0% found this document useful (0 votes)
45 views2 pages

05-ITP Masonry Work

This document outlines the Inspection and Test Plan (ITP) for masonry work at the SARAI Club House project, detailing the approval process for shop drawings, method statements, and material submittals. It specifies inspection activities, acceptance criteria, and required documentation for various stages of construction, ensuring compliance with Egyptian Standard Specifications. The plan includes a schedule for inspections and tests to be conducted throughout the project lifecycle.

Uploaded by

shaaban52
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views2 pages

05-ITP Masonry Work

This document outlines the Inspection and Test Plan (ITP) for masonry work at the SARAI Club House project, detailing the approval process for shop drawings, method statements, and material submittals. It specifies inspection activities, acceptance criteria, and required documentation for various stages of construction, ensuring compliance with Egyptian Standard Specifications. The plan includes a schedule for inspections and tests to be conducted throughout the project lifecycle.

Uploaded by

shaaban52
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Rev.

: 1

Code : 6
INSPECTION & TEST PLAN ( ITP) for Masonry Work
Date : 08/01/2025

Page : 1 OF 2

Client : MADENIT MISR Project Name: SARAI Club House Consultant:ACE Project Managment

Reference Documents Legend

A : Inspector
Applicable Code / Specs B : Client Inspector
H : Hold Point
W : Witness Point
M : Monitoring
Procedures R : Review Document
RI : Report Issuance
RT : Radiographic Test
UT : Ultrasonic Test
MSR : Material Submittal Request
MIR : Material Inspection Request
DSR : Document Submittal Request
DT : Dimensional Check
IR : Inspection Request
PQR : Procedure Qualification Record
WPQ : Welder Performance Qualification
AP : CLIENT APPROVAL
Prepared by Checked & Approved by

Name Eng. Ahmed Shaaban

Signature

Date
Rev. : 1

Code : 6
INSPECTION & TEST PLAN ( ITP) for Masonry Work Date : 08/01/2025

Page : 2 OF 2

Client MADENIT MISR Project Name:SARAI Club House Consultant:ACE Project Management

Inspection
Remarks or
No. Activity Description/Project milestones Project Reference Acceptance Criteria Frequency Verifying Document Client/owner
Contractor Consultant Report no.
representative

1 DOCUNENTS/SUBMITTALS

Egyptian Standard Specification


1.1 Approval of shop drawings Conforms to specifications&drawings Prior to start work Approved (SD) H H
&ECP-203-2007 & specs 04200

Egyptian Standard Specification


1.2 Approval of method of statement & ITP Conforms to specifications&drawings Prior to start work Approved Method Statement H H
&ECP-203-2007 & specs 04200

Egyptian Standard Specification


1.3 Material Submittal Approval Conforms to project specifications Prior to start work Approved (MSR) H H
&ECP-203-2007 & specs 04200

Egyptian Standard Specification Conforms to specifications


1.4 Materials Inspection Prior to start work Approved (MIR) H H
&ECP-203-2007 & specs 04200

2 INSPECTION

Egyptian Standard Specification&


2.1 Survey works Conforms to specifications&drawings On going IR / As Built H H
Project Specs

Egyptian Standard Specification& Prior to work


2.2 Surface Preparation for concrete According to industry Principles IR H H
Project Specs progress

1st coarse masonry works & Accessories (3Courses) Egyptian Standard Specification Prior to work
2.3 Conforms to specifications&drawings IR H H
&ECP-203-2007 & specs 04200 progress

MEP works( if any ) Egyptian Standard Specification& Prior to work


2.4 Conforms to specifications&drawings IR / Release H H
Project Specs progress

Half height masonry works Egyptian Standard Specification& Prior to work


2.5 Conforms to specifications&drawings - S W
Project Specs progress

Egyptian Standard Specification& Prior to work


2.6 Lintels Installation Conforms to specifications&drawings IR H H
Project Specs progress

Full height masonry works Egyptian Standard Specification Prior to work


2.7 Conforms to specifications&drawings IR H H
&ECP-203-2007 & specs 04200 progress

Egyptian Standard Specification& Prior to work


2.8 Curing by water for builded walls Conforms to specifications&drawings - S W
Project Specs progress

3 TESTS

Egyptian Standard Specification& accordance with ES


3.1 (Dimention -Appsorbition-Compressive strength) For Block Project Specs-Egyptian Code (ECP-205) Approved Test Result(DS) H R
Project Specs 1292

Egyptian Standard Specification& accordance with ES


3.2 Compressive strength for mortar Project Specs-Egyptian Code (ECP-205) Approved Test Result(DS) H R
Project Specs 1292