Saep 25D

The document outlines the project key and field scope quantities for various construction and engineering disciplines, detailing specific items, their quantities, and associated costs. It includes categories such as civil works, offshore and onshore fabrication, structural steel, mechanical equipment, and piping. Each item is assigned a unique KQ code and mapped to corresponding cost accounts (COAs) for financial tracking and management.

Uploaded by

mohamed salah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views7 pages

Saep 25D

The document outlines the project key and field scope quantities for various construction and engineering disciplines, detailing specific items, their quantities, and associated costs. It includes categories such as civil works, offshore and onshore fabrication, structural steel, mechanical equipment, and piping. Each item is assigned a unique KQ code and mapped to corresponding cost accounts (COAs) for financial tracking and management.

Uploaded by

mohamed salah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Project Key and Field Scope Quantities including the COA for each Item

QUANTITY SCOPE Key Qty Description


DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
All the removal of obstruction such as structures, buildings, and trees,
1 200.01 SITE CLEARING AND GRADING M2 M2 4110 other vegetation that prevent the commencement of the construction of
the intended facility.
All the earth, soil, or other material used to replace previously excavated
2 200.02 EARTH WORK - BACKFILL M3 M3 4570 material, as around a newly constructed foundation wall.

All earth, rock or other materials removal to allow the construction of a


3 200.03 EARTH WORK - EXCAVATION M3 M3 4120,4130,4470, 7610 foundation or basement or installation of underground piping or cables.

All but is not limited to, all types of reinforced ready mix concrete (2,500,
3000, 4,000 psi and higher) including all Rebars (Bare or FBE coated),
4 200.04 REINFORCED CONCRETE M3 M3 4440
including formwork and below grade coating with APCS-10.
CIVIL
(SCA 200) All reinforcement rebar used in the construction of reinforced concrete
5 200.05 STEEL BAR REINFORCEMENT MT MT 4510 (bare and coated) irrespective of the size.

All asphalt paving including, but not limited to: 100 mm asphalt course
6 200.06 ASPHALT PAVING M2 M2 4220 (binder and surface course) compaction, leveling and testing.

7 200.07 FENCING LM LM 4340 All type of fence irrespective of the type (Type I , II, etc.)
All types of buildings which may be precast or Masonry types, structural,
etc. . The cost includes all associated architectural, HVAC, mechanical
BUILDING TYPE - ex. CONTROL BLDG, and electrical cost required for the building but excludes the outfit of the
8 200.08 M2 M2 4701
PIB, SUBSTA., WAREHOUSE, ETC. building such as furniture or service equipment such as lab equipment.

All cost associated with the fabrication of the facility which ay include
1 300.01 OFFSHORE DEEP WATER - FABRICATION MT MT 5801-5809 the cost of Standby time, weather down-time, testing, scaffolding,
Mob/De-Mob, pre-commissioning & survey
All cost associated with installation of the facility which ay include the
2 300.02 OFFSHORE DEEP WATER- INSTALLATION DAYS DAYS 5801-5809 cost of Standby time, weather down-time, testing, scaffolding, Mob/De-
Mob, pre-commissioning & survey
All cost associated with transportation of the facility which ay include
3 300.03 OFFSHORE GENERAL ITEMS - TRANSPOR MT MT 5811-5819 the cost of Standby time, weather down-time, testing, scaffolding,
OFFSHORE Mob/De-Mob, pre-commissioning & survey
(SCA 300) All cost associated with installation of the facility which ay include the
4 300.04 OFFSHORE GENERAL ITEMS - INSTALLAT DAYS DAYS 5811-5819 cost of Standby time, weather down-time, testing, scaffolding, Mob/De-
Mob, pre-commissioning & survey
All cost associated with the onshore fabrication cost only of Jackets,
5 300.05 ONSHORE FABRICATION MT MT 5821-5829
subsea structures & pipeline coatings & spools
All cost associated with the offshore installation cost only of jackets,
6 300.06 OFFSHORE INSTALLATION DAYS DAYS 5831-5839
decks, pipelines, cables & well hook-up
All cost associated with the onshore fabrication cost only of topsides
7 300.07 ONSHORE FABRICATION (DECKS) MT MT 5851-5859
(decks) & platform upgrade/extension/modification

KeyQty Saudi Aramco: Company General Use Page 1 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
All light steel required for Grating, hand rails, ladders, straps, stair
1 400.01 STEEL, EXTRA LIGHT <12 LB/FT MT MT 5111, 5211, 5221 treads, rods, plates and structural shapes less than or equal to 20
pounds per foot.
All steel required for structural shapes used in the fabrication of Steel
pipe rack, columns, beams, X-brace, catwalk,
2 400.02 STEEL, LIGHT >12LB/FT TO <20LB/FT MT MT 5112, 5212, 5222
stairs, ladders between 12 to 20 pounds per foot.

All steel required for structural shapes used in the fabrication of Steel
pipe rack, columns, beams, X-brace, catwalk,
3 400.03 STEEL, MEDIUM >20LB/FT TO <40LB/FT MT MT 5113, 5213, 5223
stairs, ladders between 20 to 40 pounds per foot.

STRUCTURE
All steel required for structural shapes used in the fabrication of Steel
(SCA 400) pipe rack, columns, beams, X-brace, catwalk,
4 400.04 STEEL, HEAVY 40LB/FT TO 80LB/FT MT MT 5114, 5214, 5224
stairs, ladders between 40 to 80 pounds per foot.

All steel required for structural shapes used in the fabrication of Steel
pipe rack, columns, beams, X-brace, catwalk,
5 400.05 STEEL, EXTRA HEAVY >80LB/FT MT MT 5115, 5215, 5225
stairs, ladders greater than 80 pounds per foot.

All miscellaneous steel required for structural shapes used in the


fabrication of Steel pipe rack, columns, beams, X-brace, catwalk, stairs,
6 400.06 MICS. STEEL MT MT 5116, 5216, 5226
ladders not part of any other identified steel categories

500.01 PROCESS VESSELS


Specialized type of process equipment used as reactors such as
1 500.011 Major Reactors EACH MT 1310, Continuous Catalyst Regenerator (CCR), Fixed Bed Reactors, etc.

All Columns/Towers used for Distillation, Stripping , Absorption,


Adsorption and Extraction inclusive of all internals (Tray or Packing).
2 500.012 Columns /Towers EACH MT 2650, 1110,1120 They are typically erected vertically and are cylindrical in shape with
heads at each end of the cylinder.

All pressurized horizontal vessel used as settling drums, surge tanks,


3 500.013 Drums EACH MT 1130, 1140,1150, 1170, 1100,2050
and distillate drums.
4 500.014 Others EACH MT 1165.89 , 1165,1166
All large capacity storage tanks of all types of roofs as well as all
5 500.02 STORAGE TANKS EACH MBBL 1210,1220,1230, 1240, 1320, spherical and Spheroidal shaped tanks for all types of services.

All types of gas and air compressor required for the project irrespective
of the capacity , metallurgy or type. It includes all but not limited to
6 500.03 COMPRESSORS EACH HP 1520,1510,1530 centrifugal compressors, reciprocating compressors along with the
driver coupled to each which may be motor, turbine, combustion gas
turbines, etc.
All centrifugal gas-moving or air-moving machine with a design pressure
7 500.04 BLOWERS EACH HP 1540 of less than 100 PSIG. It includes all Single or multi-stage centrifugal
turbo blower, Rotary blower,
All types of pumps required for the projects irrespective of the capacity ,
metallurgy or type. It includes all but not limited to centrifugal pumps,
1610,1620,1630, 1640,1650, reciprocating pumps, rotary pump, diaphragm pumps, submersible
8 500.05 PUMPS EACH HP
1660,1670, pumps along with the driver coupled to each which may be motor,
turbine, combustion gas turbines, etc.

All types of Electrical Submersible Pump (ESP) for wells required for the
ELECTRICAL SUBMERSIBLE PUMP FOR
500.06 EACH HP 1680 projects irrespective of the capacity , metallurgy or type. It includes the
OFFSHORE Variable Speed Driver.
All electrical motors include all types of motors intended for driving
rotating equipment or supplying power to a facility but are not part of a
packaged unit such as motor driver compressor or motor driven pump,
9 500.07 ELECTRIC MOTORS EACH KW 1710,1340,1700 etc. Types of motors include Standard open drip-proof motors, Totally-
enclosed fan-cooled motors (TEFC), Explosion-proof motors, TEFC
motor integral with variable speed drive..

KeyQty Saudi Aramco: Company General Use Page 2 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
All steam turbine driver includes condenser and all associated
accessories required for driving an equipment or generator but is not
10 500.08 STEAM TURBINES EACH HP 1720 part of a packaged unit such as steam turbine driven compressor or
steam turbine driven pump, etc.

MECHANICAL/ All steam turbines are used to drive a generator or mechanical


PROCESS machinery is a stand alone and but not part of a packaged unit such as
EQUIPMENT 11 500.09 GAS TURBINES EACH HP 1730
steam driven compressor or pump, etc.
(SCA 500)
All boilers which are closed vessels in which water or other fluid is
12 500.1 BOILERS EACH LB/HR 2620,2410,2420 heated. The heated or vaporized fluid exits the boiler for use in various
processes or heating applications.
All process Heaters/Furnaces are equipment where heat is liberated and
transferred directly or indirectly to a solid or fluid mass for the purpose
13 500.11 PROCESS HEATERS / FURNACES EACH MMBTU/HR 2510 of effecting a physical or chemical change. The components of
Heater/Furnace include but limited to the fire box, burners, exhaust
stack, etc.
All equipment designed to transfer heat from one fluid to another fluid
which includes but not limited to Air cooler, Fixed tube sheet shell and
14 500.12 HEAT EXCHANGERS EACH M2 2640,2610,2660,2600,2610, 2630,
tube exchangers, Floating head shell exchanger, U-tube shell and tube
exchangers, etc.
All types of flares ( Derrick-supported, Guyed, Self-supported, Horizontal
ground) system which may be composed of several parts such as a flare
tip, a seal, an ignition system, a knock-out drum and a riser stack with all
15 500.13 FLARES EACH DIA & HEIGHT 2550,2930
type of flare type which could be either smokeless or non-smokeless.

Used primarily to generate electrical power through the combustion of


gas, fuel oils, and synthetic fuels to produce hot gas that rotates the
16 500.14 GAS TURBINE GENERATORS EACH MW 2210, driver. It includes the three primary sections mounted on the same shaft:
the generator, the combustion chamber (or combustor) and the gas
turbine.
Used primarily as a stand-by unit to supply electrical power in the event
of an interruption of the main power supply. It includes a voltage
17 500.15 DIESEL GENERATORS EACH MW 2220,2240 regulator—3 phase sensing with volts-per-hertz; auto start-stop module;
electric hourmeter; and voltmeter.

Used primarily to generate electrical power through the use of steam


(high, medium or low ) to rotate the shaft of the generator. It includes the
18 500.16 STEAM TURBINE GENERATORS EACH MW 2230 three primary sections mounted on the same shaft: the generator the
combustion chamber (or combustor) and the steam turbine.

All energy recovery heat exchanger that recovers heat from a hot gas
stream. It produces steam that can be used in a process (cogeneration)
or used to drive a steam turbine (combined cycle). HRSGs consist of
19 500.17 HEAT RECOVERY UNITS (HRSG) EACH M2 2520
four major components: the economizer, evaporator, super heater and
water preheater

All special equipment specific to the facility with high value cost and
20 500.18 SPECIALTY EQUIPMENT EACH Lot 1030,1040, could be a packaged unit specially designed for this facility.

All process equipment not included in any category within the


21 500.19 OTHERS EACH Lot 1050,1060,
equipment Key Quantity list.

KeyQty Saudi Aramco: Company General Use Page 3 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
CARBON STEEL PIPING- LARGE BORE All carbon steel piping irrespective of the service with large bore
1 600.01 LM MT 3112 diameter with sizes exceeding 2 inch
>2"
CARBON STEEL PIPING- SMALL BORE All carbon steel piping irrespective of the service with large bore
2 600.02 LM MT 3111 diameter with sizes equal or smaller than 2 inch
<=2"
All lined piping irrespective of the service with large bore diameter with
3 600.03 LINED PIPING - LARGE BORE LM MT 3416
sizes exceeding 2 inch
All lined piping irrespective of the service with large bore diameter with
4 600.04 LINED PIPING - SMALL BORE LM MT 3415
sizes equal or smaller than 2 inch
All Non-Metal piping irrespective of the service with large bore diameter
5 600.05 NON-METAL PIPING - LARGE BORE LM MT 3512
with sizes exceeding 2 inch
All Non-Metal piping irrespective of the service with large bore diameter
6 600.06 NON-METAL PIPING - SMALL BORE LM MT 3511
with sizes equal or smaller than 2 inch
All cross country piping irrespective of the service with large bore
diameter used for transporting products in excess of 5 KM long used for
7 600.07 CROSS COUNTRY PIPING LM MT 3910
oil, gas, water, products, etc. and may contains sectionalizing valves
stations.
STAINLESS STEEL PIPING - LARGE All Stainless steel piping irrespective of the service with large bore
PIPING 8 600.08 LM MT 3212 diameter with sizes exceeding 2 inch
BORE
(SCA 600)
STAINLESS STEEL PIPING - SMALL All Stainless steel piping irrespective of the service with large bore
9 600.09 LM MT 3211 diameter with sizes equal or smaller than 2 inch
BORE
All vales with stainless steel body irrespective the size, rating (300, 600#)
10 600.1 STAINLESS STEEL VALVES EACH EACH 3250
and type (gate, ball, check, etc.,)
All vales with carbon steel body irrespective of the size, rating (300,
11 600.11 CARBON STEEL VALVES EACH EACH 3150
600#) and type (gate, ball, check, etc.,)
All pig launcher/receivers installed on pipelines for maintenance
purposes and may be located inside or outside a facility irrespective of
the size and rating. It shall include all associated piping and vales
12 600.12 SCRAPERS / RECEIVERS EACH EACH 3940 required for launching and receiving the pig such as cranes, isolation
valves (All costs associated with mechanical, valve, electrical and
instrumentation etc., within 15 meter of the facility).

Includes the cost of material only for different sizes of rigid pipelines
12 600.12 OFFSHORE PIPELINE (SUBSEA)- RIGID MT MT 3991-3999, 5884-5889,

OFFSHORE PIPELINE (SUBSEA)- Includes the cost of material only for different sizes of flexible pipelines
12 600.12 LM LM 5891-5899
FLEXIBLE
Includes all the cos of material only for subsea cable & accessories
1 700.01 SUBSEA MARINE CABLE LM LM 7050-7054 (Power, Composite & Umbilical etc.)
1 700.02 LOW VOLTAGE CABLES LM LM 7180, 7110 All electrical and control cables 600V and below
2 700.03 MEDIUM VOLTAGE CABLES LM LM 7170 All electrical cables above 600V and less than 69KV
3 700.04 HIGH VOLTAGE CABLES LM LM 7120 All electrical cables 69KV and above
4 700.05 CABLE TRAYS (Elect. & Instrumentation) LM LM 7230 All straight line cable trays - excluding fittings
All uninterruptable power systems - excluding renewable energy UPS
5 700.06 UPS EACH KVA 7960

All low voltage transformers with primary voltage 600V and below
6 700.07 TRANSFORMERS - LV EACH KVA 7350
ELECTRICAL All medium voltage transformers with primary voltage greater than 600V
(SCA 700) 7 700.08 TRANSFORMERS - MV EACH KVA 7340
and less thank 69KV
All high voltage transformers with primary voltage 69KV and above
8 700.09 TRANSFORMERS - HV EACH KVA 7410

9 700.1 SWITCHGEAR - HV EACH KVA 7420 All types of high voltage switchgear 69KV and above
All types of medium voltage switchgear above 600V and less than 69KV
10 700.11 SWITCHGEAR - MV EACH KVA 7360

All types of low voltage switchgear, including switch racks, 600V and
11 700.12 SWITCHGEAR - LV EACH KVA 7370
below
Overhead transmission and distribution lines of all voltages.
12 700.13 TRANSMISSION LINES LM LM 7460, 7461, 7462, 7463, 7464, 7466

13 700.14 OTHERS Lot Lot

KeyQty Saudi Aramco: Company General Use Page 4 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
All types of fiber optic cables used for communication applications
1 780.01 FIBER OPTIC CABLE LM LM 7874

Includes all the cost of material only for subsea F.O. cable & accessories
2 780.02 SUBSEA FIBER OPTIC CABLE LM LM 6362

All types of data switches used for communications applications


3 780.03 DATA SWITCH (INCL LAN, WAN, ETC.) EACH Ports 7801, 7803, 7804, 7805, 7825, 7828

Refer to DATA SWITCH (Incl All types of data switches used for communications applications
4 780.04 LAN (LOCAL AREA NETWORK) EACH Switch
LAN, WAN, etc.)
COMMUNICATIONS 5 780.05 RADIO & PAGING SYSTEM EACH User/or BS 7820, 7830 All Plant Radio and Paging System
(SCA 780) All equipment and materials relating to video conferencing, CATV and
6 780.06 VIDEO CONF/CATV/SATELLITE EACH Type 7866, 7867, 7861, 7864, 7865
Satellite applications
OUTSIDE PLANT ( INCL. All outside plant works such as trenching etc.
7 780.07 LM LM 7877
EXC/DB/BACKFILLING)
All equipment and materials relating to structured cabling systems of
8 780.08 STRUCTURE CABLING SYSTEM (SCS) LM User 7876
any type of buildings
Refer to DATA SWITCH (Incl All types of data switches used for communications applications
9 780.09 WAN (WIRELESS AREA NETWORK) EACH Router/ Switch
LAN, WAN, etc.)
10 780.1 OTHERS Lot Lot
IDAS (INTRUSION DETECTION ALARM All work associated with the IDAs system which include engineering,
1 780.51 LM LM 7872 material, installation , configuration and testing.
SYSTEM)
FOFSS FIBER OPTIC FENCE SENSORS Included in Fiber Optic Cable All work associated with the FOFSS system which include engineering,
2 780.52 ZONE ZONE
Refer to 6650 above material, installation , configuration and testing.
SYSTEM
LRDAS LONG RANGE DETECTION AND All work associated with the LRDAS system which include engineering,
3 780.53 LM LM 7873 material, installation , configuration and testing.
SECURITY ASSESSMENT SYSTEM
MIDS MULTIFUNCTIONAL INFORMATION All work associated with the MIDS system which include engineering,
(SCA 780) 4 780.54 ZONE ZONE
DISTRIBUTION SYSTEM material, installation , configuration and testing.
All work associated with the RSCC system which include engineering,
5 780.55 RSCC EA EA 7881
material, installation , configuration and testing.
All work associated with the security system which include engineering,
6 780.56 OTHERS Lot Lot material, installation , configuration and testing not captured in other key
quantity
6109,6110,6111,6112,6120,6121,61 All types of field instruments to measure and transmit flow, levels,
FIELD INSTRUMENTATION (ANALYZERS,
1 800.01 EACH EACH 22,6130,6131,6140,6141,6142,6800 temperature etc. Also included are devices such as analyzers, LEL and
GAGES,ETC.) ,6180 H2S monitors.
2 800.02 PROCESS CONTROL SYSTEMS -DCS CABINET I/O 6602 All DCS cabinets and associated equipment
3 800.03 PROCESS CONTROL SYSTEMS -ESD CABINET I/O 6603,6604,6240 All ESD cabinets and associated equipment
PROCESS CONTROL SYSTEMS - All VMS cabinets and associated equipment
4 800.04 CABINET I/O 6185, 6605, 6606
VIBRATION MONITOR
PROCESS CONTROL SYSTEMS -SURGE All SCS cabinets and associated equipment
5 800.05 CABINET I/O 6607, 6608
CONTROLS
INSTRUMENTATION 6 800.06 INSTRUMENT CABLES LM LM 6360,6370,6380,6361 All instrumentation cables including home runs
(SCA 800) All types of control valves irrespective of material and function
7 800.07 CONTROL VALVES EACH EACH 6811,6812,6851,6852
8 800.08 SAFETY VALVES EACH EACH 6821,6822 All types of safety valves irrespective of material and function
9 800.09 SCADA & RTUS EACH I/O 6601,7855,7856,7857, 7858 All RTU & SCADA Shelters including associated equipment
MOTOR OPERATED VALVES /MAIN LINE All types of MOV's irrespective of material and function
10 800.1 EACH EACH 6841, 6842
VALVES
11 800.11 METERING SKIDS EACH GPM 6010 All types of metering skids
Complete leak detection system including all materials and equipment
12 800.12 LEAK DETECTION SYSTEM EACH I/O 6133

13 800.13 TOTAL I/O COUNT EACH I/O 6900,6190 Count of all I/O's used on project

KeyQty Saudi Aramco: Company General Use Page 5 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
All types of hot and/or cold Insulation applied for process and non
1 900.01 PIPE INSULATION M2 M2 8110, 8111,8112
process piping.
All types of hot and/or cold Insulation applied for process equipment.
2 900.02 EQUIPMENT INSULATION M2 M2 8121,8122,8130, 8140
INSULATION & All fireproofing applied to the equipment (skirts/legs, support steel,
COATINGS 3 900.03 FIREPROOFING M2 M2 8211,82128221,8222,8230 ladders) and various steel structures using Magnesium oxychloride,
Concrete, Pyrocrete, etc.
(SCA 900)
9020, All the required painting for the piping, equipment and steelwork.
4 900.04 PAINTING M2 M2 9030,9040,9090,9110,9120,9130,91
40,9150,9160,9210,9220
5 900.05 OTHERS Lot Lot 9190
All detailed design, drafting, engineering, and other related services
necessary to purchase equipment and materials and construct a facility.
EQUIVALENT A
1 1.01 OVERALL DETAILED ENGINEERING MHRS It covers all disciplines required to produce the detailed design package
SIZE DRAWINGS
issued constructing a facility.

All detailed design, drafting, engineering, and other related services to


the civil work necessary to construct a facility. It covers all civil activities
EQUIVALENT A
2 1.02 CIVIL DETAILED DESIGN MHRS such as site preparation, buildings, roads, etc. required to produce the
SIZE DRAWINGS
detailed design associated with the civil work required for the facility.

All detailed design, drafting, engineering, and other related services to


the mechanical work necessary to construct a facility. It covers all
EQUIVALENT A
3 1.03 MECHANICAL DETAILED DESIGN MHRS mechanical activities such as equipment and piping required to produce
SIZE DRAWINGS
the detailed design associated with the mechanical work required for the
ENGINEERING facility.
(SCA 001) All detailed design, drafting, engineering, and other related services to
the electrical work necessary to construct a facility. It covers all
EQUIVALENT A
4 1.04 ELECTRICAL DETAILED DESIGN MHRS electrical activities such as equipment and piping required to produce
SIZE DRAWINGS
the detailed design associated with the electrical work required for the
facility.
All detailed design, drafting, engineering, and other related services to
the instrumentation work necessary to construct a facility. It covers all
EQUIVALENT A instrumentation activities such as equipment and piping required to
5 1.05 INSTRUMENTATION DETAILED DESIGN MHRS
SIZE DRAWINGS produce the detailed design associated with the instrumentation work
required for the facility.

All detailed design, drafting, engineering, and other related services not
EQUIVALENT A
6 1.06 OTHER DISCIPLINE DETAILED DESIGN MHRS included in any of the other categories within the Engineering Key
SIZE DRAWINGS
Quantity required for the facility.

KeyQty Saudi Aramco: Company General Use Page 6 Of 7


Project Key and Field Scope Quantities including the COA for each Item
QUANTITY SCOPE Key Qty Description
DISCIPLINE KQ Code DESCRIPTION QUANTITY/COUNT SCOPE UNIT Mapped COAs
UNIT QUANTITY/COUNT
1 100.01 OVERALL DIRECT LABOR MHRS MHRS
All direct civil related construction manhours necessary to construct a
facility. It covers all civil activities manhours required for the
construction of the civil work of the facility. It includes all the manhours
2 100.02 CIVIL INSTALLATION DIRECT LABOR MHRS MHRS
associated with excavation, foundation, structural steel, painting, etc..
not captured in other category.

All direct mechanical/piping related construction manhours necessary to


MECHANICAL INSTALLATION DIRECT construct a facility. It covers all mechanical activities manhours
3 100.03 MHRS MHRS
required for the construction of the mechanical work such as piping of
LABOR
the facility.
All direct mechanical/equipment related construction manhours
necessary to construct a facility. It covers all process equipment related
EQUIPMENT INSTALLATION DIRECT activities manhours required for the erection/installation of all process
4 100.04 MHRS MHRS
LABOR equipment of the facility.

All direct electrical related construction manhours necessary to


construct a facility. It covers all electrical activities manhours required
ELECTRICAL INSTALLATION DIRECT for the construction of the electrical work of the facility. It includes all
CONSTRUCTION 5 100.05 MHRS MHRS
LABOR cables, conduits, cable trays, transformers, switchgear, bus ducts, etc.
(SCA 100)
All direct instrumentation related construction manhours necessary to
construct a facility. It covers all instrumentation activities manhours
INSTRUMENTATION INSTALLATION required for the construction of the electrical work of the facility. It
6 100.06 MHRS MHRS
DIRECT LABOR includes all wire, transmitter, conduits, cable trays, t, etc.

All direct communication related construction manhours necessary to


construct a facility. It covers all civil activities manhours required for the
COMMUNICATIONS INSTALLATION construction of the communication work of the facility. It includes all
7 100.07 MHRS MHRS
DIRECT LABOR wiring, paging system,. Telephone system, etc.

All other direct related construction manhours necessary to construct a


8 100.08 OTHER INSTALLATION DIRECT LABOR MHRS MHRS facility and not include as part of the civil, mechanical , etc.

All indirect construction manhours necessary to construct a facility. It


covers all manhours associated with filed supervision above foreman
9 100.09 OVERALL INDIRECT LABOR MHRS MHRS level, support services such as warehouse, transportation of labors,
required for the construction of the civil work of the facility.

Note: This is a generic list provided as guidelines only. The key quantities for each project varies depending on the project type and the scope of work for each project
therefore new items may be added and some may be deleted as applicable.

KeyQty Saudi Aramco: Company General Use Page 7 Of 7