Rev.
: 1
Code : 6
INSPECTION & TEST PLAN ( ITP) for Masonry Work
Date : 08/01/2025
Page : 1 OF 2
Client : MADENIT MISR Project Name: SARAI Club House Consultant:ACE Project Managment
Reference Documents Legend
A : Inspector
Applicable Code / Specs B : Client Inspector
H : Hold Point
W : Witness Point
M : Monitoring
Procedures R : Review Document
RI : Report Issuance
RT : Radiographic Test
UT : Ultrasonic Test
MSR : Material Submittal Request
MIR : Material Inspection Request
DSR : Document Submittal Request
DT : Dimensional Check
IR : Inspection Request
PQR : Procedure Qualification Record
WPQ : Welder Performance Qualification
AP : CLIENT APPROVAL
Prepared by Checked & Approved by
Name Eng. Ahmed Shaaban
Signature
Date
Rev. : 1
Code : 6
INSPECTION & TEST PLAN ( ITP) for Masonry Work Date : 08/01/2025
Page : 2 OF 2
Client MADENIT MISR Project Name:SARAI Club House Consultant:ACE Project Management
Inspection
Remarks or
No. Activity Description/Project milestones Project Reference Acceptance Criteria Frequency Verifying Document Client/owner
Contractor Consultant Report no.
representative
1 DOCUNENTS/SUBMITTALS
Egyptian Standard Specification
1.1 Approval of shop drawings Conforms to specifications&drawings Prior to start work Approved (SD) H H
&ECP-203-2007 & specs 04200
Egyptian Standard Specification
1.2 Approval of method of statement & ITP Conforms to specifications&drawings Prior to start work Approved Method Statement H H
&ECP-203-2007 & specs 04200
Egyptian Standard Specification
1.3 Material Submittal Approval Conforms to project specifications Prior to start work Approved (MSR) H H
&ECP-203-2007 & specs 04200
Egyptian Standard Specification Conforms to specifications
1.4 Materials Inspection Prior to start work Approved (MIR) H H
&ECP-203-2007 & specs 04200
2 INSPECTION
Egyptian Standard Specification&
2.1 Survey works Conforms to specifications&drawings On going IR / As Built H H
Project Specs
Egyptian Standard Specification& Prior to work
2.2 Surface Preparation for concrete According to industry Principles IR H H
Project Specs progress
1st coarse masonry works & Accessories (3Courses) Egyptian Standard Specification Prior to work
2.3 Conforms to specifications&drawings IR H H
&ECP-203-2007 & specs 04200 progress
MEP works( if any ) Egyptian Standard Specification& Prior to work
2.4 Conforms to specifications&drawings IR / Release H H
Project Specs progress
Half height masonry works Egyptian Standard Specification& Prior to work
2.5 Conforms to specifications&drawings - S W
Project Specs progress
Egyptian Standard Specification& Prior to work
2.6 Lintels Installation Conforms to specifications&drawings IR H H
Project Specs progress
Full height masonry works Egyptian Standard Specification Prior to work
2.7 Conforms to specifications&drawings IR H H
&ECP-203-2007 & specs 04200 progress
Egyptian Standard Specification& Prior to work
2.8 Curing by water for builded walls Conforms to specifications&drawings - S W
Project Specs progress
3 TESTS
Egyptian Standard Specification& accordance with ES
3.1 (Dimention -Appsorbition-Compressive strength) For Block Project Specs-Egyptian Code (ECP-205) Approved Test Result(DS) H R
Project Specs 1292
Egyptian Standard Specification& accordance with ES
3.2 Compressive strength for mortar Project Specs-Egyptian Code (ECP-205) Approved Test Result(DS) H R
Project Specs 1292