Concrete Pouring Data Log

The document is a concrete pouring record for various structures at the A2O Tank South Right location, recorded as of February 18, 2025. It includes details such as pouring dates, concrete test results at 7 and 28 days, and the status of each pour. All tested samples show satisfactory results, indicating compliance with the required specifications.

Uploaded by

Fahril Gibran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views1 page

Concrete Pouring Data Log

The document is a concrete pouring record for various structures at the A2O Tank South Right location, recorded as of February 18, 2025. It includes details such as pouring dates, concrete test results at 7 and 28 days, and the status of each pour. All tested samples show satisfactory results, indicating compliance with the required specifications.

Uploaded by

Fahril Gibran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONCRETE POURING RECORD

LOCATION : A2O TANK SOUTH RIGHT Recorded as of : 18-Feb-25

vol 7 days 28 days


Fc Slump Sample Concrete
No. Structure Pouring Date RFI Number Test Testing Result (Mpa) Min Test RFI Testing Result (Mpa) Status
(Mpa) (cm) (set) Supplier Testing date Testing date 100%
m3 Location Spl-1 Spl-2 Spl-3 Ave 65% Location Number Spl-1 Spl-2 Spl-3 Ave

A Base Slab 1738 20


1 Blok RCS6 462 21-Feb-24 28 15 + 2.5 5 WITON 0167 , 0182 28-Feb-24 Internal lab 20.2 20.5 20.6 20.4 73% 20-Mar-24 BAM 0238 32.23 31.77 30.68 31.6 113% OK
20.5 20.9 21.3 20.9 75% 32.28 31.55 31.20 31.7 113% OK
21 20.2 19.9 20.4 73% 32.06 31.04 31.84 31.6 113% OK
20.7 20.8 20 20.5 73% 29.69 31.75 31.51 31.0 111% OK
19.9 20.9 21 20.6 74% 31.30 32.31 31.07 31.6 113% OK

2 Blok RCS5 483 1-Mar-24 28 15 + 2.5 5 WITON 0197 8-Mar-24 Internal lab 20.7 21.3 20.2 20.7 74% 29-Mar-24 WITON 0255 31.40 32.00 31.00 31.5 112% OK
20.9 20 21.5 20.8 74% 30.00 31.80 31.00 30.9 110% OK
20.4 20.8 20.2 20.5 73% 32.40 32.20 31.10 31.9 114% OK
21.4 20.5 21.1 21.0 75% 32.00 32.20 32.00 32.1 115% OK
21.6 20.7 21 21.1 75% 31.60 32.30 31.60 31.8 114% OK

3 Blok RCS8 357 13-Mar-24 28 15 + 2.5 4 WITON 0226 20-Mar-24 Internal lab 20.5 20.7 21.2 20.8 74% 10-Apr-24 BAM 0280 34.97 35.05 34.48 34.8 124% OK
20.6 20.3 21.3 20.7 74% 34.33 33.60 35.44 34.5 123% OK
21.7 22.3 20.6 21.5 77% 36.07 34.21 35.26 35.2 126% OK
21.3 21 22.1 21.5 77% 34.14 34.78 33.90 34.3 122% OK

4 Kicker wall RCS5 (west side) 16 18-Mar-24 28 15 + 2.5 1 WITON 0234 25-Mar-24 Internal lab 20.2 20 20.5 20.2 72% 15-Apr-24 WITON 0285 30.50 30.20 29.50 30.1 107% OK

5 Blok RCS 7 420 21-Mar-24 28 15 + 2.5 5 WITON 0236 28-Mar-24 Internal lab 20.2 20.3 20.6 20.4 73% 18-Apr-24 WITON 0289 32.20 30.60 31.20 31.3 112% OK
20.2 20.1 20.5 20.3 72% 30.80 31.80 30.80 31.1 111% OK
20.2 20.4 20.5 20.4 73% 32.50 31.60 31.40 31.8 114% OK
20.1 20 21 20.4 73% 31.20 31.00 30.90 31.0 111% OK
20.8 20.7 20.5 20.7 74% 31.50 30.90 31.30 31.2 112% OK
B Kickers & Wall 147 3
1 Kickers wall RCS5 49 23-Mar-24 28 15 + 2.5 1 WITON 0234 30-Mar-24 Internal lab 20.5 20.3 21 20.6 74% 20-Apr-24 Internal lab 0297 30.40 31.00 29.30 30.2 108% OK

2 Kickers wall RCS8 49 29-Mar-24 28 15 + 2.5 1 WITON 0249 5-Apr-24 Internal lab 20.5 20.2 20.8 20.5 73% 26-Apr-24 BAM 0304 32.11 33.12 32.65 32.6 117% OK

3 Kickers wall RCS7 49 4-Apr-24 28 15 + 2.5 1 WITON 0249 11-Apr-24 Internal lab 25.7 25.9 25.8 25.8 92% 2-May-24 BAM 0320 35.66 37.17 35.29 36.0 129% OK

C Wall 2020 43

1 ATRS Wall + Column - Row K (1) 40 13-May-24 28 15 + 2.5 1 WITON 0325 20-May-24 Internal lab 20.5 20.7 20.4 20.5 73% 10-Jun-24 BAM 0387 33.38 32.19 35.51 33.7 120% OK

2 ATRS Wall + Column - Row K (2) 38 23-May-24 28 15 + 2.5 1 WITON 0356 30-May-24 Internal lab 21 20.7 20.5 20.7 74% 20-Jun-24 BAM 0410 33.27 32.68 32.13 32.7 117% OK

3 ATRS Wall + Column - Row K (3) 33 31-May-24 28 15 + 2.5 1 WITON 0356 7-Jun-24 Internal lab 20.7 20.2 21 20.6 74% 28-Jun-24 BAM 0425 35.64 34.63 35.43 35.2 126% OK

4 ATRS Wall Grid 11 - 1st lift (1) 74 1-Jun-24 28 15 + 2.5 1 WITON 0356 8-Jun-24 Internal lab 20.7 20.6 20.9 20.7 74% 29-Jun-24 BAM 0425 34.35 33.73 35.23 34.4 123% OK

5 ATRS Wall Row J - 1st lift (1) 68 10-Jun-24 28 15 + 2.5 1 WITON 0383 17-Jun-24 Internal lab 21.2 21 21 21.1 75% 8-Jul-24 BAM 0448 29.88 35.20 34.64 33.2 119% OK

6 ATRS Wall Row I - 1st lift (1) 41 14-Jun-24 28 15 + 2.5 1 WITON 0383 21-Jun-24 Internal lab 20.4 20.5 20.8 20.6 73% 12-Jul-24 BAM 0457 34.46 33.59 33.66 33.9 121% OK

7 ATRS Wall Row J - 1st lift (2) 82 19-Jun-24 28 15 + 2.5 1 WITON 0383 26-Jun-24 Internal lab 20.7 20.9 20.8 20.8 74% 17-Jul-24 BAM 0467 34.93 34.41 37.39 35.6 127% OK

8 ATRS Wall Row H + Grid 13 - 1st lift (1) 56 24-Jun-24 28 15 + 2.5 1 WITON 0383 1-Jul-24 Internal lab 20.5 20.6 20.8 20.6 74% 22-Jul-24 BAM 0467 34.03 33.43 33.89 33.8 121% OK

9 ATRS Wall Row J - 1st lift (3) 84 27-Jun-24 28 15 + 2.5 1 WITON 0421 4-Jul-24 Internal lab 20.5 20.6 20.6 20.6 73% 25-Jul-24 BAM 0476 32.87 33.51 34.23 33.5 120% OK

10 ATRS Wall Grid 11 - 2nd lift (1) 42 29-Jun-24 28 15 + 2.5 1 WITON 0421 6-Jul-24 Internal lab 20.8 21 20.6 20.8 74% 27-Jul-24 BAM 0476 33.27 34.43 33.62 33.8 121% OK

11 ATRS Wall Row I - 1st lift (2) 84 5-Jul-24 28 15 + 2.5 1 WITON 0421 12-Jul-24 Internal lab 20.59 20.66 21.02 20.8 74% 2-Aug-24 BAM 0481 33.13 33.67 33.27 33.4 119% OK

12 ATRS Wall Row H 1st lift (2) 52 9-Jul-24 28 15 + 2.5 1 WITON 0449 16-Jul-24 Internal lab 20.9 20.69 21.08 20.9 75% 6-Aug-24 BAM 0489 34.26 33.94 30.78 33.0 118% OK

13 ATRS Wall Grid 20 1st lift (1) 7 12-Jul-24 28 SCC Flow 1 WITON 0449 19-Jul-24 Internal lab 21.75 20.49 22.07 21.4 77% 9-Aug-24 BAM 0489 34.36 35.07 34.45 34.6 124% OK
Page 1of 3