The Daily Progress Report for the Augmentation of Sea Water Intake Channel at Reliance Industries Ltd. details work activities and equipment status as of February 15, 2025, highlighting ongoing dredging and excavation efforts. Key issues include a breakdown of the grab dredger and non-availability of spare parts for Excavator 650. Progress towards project targets shows cumulative achievements in both soft soil and hard rock areas.

Uploaded by

JITENDRA KUMAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views2 pages

DPR 119 DT 28-12-2024

The Daily Progress Report for the Augmentation of Sea Water Intake Channel at Reliance Industries Ltd. details work activities and equipment status as of February 15, 2025, highlighting ongoing dredging and excavation efforts. Key issues include a breakdown of the grab dredger and non-availability of spare parts for Excavator 650. Progress towards project targets shows cumulative achievements in both soft soil and hard rock areas.

Uploaded by

JITENDRA KUMAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DAILY PROGRESS REPORT Deep Dredging & Infra Pvt. Ltd.

Client RELIANCE INDUSTRIES LTD DPR Date 14/Feb/2025


Wo No. 230183121 Reporting Date 15/Feb/2025
Project Augmentation of Sea Water Intake Channel at Reliance Ind, Jamnagar. DPR No. 119
Project No 102408

A Weather Report
S. No. Today
a Weather Sunny

B Today's Work Activities C Work Plan for Next Day


1 CSD working at 0.550 KP Both side long boom excavator positioned for working
2 Grab Dredger breakdown due to lever problem Second Drill machine to be started at south side
3 Ex- 450, Ex-370, Ex-380, Ex-210 & Ex- 650 working simultaneously and removing hard rock Excavator Working at 0.700 KP in North side and south side for making working bed
4 Excavator 205 working at 0.700 KP (South), Removing sludge Grab dredger to be shifted at 0.590 KP
5 Both Drilling Machines working and continued, 62 Holes Completed,
6 Survey boat breakdown due to gear lever problem

D Equipment Status
Break down time (if any)
Working
S. No. Equipment Details Working Location (Yes/No) Remarks
From To
1 Cutter Suction Dredger 0.550 KP Yes
2 Bulldozer Dumping Area Yes
3 I. Excavator North Side Yes
4 II. Excavator North Side Yes
5 III. Excavator North Side Yes
6 IV. Excavator South Side No
7 V. Excavator North Side Yes
8 VI. Excavator B/D Yes Awaiting for spare parts, in transit
9 VII. Excavator South Side Yes
10 VIII. Excavator "Y" Channel Yes
11 IX. Excavator North Side Yes
12 Dumpers/Tippers Dumping Area Yes
13 Drilling Rig 0.620 KP Yes
14 Grab Derger (Seven Star I) 0.440 KP Yes Operational and working
Total
F Progress
Cumulative
Quantity Details Monthly (Dec'24) Till date
Target
Sr. No. Area UOM Completion
Today's Cumulative Achieved (till
Scope Quantity Progress Previous Progress Plan 22th Dec'24) Plan Actual

1 MAIN INTK CHNL IN ALL TYP SOIL CUM 50,000 200 32656 32856 7000 10455 26000 32856 31/May/25

2 MAIN INTK CHNL IN HARD ROCK CUM 125,000 750 38501 39251 15000 13805 34000 39251 15/Jun/25

Total CUM 175,000 950 71157 72107

G Equipment Details
Qty As per Status of
S.No. Vessel Remarks
WO Mobilization

1 Bulldozer 1 Nos Mobilized On Site


2 Cutter Suction Dredger 1 Nos Mobilized On Site
3 Survey Equipment Bathymetry 1 Nos Mobilized On Site
4 Survey Equipment Land Survey 1 Nos Mobilized On Site
5 Excavators 9 Nos Mobilized On Site
6 Rock Breaker Attachment 2 Nos Mobilized On Site
7 Dumpers 8 Nos. Mobilized On Site
8 Crane (50 to 75 Ton) 1 Nos Mobilized On Site
9 Tug boat 1 Nos Mobilized On Site
10 DG 2 Nos Mobilized On Site
11 Survey Boat 1 No Mobilized On Site
12 Service Boat 1 No Mobilized On Site
13 Drilling Rig with compressor 2 Nos Mobilized On Site
14 Grab Dredger (Seven Star I) 1 Nos Mobilized On Site
15 JCB 1 Nos Mobilized On Site

H Major Issues & Information


1 Non Availability of Excavator 650 spare parts , Ordered and in transit