1). Sufficient flow data is available to calculate the statistical 1- in 5-year low
flows at the Dakawa gauge (CDM Smith 2013, Annex F).
The Diwale River flows into the Wami River between the Dakawa gauge and the
Mtibwa EFA site as do several small drainages from the south of the Wami River.
The Mkindo and Divue rivers are both perennial and flow into the Diwale River. The
Mkindo River is the major tributary of the Diwale River. The Mkindo River has two
tributaries that flow into the river below the Mkindo gauge, the perennial Dizingwi
River and the seasonal Mgongola River.
There are no gauges on Divue, Dizingwi and Mgongola rivers or any of the small
drainages that flow into the Wami River from the south between the Dakawa gauge
and the Mtibwa EFA site, so their flows are not captured in the following analysis.
Flow data on the Diwale River (1GB1A) is available for six years from 1965 to 1970.
Six years is not sufficient for detailed statistical analysis of flow data. Therefore, to
adopt a conservative approach, the lowest average flow during each half-month
period was calculated and the lowest average for the six years of data was extracted
from the record and used in this analysis.
For the Mkindo River (1GB2) flow data is available for six years: 1965 to 1969 and
2009/2010. A similar approach to that used for the Diwale River was applied for the
Mkindo River to estimate a dry year flow for each half month period during the
abstraction period.
Abstractions
The Mtibwa Sugar Estate, Dakawa irrigation scheme, Mkindo irrigation scheme and
Dizungu Sugar Estate abstract water in the area of interest upstream of the Mtibwa
EFA site. The Mtibwa Sugar Estate has two current water rights. One is for 1.5 m3/s
year-round from the Diwale River below the junction with the Mkindo River11. It uses
this water to irrigate 5,200 ha with sprinklers. The other water right is for 2.5 m3/s
year-round from the Wami River.12 It currently uses a portion of this water to irrigate
3,000 ha with sprinklers on the south side of the Wami River.
11   Water Right Registration Number 4501 of 1980 (WRBWO 2015). Provisional, renewable every three
     years.
12   Water Right Registration Number 4959 of 1990 (WRBWO 2015). Provisional, renewable every three
     years.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                      6-9
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME   6-10
 Figure 6.1:   Schematic Location and Relation of Factors for EFA Analysis on the Wami River at Mtibwa EFA Site
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                        6-11
Mtibwa Sugar Estate is developing 20,000 ha of new sugar fields on the south side of
the Wami River. By the end of 2016 it will add an additional 3,000 ha to the existing
3,000 ha in this area13. IRRIP estimates that by the end of 2016 the Estate will
consume all of its 2.5 m3/s water right on the Wami River for irrigation of these 6,000
ha.
To develop the remaining 14,000 ha of cultivation, the Mtibwa Sugar Estate has
applied for an additional 7.5 m3/s water right from the Wami River.14 The Estate says
it is in the final stages of receiving that right. The right will be restricted to the wet
season and the Estate plans to abstract from March through May or June.15 This
water will be used to fill two reservoirs with a total capacity of 70 million m3 from
which water will be withdrawn for irrigation during the dry season. The Estate is sure
enough that it will receive the 7.5 m3/s water right that it has invested a significant
amount of capital in the construction of a pump house with 6-pumps on the Wami
River.16 Although the Estate does not have a specific development plan, it is
reasonable to assume that sometime in the next 5 to 10 years it will be abstracting an
additional 7.5 m3/s from the Wami River from March through June, as it will take four
months to fill the reservoirs, if they are doing so at 7.5 m3/s.
The Dakawa irrigation scheme has a water right from the Wami River for 5.0 m3/s
from March through November.17 It currently abstracts 3.5 m3/s but is in the process
of rehabilitating its system and will soon be abstracting from 2.35 to 3.88 m3/s,
depending on the month, at a seasonal average rate of 3.22 m3/s (CDM Smith 2013).
The Mkindo irrigation scheme has a right of 0.624 m3/s (WRBWO 2015), but its
irrigation requirement for the 110 ha it currently irrigates is 0.22 m3/s. The proposed
Mgongola irrigation scheme will require an additional 1.18 m3/s. These abstractions
are based on the assumption of a 2 l/s/ha abstraction rate. If the proposed scheme
is constructed, the two schemes will be managed as one scheme, requiring a total
abstraction of 1.4 m3/s and requiring the current water right to be increased by 0.776
m3/s.
As shown in Figure 6.1, the intake site for the existing Mkindo irrigation scheme is
upstream of the Mkindo gauge (1GB2), which means that the gauge records flows
after the existing extraction. Therefore, abstraction information for the Mkindo
irrigation scheme is included in the analysis for information purposes only.
There is no data available on the abstraction for the Dizungu Sugar Estate, which is
an area of approximately 300 ha. It is reported that the Estate does irrigate with
surface water, but no information is available about the abstraction.
Analysis and Conclusions
Taking all of the above factors into consideration, input-output analysis was
conducted of the impact of the proposed Mgongola scheme on the Mtibwa EFA site
RAD. Table 6.2 presents the results of this analysis.
13   From Mtibwe Sugar Estate General Manager at a meeting at the Plantation with IRRIP and Mtibwa
     staff on January 27, 2015.
14   Ibid.
15   Ibid.
16   Observed by IRRIP on January 27, 2015.
17   Water Right Registration Number 4583 of 2007 (WRBWO 2015). Final (permanent).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                      6-12
Table 6.2: Low-Flow Year Residual Flows and Recommended Average Discharge (RAD) at the Mtibwa EFA Site (m3/s)
                         (a)           (b)           (c)             (d)               (e)               (f)              (g)             (h)                         (j)
                                                                                                                                     (a+b+c-e-f-g)                   (h-i)
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                               6-13
As can be seen in Table 6.2 construction of the proposed Mgongola irrigation
scheme will cause the downstream flows to drop below the flow of water that the EFA
has established as being necessary to meet the ecological, geomorphological, and
human domestic requirements (the RAD) during two periods (2nd periods of March
and June).
To test the viability of other irrigation alternatives, the same analysis was conducted
using the irrigation alternative with the least water requirement, the sprinkling
alternative. Assuming that the sprinkling alternative was fully implemented on the
entire 589 ha area, the additional water requirement would be reduced from 1.18 to
0.86 m3/s. The results of this analysis showed the residual flows at the Mtibwa EFA
site would still be lower than the RAD in the 2nd periods of March and June.
This analysis does not include flows from Divue, Dizingwi and Mgongola rivers or any
of the small drainages that flow into the Wami River from the south between the
Dakawa gauge and the Mtibwa EFA site. No data is available for these water
sources. However, it is unlikely that these flows would offset the RAD deficits as
these rivers are minor (and at least in one case intermittent) and they would have to
have a combined flow equal to the gauged flow in the Mkindo River in the 2nd period
of June, and 18% greater than the combined gauged flow of the Diwale and Mkindo
rivers in the 2nd period of March. Neither of these are reasonable assumptions.
In summary, all of the irrigation alternatives will result in significant, immitigable
impacts on downstream water users, both human and ecological. The driving force
behind this outcome is the planned future water consumption needs of the Mtibwa
Sugar Estate. Short of reducing the water rights for the Estate, these impacts cannot
be mitigated. Reducing the rights is unlikely considering the substantial capital
investments the Estate has made and plans to make to use those rights, and the
apparent inability of the WRBWO to allocate rights based on the EFA, in spite of their
stated intention to do so (WRBWO 2015).
Biological Environment
Due to the fact that the project area for the Mgongola irrigation scheme is and will
continue to be a severely human altered landscape, it has very little area that even
approach natural ecosystems within its boundaries. Except for the possible impacts
on the aquatic environment in the rivers, downstream of the project area (discussed
below), there will be no impacts from project operation on the biological environment
outside the boundaries of the irrigation scheme.
Effects on Aquatic Species
Aquatic flora and fauna in the Mgongola, Mkindo and Diwale rivers downstream of
the drainage discharges into the Mgongola River could be impacted by project
operation if water contamination by fertilizers and pesticides become a problem. As
was the case for the potential water quality impacts from fertilizers and pesticides, if
farmers adopt sprinkling under the Sprinkler Irrigation alternative or the SRI
alternative, the potential impacts on aquatic fauna in the rivers would be less than
those of the Proposed Action and the other irrigation alternatives.
Socio-Economic Environment
Land Use Conflicts
As reported in Sections 5.4.2 and 5.4.3, pastoralists from the Kambala village bring
their cattle to the banks of the Mgongola, Dizingwa and Mkindo rivers during the dry
season to gain access to water and to graze their cattle on fallow, rain-fed farmland,
including that in the Mgongola project area. The grazing is primarily done via an
informal agreement, although some farmers may be receiving payment from
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           6-14
pastoralists for use of their land. Whatever the arrangement is, it has deteriorated in
recent years, causing some conflicts between farmers and cattle herders, even to the
point of violence (de Bruin et al. 2012).
This conflict is likely to increase if the Mgongola irrigation scheme is constructed, as
it is most likely that grazing in the dry season by non-members of the WUA will be
prohibited. Grazing cattle can trample the irrigation infrastructure such as canals and
bunds and disrupt field leveling. If the cattle are owned by the farmers, then they
have an incentive to manage them so as not to trample the infrastructure. But if the
cattle are owned by others, no such incentive exists. The nearby Dakawa Rice Farm
tried to manage grazing by non-member herders, but after several unsuccessful
attempts, decided to prohibit it instead.
Water Use Conflicts
Local water use conflicts were identified in the Scoping Statement as a potentially
significant impact of the project. Upon further evaluation, however, it was determined
that no local water use conflicts would be created by implementation of the project,
except those associated with watering cattle, which are addressed in the preceding
paragraphs on “Land Use Conflicts.”
Increase in Water-Related Diseases
Increase in water-related diseases was identified in the Scoping Statement as a
potentially significant negative impact; however, after further investigation it has
determined that the project could have no impact on these diseases or even lead to a
decrease rather than an increase in water-related diseases.
Although there are many water-related diseases, many of them are transmitted via
ingestion (typhoid, cholera, dysentery and worms), which will not be impacted by
construction of the Mgongola irrigation scheme. Other diseases, however, which are
transmitted by hosts that breed in stagnant water (e.g., schistosomiasis [bilharzias],
malaria, filariasis, sleeping sickness and yellow fever diseases), have been
associated with irrigation. Of these, malaria is the most relevant for the Mgongola
irrigation scheme, as it is the most prominent water-related disease in the Mvomero
district, representing 50% of all reported disease cases. Mosquitos that transmit
malaria breed in stagnant water.
The project area is already used for paddy rice production, so the area is already
often ponded with stagnant water, providing mosquito breeding grounds. By
improving the ability of farmers to manage water, the length of time that water is
ponded in the fields will increase, at least during the period when having ponded
water in the fields is desirable (e.g., during the active growing period). However, by
improving the drainage in the fields, farmers will be able to remove ponded water
when it is not desirable (e.g., before and during harvest). So it is not clear if the
project will increase or decrease breeding periods. Indeed, it may only change the
timing of when water is ponded in the fields rather than increasing or decreasing the
total time of ponding.
In addition, recent research has suggested that the simple link between irrigation and
increased malaria may not be nearly as simple as it appears:
       It has often been assumed that high numbers of malaria vector Anopheles
       mosquitoes (Diptera: Culicidae) resulting from irrigation schemes lead
       inevitably to increased malaria in local communities. However, recent studies
       in Africa have revealed a more complex picture. Increased numbers of
       vectors following irrigation can lead to increased malaria in areas of unstable
       transmission, where people have little or no immunity to malaria parasites,
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          6-15
       such as the African highlands and desert fringes. But for most of sub-
       Saharan Africa, where malaria is stable, the introduction of crop irrigation has
       little impact on malaria transmission. Indeed, there is growing evidence that
       for many sites there is less malaria in irrigated communities than surrounding
       areas. The explanation for this finding is still unresolved but, in some cases at
       least, can be attributed to displacement of the most endophilic and
       anthropophilic malaria vector Anopheles funestus Giles by An. arabiensis
       Patton with lower vectorial capacity, as the latter thrives more than the former
       in ricefields. (Ijumba and Lindsay 2001)
These findings have been supported by subsequent, similar research (Ijumba et al.
2002, Muturi et al. 2008 and Mwangangi et al. 2010).
Scheme Management Capacity
The main challenge to the sustainability and efficient operation and management of
the Mgongola irrigation scheme is the capacity of WUA to properly manage it. The
WUA is a new organization, but it will benefit from having in its membership the
members of the Mkindo irrigation scheme cooperative, which will be merged into the
new WUA.
MZITSU is coordinating the setting-up and training of the combined WUA, in
cooperation with the Mvomero LGA and NAFAKA. They are in the process of
helping the WUA:
          Secure a consolidated land tenure certificate.
          Develop a training program.
          Establish financial management procedures, including collection of water
           fees and other dues. Water measurement structures are being included in
           the designs, but the WUA will need to develop a system to charge farmers
           for actual water consumed.
          Establish water management practices and cropping patterns for the
           scheme.
          Develop support for post-harvest processing and marketing.
But as this is a brand new WUA, it will be necessary, for the GoT and USAID to
continue to provide institutional capacity building assistance in the first several years
of its operation.
WRBWO Capacity to Control Water Abstractions
WRBWO has responsibility for monitoring water flows and granting water rights. It
also has the authority to restrict water withdrawals if flows are impacted. It does not,
however, have all the resources necessary to fully monitor flows. The GoT as well as
international donors are aware of this problem and are working to solve it. The GoT’s
Water Sector Development Program (WSDP), supported by several international
donors, has been in effect since 2007 and has a capacity building program for Water
Basin Offices. The WRBWO has been a recipient of this capacity building and its
capacity to monitor and regulate water use has increased. JICA is currently
conducting a capacity assessment of WRBWO to identify area requiring more
assistance. iWASH has a program component to develop low cost remote
instrumentation for monitoring flows, abstractions, discharges etc.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            6-16
Land Ownership
Land ownership was identified in the Scoping Statement as a potentially significant
impact of the project. Upon further evaluation, however, it was determined that no
land ownership issues would be created by implementation of the project.
Change of Community Lifestyle
Construction and use of an irrigation scheme for 589 hectares in the Mgongola
project area will increase incomes in the nearby villages of Mkindo, Dihombo and
Hembeti. These are very poor villages, so increased incomes will primarily have a
positive impact on the villages. The potential positive impacts of increased income
from irrigation can be seen when comparing the community lifestyle in Dakawa
village (which is reliant on irrigated paddy rice as the primary source of income) with
that in Mkindo and Hembeti villages (which are dependent largely on rain-fed rice
production). Dakawa village is clearly more prosperous than the other two villages
(Keraita 2012).
Increased incomes in the villages, however, may also create problems, particularly if
it causes in-migration. The project area, however, is already cultivated and those
cultivating the area will be the recipients of the project benefits, so no new
agricultural land will be made available, thus limiting the potential for in-migration.
Increased rice production in the project area could create demand for wage laborers.
Much of this demand will be met by family members, but there may be some influx of
wage laborers during planting (particularly if seedling planting is adopted) and
harvest. It is unlikely that this demand will cause permanent or significant in-
migration.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           6-17
including flood protection and drainage. Other negative impacts will be similar to
those of the Proposed Action.
Effects of Pesticide and Fertilizer Use
Same as the Proposed Action.
Water Contamination
Same as the Proposed Action.
Effects on Aquatic Fauna
Same as the Proposed Action.
Land Use Conflict
Less than the Proposed Action. The existing conflicts will continue, but they will not
be exacerbated by the need to eliminate grazing from the area, as there will be no
irrigation infrastructure that will be damaged by grazing.
Change of Community Lifestyle
Similar as the Proposed Action, but at a lower level as the economic benefits will be
less than for any of the irrigation alternatives.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           6-18
Pastoralists from the Kambala village bring their cattle to the banks of the Mgongola,
Dizingwa and Mkindo rivers during the dry season to gain access to water and to
graze their cattle on fallow, rain-fed farmland, including that in the Mgongola project
area. The grazing is primarily done via an informal agreement, although some
farmers may be receiving payment from pastoralists for use of their land. Whatever
the arrangement is, it has deteriorated, causing some conflicts between farmers and
cattle herders in recent years, even to the point of violence (de Bruin et al. 2012).
This conflict is likely to increase if the Mgongola irrigation scheme is constructed, as
it is most likely that grazing in the dry season by non-members of the WUA will be
prohibited. Local Government Authorities and the Morogoro Zonal Irrigation and
Technical Services Unit will need to work with the WUA and the herders from
Kambala to develop acceptable alternatives for securing access to water and feed for
the cattle during the dry season.
The assessment of fertilizer and pesticide use on the local rivers and their
ecosystems at and downstream from the Mgongola project area was based on
professional judgment, as there is no water quality data for the river in the vicinity of
the of the project area that would allow analysis. It would be prudent to collect water
quality data and do an analysis of these impacts during at least one cropping season.
If a problem is identified, then a subsequent routine monitoring program should be
established and on-farm use controls implemented.
The long-term success of the irrigation scheme is dependent upon the capability of
the newly formed WUA to manage it. IRRIP1 does plan to provide the WUA with
operator training and an operations manual. In addition, the GoT and the USAID-
funded NAFAKA Project has helped establish the WUA. But as this is a brand new
WUA, it will be necessary, for the GoT and USAID to continue to provide institutional
capacity building assistance in the first several years of its operation.
6.7      Possible Conflicts with Land Use Plans, Policies and Controls for the
         Area
The proposed activities all fall within the current land use plans, policies and controls
for the land on which it is located.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                       6-20
7       ENVIRONMENTAL MITIGATION AND MONITORING
7.1     Mitigation Measures
This section of the EA presents the mitigation measures that are necessary to reduce
or minimize the impacts of the project. It builds on the general mitigation measures
presented in Table 4.7 and Table 4.8, but are considerably more detailed, including
what is to be done by whom, and who will monitor their implementation. Table 7.1
presents the mitigation measures for mobilization and construction activities and
Table 7.2 presents the mitigation measures for operation.
All of the mitigation measures for mobilization and construction activities will be
implemented by the construction contractor(s) via clauses in the contract(s). The
implementation of these mitigation measures will be monitored by IRRIP1, which has
the responsibility for overseeing implementation of the construction contracts.
Other than providing some training in system operation at the time of commissioning,
and the development of operation and maintenance plans for the WUA, IRRIP1,
under its current contract, will not be involved in system operation. The irrigation
scheme will be operated by WUA, its future owner. Implementation of the
operational mitigation measures will largely rest with WUA and other GoT agencies;
however, in some cases other USAID projects, such as NAFAKA and iWASH, may
be involved in supporting the WUA and the WRBWO in the implementation of
mitigation measures.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                       7-1
 Table 7.1: Mobilization and Construction Mitigation Measures for the Proposed Action and All Irrigation Alternatives
                                                                                                                                        Timing &
                                                                                                                                      Responsible
                                                                                                                                       Parties for
      Impact                                    Specific Mitigation Measure                                     How Monitored          Monitoring
 Soil Erosion      SE1.   Land clearance shall be limited to the minimum needed for the irrigation, drainage,
                          flood control, and road infrastructure.
                   SE2.   Avoid executing excavation works under aggressive weather conditions.
                   SE3.   Erect temporary erosion control barriers around work sites during site preparation
                          and construction to direct runoff away from the site in a manner that will minimize
                                                                                                                                    At Least Monthly
                          erosion.
                   SE4.   Stabilize and compact the soils in canals and on embankments after completion of      Routine Site
                                                                                                                                    IRRIP1 Project
                          each stage of works.                                                                  Inspections
                                                                                                                                    Manager
                   SE5.   Return road beds, drainages and surfaces disturbed during construction to their
                          original (or better) condition.
                   SE6.   Place clear markers indicating the limits of the construction trenches and
                          stockpiling area of excavated materials to restrict equipment and personnel
                          movement, thus limiting the physical disturbance to land and soils in adjacent
                          areas.
                                                                                                                                    Conclusion of
                                                                                                                                    individual works
                   SE7. Revegetate canal and flood control embankments, drain outfalls and other                Routine Site
                        disturbed area at the conclusion of construction activities.                            Inspections
                                                                                                                                    IRRIP1 Project
                                                                                                                                    Manager
                   SE8. Every effort shall be made to secure borrow materials from existing, government
                                                                                                                                    Mobilization Period
                         approved sites.
                                                                                                                Borrow Site
                   SE9. Develop new sites, if necessary, in agreement with the village government or
                                                                                                                Location Approval   IRRIP1 Project
                         owners and with government or IRRIP1 approval. New sites should be developed
                                                                                                                                    Manager
                         on non-agricultural or unproductive land.
                   SE10. Close borrow pits that are no longer in use by backfilled with approved materials                          At Closure
                         and/or landscaping, or turning them into water storage points for livestock.           Routine Site
                   SE11. In all cases, grade the edges of the pits to ensure safe access for children and       Inspections         IRRIP1 Project
                         livestock.                                                                                                 Manager
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                             7-2
 Table 7.1: Mobilization and Construction Mitigation Measures for the Proposed Action and All Irrigation Alternatives
                                                                                                                                             Timing &
                                                                                                                                           Responsible
                                                                                                                                            Parties for
       Impact                                     Specific Mitigation Measure                                         How Monitored         Monitoring
 Soil Pollution    SS1.   Use vehicles and equipment which are in good condition and properly service and
                          check them to make sure that they do not leak lubricants and fuels.
                   SS2.   Use drip pans to contain all hydrocarbon leakages on construction equipment.                                   At Least Monthly
                   SS3.   Machine refueling shall be carried out only at designated areas.
                                                                                                                      Routine Site
                   SS4.   Selection vehicle routes wherever possible to avoid passing through agricultural                               IRRIP1 Project
                                                                                                                      Inspections
                          fields.                                                                                                        Manager
                   SS5.   Store and handle fuels and lubricants within containment facilities (e.g. bounded
                          areas, leak proof trays, etc.) designed to prevent the release of spilled substances
                          to the soil. These facilities should be maintained and kept drained of rainwater.
                   SS6.   Develop and implement a Contractor’s Site Environment, Health and Safety Plan
                          (SEHASP) including the following:
                              - Procedures for storage and handling of hazardous substances (e.g. batteries,          Approval of Plan
                                                                                                                                         IRRIP1 Project
                                  chemicals, fuel)                                                                    Prior to
                                                                                                                                         Manager
                              - Designs and siting requirements for on-site maintenance, refueling and                Mobilization
                                  cleaning of vehicles and equipment, if needed, including the provision of
                                  containment of leaks and discharges.
                              - Spill procedures and response kits for containment of spills and removal and
                                  disposal of contaminated soils
                                                                                                                                         At Least Monthly
                              - Designation of concrete batching areas with proper isolation from the soil            Compliance with
                                  surface, if needed.                                                                 Plan via Routine
                                                                                                                                         IRRIP1 Project
                              - Cleaning of concrete ready-mix vehicles on-site in specially prepared places          Site Inspections
                                                                                                                                         Manager
                                  where the concrete wastes are contained and disposed of at an IRRIP1-
                                  approved site.
 Loss of Topsoil   LT1.   If fill material is removed from fields, the top 200 mm (or as appropriate for each
                                                                                                                                         At Least Monthly
                          field) of top soil should first be moved to one side before taking suitable fill material
                                                                                                                      Routine Site
                          from beneath the top soil layer.
                                                                                                                      Inspections        IRRIP1 Project
                   LT2.   After the required fill has been removed, the land shall be leveled to ±10 mm and
                                                                                                                                         Manager
                          the topsoil should be returned to the field and also leveled to ±10 mm.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                  7-3
 Table 7.1: Mobilization and Construction Mitigation Measures for the Proposed Action and All Irrigation Alternatives
                                                                                                                                       Timing &
                                                                                                                                     Responsible
                                                                                                                                      Parties for
      Impact                                     Specific Mitigation Measure                                    How Monitored         Monitoring
 Water             Implementation of Mitigation Measures for Soil Erosion, Soil Pollution, and Generation of
 Contamination     Solid Waste plus the following:                                                                                 At Least Monthly
                    WC1. No vehicle or machine refueling shall be carried out within 100 m of a water           Routine Site
                          source.                                                                               Inspections        IRRIP1 Project
                    WC2. Provide improved pit latrines in the field areas for workers. These latrines will                         Manager
                          remain after construction for use by farmers.
 Generation of      SW1. Organic matter resulting from site clearance shall be disposed of in sites approved
 Solid Waste              by IRRIP1 where any of the following methods can be applied:                          Approval of Plan
                           - Burying/composting for soil conditioning;                                                             IRRIP1 Project
                                                                                                                Prior to
                           - Controlled burning; or                                                                                Manager
                                                                                                                Mobilization
                           - Dried and used in farms to control growth of unwanted weeds
                    SW2. Allocate a special area for petty business such as food stalls and provide garbage
                          bins.
                    SW3. Solid wastes generated from construction activities will be collected and disposed                        At Least Monthly
                          of in a site whose size and location will be determined by the IRRIP1 Project         Compliance with
                          Manager in agreement with villagers. Decomposable materials will be buried.           Plan via Routine
                                                                                                                                   IRRIP1 Project
                          Plastics and other recyclable materials will be collected and sent for recycling in   Site Inspections
                                                                                                                                   Manager
                          Morogoro town. Hazardous waste will be disposed of in accordance with
                          Mitigation Measure SS6.
                    SW4. Practice good housekeeping at works sites to minimize wastes generated.
                                                                                                                                   At Least Monthly
                    SW5. Post appropriate signage such as “DO NOT LITTER” or “USITUPE TAKA” at all
                                                                                                                Routine Site
                          strategic sites.
                                                                                                                Inspections        IRRIP1 Project
                    SW6. All excavated spoils should be well managed through levelling or tipped into
                                                                                                                                   Manager
                          borrow areas which are no longer useful.
 Dust and Air       DAP1. Construction machines/equipment shall be well-maintained to ensure optimum fuel
 Pollution                combustion. All the vehicles shall be frequently checked and serviced during the
                          whole rehabilitation period so that the levels of exhaust emissions are reduced.                         At Least Monthly
                    DAP2. Movement of vehicles shall be kept to a minimum necessary for completing the          Routine Site
                          job.                                                                                  Inspections        IRRIP1 Project
                    DAP3. Ensure site roads are kept regularly damped down, compacted or suitably                                  Manager
                          surfaced to minimize dust emissions from vehicle use.
                    DAP4. Avoid idling vehicles and equipment engines that are left running unnecessarily.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                            7-4
 Table 7.1: Mobilization and Construction Mitigation Measures for the Proposed Action and All Irrigation Alternatives
                                                                                                                                         Timing &
                                                                                                                                       Responsible
                                                                                                                                        Parties for
      Impact                                       Specific Mitigation Measure                                    How Monitored         Monitoring
 Noise Pollution                                                                                                  Approval of Plan
                     NP1. Locate the machinery yard in an area which is not too close to residential                                 IRRIP1 Project
                                                                                                                  Prior to
                          premises.                                                                                                  Manager
                                                                                                                  Mobilization
                     NP2. Vehicles and equipment shall be fitted with noise silencers such as mufflers and
                          serviced regularly to ensure that they are operating at manufacturers’
                          specifications.                                                                                            At Least Monthly
                     NP3. During construction works, the contractor should only work during approved hours        Routine Site
                          so that villagers living close to the site are not disturbed during sleeping and        Inspections        IRRIP1 Project
                          resting hours.                                                                                             Manager
                     NP4. Prior to initiating the works near noise sensitive receivers, notify residents of the
                          plans, including expected duration.
 Effects on the                                                                                                                      At Least Monthly
 Aquatic Fauna       Mitigation Measures for Water Quality                                                        Routine Site
                                                                                                                  Inspections        IRRIP1 Project
                                                                                                                                     Manager
 Displacement of
 Economic                                                                                                         Approval of Plan
                                                                                                                                     IRRIP1 Project
 Activities          DEA1. Schedule construction activities to minimize impacts on current farming activities.    Prior to
                                                                                                                                     Manager
                                                                                                                  Mobilization
 Disturbance of
 Graves                                                                                                           Approval of Plan
                     DG1. Develop and implement procedures for respectfully handling the disturbance of                              IRRIP1 Project
                                                                                                                  Prior to
                          any grave sites encountered during construction.                                                           Manager
                                                                                                                  Mobilization
 Worker/Community
 Health and Safety                                                                                                Approval of Plan
                                                                                                                                     IRRIP1 Project
 Impacts                                                                                                          Prior to
                                                                                                                                     Manager
                                                                                                                  Mobilization
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                              7-5
 Table 7.1: Mobilization and Construction Mitigation Measures for the Proposed Action and All Irrigation Alternatives
                                                                                                                                        Timing &
                                                                                                                                      Responsible
                                                                                                                                       Parties for
     Impact                                      Specific Mitigation Measure                                     How Monitored         Monitoring
                   HS1. Develop and implement a Contractor’s SEHASP addressing work place health and
                        safety issues, including:
                          - A reporting program for occupational injuries, illnesses, accidents and near
                             misses;                                                                                                At Least Monthly
                                                                                                                 Compliance with
                          - Protocols for investigating occupational injuries, illnesses, accidents and near
                                                                                                                 Plan via Routine
                             misses;                                                                                                IRRIP1 Project
                                                                                                                 Site Inspections
                          - A sensitization program for workers and community residents to reduce the                               Manager
                             spread of STDs, STIs and HIV/AIDS; and
                          - A sensitization program for community residents, including children, on the
                             dangers at the construction sites.
                   HS2. Identify and provide appropriate personal protective equipment (PPE) that offers
                        adequate protection to the workers including eye protection, dust masks, hard hats,
                        gloves, high visibility jackets, hearing protection equipment, proper clothing, safety
                        boots, safe ladders, etc.                                                                                   At Least Monthly
                   HS3. Properly maintain PPE, including cleaning when dirty and replacement when                Routine Site
                        damaged or worn out.                                                                     Inspections        IRRIP1 Project
                   HS4. Train all employees working in the project in the proper use PPE when at work to                            Manager
                        avoid occupational risks.
                   HS5. Train all employees working in the project in the implementation of Mitigation
                        Measure SS6
 Change of                                                                                                                          At Least Monthly
 Community         CCL1. Sensitize workers to community by laws and expected, proper behavior in                 Routine Site
 Lifestyle               communities.                                                                            Inspections        IRRIP1 Project
                                                                                                                                    Manager
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                             7-6
 Table 7.2: Operation Mitigation Measures for the Proposed Action and All Action Alternatives
                                                                                                                                     Timing &
                                                                                                                                   Responsible
                                                                                                   Implemented                      Parties for
     Impact                                Specific Mitigation Measure                                  By       How Monitored      Monitoring
 Soil Salinity                                                                                                                   End of irrigation
 (Sprinkler       SS1.    Monitor soil salinity at the end of each irrigation season and take                                    season
                                                                                                   WUA           Soil Sampling
 Irrigation)              remedial actions if salinity reaches critical levels.
                                                                                                                                 WUA
 Effects of                                                                                                                      Whenever such
 Pesticides and                                                                                                                  assistance is
                                                                                                                 NAFAKA
 Fertilizer Use    PF1.   Comply with the conditions of the NAFAKA PERSUAP when                                                  given
                                                                                                                 PERSUAP
                          providing any assistance to Mgongola farmers that might include          NAFAKA
                                                                                                                 Reporting
                          training on, discussing or promotion of the use of pesticide inputs.                                   NAFAKA staff
                                                                                                                 Requirements
                                                                                                                                 and/or
                                                                                                                                 consultants
                                                                                                                                 Whenever such
                                                                                                                                 assistance is
                   PF2.   Sensitize Mgongola farmers about the proper application of fertilizers                                 given
                                                                                                                 NAFAKA Annual
                          and the impacts improper use can have on the Mkindo and Mgongola         NAFAKA
                                                                                                                 Reports
                          rivers                                                                                                 NAFAKA staff
                                                                                                                                 and/or
                                                                                                                                 consultants
                                                                                                                                 Annually during
                                                                                                                 Sampling,
                   PF3.   Water quality monitoring for nutrients and pesticide residues above                                    the irrigation
                                                                                                                 Laboratory
                          the Mkindo diversion and below the discharges from the irrigation        WRBWO                         period
                                                                                                                 Analysis and
                          scheme drains
                                                                                                                 Reports
                                                                                                                                 WRBWO
 Water
 Contamination    Mitigation Measures for Effects of Pesticides and Fertilizer Use
                                                                                                                                 Monthly
                  WQ1.     Monitor water withdrawals by Mgongola irrigation scheme                 WUA           Daily logs
                                                                                                                                 WRBWO
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                           7-7
 Table 7.2: Operation Mitigation Measures for the Proposed Action and All Action Alternatives
                                                                                                                                           Timing &
                                                                                                                                         Responsible
                                                                                                  Implemented                             Parties for
     Impact                                Specific Mitigation Measure                                 By           How Monitored         Monitoring
 Water Quantity   WQ2.     Monitor all water withdrawals on the Wami River and its tributaries                      Abstractor
 Impacts to                from the Dakawa Gauging Station (1G1) to the Mtibwa EFA site during                      Records or Field
                                                                                                                                       Semi-monthly
 Downstream                March through July                                                                       Measurements
 Users and        WQ3.     Monitor flows during March through July at the Dakawa Gauging
                                                                                                                                       WRBWO
 Ecosystems                Station (1G1), Mkindo Gauging Station (1GB2), Diwale Gauging                             Gauging stations
                                                                                                 WRBWO
 (Irrigation               Station (1GB1A) and the Mtibwa EFA site
 Alternatives)                                                                                                                         Annually
                  WQ4.     Use the data from WQ1 through WQ3 to do an analysis of status of
                           the RAD at the Mtibwa EFA and the impact upon it of the DRF and the                      Report
                                                                                                                                       WRBWO
                           other withdrawals.
                                                                                                                                       WUA
 Effects on
 Aquatic          Mitigation Measures for Effects of Pesticides and Fertilizer Use
 Species
 Land Use         LUC1. Creation of a livestock corridor on through which animals can be                            Creation of the    During
 Conflicts              herded to reach the rivers for water.                                                       Corridor           construction and
                  LUC2. Designation of grazing and watering areas outside of the project                                               mobilization
                                                                                                 LGA, MZITSU
                        boundaries, in between the flood control structures and the banks of                        Designation of     period
                                                                                                 in collaboration
                        the rivers                                                                                  areas
                                                                                                 with WUA and
                                                                                                                                       LGA, MZITSU
                                                                                                 Kambala
                  LUC3. Establishment of an NGO composed of farmers and herders to               pastoralists       Establishment of
                                                                                                                                       Annually
                        address cultivation/grazing conflicts, modeled on the Kambala                               NGO
                        association known as KIPOK, a Maasai word literally means                                   Minutes of
                                                                                                                                       LGA, MZITSU
                        “healing”.                                                                                  meetings
 Capacity of                                                                                     MZITSU and                            Monthly
 WUA                                                                                             IRRIP1* or         WUA Board
                  CWU1. Develop and support an institutional capacity building program for the
                                                                                                 other USAID-       Minutes            IRRIP1* or other
 (Irrigation            WUA
                                                                                                 funded Project     Site Visits        USAID-funded
 Alternatives)
                                                                                                                                       Project
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                7-8
 Table 7.2: Operation Mitigation Measures for the Proposed Action and All Action Alternatives
                                                                                                                                                        Timing &
                                                                                                                                                      Responsible
                                                                                                               Implemented                             Parties for
     Impact                                    Specific Mitigation Measure                                          By             How Monitored       Monitoring
* Providing this type of technical assistance is not currently in the CDM Smith contract with USAID for implementation of IRRIP1.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                           7-9
7.2      Monitoring
Two types of monitoring will be necessary to ensure that this project will have the
limited environmental impacts that have been identified in this EA: mitigation
monitoring and resource monitoring.
Mitigation monitoring will ensure that the mitigation measures are implemented.
Monitoring of implementation of the mitigation measures during mobilization and
construction have been included in Table 7.1. IRRIP1 has responsibility for
monitoring the implementation of all of these mitigation measures in its role as the
Project Manager during construction (i.e., Supervising Engineer). Reporting on the
implementation of these mitigation measures will be done through IRRIP1’s Quarterly
Progress Reports to USAID.
Monitoring the implementation of the mitigation measures for operation is to be
undertaken by various entities, as identified in Table 7.2.
Resource monitoring is undertaken to ensure that the impacts to the environment are
as predicted in the EA. For the construction of the Mgongola irrigation scheme, two
types of resource monitoring have been identified: water quality monitoring and
water flow monitoring. This monitoring is to be undertaken to ensure that the
predicted results were accurate for the impact of pesticides and fertilizers on the
Wami River and the impact of DRF withdrawals on the environmental flow in the
Wami River.
The water quality monitoring required for this project is embedded in the mitigation
measures as Measure PF3 in Table 7.2. This monitoring will be undertaken by
WRBWO. It should be done at least during one irrigation season. If a problem is
identified, then a subsequent routine monitoring program should be established and
on-farm use controls implemented with WUA.
The water quality monitoring required for this project is embedded in the mitigation
measures as Measures WQ1, WQ2, WQ3 and WQ4 in Table 7.2. This monitoring is
also to be undertaken by WRBWO. It should be done annually during the months
when the irrigation scheme is abstracting water (March through July).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            7-10
8      LIST OF PREPARERS
CDM Smith Team
      Eng. Keith F. Williams, P.E., Chief of Party
      Mr. Lane Krahl, Environmental Impact Specialist
      Eng. Chris Hall, Senior Irrigation Engineer
      Mr. Peter Ede, Senior Hydrologist
      Ms. Katherine Spink, Hydrologist
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                   8-1
9        REFERENCES
ACDI/VOCA. 2012. Tanzania Staples Value Chain - NAFAKA Pesticide Evaluation
      Report and Safer Use Action Plan (PERSUAP). NAFAKA, for
      USAID/Tanzania. 26 July 2012. 98pp.
Baillie, JEM, C Hilton-Yaylor and CSN Stuart. 2004. The IUCN Red List of
         Threatened Species, IUCN, Gland.
Berkhout, Ezra and Dominic Glover. 2011. The Evolution of the System of Rice
      Intensification as a Socio-technical Phenomenon: A report to the Bill &
      Melinda Gates Foundation, Wageningen University and Research Centre,
      Wageningen, Netherlands.
BirdLife International, 2013. Important Bird Areas factsheet: Uluguru Mountains.
        Downloaded from http://www.birdlife.org on 18 November 2013.
Bouman, B.A.M., R.M. Lampayan, and T.P. Tuong. 2007. Water Management in
     Irrigated Rice: Coping with Water Scarcity. International Rice Research
     Institute (IRRI), Los Baños, Philippines. 54pp.
Brouwer, C., K. Prins and M. Heibloem. 1989. Irrigation Water Management:
      Irrigation Scheduling. Training manual no. 4, Publications Division, Food and
      Agriculture Organization of the United Nations, Rome, Italy.
      http://www.fao.org/docrep/t7202e/t7202e07.htm#TopOfPage, accessed on 29
      November 2013.
Bracebridge, Claire. 2006. Mkindo Forest Reserve: Forest Disturbance Report.
      Report for Tanzania Forest Conservation Group and Participatory
      Environmental Management Programme, May 2006, Dar es Salaam,
      Tanzania. 72pp. http://www.tfcg.org/downloads/Mkindo-Forest-Disturbance-
      Report-FINAL.pdf Brownlie and Willemse. 1996. First Step Assessment
      Criteria for Evaluation of Environmental Impacts
The Cadmus Group. 2013. Environmental Assessment for Construction of
      Kilombero Valley Irrigation Schemes for USAID/Tanzania, March 2013.
      135pp.
CDM Smith. 2013a. Design Report: Mgongola Irrigation Scheme. IRRIP1, for
     USAID/Tanzania. 30 September 2013. 64pp.
CDM Smith. 2013b. Feasibility Study Evaluation Report: Mgongola Irrigation
     Scheme. IRRIP1, for USAID/Tanzania. 21 August 2013. 36pp.
CDM Smith. 2013c. Draft Environmental Assessment, Rehabilitation of Dakawa
     Irrigation Scheme. IRRIP1, for USAID/Tanzania. 4 December 2013. 105pp.
CDM Smith. 2011. Environmental Assessment Status Report. IRRIP1, for
     USAID/Tanzania, October 2011. 44pp.
CITES. 2013. Appendices I, II and III. Valid from 12 June 2013.
      http://www.cites.org/eng/app/appendices.php, accessed on 20 November
      2013.
Conde, V. and C. F. Rocha. 2006. Habitat disturbance and small mammal richness
      and diversity in an Atlantic rainforest area in south-eastern Brazil, Brazilian
      Journal of Biology vol. 66 No.4.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          9-1
de Bruin, Annemarieke, Steve Cinderby, Boniface Mbilinyi, Henry Mahoo, and Jennie
       Barron. 2012. Watershed Level Baseline Assessment in the Mkindo
       Watershed, Wami Basin, Tanzania. Technical Report, Agricultural Water
       Management Solutions Project, Stockholm Environment Institute, Stockholm,
       Sweden. 24pp. http://awm-
       solutions.iwmi.org/Data/Sites/3/Documents/PDF/publication-outputs/learning-
       and-discussion-briefs/mkindo-baseline_120716.pdf
District Executive Director - Mvomero District Council Socio-Economic Profile - 2010
Eccles DH, 1992. FAO Identification Sheets for Fishery Purposes, Field Guide to
       Freshwater fishes of Tanzania, FAO /UNDP Project URT/87/016, Rome Italy.
Eklou A. Somado, Robert G. Guei and N. Nguyen. 2008. Overview: Rice in Africa.
       In: NERICA: the New Rice for Africa – a Compendium. Consultative Group
       on International Agricultural Research (CGIAR) and Africa Rice Center
       (WARDA), Cotonou, Benin. pp. 1-9.
Environmental BENCHMARK. 2014. Draft Environmental and Social Impacts
       Assessment for the Proposed 620-ha Mgongola Irrigation Project in Hembeti
       Ward in Mvomero District, Morogoro Region. Submitted to NEMC 14 March
       2014. 191pp.
Environmental BENCHMARK, 2013a. Environmental and Social Impacts
       Assessment for Proposed Rehabilitation of Irrigation and Drainage
       Infrastructures for Dakawa Rice Farm in Wami Dakawa Village in Mvomero
       District in Morogoro Region. Submitted to NEMC, 20 June 2013. Approved
       by NEMC 15 August 2013. 243pp.
Environmental BENCHMARK. 2013b. Scoping Report for the Proposed 620-ha
       Mgongola Irrigation Project in Hembeti Ward in Mvomero District, Morogoro
       Region. Submitted to National Environment Management Council (NEMC).
       24 September 2013.
Hines, Deborah A. and Karlyn Eckman, 1993. Indigenous multipurpose trees of
       Tanzania: Uses and economic benefits for people. Cultural Survival Canada
       and Development Services Foundation of Tanzania, Ottawa, Ontario,
       Canada. http://www.fao.org/docrep/x5327e/x5327e00.htm#Contents
Ijumba Jasper N. and Steve.W. Lindsay. 2001. Medical and Veterinary Entomology,
       March 2001, 15(1):1-11.
Ijumba, Jasper N., F. C. Shenton, S. E. Clarke, F. W. Mosha and S. W. Lindsay.
       2002. Irrigated crop production is associated with less malaria than traditional
       agricultural practices in Tanzania. Transactions of the Royal Society of
       Tropical Medicine and Hygiene, March 2002, 96:476-480
International Fertilizer Development Centre (IFDC). 2013. The rice value chain in
        Morogoro, Tanzania: Current status and strategies for development.
        NAFAKA, June 2013.
International Rice Research Institute (IRRI). 2013. Rice production and processing.
        http://irri.org/index.php?option=com_k2&view=item&id=9151&Itemid=100480
        &lang=en, accessed on 29 November 2013.
IUCN. 2013. The IUCN Red List of Threatened Species. Version 2013.1.
      http://www.iucnredlist.org, accessed on 20 November 2013.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          9-2
IUCN. 2013. IUCN Red List Categories and Criteria: Version 3.1. Second edition.
      Gland, Switzerland and Cambridge, UK: IUCN. iv + 32pp.
iWASH. 2013a. Wami River Bub Basin, Tanzania: Initial Environmental Flow
     Assessment II. Tanzania Integrated Water, Sanitation and Hygiene (iWASH)
     Program, Water Development Alliance, and Wami-Ruvu Basin Water Office,
     August 2013. 80pp.
iWASH. 2013b. Climate in the Wami and Ruvu Basins, Tanzania: Current
     Characteristics and Future Projections. Draft interim report. Tanzania
     Integrated Water, Sanitation and Hygiene (iWASH) Program, September
     2013. 68pp.
JICA. 1998. Development Plan of Mgongola Scheme, Morogoro District. In: Volume
      II Annexes, Annex D of the Feasibility Study on the Smallholder Irrigation
      Projects in Central Wami River Basin. Japan International Cooperation
      Agency (JICA) and the Ministry of Agriculture and Cooperatives of the United
      Republic of Tanzania, January 1998. 178pp.
Katambara, Zacharia, Frederick C. Kahimba, Henry F. Mahoo, Winfred B. Mbungu,
      Fikiri Mhenga, Paul Reuben, Muyenjwa Maugo, and Anthony Nyarubamba.
      2013. Adopting the system of rice intensification (SRI) in Tanzania: A review.
      Agricultural Sciences Vol. 4, No. 8, pp. 369-375
Keraita, Bernard, Meredith Giordano and Henry Mahoo. 2012. Impacts of Improving
       Traditional Irrigation Schemes in Mvomero District, Tanzania. Case Study,
       AgWater Solutions Project, International Water Management Institute,
       Colombo, Sri Lanka. 16pp. http://awm-
       solutions.iwmi.org/Data/Sites/3/Documents/PDF/publication-outputs/learning-
       and-discussion-briefs/tz-traditional-irrigation.pdf
Kingdom J., 1998. East African mammals: an atlas of evolution in Africa vol 3 part D.
      Bovids, University of Chicago press. Lyn C., A.-M. Clark, P.E. Moler and B.W.
      Bowen. 2003. Fragmented landscapes, habitat specificity, and conservation
      genetics of three lizards in Florida scrub. Conservation Genetics Volume 4,
      Number 2, 199-212.
Mati, Bancy M. 2012. System of Rice Intensification (SRI), Growing more rice while
       saving on water: Practical Notes for SRI Farmers. National Irrigation Board,
       Jomo Kenyatta University of Agriculture & Technology, Nairobi Kenya. 12pp.
McDonald, A.J., P.R. Hobbs, and S.J. Riha. 2006. Does the system of rice
     intensification outperform conventional best management?: A synopsis of the
     empirical record. Field Crops Research, Volume 96, Issue 1, 15 March 2006,
     Pages 31–36.
Milder, Jeffrey C., Louise E. Buck, Abigail K. Hart and Sara J. Scherr. 2012. The
        SAGCOT Greenprint: A green Growth Investment Framework for the
        Southern Agricultral Growth Corridor of Tanzania, Draft, August 2012.
        EcoAgricultrue Parners, SAGCOT Centre, SAGCOT Green Reference Group,
        Dar El Salem, Tanzania. 145pp.
Ministry of Food and Agriculture (MoFA). 2009. National Rice Development Strategy
        (NRDS) (Draft). MoFA, Republic of Ghana, February 2009. 25 pp.
Ministry of Water and Irrigation (MWI). 2010. Project Proposal: Mgongola Irrigation
        Project. Irrigation and Technical Services Division, MWI, United Republic Of
        Tanzania, September 2010. 33pp.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                        9-3
Mung’ong’o, Claude and Davis Mwamfupe. 2003. Poverty and Changing
      Livelihoods of Migrant Maasai Pastoralists in Morogoro and Kilosa Districts,
      Tanzania. Research Report No. 03.5, Research on Poverty Alleviation
      (REPOA), Mkuki Na Nyota Publishers LTD, Dar es Salaam, Tanzania. 49pp.
      http://www.repoa.or.tz/documents/03.5_-_Mungongo_Mwamfupe_.pdf
Muturi, Ephantus J., Simon Muriu, Josephat Shililu, Joseph Mwangangi, Benjamin G.
        Jacob, Charles Mbogo, John Githure and Robert J. Novak. 2008. Effect of
        rice cultivation on malaria transmission in central Kenya. The American
        Journal of Tropical Medicine and Hygiene, February 2008, 78(2) 270-275.
        http://www.ajtmh.org/content/78/2/270.full.pdf+html
Mwangangi, Joseph M., Josephat Shililu, Ephantus J. Muturi, Simon Muriu, Benjamin
     Jacob, Ephantus W. Kabiru, Charles M. Mbogo, John Githure, and Robert J.
     Novak. 2010. Anopheles larval abundance and diversity in three rice agro-
     village complexes Mwea irrigation scheme, central Kenya. Malaria Journal,
     2010, 9:228. http://www.malariajournal.com/content/pdf/1475-2875-9-228.pdf
Nguyen, Van Nguu. 2010. Sustainable Intensification of Rice Production for Food
      Security in the Near Future – A Summary Report. International Rice
      Commission, FAO, Rome, Italy. 14 pp.
      http://www.fao.org/fileadmin/templates/agphome/documents/Rice/sustintricep
      rod.pdf. Accessed on 16 January 2014.
Otenga, J.W. and R. Sant'Annab. 1999. Rice production in Africa: Current Situation
      and Issues. International Rice Commission Newsletter, Vol. 48, Food and
      Agriculture Organization of the United Nations, Rome, Italy.
      http://www.fao.org/docrep/003/x2243t/x2243t05.htm, accessed on 29
      November 2013.
Paavola, Jouni. nd. Livelihoods, Vulnerability and Adaptation to Climate Change in
      the Morogoro Region, Tanzania. Centre for Social and Economic Research
      on the Global Environment, University of East Anglia, UK (undated, thought to
      be c. 2005).
Sarmett, Julius, Elizabeth Anderson and Appa Mandari. 2008. Wami River Sub-
      Basin, Tanzania: Initial Environmental Flow Assessment. Wami-Ruvu Basin
      Water Office, Global Water for Sustainability Program, Florida International
      University, and Water Development Alliance. Synthesis Report, June 2008.
      151pp. http://pdf.usaid.gov/pdf_docs/pnads254.pdf accessed on 13
      November 2013.
Shapely, SP and DM. Bishop, 1965. Sedimentation in a salmon stream. J. Fish. Res.
      Bd. Canada. 22 (4):919-928.
Sinclair, I, P. Hockey, and W Tarboton. 2002. Sasopl Birds of Southern Africa, The
        Regions Most Comprehensive Guide. Struik Publishers, Cape Town, South
        Africa.
Spawls S, K.M. Howell and R.C. Drews. 2006. Pocket Guide to the Reptiles and
      Amphibians of East Africa, A&C Black, London.
SRI International Network and Resources Center (SRI-RICE). 2014. College of
       Agriculture and Life Sciences, Cornell University. http://sri.ciifad.cornell.edu/
       accessed on June 11, 2014.
Stockbauer, Bette, 1999. A Review of the Literature: Supporting a Rationale for
      Mpingo Conservation. June 1999. African Blackwood Conservation Project
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            9-4
       website, http://www.blackwoodconservation.org/review.html accessed on 20
       November 2013.
Subsidiary Legislation (Suppl. No. 16 of 4th May 2001).
Tanzania Bureau of Standards – National Environmental Standards Compendium
      (NESC).
Tanzania Coastal Management Partnership (TCMP), 2008. A Profile of the Wami
      River Sub-Basin. Coastal Resources Center at the University of Rhode
      Island, for USAID, June 2008. 28pp.
Trulio, L. 2000. Basics of Bird Conservation in the U.S., US Environmental
        Protection Agency (EPA)
United Republic of Tanzania. 2005. Environmental Impact Assessment and Audit
       Regulations. Minister of State, Vice President’s Office, (Environment and
       Union Matters), Dar es Salaam, Tanzania. 53pp.
United Republic of Tanzania. 2004. Environmental Management Act, 14 July 2004,
       Dar es Salaam, Tanzania. 158pp.
United Republic of Tanzania. 2003. 2002 Population and Housing Census - General
       Report, January 2003.
United States Government. 2013. Environmental Procedures. Code of Federal
       Regulations, Title 22 Foreign Relations, Volume 1, Chapter II Agency for
       International Development, Part 216 Environmental Procedures (22CFR216),
       4 April 2013 Edition. pp 976-989.
USAID. 2011. Tanzania FY 2011–2015 Multi-Year Strategy. Feed the Future.
      Approved 22 February 2011. 47pp.
USAID. 2010. Initial Environmental Examination of the “Feed the Future” program.
      Approved 15 December 2010. 47pp.
USAID. 2007. Environmental Guidelines for Small-Scale Activities in Africa.
Wami/Ruvu Basin Water Office (WRBWO). 2015. Report on Water Use in Wami
      Subcatchment. 23 January 2015. 6 pp.
World Bank Group, 1998. Pollution Prevention and Abatement Handbook.
Zitske, B. P., M. G. Betts and A. W. Diamond. 2011. Negative Effects of Habitat
        Loss on Survival of Migrant Warblers in a Forest Mosaic, Conservation
        Biology, Volume 10.1111/ Pg.No.1523-1739.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         9-5
ANNEX A: NEMC’S SCOPING REPORT APPROVAL
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME   A-1
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME   A-2
ANNEX B: FAUNA OBSERVATIONS IN AND NEAR THE
         PROJECT AREA
Bird Species
In total 38 bird species were recorded, some 29 within the Mkindo Forest Reserve,
mostly within miombo woodland and 9 in the rice farms and grassland in and around
the project area. All observed birds were widespread throughout Tanzania and
common in more open habitat types, such as woodland and grassland. No species
were noted to be threatened to extinction as listed by IUCN.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                     B-1
         Table B.1: Bird Observations In and Near the Project Area
                   Species                         Common Name
         Ploceus bicolor                Dark-Backed Weaver
         Euplectes ardens               Red-Collared Widowbird
         Euplectes capensis             Yellow Bishop
         Euplectes orix                 Southern Red Bishop
         Uraeginthus sp                 Cordon-Bleu
         Lagonosticta rubricata         African Fire Finch
         Lonchura cucullata             Bronze Mannikin
         Vidua macroura                 Pin-Tailed Whydah
         Vidua chalybeata               Village Indigo Bird
         Source: Bracebridge, 2006
Mammal Species
Fourteen mammal species were observed, 13 within the nearby Mkindo Forest
Reserve and one (a resident group of Syke’s monkey) on the edge of the rice farms.
Five primate species were seen and/or heard. The track of a large antelope was
found leading down a steep slope to the Dizingwi river. The identity is uncertain, but
it may be waterbuck, sable or kudu. The most commonly encountered species was
yellow baboons (Papio cynocephalus). One primate species, the Zanzibar galago
(Galagoides zanzibaricus), is near-endemic to the nearby Eastern Arc Mountains and
is Vulnerable to extinction as listed by IUCN.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                         B-2
Reptile Species
Six reptile species were observed in and around the project area but none of them
are endemic or threatened by extinction, as listed by IUCN or CITES.
Amphibian Species
Four amphibian species were observed. None of them are threatened to extinction
as listed by IUCN and CITES, although it is likely with revisions that Callulina cf kreffti
will have a categorization of Endangered or Critically Endangered (IUCN).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                              B-3
ANNEX C: RELEVANT SECTIONS OF THE SCOPING
         STATEMWENT
3   SCOPING METHODOLOGY
The methodology used for scoping consisted of:
          Review of relevant and available literature;
          Field reconnaissance work to become familiar with the project area and to
           “ground-truth” baseline conditions and impressions; and
          Consultations with stakeholders.
3.1 Literature Review
IRRIP1 reviewed literature on the potential environmental impacts of lowland rice
irrigation schemes, relevant reports on previously proposed irrigation schemes in the
area, and existing baseline conditions to understand the situation and the potential
environmental and socio-economic issues that are relevant to the construction of the
Mgongola irrigation scheme. The literature reviewed included:
          Project documents relevant to the proposed action;
          Prior, relevant environmental assessments completed in Tanzania;
          USAID and other international guidelines on lowland rice irrigation
           schemes and their environmental impacts; and
          Available baseline documentation on the environmental and socio-
           economic conditions of the project area.
A list of documents reviewed is provided in Section 9 [of the Scoping Statement].
3.2 Field Work
Several field reconnaissance trips were conducted to observe and record information
on the existing irrigation system and the environmental and social conditions in the
project area. During these trips the Scoping Statement Team also had informal
conversations with farmers and local residents about the current situation.
3.3 Consultations
Meetings were held with stakeholders in the project area to provide information on
the project and to solicit inputs on perceived issues and problems that may be
associated with development of a new irrigation scheme. Meetings were held with
the following concerned governmental agencies (Annex A [of the Scoping
Statement]):
          Morogoro Regional Administrative Secretary
          Mvomero District Administrative Secretary
          Mvomero District Offices
          Wami-Ruvu Basin Water Office, Morogoro Office
          Morogoro Urban Water and Sewerage Authority
Consultations with government authorities were made through interviews and
discussions.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           C-1
In addition, a community meeting was held in the Hembeti Ward on 16 May 2013,
attended by 31 residents from all the villages in the vicinity of the proposed project
(Hembeti, Dihombo, Mkindo, Kigugu and Mbogo). A list of the attendees is
presented in Annex B [of the Scoping Statement].
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                               C-2
         Loss of top soil during construction and from field levelling.
         Solid waste generation.
         Water contamination, primarily as a by-product of soil erosion and soil
          pollution, but also associated with activities in and near rivers.
         Dust and air pollution from vehicles and equipment.
         Noise pollution from vehicles and equipment.
         Vegetation loss.
         Effects on the terrestrial fauna.
         Effects on aquatic fauna, associated with water quality impacts and
          reduced water quantity.
         Health and safety impacts, primarily worker health and safety but also
          some issues for community members.
         Change of community lifestyle from impacts of having construction
          workers in the community as short-term residents.
5.2.2 During Operation
         Reliable supply of irrigation water and associated increased rice
          production.
         Reduced flooding of fields.
         Soil salinity.
         Water logging.
         Water use conflicts.
         Water quantity impacts on downstream users and ecosystems.
         Effects on aquatic fauna, associated with water quality impacts and
          reduced water quantity.
         Increase in water related diseases.
         Scheme management capacity.
         WRBWO capacity to control water abstractions.
Table C.1 presents a consolidated list of potential issues.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                          C-3
Table C.1: Consolidated List of Potential Environmental Issues
During Operation
 Flooding                     Effects on aquatic fauna      Reliable supply of irrigation
 Soil salinity                                                water
 Water logging                                               Increased rice production
 Water quantity impacts on                                   Opportunities for
  downstream users and                                         employment
  ecosystems                                                  Land use conflict –
 Effects of pesticide and                                     cultivation/grazing
  fertilizer use                                              Water use conflicts
 Water contamination                                         Scheme management
                                                               capacity
                                                              WRBWO capacity to
                                                               control water abstractions
                                                              Disturbance of graves
                                                              Land ownership
                                                              Lack of proper land use
                                                               plan.
                                                              Increase in water related
                                                               diseases
                                                              Change of community
                                                               lifestyle
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 C-4
ANNEX D: MGONGOLA IRRIGATION SCHEME ENVIRONMENTAL
         FLOW ASSESSMENT IN THE WAMI RIVER
Environmental flow requirements for the Wami River
The 2013 WRBWO Environmental Flow Assessment (EFA) report (iWASH 2013) provided
an update to the previous 2008 assessment for the Wami River, which developed monthly
flow objectives based on 2007 field work (Sarmett et al. 2008). This second phase of work
included the collection of data during 2011, to provide data for a wetter period and develop a
wider assessment of the hydrology of the catchment. Consideration was given to revisions to
the initially recommended environmental flows from the first round of EFA studies. A holistic
view was taken for the calculation of environmental flows, whereby hydrology,
geomorphology, ecology and water quality have been considered alongside the socio-
economic needs of the local population.
Of the sites assessed by WRBWO, the abstraction for the Mgongola irrigation scheme on
the Mkindo River is located nearest to and upstream from the Wami River at the Mtibwa EFA
site. The reassessment undertaken by WRBWO in 2013 concluded that no change to the
previously reported environmental flows is required from those reported in 2008 at the
Mtibwa site. The dry year environmental flows for the Wami River at the Mtibwa EFA site
from the 2008 and 2013 assessments can be seen below in Table D-1.
Table D.1: Driest Year Recommended Average
           Discharge (RAD) at Wami River at the
           Mtibwa EFA Site
                            Driest year RAD
       Month              Wami River at Mtibwa
       March                       3.0
       April                       5.0
       May                         5.0
       June                        5.0
        July                       4.1
Adapted from Table 45 in iWASH (2013)
It should be noted that between the two EFA field investigations in 2008 and 2011, the
original Mtibwa site had been significantly modified by construction of a bridge downstream
and dredging making this site no longer suitable for the EFA study. In 2011, a new site
downstream of the original site was adopted for the EFA.
Water requirements in the context of the 2008 and 2013 EFA
There are no EFA sites on the Mkindo River; therefore, the impact on this river cannot be
assessed. However, the flow from the Mkindo will impact the flow at the Mtibwa EFA site on
the main Wami River. To assess the impact of the abstraction for the irrigation scheme on
the Mtibwa EFA site a number of factors need to be considered, including:
       Flow on the main Wami River at Dakawa gauging station (1G1);
       Flow on the River Mkindo at Mkindo gauging station (1GB2);
       Flow on the Diwale River (1GB1A);
       Other flows (e.g., Dizingwi, Mgongola and Divue rivers)
       Abstraction rates for the Mgongola irrigation scheme;
       Abstraction rates for the Dakawa irrigation scheme;
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 D-1
       Abstraction rates for the Mtibwa Sugar Estate;
       Abstraction rates for the Dizungu Sugar Estate; and
       Recommended average discharge (RAD) values for the EFA at Mtibwa.
Figure D-1 shows the schematic location and relationship of these factors. Based on data
available it has been assumed that there are no other major abstractions between the
Dakawa gauging station and the Mtibwa EFA site on the Wami River or the gauging stations
and Mtibwa EFA site on the tributaries.
As shown in Figure D-1, the intake site for the existing Mkindo irrigation scheme is upstream
of the Mkindo gauge (1GB2) and the Mtibwa EFA site. Therefore, the gauge records flows
after the existing extraction which has been permitted from 1988 onwards. The Mkindo
River, the source of irrigation water for the proposed Mgongola scheme, flows into the
Diwale River upstream of where the Diwale River joins the main Wami River. The junction of
the Diwale and Wami rivers is upstream of the Mtibwa EFA site.
Flow data
Flow data on the Wami River is available for several years from the Dakawa gauge (1G1).
Sufficient flow data is available to calculate the statistical 1- in 5-year low flows at the
Dakawa gauge (CDM Smith 2013, Annex F).
The Diwale River flows into the Wami River between the Dakawa gauge and the Mtibwa
EFA site as do several small drainages from the south of the Wami River. The Mkindo and
Divue rivers are both perennial and flow into the Diwale River. The Mkindo River is the
major tributary of the Diwale River. The Mkindo River has two tributaries that flow into the
river below the Mkindo gauge, the perennial Dizingwi River and the seasonal Mgongola
River. There are no gauges on Divue, Dizingwi and Mgongola rivers or any of the small
drainages that flow into the Wami River from the south between the Dakawa gauge and the
Mtibwa EFA site, so their flows are not captured in the following analysis.
Flow data on the Mkindo River (1GB2) is available for six years; 1965 to 1969 and
2009/2010. For six years of data, detailed statistical analysis of flow data at Mkindo is not
applicable. Therefore, to adopt a conservative approach the lowest average flow during
each half month period was calculated and the lowest average for the six years of data was
extracted from the record. These values are all lower than the average daily flow (Table D-
2) reported in the EFA (Sarmett et al. 2008), thus conservative values for this assessment as
it considers wet season months.
Table D.2: Catchment and Flow Characteristics at
           Diwale and Mkindo Gauging Stations
                                 Mkindo (1GB2)   Diwale (1GB1A)
 Annual Daily Flow (m3/s)             32.71           9.66
 Q70* (m3/s)                           10.8            2.8
  Area (km2)                           90.7           173.8
* Flow will exceed this value 70% of the time
               From: Sarmett et al. 2008
For the Diwale River (1GB1A) flow data is available for six years from 1965 to 1970. A
similar approach to that used for the Mkindo River was applied for the Diwale River to
estimate a dry year flow for each half month period during the abstraction period.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                 D-2
Figure D.1:   Schematic of the Diwale/Wami Watershed from the Dakawa Gauge to the Mtibwa EFA Site
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                          D-3
Water rights and abstractions
The Mtibwa Sugar Estate, Dakawa irrigation scheme, Mkindo irrigation scheme and
Dizungu Sugar Estate abstract water in the area of interest upstream of the Mtibwa
EFA site. The Mtibwa Sugar Estate has two current water rights. One is for 1.5 m3/s
year-round from the Diwale River below the junction with the Mkindo River18. It uses
this water to irrigate 5,200 ha with sprinklers. The other water right is for 2.5 m3/s
year-round from the Wami River.19 It currently uses this water to irrigate 3,000 ha
with sprinklers on the south side of the Wami River.
Mtibwa Sugar Estate is developing 20,000 ha of new fields on the south side of the
Wami River. By the end of 2014 it had 3,000 ha in production, and plans to add an
additional 3,000 ha by the end of 201620. IRRIP estimates that with completion of the
additional 3,000 ha, the Estate will consume its 2.5 m3/s water right on the Wami
River.
To develop the remaining 14,000 ha of cultivation, the Mtibwa Sugar Estate has
applied for an additional 7.5 m3/s water right from the Wami River.21 The Estate says
it is in the final stages of receiving that right. The right will be restricted to the wet
season, it is not clear how the water right will define “wet season,” but the Estate
says it plans to abstract from March through May or June. This water will be used to
fill two reservoirs with a total capacity of 70 million m3 from which water will be
withdrawn for irrigation during the dry season. The Estate is sure enough that it will
receive the 7.5 m3/s water right that it has invested a significant amount of capital in
the construction of a pump house with 6-pumps on the Wami river.22 Although the
Estate does not have a specific development plan, it is reasonable to assume that
sometime in the next 5 to 10 years it will be abstracting an additional 7.5 m3/s from
the Wami River from March through June, as it will take four months to fill the
reservoirs, if they are doing so at 7.5 m3/s.
The Dakawa irrigation scheme has a water right from the Wami River for 5.0 m3/s
from March through November.23 It currently abstracts 3.5 m3/s but is in the process
of rehabilitating its system and will soon be abstracting from 2.35 to 3.88 m3/s,
depending on the month, at a seasonal average rate of 3.22 m3/s (CDM Smith 2013).
The existing Mkindo irrigation scheme has a water right of 0.624 m3/s and it is
estimated that it currently abstract 0.22 m3/s. The proposed Mgongola irrigation
scheme will require an additional 1.18 m3/s. These abstractions are based on the
assumption of a 2 l/s/ha abstraction rate. If the proposed scheme is constructed, the
two schemes will be managed as one scheme, requiring a total abstraction of 1.4
m3/s and requiring the current water right to be increased by 0.776 m3/s.
18   Water Right Registration Number 4501 of 1980 (WRBWO 2015). Provisional, renewable every three
     years.
19   Water Right Registration Number 4959 of 1990 (WRBWO 2015). Provisional, renewable every three
     years.
20   From Mtibwe Sugar Estate General Manager at a meeting at the Plantation with IRRIP and Mtibwa
     staff on January 27, 2015.
21   Ibid.
22   Located at S6°23’53.0” by E37°38’25.4” and observed and photographed by IRRIP staff on January
     27, 2015.
23   Water Right Registration Number 4583 of 2007 (WRBWO 2015). Final (permanent).
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                       D-4
There is no data available on the abstraction for the Dizungu Sugar Estate, which is
an area of approximately 300 ha. It is reported that the Estate does irrigate with
surface water, but no information is available about the abstraction.
Taking all of the above factors into consideration, input-output analysis was
conducted of the impact of the proposed Mgongola scheme on the Mtibwa EFA RAD.
Multiple scenarios were analysed, the results of which indicated that the critical factor
is water use by the Mtibwa Sugar Estate. This report contains two “most likely”
results:
   1. Assuming that the Mtibwa Sugar Estate uses only their full, current water
      rights (Table D-3), which is the most likely scenario at the end of 2016.
   2. Assuming that the Mtibwa Sugar Estate secures and uses an additional water
      right of 7.5 m3/s from March through June (Table D-4), which is the most likely
      long-term scenario (some time in the next 5 to 10 years).
As can be seen in Tables D-3 and D-4, in the short-term (by the end of 2016), there
will be sufficient water for the Mgongola scheme, but in the longer-term (5 to 10 years
out), water used by the Mtibwa Sugar Estate will consume all of the available water in
two periods (2nd periods of March and June), reducing flows at the Mtibwa EFA site in
two these two periods below the RAD.
To assess the potential impacts on the RAD of other irrigation alternatives, an
analysis was conducted on the irrigation alternative with the least water requirement,
the sprinkling alternative. Assuming that the sprinkling alternative was fully
implemented on the entire 589 ha area, the water requirement would be reduced
from 1.18 to 0.86 m3/s. The results of this analysis are presented in Table D-5. As
with the proposed action, the sprinkler alternative results in reducing the flow at the
Mtibwa EFA site below the RAD in the 2nd periods of March and June.
Climate change scenario
To offer a long-term view of the availability of water at Dakawa, the historic record
has been reviewed to identify any visible decadal trends in flow. As shown in Figure
D-2, no discernible trends are shown in the recorded data.
Figure D.2:    Recorded Monthly River Flows at Dakawa 1953-1983
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                            D-5
Table D.3 Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa EFA Site, End of 2016 Scenario
                     (a)              (b)           (c)             (d)            (e)             (f)                (g)           (c+d+e-a-
                   Sugar          Mkindo         1-in-5 yr                                    Dakawa 2000          Mgongola             f-g)
                   Estate        Irrigation        flow         Low flow       Low flow        ha Scheme            Scheme          Residual         Driest      Over or
                   Water           Water         Dakawa            at             on             Pump              Additional          Flow        year RAD      Under
   Period           Use*            Use**         Gauge         Mkindo**       Diwale**       Requirement          Water use        at Mtibwa      at Mtibwa      RAD
    March 2         4.00             0.22          10.8           2.5             1.3             3.42               1.18                6.0          3.0          3.0
     April 1        4.00             0.22          19.7           8.3             7.2             2.71               1.18              27.3           5.0         22.3
           2        4.00             0.22          32.6           9.9            12.4             3.45               1.18              46.3           5.0         41.3
      May 1         4.00             0.22          39.0           6.5             8.5             3.48               1.18              45.3           5.0         40.3
           2        4.00             0.22          25.4           5.9             8.4             3.79               1.18              30.7           5.0         25.7
     June 1         4.00            0.22           14.5           4.8             6.0             3.88               1.18              16.2           5.0         11.2
           2        4.00             0.22          11.9           3.1             2.7             3.14               1.18                9.4          5.0          4.4
      July 1        4.00             0.22            9.2          2.4             2.0             2.76               1.18                5.7          4.1          1.6
           2        4.00             0.22            9.0          2.1             3.2             2.35               1.18                6.7          4.1          2.6
 Notes:
 * Full use of current water rights on 11,000 ha of sugar.
 ** For information purposes only, as the abstraction for Mkindo Irrigation is above the Mkindo gauge, so it is already accounted for in the Mkindo flow data.
 † Assumes lowest average flow in half month period for Mkindu and Diwale based on 6 years of gauge data at each station.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                                 D-6
Table D.4: Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa EFA Site, 5 to 10 Years in Future Scenario
                   Sugar          Mkindo         1-in-5 yr                                    Dakawa 2000          Mgongola
                   Estate        Irrigation        Flow        Low Flow        Low Flow        ha Scheme            Scheme          Residual         Driest      Over or
                   Water           Water         Dakawa         Mkindo          Diwale           Pump              Additional          Flow        year RAD      Under
   Period           Use*            Use**         Gauge         Gauge†          Gauge†        Requirement          Water Use        at Mtibwa      at Mtibwa      RAD
    March 2        11.50             0.22          10.8           2.5             1.3             3.42               1.18               -1.5          3.0         -4.5
     April 1       11.50             0.22          19.7           8.3             7.2             2.71               1.18              19.8           5.0         14.8
           2       11.50             0.22          32.6           9.9            12.4             3.45               1.18              38.8           5.0         33.8
      May 1        11.50             0.22          39.0           6.5             8.5             3.48               1.18              37.8           5.0         32.8
           2       11.50             0.22          25.4           5.9             8.4             3.79               1.18              23.2           5.0         18.2
     June 1        11.50            0.22           14.5           4.8             6.0             3.88               1.18               8.7           5.0          3.7
           2       11.50             0.22          11.9           3.1             2.7             3.14               1.18               1.9           5.0         -3.1
      July 1        4.00             0.22            9.2          2.4             2.0             2.76               1.18               5.7           4.1          1.6
           2        4.00             0.22            9.0          2.1             3.2             2.35               1.18                6.7          4.1          2.6
 Notes:
 * From Mtibwa Sugar Estate General Manager at a meeting at the Plantation with IRRIP staff on January 27, 2015.
 ** For information purposes only, as the abstraction for Mkindo Irrigation is above the Mkindo gauge, so it is already accounted for in the Mkindo flow data.
 † Assumes lowest average flow in half month period for Mkindu and Diwale based on 6 years of gauge data at each station.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                                 D-7
Table D.5: Low-flow Residual Flows (m3/s) in Relation to the RAD at Mtibwa EFA Site with Sprinkler Irrigation, Current Abstractions
           Scenario
                   Sugar          Mkindo         1-in-5 yr                                    Dakawa 2000          Mgongola
                   Estate        Irrigation        Flow        Low Flow        Low Flow        ha Scheme            Scheme          Residual         Driest      Over or
                   Water           Water         Dakawa         Mkindo          Diwale           Pump              Additional          Flow        year RAD      Under
   Period           Use*            Use**         Gauge         Gauge†          Gauge†        Requirement          Water Use        at Mtibwa      at Mtibwa      RAD
    March 2        11.50             0.22          10.8           2.5             1.3             3.42               0.86               -1.2          3.0          -4.2
     April 1       11.50             0.22          19.7           8.3             7.2             2.71               0.86              20.1           5.0         15.1
           2       11.50             0.22          32.6           9.9            12.4             3.45               0.86              39.1           5.0         34.1
      May 1        11.50             0.22          39.0           6.5             8.5             3.48               0.86              38.1           5.0         33.1
           2       11.50             0.22          25.4           5.9             8.4             3.79               0.86              23.5           5.0         18.5
     June 1        11.50            0.22           14.5           4.8             6.0             3.88               0.86                9.0          5.0          4.0
           2       11.50             0.22          11.9           3.1             2.7             3.14               0.86                2.2          5.0         -2.8
      July 1        4.00             0.22           9.2           2.4             2.0             2.76               0.86                6.0          4.1          1.9
           2        4.00             0.22           9.0           2.1             3.2             2.35               0.86                7.0          4.1          2.9
 * From Mtibwa Sugar Estate General Manager at a meeting at the Plantation with IRRIP staff on January 27, 2015.
 ** For information purposes only, as the abstraction for Mkindo Irrigation is above the Mkindo gauge, so it is already accounted for in the Mkindo flow data.
 † Assumes lowest average flow in half month period for Mkindu and Diwale based on 6 years of gauge data at each station.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                                                                                                                 D-8
In the absence of site-specific climate change data, a general assessment of the
sensitivity of environmental flow compliance can be made by assuming a 10%
reduction in river flows as a result of climate change. This constitutes a conservative
assessment for a 30 year period particularly during the wet season where the latest
climate change reports for Tanzania suggest that rainfall is likely to increase
(McSweeney et al. 2012). The results of this analysis showed that the negative
impact on the RAD occurred in the same periods, but were greater in magnitude.
Conclusions
Under current conditions and in the short-term future (end of 2016), proposed action
and all other irrigation alternatives for the Mgongola scheme will result in flows above
the RAD at the Mtibwa EFA site. But as the Mtibwa Sugar Estate brings on its
additional water rights, which appears to be inevitable, the RAD will not be met
during 2 of the 9 semi-monthly periods (2nd periods of March and June) of the
irrigation season for the Mgongola scheme.
This analysis does not include flows from Divue, Dizingwi and Mgongola rivers or any
of the small drainages that flow into the Wami River from the south between the
Dakawa gauge and the Mtibwa EFA site. No data is available for these water
sources. However, it is unlikely that these flows would offset the RAD deficits as
these rivers are minor (and at least in one case intermittent) and they would have to
have a combined flow equal to the gauged flow in the Mkindo River in the 2nd period
of June, and 18% greater than the combined gauged flow of the Diwale and Mkindo
rivers in the 2nd period of March. Neither of these are reasonable assumptions.
Citations
CDM Smith. 2013. Draft Environmental Assessment, Rehabilitation of Dakawa
     Irrigation Scheme. IRRIP1, for USAID/Tanzania. 4 December 2013. 105pp.
iWASH. 2013. Climate in the Wami and Ruvu Basins, Tanzania: Current
     Characteristics and Future Projections. Draft interim report. Tanzania
     Integrated Water, Sanitation and Hygiene (iWASH) Program, September
     2013. 68pp.
McSweeney, C., M. New and G. Lizcano. 2012. UNDP Climate Change Country
     Profiles: Tanzania. 27 pp. Available: http://country-profiles.geog.ox.ac.uk/
     [Accessed 29 January 2015].
Sarmett, Julius, Elizabeth Anderson and Appa Mandari. 2008. Wami River Sub-
      Basin, Tanzania: Initial Environmental Flow Assessment. Wami-Ruvu Basin
      Water Office, Global Water for Sustainability Program, Florida International
      University, and Water Development Alliance. Synthesis Report, June 2008.
      151pp. http://pdf.usaid.gov/pdf_docs/pnads254.pdf accessed on 13
      November 2013.
Wami/Ruvu Basin Water Office (WRBWO). 2015. Report on Water Use in Wami
      Subcatchment. 23 January 2015. 6 pp.
ENVIRONMENTAL ASSESSMENT
CONSTRUCTION OF MGONGOLA IRRIGATION SCHEME                                           D-9
           Engineering Services for the Tanzania
Irrigation and Rural Roads Infrastructure Project (IRRIP1)