PROJECT:            Construction of Kubo House
LOCATION:           N0.37 Woodhouse St., G.H. , Olongapo City
OWNER:              Mr. & Mrs. Ferdie Cruz
DATE:               10-Nov-24
SUBJECT:            BREAKDOWN OF ESTIMATES
                    Direct Materials and Labor Cost
Area                3mx5m Bedroom with GF CR and Kitchen
PREPARED BY:        AAE
        1 GENERAL REQUIREMENTS
          WORK DESCRIPTION/ SCOPE OF WORKS                     QTY         UNIT   COST        MATERIAL
      1.1 Mobilization and Demobilization                             1 lot        5,000.00     5,000.00
      1.2 Site Supervision                                            1 lot              -            -
      1.8 Architectural and Engineering Design                        1 lot        5,000.00     5,000.00
                    TOTAL FOR GENERAL REQUIREMENTS                                             10,000.00
        2 SITE WORKS ( Debris and Backfill Area)
          WORK DESCRIPTION/ SCOPE OF WORKS                      QTY        UNIT   COST        MATERIAL
      2.1 Floor area Leveling                                         1 lot       12,000.00    12,000.00
      2.2 Drain pipes relocation                                      1 lot        2,400.00     2,400.00
      2.3 Area backfilling                                            1 lot        2,000.00     2,000.00
      2.4 Backfilling of excavated portion                            1 lot        3,400.00     3,400.00
                    TOTAL                                                                      19,800.00
          Note: Backfilling materials to be provided by Owner ( As needed)
        3 EXISTING CHB WALL @ GF
          WORK DESCRIPTION/ SCOPE OF WORKS                      QTY        UNIT   COST        MATERIAL
      3.1 CHB laying to meet the hieght/ level at garden              1 lot       45,000.00    42,000.00
      3.2 Plastering Works
          3.2.1      Rip-rap plastering on the affected area          1 lot       12,000.00    12,000.00
          3.2.2      CHB wall plastering                              1 lot       18,000.00    18,000.00
          3.2.3      Removal of Kapak plastering                      1 lot       16,000.00    16,000.00
          3.2.4      Additional rebars on CHB wall                    1 lot        8,000.00     8,000.00
          3.2.5      Fire wall plastering                             1 lot       10,000.00    10,000.00
                    TOTAL                                                                      64,000.00
        4 2nd STEEL FRAMING WORKS
          WORK DESCRIPTION/ SCOPE OF WORKS                     QTY        UNIT    COST        MATERIAL
      4.1 Tubular Columns
          4.1.1     Steel Tubular Columns 2"X4" Erection              1 lot       32,000.00    32,000.00
          4.1.2     Welding works                                     1 lot       15,000.00    15,000.00
          4.1.3     Epoxy primer painting                             1 lot        6,000.00     6,000.00
      4.2 Tubular Beams and Floor framing
    4.2.1    Steel tubular 2"x3" floor joist                      1 lot      66,000.00    66,000.00
    4.2.2    Welding works                                        1 lot      36,000.00    36,000.00
    4.2.3    Epoxy primer painting                                1 lot      10,000.00    10,000.00
    4.2.4    Steel Stair going to doen to CR-Kitchen              1 lot      19,000.00    19,000.00
4.3 Cement Board Installation 12mm Thick                          1 lot      85,000.00    85,000.00
                TOTAL
  5 KITCHEN & BATHROOMS WORKS ( Existing Walls)
    WORK DESCRIPTION/ SCOPE OF WORKS                       QTY        UNIT   COST        MATERIAL
5.1 Cement Plastering and Tile Works
    5.1.1       Plastering works affected areas                   1 lot       8,000.00     8,000.00
    5.1.2       Tile works                                        1 lot       1,200.00     1,200.00
    5.1.3       Pipe installation provisions                      1 lot       3,000.00     3,000.00
    5.1.4       Grouting works                                    1 lot       2,000.00     2,000.00
    5.1.5       Painting Works                                    1 lot       6,000.00     6,000.00
    4.1.6       Area Ceiling Works                                1 lot       6,000.00     6,000.00
    4.1.7       Ceiling Painting works                            1 lot       3,000.00     3,000.00
5.2 Plumbing Works. Re-piping and pipe layout                     1 lot       5,600.00     5,600.00
5.3 Lightings and EE Fixtures                                     1 lot       5,880.00     5,880.00
5.4 Consumables & Accessories                                     1 lot       2,000.00     2,000.00
    Note: Plumbing fixtures and Tile to be Provided by Owner
                TOTAL
  6 2nd FLOOR WALL WORKS
    WORK DESCRIPTION/ SCOPE OF WORKS                       QTY        UNIT   COST        MATERIAL
5.1 Metal Studs and Cement Boards Interiro Work
    5.1.1       Metal Studs installation 2"x3"                    1 lot      26,000.00    26,000.00
    5.1.2       Cement boards Installation 9mm.thick              1 lot      36,000.00    36,000.00
    5.1.3       Sawali wall installation Exterior                 1 lot      28,000.00    28,000.00
    5.1.4       Wall insulation works                             1 lot      16,000.00    16,000.00
    5.1.5       Sawali anay proof painting                        1 lot       4,000.00     4,000.00
    5.1.6       Sawali Varnishing works                           1 lot       6,000.00     6,000.00
5.2 Electrical pipe provision installation                        1 lot       2,000.00     2,000.00
5.3 Rust proofing paint of all metal studs                        1 lot       5,000.00     5,000.00
5.4 Consumables & Accessories                                     1 lot       2,000.00     2,000.00
    Note: Wall facing the Creek is not included for Sawali Wall
                TOTAL
  6 ROOFING AND CEILING WORK
    WORK DESCRIPTION/ SCOPE OF WORKS                       QTY        UNIT   COST        MATERIAL
6.1 Tubular Steek Roof Framing
    5.1.1       Tubular steel 2"x4'                               1 lot      22,000.00    22,000.00
    5.1.2       Welding Works                                     1 lot       6,000.00     6,000.00
    5.1.3       Epoxy painting works                              1 lot       8,000.00     8,000.00
    5.1.4       Ceiling hangers and framings                      1 lot       9,500.00     9,500.00
    5.1.5       Cement board ceiling works                        1 lot      16,000.00    16,000.00
    5.1.6       Ceiling Painting works                            1 lot       5,000.00     5,000.00
5.2 Electrical pipe provision installation                        1 lot       2,000.00     2,000.00
5.3 Gutters and Pipe drains                                       1 lot       6,500.00     6,500.00
5.4 Consumables & Accessories                                     1 lot       2,000.00     2,000.00
 Note: To design an A-Frame roofing facing the garden.
           TOTAL
6 TOTAL COST
 Design Ideas
           Kubo Sawali Cladding Wall
           Kubo BedRoom Area                             Kubo Kitchen and CR Area
Wall Framing
LABOR       TOTAL
 5,000.00    10,000.00
20,000.00    20,000.00
 5,000.00    10,000.00
30,000.00    40,000.00
LABOR       TOTAL
 8,400.00    20,400.00
 2,000.00     4,400.00
 8,000.00    10,000.00
 6,000.00     9,400.00
24,400.00    44,200.00
LABOR       TOTAL
21,000.00    63,000.00
       -
 6,000.00    18,000.00
 9,000.00    27,000.00
 8,000.00    24,000.00
 4,000.00    12,000.00
 5,000.00    15,000.00
32,000.00    96,000.00
LABOR       TOTAL
16,000.00    48,000.00
 7,500.00    22,500.00
 3,000.00     9,000.00
       -
33,000.00    99,000.00
18,000.00    54,000.00
 5,000.00    15,000.00
 9,500.00    28,500.00
42,500.00   127,500.00
            403,500.00
LABOR       TOTAL
 4,000.00    12,000.00
   600.00     1,800.00
 1,500.00     4,500.00
 1,000.00     3,000.00
 3,000.00     9,000.00
 3,000.00     9,000.00
 1,500.00     4,500.00
 2,800.00     8,400.00
 2,940.00     8,820.00
 1,000.00     3,000.00
             64,020.00
LABOR       TOTAL
13,000.00    39,000.00
18,000.00    54,000.00
14,000.00    42,000.00
 8,000.00    24,000.00
 2,000.00     6,000.00
 3,000.00     9,000.00
 1,000.00     3,000.00
 2,500.00     7,500.00
 1,000.00     3,000.00
            187,500.00
LABOR       TOTAL
11,000.00    33,000.00
 3,000.00     9,000.00
 4,000.00    12,000.00
 4,750.00    14,250.00
 8,000.00    24,000.00
 2,500.00     7,500.00
 1,000.00     3,000.00
 3,250.00     9,750.00
 1,000.00     3,000.00
                115,500.00
                950,720.00
Floor Framing