Nonconformity

The document contains multiple Nonconformity Reports (NCRs) for various companies, each detailing major nonconformities related to construction and safety standards. Each report includes a description of the nonconformity, root cause analysis, and proposed corrective actions to address the issues. The NCRs highlight the need for improved processes, supervision, and communication to ensure compliance with standards.

Uploaded by

Ramez Mamdouh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views10 pages

Nonconformity

The document contains multiple Nonconformity Reports (NCRs) for various companies, each detailing major nonconformities related to construction and safety standards. Each report includes a description of the nonconformity, root cause analysis, and proposed corrective actions to address the issues. The NCRs highlight the need for improved processes, supervision, and communication to ensure compliance with standards.

Uploaded by

Ramez Mamdouh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

NONCONFORMITY REPORT

Company Name :hussan allam NCR Number: 10

Reference Standard:Technical Spec Date:12:00:00 AM

Clause:8.6.a Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Handover of a building as doucment no 52 dated 415 before all required safety inspections were completed.

Auditee: Auditor: Senior Management:

(ahmed) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Inadequate knowledge of handeling over procedures

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Implement a checklist of required inspections and ensure all inspections are completed before handover.

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :sabbour NCR Number: 9

Reference Standard:ISO 9001/2017 Date:12:00:00 AM

Clause:8.7.1.a Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Rejected materials in MRR number 201 dated 2/2/2025 were not properly recorded or disposed of.

Auditee: Auditor: Senior Management:

(Ali) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


No structured process for controlling nonconforming outputs.

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Implement a tracking system for nonconforming materials

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :concord NCR Number: 8

Reference Standard:ISO 9001/2016 Date:12/2/2025

Clause:8.5.1.g Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Scaffolding with green gard label found unstable and notcomplay with safety regulation in floor 3 zone 1 and inuse

Auditee: Auditor: Senior Management:

(Mohamed) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Lack of trained personnel and missing inspections

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Ensure scaffolding is installed by certified workers with regular inspections

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :orascom NCR Number: 7

Reference Standard:ISO 9001/2015 Date:11/2/2025

Clause:8.5.1.e Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Rebars placed with incorrect cover and spacing in floor 5 zone 1 and supervisior is not following the approved drawing

Auditee: Auditor: Senior Management:

(Khaled) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Lack of supervision and incorrect reading of drawings.

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Strengthen site supervision and conduct regular rebar inspections

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :nile construction NCR Number: 6

Reference Standard:ISO 9001/2015 Date:10/2/2025

Clause:8.5.1.a.1 Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Concrete delivery note number 364 dated 2/12/2024 to site did not meet the specified strength.

Auditee: Auditor: Senior Management:

(ramy) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Miscommunication of mix design between contractor and supplier

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Implement strict verification of concrete mix before pouring

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :madkour NCR Number: 5

Reference Standard:ISO 9001/2015 Date:9/2/2025

Clause:8.4.3.c & e Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Repeated nonconforming NCR Number 10,15,17,110,130,and 150 for materials received from the same supplier without
action taken

Auditee: Auditor: Senior Management:

(Abdalla) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


No structured supplier performance review

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Implement a supplier evaluation and monitoring system

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :hussan allam NCR Number: 4

Reference Standard:project specifications Date:8/2/2025

Clause:8.4.2.a Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Materials on delivered note number 302 dated 3/5/2025 did not match project specifications

Auditee: Auditor: Senior Management:

(ahmed) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Materials delivered did not match project specifications.

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Strengthen procurement verification procedures and supplier

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :sabbour NCR Number: 3

Reference Standard:ISO 9001/2015 Date:7/2/2025

Clause:8.3.6.a Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Design modifications were made and executed on electrical room arch. without formal approval.

Auditee: Auditor: Senior Management:

(Ali) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Absence of a structured design change management system.

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Establish a formal design change control process

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :concord NCR Number: 2

Reference Standard:ISO 9001/2015 Date:6/2/2025

Clause:8.2.1.a Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Missing of client requirment regarding concret design mix

Auditee: Auditor: Senior Management:

(Mohamed) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Inadequate Communication with customers

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Review client requirements with the construction team, clarify any ambiguities, and implement a system for verifying
compliance with specifications.

Proposed Implementation Date

4
NONCONFORMITY REPORT

Company Name :orascom NCR Number: 1

Reference Standard:ISO 9001/2015 Date:5/2/2025

Clause:8.1.e Category: Major

Auditor:Ramez mamdouh

Description of the nonconformity


Project schedule number 5001 dated 5/9/2022 is not adequately detailed and missing project manager sign

Auditee: Auditor: Senior Management:

(Khaled) (Ramez mamdouh) (saied Mahmoud)

Root Cause (to be completed by auditee and agreed with auditor)


Insufficient planning and resource allocation

Proposed Corrective Action (to be completed by auditee and agreed with auditor)

Revise project scheduling process, implement detailed critical path analysis, and allocate resources effectively.

Proposed Implementation Date