Module 2
Module 2
Module 2
2. Routine Inspection
Routine inspection is the periodic and quick examination of the general conditions of
concrete structure which is carried out by competent and qualified engineers.
Each inspection should be recorded accurately and properly. Primarily, the inspector
carries out visual assessment, and may employ simple instrumental aids to specify the
condition of the concrete structure.
3. Detailed Inspection
Detailed or comprehensive inspection is a more intensive, time consuming, and thorough
inspection than the routine inspection. It is performed between certain number of routine
inspection and is scheduled based on the importance of the structure.
The inspector should closely examine all the details of the structure such as structural,
mechanical, environmental, durability, material, and electrical details.
If necessary, specialized tools, such as hammer sound testing or any other non-destructive
test, would be used to accurately determine the state of the structure. The detailed
inspection should be carried out by specially trained engineers who can plan
comprehensive repairs.
4. Special Inspection
Special inspection of concrete structures is done in special conditions after the occurrence
of unusual events. So, special inspection is need-based and is carried out as and when
required. Special inspection may require supplementary testing and structural
analysis and may require detailed involvement of a structural engineer.
The outcomes of this type of inspection should be enough to make a proper decision
about the next action to be undertaken for the structure under considerations. Conditions
in which special inspection is required may include but not limited to the following
circumstances:
In case of exceptional events for example flood, storm, fire, accidents, etc.
3) Collection of samples and carrying out tests both in situ and in lab.
7) Diagnosis.
A simple flow chart incorporating the above points is presented in fig 1.1.
AWH ENGG COLLEGE
AWH ENGG COLLEGE
Visual inspection
Visual inspection is one of the most versatile and powerful tools to evaluate the
condition of a concrete structure. Visual inspection can provide detailed information
that may lead to positive identification of the cause of distress.
Non-destructive tests of concrete is a method to obtain the properties of concrete from the
existing structures. This test provides immediate results.
➢ Radioactive Method
➢ Nuclear Methods
➢ Magnetic Methods
➢ Electrical methods
➢ Radar Technique
➢ Radiography Methods
Rebound hammer
PRINCIPLE
This is principally a surface hardness tester. It works on the principle that the rebound of
an elastic mass depends on the hardness of the surface against which the mass
strikes.
AWH ENGG COLLEGE
When the plunger of rebound hammer is pressed against the surface of concrete, a spring
controlled mass with a constant energy is made to hit concrete surface to rebound back.
The extent of rebound, which is a measure of surface hardness, is measured on a
graduated scale. This measured value is designated as Rebound Number (rebound index).
Objective
As per the Indian code IS: 13311(2)-1992, the rebound hammer test have the following
objectives:
PROCEDURE
The hammer weighs about 1.8 kg and is suitable for use both in a laboratory and in the
field.
Any loose particles should be rubbed off from the concrete surface with a grinding
wheel or stone, before hammer testing.
Six readings of rebound number is taken at each point of testing and an average of
value of the readings is taken as rebound index for the corresponding point of
observation on concrete surface.
AWH ENGG COLLEGE
3. The probe and spring arrangement will require regular cleaning and maintenance
4. Flaws cannot be detected with accuracy
Factors Influencing
Below mentioned are the important factors that influence rebound hammer test:
1. Type of Aggregate
2. Type of Cement
3. Surface and moisture condition of the concrete
4. Curing and Age of concrete
5. Carbonation of concrete surface
This test is done to assess the quality of concrete by ultrasonic pulse velocity method as
per IS: 13311 (Part 1) – 1992.
Principle of this test is – The method consists of measuring the time of travel of an
ultrasonic pulse passing through the concrete being tested. Comparatively higher velocity
is obtained when concrete quality is good in terms of density, uniformity, homogeneity
etc.
Longitudinal pulse velocity (in km/s or m/s) is given by:
v = L/T
where
v is the longitudinal pulse velocity,
L is the path length,
Applications
Measurement of the velocity of ultrasonic pulses of longitudinal vibrations passing
through concrete may be used for the following applications:
Transducer arrangement:
The receiving transducer detects the arrival of the pulse. To make measurements of pulse
velocity by placing the two transducers on either:
Among the above methods direct transmission will give most desirable results.
Interpretation of Results:
The quality of concrete in terms of uniformity, incidence or absence of internal flaws,
cracks and segregation, etc, indicative of the level of workmanship employed, can thus be
assessed using the guidelines given below
AWH ENGG COLLEGE
Moisture content
Path length
The semi-destructive testing of concrete is a partial destructive test, where samples are
required for testing. Here small area of the concrete will be damaged during testing.
This test enables the prediction of the service life of concrete structures.
In this test, the steady voltage (V) is applied to a concrete specimen for 6 hours,
and the current (i) going through the concrete is recorded to find the coulombs.
AWH ENGG COLLEGE
The more permeable the concrete, the higher the coulombs; the less porous the
concrete, the lower the coulombs.
Apparatus:
This test apparatus comprises two reservoirs. One of them has 3 % of NaCl solution and
another reservoir has 0.3 M NaOH Solution, Concrete having a thickness of 50
millimeters and diameter 90 to 100 millimeters is used as a test specimen.
Test Procedure:
<100 Negligible
Carbonation;
Carbonation of concrete is a process by which carbon dioxide from the air penetrates
into concrete through pores and reacts with calcium hydroxide to form calcium
carbonates. The conversion of Ca(OH)2 into CaCO3 by the action of CO2 results in a
small shrinkage.
CO2 by itself is not reactive. In the presence of moisture, CO2 changes into dilute
carbonic acid, which attacks the concrete and also reduces alkalinity of concrete (i.e. pH
value reduces).
AWH ENGG COLLEGE
The pH value of pore water in the hardened concrete is generally between 12.5 to 13.5
depending upon the alkali content of cement. The high alkalinity forms a thin passivating
layer around steel reinforcement and protect it from action of oxygen and water. As long
as steel is placed in a highly alkaline condition, it is not going to corrode. Such condition
is known as passivation.
The carbonation process is also called depassivation.
In actual practice CO2 present in atmosphere in smaller or greater concentration,
permeates into concrete and carbonates the concrete and reduces the alkalinity of
concrete. The pH value of pore water in the hardened cement paste, which was around
13, will be reduced to around 9.0. When all the Ca (OH)2 has become carbonated, the pH
value will reduce up to about 8.3. In such a low pH value, the protective layer gets
destroyed and the steel is exposed to corrosion. The carbonation of concrete is one of
the main reasons for corrosion of reinforcement.
The time required for carbonation can be estimated knowing the concrete grade and using
the following equation:
The significance of carbonation is that the usual protection of the reinforcing steel present
in concrete due to the alkaline conditions caused by hydrated cement paste is neutralized
by carbonation. Thus, if the entire concrete cover over the reinforcing steel is carbonated,
corrosion of the steel would occur if moisture and oxygen could reach the steel.
The concrete core is sprayed with phenolphthalein solution, the depth of the uncoloured
layer (the carbonated layer) from the external surface is measured to the nearest mm at 4
or 8 positions, and the average taken.
If the test is to be done in a drilled hole, the dust is first removed from the hole using an
air brush and again the depth of the uncoloured layer measured at 4 or 8 positions and the
average taken. If the concrete still retains its alkaline characteristic the colour of the
concrete will change to purple. If carbonation has taken place the pH will have changed
to 7 (i.e. neutral condition) and there will be no colour change.
The only limitation is the minor amount of damage done to the concrete surface by
drilling or coring.
Resistivity Meter
The corrosion of steel in concrete is an electrochemical process that generates a flow of
current. The resistivity of the concrete influences the flow of this current. The lower the
electric resistance, the more easily corrosion current flows through the concrete and the
greater is the probability of corrosion. Thus, the resistivity of concrete is a good
indication of the probability of corrosion.
Resistivity meter can be used to assess the corrosion of steel reinforcement embedded in
concrete. It is a very simple technique and can be adopted easily in the field.
AWH ENGG COLLEGE
During corrosion process, an electric current flow between the cathodic and
anodic sites through the concrete and this flow can be detected by
measurement of potential drop in the concrete.
Hence, surface potential measurement is used as a non-destructive testing for
identifying anodic and cathodic regions in concrete structure and indirectly
detecting the probability of corrosion of rebar in concrete.
This is another useful NDT technique to know the condition of steel rebar
embedded inside the concrete .
The resistivity method is another electrochemical method, which relies upon the
principle that corrosion is an electrochemical process.
An ionic current must pass between the anode and cathode areas for corrosion
monitoring of RC structures
AWH ENGG COLLEGE
Tafel extrapolation
Core test
The testing of concrete cores is carried out according to the ASTM Standard C 42.
The number, size, and location of core samples should be carefully selected to
permit all necessary laboratory tests.
It is better to drill core through full depth of member to avoid the need of its
breaking for extraction. An extra 50 mm is usually drilled to allow for possible
damage at the base of the core.
At least three cores must be removed at each location in the structure for strength
determination.
The hole drilled to take the core is filled by packaged repair material. The material
must not fall down under gravity. In some cases, a precast cylinder of concrete
may be fitted in the core hole by using cement grout or epoxy resin.
Minimum core diameter is 100 mm but 75 mm and 50mm diameters may be used
in special cases.
The number of 50 mm diameter cores must be three times the number of 100 mm
diameter cores to get the same accuracy. The 20 percent top portion of member
with a minimum of 50 mm and maximum of 300 mm and a side cover of 50 mm
within the member is preferably not included in the portion of the core to be
tested.
the effect of the length to diameter ratio of the core (R) on the strength is given as under:
Load test.
Load test.
Mainly 2 types
Load test on specimens
Load test on structure
1. Compression test
Procedure:
This concrete is poured in the mold and appropriately tempered so as not to have any
voids.
After 24 hours, moulds are removed, and test specimens are put in water for curing.
The top surface of these specimen should be made even and smooth. This is done by
placing cement paste and spreading smoothly on the whole area of the specimen.
These specimens are tested by compression testing machine after seven days curing or 28
days curing.
Load should be applied gradually at the rate of 140 kg/cm2 per minute till the Specimens
fails.
Load at the failure divided by area of specimen gives the compressive strength of
concrete.
Procedure
wet specimen from water after 28 of curing is used for tensile strength estimatimation.
record the weight and dimension of the specimen.
Set the compression testing machine for the required range.
Place plywood strip on the lower plate and place the specimen.
Align the specimen
Place the other plywood strip above the specimen.
Bring down the upper plate so that it just touch the plywood strip.
Apply the load continuously without shock at a rate within the range 0.7 to 1.4 MPa/min (1.2
to 2.4 MPa/min based on IS 5816 1999)
Finally, note down the breaking load(P)
Specimen: The standard size of the specimens are 15 x 15 x 70 cm. Alternatively, if the largest
nominal size of the aggregate does not exceed 20 mm, specimens 10 x 10 x 50 cm may be used.
Loading :
AWH ENGG COLLEGE
Procedure:
The specimen is then placed in the machine in such a manner that the load is applied to
the uppermost surface as cast in the mould, along two lines spaced 20.0 or 13.3 cm apart.
The axis of the specimen is carefully aligned with the axis of the loading device.
The load is applied without shock and increasing continuously, at a rate of loading of 400
kg/min for the 15.0 cm specimens and at a rate of 180 kg/min for the 10.0 cm specimens.
The load is increased until the specimen fails, and the maximum load applied to the
specimen during the test is recorded.
The appearance of the fractured faces of concrete and any unusual features in the type of
failure is noted.
The flexural strength of the specimen is expressed as the modulus of rupture fb . if
‘a’ equals the distance between the line of fracture and the nearer support, measured on the
centre line of the tensile side of the specimen, in cm,
fb When ‘a’ is greater than 20.0 cm for 15.0 cm specimen or greater than 13.3 cm for a10.0 cm
specimen, or
when ‘a’ is less than 20.0 cm but greater than 17.0 cm for 15.0 specimen, or less than 13.3cm but
greater than 11.0 cm for a 10.0 cm specimen where b = measured width in cm of the specimen,
AWH ENGG COLLEGE
The procedure of load test on concrete structures presented here depends on ACI -2008
Chapter 20.
A load test is usually not made until the portion of the structure to be subjected to load is
at least 56 days old. If a load test is decided as a means of the strength evaluation process
for a particular project, the first step is that
all the involved parties decide and
agree upon the region to be loaded,
the magnitude of the load,
the physical load test procedure, and
acceptance criteria.
the loads, extra concrete strength and multi-directional sharing of the loads not
considered in ordinary designs.
a) The spans and panels having more doubt during survey are considered.
b) The number and arrangement of spans or panels loaded are selected to maximize the
deflection and stresses in the critical regions of the structural elements to be tested.
AWH ENGG COLLEGE
c) The load is applied at locations where its effect on the suspected defect is a maximum.
Loading criteria
1. Before conducting the test, it must be made sure that the structure does not fully
collapse under the test load and sufficient safety measures must be taken to save the
working people and other parts of the building in case of an unexpected sudden
failure. Safety measures adopted for the testing must not interfere with load test
procedures and these must not affect results.
3. Carefully think about the types of expected cracks, method of measuring the width and
length of expected cracks, expected locations where the cracks will be measured, and
approximate limits for opening and development of cracks.
4. Deflection gages are installed on all critical sections. Measurements must be made at
locations where maximum response is expected. Additional measurements can be made if
required.
AWH ENGG COLLEGE
5. The initial value for all applicable response measurements (such as deflection, rotation,
strain, slip, crack widths) are recorded not more than 1 hour before application of the first
load increment.
6. A load equal to service dead load D that is not already present, such as for partitions,
false ceilings and ducts, must be applied and it should remain in place until the
completion of the load test. Deflection readings are taken immediately after the
application of this additional load. The test can be started after an interval of 48 hours.
After dead load deflections have stabilized, existing cracks and other defects must be
observed, marked, and recorded.
7. Test load defined above is applied in approximately four or more equal increments. It
is better to carry out visual inspection of the structure after each load increment.
8. Uniform test load is applied in a manner to ensure uniform distribution of the load to
the portion of the structure being tested. The loading units placed on the surface must not
have bridging or arching between them because this may make the load non-uniform with
reduction of load near the mid-span.
10. If the measured deflections exceed expected values, the test must either be stopped or
a written permission must be taken from the supervising engineer.
11. After each increment of the load, the formation or worsening of cracking and distress,
and the presence of excessive deformations, rotations, etc., must be carefully observed.
The investigator must approximately analyze the observed data and determine whether it
is safe to proceed with the next increment. It is advantageous that load-deflection curves
are developed during the load test for all critical points of deflection measurements.
12. Maintain the full test load on the structure for at least 24 hours and record all response
measurement after this time interval.
13. Total test load is removed in the least possible time after all response measurements
are made in the above step.
14. Wait for 24 hours after the removal of the entire test load. All the response
measurements are made after 24 hours again.
15. Physical load testing is basically used only for evaluating the strength of a structure
for vertical gravity loads. Leaving some exceptions, in-situ load testing is not used for
evaluating the strength of a structure against lateral loads.
AWH ENGG COLLEGE
Pullout test:
The fundamental principle behind pull out testing is to correlate to the compressive strength of
concrete. This correlation is achieved by measuring the force required to pull a steel disc or ring,
embedded in fresh concrete, against a circular counter pressure placed on the concrete surface
concentric with the disc/ring.
Depending upon the placement of disc/ring in he fresh concrete, pull out test can be divided into
2 types,
1. LOK test
2. CAPO test
LOK Test:
The LOK-TEST system is used to obtain a reliable estimate of the in-place strength of concrete
in newly cast structures in accordance with the pullout test method described in ASTM C900, BS
1881:207, or EN 12504-3.
The Windsor probe, like the rebound hammer, is a hardness tester that the penetration of the
probe reflects the compressive strength.
1. Place the positioning device on the surface of the concrete at the location to be tested.
2. Mount a probe in the driver unit
3. Position the driver in the positioning device
4. Fire the probe into the concrete.
5. Remove the positioning device and tap the probe on the exposed end with a small
hammer to ensure that it has not rebounded and to confirm that it is firmly embedded.
6. Place the measuring base plate over the probe and position it so that it bears firmly on the
surface of the concrete without rocking or other movement.
Results
The penetration resistance of concrete is computed by measuring the exposed length of
probes driven into concrete. In order to estimate concrete strength, it is necessary to
establish a relationship between penetration resistance and concrete strength.
AWH ENGG COLLEGE